Generation Capacity Guide

Similar documents
Network capability and performance

NETWORK DEVELOPMENT ACHIEVING. Assessing the need for network development. Non-regulated customer connections POWERLINK ANNUAL REPORT 2011/12

Network capability and performance

15 Nelson-Marlborough Regional Plan

South Australia Victoria (Heywood) Interconnector Upgrade. RIT-T: Project Specification Consultation Report

POWER SYSTEM OPERATING INCIDENT REPORT: TRIP OF 837 TARONG MT. ENGLAND 275 KV LINE AND MT. ENGLAND NO KV BUSBAR ON 30 OCTOBER 2011

Eyre Peninsula electricity supply options investigation

15 Nelson-Marlborough Regional Plan

CHAPTER 2 - NETWORK DEVELOPMENT UPDATES FOR 2011

Emerald Reactive Support Alternative Solution Expressions of interest

MULTIPLE LINE OUTAGES IN THE MOUNT ENGLAND TARONG AREA IN QUEENSLAND, 13 FEBRUARY 2017

18/10/2018. Mr Peter Adams General Manager, Wholesale Markets Australian Energy Regulator. By

Jemena Electricity Networks (Vic) Ltd

Enquiry Form (Non-Registered Generator With Capacity less than 5 MW)

Utilities (Technical Regulation) (Electricity Transmission Supply Code) Approval 2016 (No 1)*

Eyre Peninsula Electricity Supply Options

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

Grid Integration Costs: Impact of The IRP Capacity Mix on System Operations

POWER SYSTEM INCIDENT REPORT NORTHERN POWER STATION STABILISER OUTAGE APRIL AND MAY 2010

Powering Sydney s Future

REGIONAL VICTORIAN THERMAL CAPACITY UPGRADE RIT-T PROJECT ASSESSMENT CONCLUSION REPORT

Large Embedded Generation User Guide A

SOUTH AUSTRALIAN HISTORICAL MARKET INFORMATION REPORT SOUTH AUSTRALIAN ADVISORY FUNCTIONS

Interconnection System Impact Study Report Request # GI

POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 UNIT ON 9 FEBRUARY 2012

Merger of the generator interconnection processes of Valley Electric and the ISO;

statistics Added in 2005/2006

The Energy Queensland Group Notice of no non-network options

TRANSMISSION PLANNING CRITERIA

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

APPLICATION FOR INSTALLATION OF SMALL SCALE EMBEDDED ELECTRICITY GENERATION

TRIP OF HORSHAM-REDCLIFFS 220 KV TRANSMISSION LINE AND MURRAYLINK INTERCONNECTOR ON 12 NOVEMBER 2015

Distributed Energy Resources Grid Connection Guidelines

Guidelines for connection of generators:

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation

POWER SYSTEM OPERATING INCIDENT REPORT TRIPS OF YALLOURN W POWER STATION UNITS W1 AND W3 ON 14 NOVEMBER 2012

WESTERN INTERCONNECTION TRANSMISSION TECHNOLGOY FORUM

City of Palo Alto (ID # 6416) City Council Staff Report

CHAPTER 8 - GAS AND ELECTRICITY TRANSMISSION COMPARATIVE CASE STUDY

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

The Role of DSO as Facilitator of the Electricity Markets in Macedonia. Key aspects and considerations

Power Potential Guide to Participating : A technical 0 guide to the services for synchronous and non-synchronous DER participants 04/10/2017

Alberta Electric System Operator Saleski Transmission Project Needs Identification Document

Final Report. Solar feed in tariff for regional Queensland for

LIST OF REGIONAL BOUNDARIES AND MARGINAL LOSS FACTORS FOR THE FINANCIAL YEAR

Effects of Smart Grid Technology on the Bulk Power System

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82

Feasibility Study Report

The Power Potential Project A guide to participating

TERMS AND CONDITIONS

Decision on Merced Irrigation District Transition Agreement

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

For personal use only

POWER SYSTEM OPERATING INCIDENT REPORT MULTIPLE CONTINGENCY EVENT IN NORTH WEST TASMANIA ON 6 APRIL 2012

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

The Development of Competitive Renewable Energy Zones in Texas

MYPD3 tariff restructuring plan use-of-system charges. Brochure

SOUTH AUSTRALIAN HISTORICAL MARKET INFORMATION REPORT SOUTH AUSTRALIAN ADVISORY FUNCTIONS

Basic Connection Services Application and Price Guide

AS/NZS :2016. Grid connection of energy systems via inverters AS/NZS :2016. Part 1: Installation requirements

