TANK RISER SUSPENSION SYSTEM CONCEPTUAL DESIGN (U)

Similar documents
4lliedSig nal. Development of a Digital Control Unit to Displace Diesel Fuel With Natural Gas. Federal Manufacturing & Tech nolog ies. A. D.

Glendale Water & Power Smart Grid Project

The Realities of Consumer-Owned Wind Power For Rural Electric Co-operatives

Production Summary for Extended Barrel Module Fabrication at Argonne for the ATLAS Tile Calorimeter

Sacramento Municipal Utility District s EV Innovators Pilot

Test Rig Design for Large Supercritical CO 2 Turbine Seals

MAST R OS71 NOV DOE/METC/C-96/7207. Combustion Oscillation: Chem,;a Purge Time. Contrc Showing Mechanistic.ink to Recirculation Zone

Electron Positron Proton Spectrometer for use at Laboratory for Laser Energetics

Multi-Stage Selective Catalytic Reduction of NO in Lean-Burn Engine Exhaust. B. M. Penetrante M. C. Hsiao B. T. Merritt G. E.

Utilization of Associated Gas to Power Drilling Rigs A Demonstration in the Bakken

REPORT ON TOYOTA/PRIUS MOTOR DESIGN AND MANUFACTURING ASSESSMENT

Jerry Shoemaker Manager, Smart Grid PMO February 20, 2014

Hurricane Andrew Photovoltaic Traffic Control Relief Preliminary Report

MODERN GRID S T R A T E G Y

Waste Heat Recuperation for Passenger Vehicles

This document was prepared in conjunction with work accomplished under Contract No. DE-AC09-96SR18500 with the U.S. Department of Energy.

Model-Based Integrated High Penetration Renewables Planning and Control Analysis

Building Blocks and Opportunities for Power Electronics Integration

BLOCKING DIODES AND FUSES IN LOW-VOLTAGE PV SYSTEMS

A Study of Lead-Acid Battery Efficiency Near Top-of-Charge and the Impact on PV System Design

DOUBLE ROW LOOP-COILCONFIGURATION FOR HIGH-SPEED ELECTRODYNAMIC MAGLEV SUSPENSION, GUIDANCE, PROPULSION AND GUIDEWAY DIRECTIONAL SWITCHING

MASTER \ C. Idaho National Engineering Laboratory. INEL 96J014t we.l~%/0o/60 PREPRINT. MOTOR-OPERATOR GEARBOX EFFICIENCY 5 i u.

TerraPower s Molten Chloride Fast Reactor Program. August 7, 2017 ANS Utility Conference

Alternative Fuel Price Report

Determination of Spring Modulus for Several Types of Elastomeric Materials (O-rings) and Establishment of an Open Database For Seals*

THE ALTERNATIVE FUEL PRICE REPORT

Mechanical Integrity Issues of MCM-Cs for High Reliability Applications. Federal Manufacturing & Technologies. Howard Morgenstern, Tom Tarbutton, and

Hybrid Electric Vehicle End-of-Life Testing On Honda Insights, Honda Gen I Civics and Toyota Gen I Priuses

RECElVEp. Lubrication for High Load Duplex Bearings. Federal Manufacturing & Technologies. R. G. Steinhoff KCP Published August 1997

THE IMPACT OF BIODIESEL FUEL BLENDS ON AFTERTREATMENT DEVICE PERFORMANCE IN LIGHT-DUTY VEHICLES

Borrego Springs Microgrid Demonstration Overview

Real Time Applications Using Linear State Estimation Technology (RTA/LSE)

Belt Conveyors Separating Fact from Fiction Richard Enning Bob Schaefer Steve Timmer

Abstract. Background and Study Description

NREL s PHEV/EV Li-ion Battery Secondary-Use Project

Presenters: Mr. Moresh Kolhe Mr. Babu Bhondave Mahindra & Mahindra (AFS) Copyright 2012 Mahindra & Mahindra Ltd. All rights reserved.

A Modified Lower Hybrid Coupler for TPX.

Food Service Technology Center

Project Title: Contract Number: Milestone Number: Report Date: Contract Contact: Phone: Congressional District: Executive Summary:

Food Service Technology Center

3QFY2018 Financial Results. Quarter Ended 31 December 2017

Mobile and Locomotive Cranes

AND HYDRAULIC STUDIES

Experience with Small Turbomachinery in a 400 Watt Refrigerator

Varidrive Set with Metal Chain INSTRUCTIONS

1QFY2018 Financial Results. Quarter Ended 30 June 2017

Description of a Solder Pulse Generator for the Single Step Formation of Ball Grid Arrays

ECH MIRROR INTERFACE TANK FOR 110 GHz, 1 MW GYROTRON

HIGH LEVEL WASTE TANK CLOSURE PROJECT AT THE IDAHO NATIONAL ENGINEERING AND ENVIRONMENTAL LABORATORY

P.O. BOX LITTLE ROCK, AR FAX #: HIRERIGHT CUSTOMER #: MAVTRAN

INLINE MONITORING OF FREE WATER AND PARTICULATE CONTAMINATION OF JET A FUEL

INSTITUTE OF TECHNOLOGY

Project Title: Lowertown Ballpark (CHS Field) Solar Arrays Contract Number: EP4-34 Milestone Number: 1 Report Date: June 21, 2016

S-80,266. Oleg M. Kotlyar

PRODUCTION HYDRAULIC PACKER FIELD TEST

711. USE OF VEHICLES ON SCHOOL BUSINESS

Food Service Technology Center

GA A23904 RESEARCH ACTIVITIES AT GENERAL ATOMICS

Food Service Technology Center

SEPTEMBER 22, 2010 UNITEC PARTS COMPANY INSTALLATION PROCESS MANUAL UT-ID ABA6940CD Folding Door Restrictor Specifications

Food Service Technology Center

Additional Transit Bus Life Cycle Cost Scenarios Based on Current and Future Fuel Prices

REPORT NUMBER: 114-CAL SAFETY COMPLIANCE TESTING FOR FMVSS No. 114 THEFT PROTECTION AND ROLLOWAY PREVENTION

Zap 5LX-S. Model No.: BH9938U-5-2. Questions or Concerns? (855)

REPORT NUMBER: NCAP305I-MGA NEW CAR ASSESSMENT PROGRAM (NCAP) FMVSS No. 305 Indicant Test

ELECTRIC POLICY INTRODUCTION CHAPTER I GENERAL



AARMAC TRANSPORT, INC nd Ave SW MINOT, ND 58701

ENERGY ANALYSIS OF A POWERTRAIN AND CHASSIS INTEGRATED SIMULATION ON A MILITARY DUTY CYCLE

Alcohol & Substance Abuse Information. Please complete the following six pages. Sign all forms where highlighted in yellow

Air Curtain. Installation, Operating and Maintenance Instructions

APRIL 2017 UNITEC PARTS COMPANY INSTALLATION PROCESS MANUAL UT-ID ABA6940CD Folding Door Restrictor Specifications

High-Level Waste Mechanical Sludge Removal at the Savannah River Site F Tank Farm Closure Project

ADDENDUM NO. 1. April 6, Project: Gas and Diesel Bid for School System Stations

Cooling System Simulation for Indian Utility Vehicle using COOL3D

Start a Franchise In 10 Steps

Personal Information Office use only Recruiting Terminal ID: Domicile Terminal Contact Information CDL Information Endorsements: Driver Information

Internal PVC Rod-Style Fluid Level Sensor

Toro Sprayer Calibration Tool

Qualification of Box HEPA Filters for Nuclear Applications

Market Briefing: S&P 500 Bull & Bear Markets & Corrections

REPORT NO. TR-P NC SAFETY COMPLIANCE TESTING FOR FMVSS 223 REAR IMPACT GUARDS 2007 TRANSFREIGHT TECHNOLOGY NHTSA NO.

PEP Review HIGH-PURITY ISOBUTYLENE FROM T-BUTANOL BY LYONDELLBASELL PROCESS By Sumod Kalakkunnath (February 2013)

C&J Bus Lines. Driver Employment Application

2011 NDIA GROUND VEHICLE SYSTEMS ENGINEERING AND TECHNOLOGY SYMPOSIUM POWER AND MOBILITY (P&M) MINI-SYMPOSIUM AUGUST 9-11 DEARBORN, MICHIGAN

US Economic Indicators: Industrial Production & Capacity Utilization

Comparison of price incentive models for locally matched electricity networks. Appendix C: Private Wires - Legal Definitions

CREEP PERFORMANCE TEST REPORT. Rendered to: TREX COMPANY LLC. Seclusions Composite Privacy Fence System TYPE: Composite Fence System

FINAL REPORT CATHODIC PROTECTION EVALUATION. 42-Inch Water Transmission Pipeline Contract 1 Station 0+00 to South Texas Water Authority

SAFETY COMPLIANCE TESTING FOR FMVSS NO. 225 CHILD RESTRAINT ANCHORAGE SYSTEMS LOWER AND TETHER ANCHORAGES

STATE OF NORTH CAROLINA

Service Guide JATCO Environmental Protection Tank Model J-7000

Structurlam Mass Timber Corporation Revised October 11, 2018

SANDAG Vanpool Program Guidelines as of February 2018

User Guide. Digital Shipping Scale S150

Federal Motor Carrier Safety Regulations

EXECUTIVE ORDER D Relating to Exemptions Under Section 27156

FAQ. Do I have a choice for a service provider?