Power System Operating Incident Report Trip of Red Cliffs Horsham and Red Cliffs-Wemen Kerang 220 kv transmission lines on 15 January 2014

Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any

Supplemental Report on the NCTPC Collaborative Transmission Plan

KERALA STATE ELECTRICITY REGULATORY COMMISSION. NOTIFICATION Dated, Thiruvananthapuram 6 th August,2007

Impact of Distributed Energy Resources on Transmission System Reliability

Export limits for Embedded Generators up to 200 kva connected at Low Voltage

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks

System Impact Study Report

POWER SYSTEM OPERATING INCIDENT REPORT LIGHTNING STRIKES IN TASMANIA AND PACIFIC ALUMINIUM POTLINE LOAD REDUCTIONS 21 MARCH 2013

Distributed resource participation in the Australian National Electricity Market

PHILIPPINE DISTRIBUTION CODE 2017 EDITION

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Clean Energy Council submission to the Energy Networks Australia. Technical Guidelines for Basic Micro and Low Voltage Embedded Generation Connections

Energy Regulation : Australian Experience. Engr.Khondkar Abdus Saleque

Copyright and Disclaimer

Power System Operating Incident Report Trip of Murray Lower Tumut No kv Transmission Line at Murray End Only on 18 November 2013

Micro Embedded Generating Units (0-30 kva)

Connecting your business diesel generation

ATTACHMENT A TRANSGRID PROJECT ASSESSMENT REPORTS INDEPENDENT PLANNING REVIEW

2016 Load & Capacity Data Report

Assessing the Potential Role of Large-Scale PV Generation and Electric Vehicles in Future Low Carbon Electricity Industries

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016

DFO STATEMENT OF NEED REPORT

The Role of Electricity Storage on the Grid each location requires different requirements

Distributed Energy Resources

Guideline for Parallel Grid Exit Point Connection 28/10/2010

Statement of Expected Price Trends

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

BUILDING A LEVEL PLAYING FIELD FOR LOCAL ENERGY WITH LOCAL NETWORK CREDITS AND VIRTUAL NET METERING

POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF 220 KV C BUSBAR AT GORDON POWER STATION ON 26 NOVEMBER 2011

Unitil Energy Demand Response Demonstration Project Proposal October 12, 2016

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

Header. Reasonableness Test RT 007/11 Balhannah & Uraidla 66 / 33 kv Substations. RT Balhannah and Uraidla - Final Draft Page 1 of 8

February 10, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF B 220 KV BUSBAR AT GEORGE TOWN ON 27 NOVEMBER 2012.

Embedded Generation Guidelines

The Long-Range Transmission Plan

Interconnection Feasibility Study Report GIP-222-FEAS-R3

2017 Interim Area Transmission Review of the New York State Bulk Power Transmission System

National Distributed Energy Resources Grid Connection Guidelines. Technical Guidelines for Basic Micro EG Connections

Transcription:

This guide outlines the potential generation capacity which may be available at various locations across Powerlink s transmission network. The data presented is not comprehensive. This information is preliminary only and is not intended to replace the existing processes that must be followed to seek connection to Powerlink s transmission network. The data has been prepared using the methodology and assumptions outlined in this document, noting that capacity is a dynamic concept and that it changes in response to real time network conditions, environmental conditions and constraints. In practice, higher or lower capacities than those listed in Table 2 may be achievable at different points in time. Powerlink encourages interested parties to contact Powerlink s Business Development team by phoning (+617) 3860 2111 during business hours, or by emailing BusinessDevelopment@powerlink.com.au. Interested parties are also encouraged to refer to Powerlink s Transmission Annual Planning Report (TAPR), which provides information relevant to the development of new generation projects. The information presented in this document is current at 1 June 2018, including taking into account the draft System Strength Impact Assessment Guidelines published by the Australian Energy Market Operator (AEMO) in May 2018. The publication of this guideline has been bought about by publication of The National Electricity Amendment (Managing power system fault levels) Rule 2017 No.10. Updated network capacity information may be published on Powerlink s website from time to time, and interested parties should check this information. To join Powerlink s Non-network Engagement Stakeholder Register (NNESR) and be notified of any updates to this data, please email NetworkAssessments@powerlink.com.au. Calculation methodology Indicative available generation connection capacity is outlined at more than 60 locations across Powerlink s transmission network. Powerlink has assessed the available generation connection capacity at a number of locations across the network predominantly at the 275kV and 132kV level. Locations close to major urban areas were considered less likely to host a large Variable renewable energy (VRE) project and were excluded from the assessment. Powerlink and Energex and Ergon Energy (part of the Energy Queensland Group) are required to liaise regarding the assessment of new connections. While the arrangements for connection differ due to the Rules that apply to a Distribution Network Service Provider (DNSP) and Transmission Network Service Provider (TNSP), the obligations around system strength and system security relating to generators apply equally to new connections on the network as a whole. Analysis is based on the existing and committed transmission network arrangements. The analysis also takes account of recent generator commitments. Possible (uncommitted) future network changes, including those outlined in Chapters 5 and 7 of Powerlink s 2018 TAPR, may alter the level of supportable generation. The calculation methodology is based on the Guidelines published by AEMO, continuing to build upon the existing technical standards that currently apply to transmission network design and power system performance. Changes to these standards have the potential to change the network capacity available to generators. Congestion The location and pattern of generation dispatch influences power flows across most of the Queensland system. Power flows can also vary substantially with planned or unplanned outages of transmission network elements. Power flows may also be higher at times of local area or zone maximum demand or generation, and/or when embedded generation output is lower. Depending on these system conditions sections of Powerlink s transmission network may constrain under system normal and contingency conditions. The exposure to congestion may increase with new generation commitments. Maximum power transfer capability may be set by transient stability, voltage stability, thermal plant ratings (transformer and conductor ratings) or protection relay load limits. System strength may also be a constraint that limits the output from VRE generation in an area of the network. Where constraints occur on the network due to thermal, voltage or transient stability limits, AEMO will constrain generation based on the market system rules within the National Electricity Market Dispatch Engine (NEMDE) to maintain system security. 2

Three criteria are published for each connection point as described below: 1. Thermally Supportable Generation A connection point s thermal capacity relates to the highest level of generation that can be exported through a connection point without exceeding the rating of a transmission circuit following the loss of a network element. This field is applicable to all forms of generation. The thermally supportable generation only relates to constraints on the local network, including the network adjacent to the connection point and between the connection point and the main transmission system. It is not intended to provide information on intra-network or inter-network constraints. The levels of thermally supportable generation reported in Table 2 are based on the single generation dispatch shown in Table 1. This generation profile is applied to a typical summer noon load and coincident output for the committed VRE generation projects. The thermally supportable generation at a connection point may be substantially greater or lower with different generation patterns, network configurations and load levels. For example, the thermally supportable generation available at Strathmore 132kV is reported as being 100-150MW (refer to Table 2). However, under lower Far North Queensland and Ross generation and higher North generation the available generating capacity at Strathmore 132kV can be less than 50MW. Table 1 Base summer noon generation dispatch assumptions for the available thermal capacity guide Zone/Interconnector Generation sent out (MW) Far North 260 Ross 449 North 282 Central West 2,537 Gladstone 1,223 Wide Bay 233 Surat 144 Bulli 2,070 South West 1,925 Moreton 494 Qld-NSW Interconnector Southerly Flow (swing) 300 Terranora Interconnector Southerly Flow 50 Each connection point s thermal capacity was calculated by iteratively applying increasing levels of generation to the connection point, (balanced by changing power flows on the Queensland to New South Wales Interconnector), and performing contingency analysis. The thermal limit of a connection point was assessed as being reached when a rating breach was identified within the local network. It may be possible for generation to be exported in excess of the thermally supportable generation if a fast generation run-back scheme limits generation output following relevant network contingency events. Powerlink has assessed each connection point individually, and has not assessed whether multiple generators in a region are likely to result in congestion on the backbone transmission network. 2. System Strength Supportable Generation Powerlink s 2018 TAPR outlines that advances in renewable energy technologies and displacement of existing synchronous generation is driving a transformation in energy throughout the National Electricity Market (NEM). The displacement of this synchronous generation with asynchronous VRE generation is likely to significantly reduce the system fault levels. This reducing system strength can impact the stability and security of the power system. 3

As required under Rule 2017 No. 10 (Managing Power System Fault Levels), AEMO published the System Strength Impact Assessment Guidelines for consultation on 5 March 2018, with an update on 14 May 2018. The final guidelines are to be published on. As such, it is not possible for Powerlink to fully consider these in the current version of this document. An adverse impact on system strength may be caused by the aggregation of multiple electrically close VRE generating units, or by a large plant on its own. Where multiple VRE generating systems are connected in close proximity, a screening index that can account for nearby asynchronous generation is required. The guidelines require that Powerlink undertake a Preliminary Assessment at the connection enquiry phase to assess this impact. Powerlink has selected the Available Fault Level (AFL) methodology as an appropriate screening measure to assess likely system strength impacts. The AFL methodology calculates the AFL at the proposed connection point for the VRE generator. This is then used to calculate the aggregate Short Circuit Ratio (SCR). Where the aggregate SCR is less than three, it will be necessary for the proponent to undertake a full assessment. The full assessment requires electro-magnetic transient (EMT) type studies as part of the application process. This is to ensure that any adverse system strength impact is adequately addressed as part of the connection application either via a system strength remediation scheme or system strength connection works. Where the aggregate SCR is greater than three, the strength of the connection point is sufficient for power electronic connected systems, such as VRE generation, to maintain stable operation. The aggregate SCR at the connection point strongly influences a plant s ability to operate satisfactorily both in steady state and following a system disturbance. New VRE generation may also adversely interact with existing network voltage control devices 1. The possibility of adverse interactions with these devices can be estimated by the change in the voltage at the point where the new VRE generation is connecting. Where the interaction is greater than 3%, it will be necessary to undertake a full assessment. This requirement is independent of the aggregate SCR assessment described above, and either assessment can trigger the requirement for full assessment. The methodology also takes account of the possible displacement 2 of synchronous generation in Queensland as a result of new entrants in Queensland. The commitment of new VRE generation, currently approximately 2700MW, is expected to significantly alter the generation patterns of synchronous plant. Powerlink does not know the nature or extent of how this will impact synchronous generation profiles in the future. To reasonably account for this impact, existing synchronous generation has been offset throughout the state to achieve possible generation profiles. Other synchronous generation profiles are possible that may result in different system strength limitations. Powerlink has assessed this displacement against daytime minimum loads. In 2017, the daytime minimum delivered load in Queensland fell below 4,300MW, in comparison to a night-time minimum delivered load of below 4,250MW. Due to the prevalence of solar Photovoltaic (PV) generation in Queensland, the minimum synchronous generation profile is expected to occur through the middle of the day, particularly in April, May, August and September. Due to the interaction of non-synchronous VRE generation in the network, Powerlink has assessed the available capacity from a system strength perspective in each zone, rather than at each connection point. Some connection points may have been excluded where they offer significantly less capacity than others in a region. Other connection points within a zone may offer more capacity than indicated, but would impact on other connection points within that zone. It remains the case that generation must meet the NER generator performance standards, and generation proponents are required to demonstrate that their proposed generation technology is able to meet these standards during the connection process. 3. VRE supportable generation VRE generation, including most forms of solar and wind generation, will be subject to the most-limiting of the thermally supportable generation and the system strength supportable generation. As such, the lower of these two parameters at each location is presented in Table 2 as the VRE supportable generation (i.e. it is simply the minimum of the thermally supportable and system strength supportable generation values). 1 Including Static VAr Compensators (SVCs) and Static Synchronous Compensators (STATCOMs) 2 Displacement may occur for periods when it is not economic for a synchronous generator to operate, and is distinct from retirement which is permanent removal from the market. 4

Indicative supportable generation The results of the application of the calculation methodology described above are presented below in Table 2. The VRE supportable generation metric is also displayed geographically on the AREMI spatial data platform. AREMI enables the supportable generation data to be viewed in conjunction with other datasets which may be of interest to prospective renewable generation developers. This information is provided as a guide only and not a substitute for the information to be obtained during the connection enquiry process. This process includes the provision of capacity and congestion information for customers seeking to connect to Powerlink s transmission network. Generator proponents are also encouraged to refer to Powerlink s 2018 TAPR, which provides more detail on these issues, particularly: ychapter 5 describes possible and proposed changes to the network in the five-year and 10-year outlook period. ychapter 6 presents existing capacity and performance of the main transmission network backbone. ychapter 7 identifies network limitations that may arise within the 10-year outlook period due to new loads within the resource rich areas of Queensland or at the associated coastal port facilities whose development status is not yet at the stage that they can be included (either wholly or in part) in the medium economic forecast of Chapter 2. ychapter 7 also provides a summary of the technical challenges due to the changing mix of generation and the role TNSP s will play in providing directly or facilitating system security services. yappendix C illustrates sample power flows at time of peak demand (which is typically late in the day). yappendix D provides the Powerlink derived intra-regional limit equations, which are implemented in the national electricity market dispatch engine to constrain the generation dispatch within the technical capabilities of the network. y Appendix E provides indicative minimum and maximum short circuit currents and lowest plant rating at connection points providing an indication of required switchgear rating. 5

Table 3 Zone Far North Ross North Central West Gladstone Wide Bay Bulli Surat South West Moreton 6 Indicative 132kV transmission connection point supportable generation capacities Voltage Level (kv) Thermally supportable generation (MW) 275 300-400 132 150-200 132 150-200 132 100-150 275 600-700 132 100-150 275 500-600 132 350-400 275 300-400 132 250-300 System strength supportable generation (MW) Nonsynchronous supportable generation (MW) up to 50 up to 50 up to 50 up to 50 up to 100 up to 100 up to 100 up to 100 400+ up to 400 up to 350 up to 300 Includes the substations: Chalumbin, Walkamin Chalumbin, Edmonton, Innisfail, Kamerunga, Turkinje Ross Cardwell, Clare South, Ingham South, Ross, Tully, Yabulu South Nebo, Strathmore Alligator Creek, Bowen North, Collinsville North, Kemmis, Mackay, Moranbah, Nebo, Newlands, Peak Downs, Pioneer Valley, Proserpine, Strathmore Bouldercombe, Broadsound, Calvale, Lilyvale, Stanwell Biloela, Blackwater, Bouldercombe, Dysart, Lilyvale, Moura, Pandoin Calliope River, Larcom Creek, Wurdong Calliope River, Gladstone South, Larcom Creek, Yarwun Gin Gin, Teebar Creek, Woolooga Gin Gin, Teebar Creek, Woolooga 330 800+ Braemar, Bulli Creek, 800+ 800+ Millmerran Braemar, Western Downs 132 150-200 330 800+ up to 300 up to 200 400+ 400+ Columboola, Wandoan South Chinchilla, Columboola, Wandoan South Middle Ridge Halys, Middle Ridge, Tarong 110 400+ Middle Ridge 275 500-600 Mt England, Palmwoods 132 200-250 400+ up to 250 Palmwoods 110 400+ Blackstone Disclaimer This guide is provided for information purposes only. This means Powerlink does not warrant the accuracy or currency of the guide. The material is not provided for the recipient to rely on or act on, nor does it have any legal effect. The guide is subject to many assumptions, dependencies, contingencies and variables and Powerlink is under no obligation to inform the recipient if the guide changes or becomes inaccurate. Key Modelling Assumptions 1. Thermally supportable generation capacity has been assessed using a single, indicative, summer midday pattern of load and generation. The thermally supportable generation at a location may be substantially greater and/or lower with different load and generation patterns. 2. All analysis is based on the existing configuration of the transmission network with committed changes to the network applied. Possible future network changes, including those outlined in chapters four and six of Powerlink s TAPR may alter the level of supportable generation. 3. New non-synchronous generators are assumed to be able to operate with a short circuit ratio of three, and to comply with NER automatic access standard for reactive power capability. (Refer to the calculation methodology section for further description and additional assumptions) General notes 1. The provided figures are indicative. Detailed and project specific analysis is undertaken as part of the connection application process, including an assessment of stability, network congestion and compliance with the generator performance standards. 2. Generation opportunities presented in this section are not cumulative. If a new generator commits, it may impact the supportable generation at multiple locations. 3. Transmission network connections do not confer firm access to the National Electricity Market (NEM). The dispatch of generation within the NEM, including management of any congestion, is the responsibility of the Australian Energy Market Operator (AEMO). Powerlink proactively monitors the potential for congestion to occur in accordance with the National Electricity Rules (NER), and will assess the potential network augmentations and/or non-network options to maximise market benefits using the Australian Energy Regulator s (AER) Regulatory Investment Test for Transmission (RIT-T). Where augmentations are found to be economic, Powerlink may augment the network or implement non-network solutions to ensure that the electricity market operates efficiently and at the minimum overall long run cost to consumers. For more information, please contact Powerlink s Business Development team: (+617) 3860 2111, BusinessDevelopment@powerlink.com.au

Contact us Registered office Postal address 33 Harold St Virginia Queensland 4014 Australia ABN 82 078 849 233 GPO Box 1193 Virginia Queensland 4014 Australia Telephone (+617) 3860 2111 (during business hours) Website www.powerlink.com.au Social media