REPORT NUMBER: 114-CAL SAFETY COMPLIANCE TESTING FOR FMVSS No. 114 THEFT PROTECTION AND ROLLOWAY PREVENTION

Transcription:

Revision 0 TANK RISER SUSPENSION SYSTEM CONCEPTUAL DESIGN (U) R. F. Fogle September 15, 2002 Westinghouse Savannah River Company LLC Savannah River Site Aiken, South Carolina 29802

This document was prepared in conjunction with work accomplished under Contract No. DE-AC09-96SR18500 with the U. S. Department of Energy. DISCLAIMER This report was prepared as an account of work sponsored by an agency of the United States Government. Neither the United States Government nor any agency thereof, nor any of their employees, makes any warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product or process disclosed, or represents that its use would not infringe privately owned rights. Reference herein to any specific commercial product, process or service by trade name, trademark, manufacturer, or otherwise does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States Government or any agency thereof. The views and opinions of authors expressed herein do not necessarily state or reflect those of the United States Government or any agency thereof. This report has been reproduced directly from the best available copy. Available for sale to the public, in paper, from: U.S. Department of Commerce, National Technical Information Service, 5285 Port Royal Road, Springfield, VA 22161, phone: (800) 553-6847, fax: (703) 605-6900 email: orders@ntis.fedworld.gov online ordering: http://www.ntis.gov/help/index.asp Available electronically at http://www.osti.gov/bridge Available for a processing fee to U.S. Department of Energy and its contractors, in paper, from: U.S. Department of Energy, Office of Scientific and Technical Information, P.O. Box 62, Oak Ridge, TN 37831-0062, phone: (865)576-8401, fax: (865)576-5728 email: reports@adonis.osti.gov

TABLE OF CONTENTS EXECUTIVE SUMMARY... 5 BACKGROUND... 5 CONCEPTUAL DESIGN... 6 CONCLUSION... 14 ACKNOWLEDGEMENTS... 14 REFERENCES... 14 Appendix A... 15 Appendix B... 20 Appendix C... 26 Appendix D... 29 TABLE OF FIGURES Figure 1: Rail installation in a riser... 6 Figure 2: Riser with 4 tube installed... 7 Figure 3: Sectioning equipment to fit inside tank... 8 Figure 4: Failed equipment completely removed from tank... 9 Figure 5: Inserting failed equipment into a tank using the guide rail system... 10 Figure 6: Lowering failed equipment into the tank... 11 Figure 7: Failed equipment sections hanging inside the tank... 12 Figure 8: New equipment installed... 13 September 15, 2002 Page 4 of 30

EXECUTIVE SUMMARY A team of engineers from High Level Waste (HLW), the Savannah River Technology Center (SRTC), and Project Engineering and Construction Division (PE&CD) explored ways of more effectively utilizing the HLW tank s risers during waste removal and closure activities. Currently, some of the risers are being used to store failed and contaminated equipment. To make those risers available for tank operation, failed equipment must be moved out of the tank and relocated or disposed of appropriately. Disposing of contaminated equipment is a time consuming and expensive process. This report describes the Tank Riser Suspension System (TRSS). It will allow failed equipment to be stored inside of the tank while making riser space available for other tank process equipment. In addition, the TRSS will permit disposing of failed equipment in the tank as part of tank closure activities. BACKGROUND High-level radioactive liquid wastes are received, stored, and processed in large underground tanks at SRS. Five different types of tanks were built at SRS. Four of the five tanks are shown in Appendix A. Each type is unique and incorporates the lessons learned from past designs. There are risers on or integral with the top of each tank. Each tank type has a unique riser configuration as shown in Appendix B. The risers permit access to the tank and the tank s annulus. They are used primarily for the installation of pumps, cooling equipment, instrumentation probes, measuring devices, monitoring tools, and samplers. Examples of pumps used in the waste tanks can be found in Appendix C. Type I Waste tanks have 15 risers, including the center riser. Type II Waste tanks have 28 risers. Type III Waste Tanks and Type IIIA Waste tanks have 40 risers. Type IV Waste tanks have 7 risers, including the center riser. The inside diameter (ID) of typical risers normally ranges between 23 and 42, but some of them are very large. For example, the ID of the center riser of a Type IV tank is approximately 9 feet. A drawing of the cross section of a typical riser can be found in Appendix D. There are a limited number of risers on a tank top. Efficiently utilizing them is crucial for successful waste removal and tank disclosure operations. Some of the risers are occupied by failed and contaminated equipment. To make those risers available for tank operation, the stored failed equipment must be moved out of the tank and disposed of appropriately. Disposing of contaminated equipment is a time consuming and expensive process. An alternative is the TRSS. It permits storing equipment inside of the tank while making the riser space available for other tank process equipment. This option will allow disposing of failed equipment in the tank during tank closure and may significantly reduce personnel radiation exposure and waste disposal costs. September 15, 2002 Page 5 of 30

CONCEPTUAL DESIGN The TRSS is based on the concept of hanging failed equipment with cables in a riser. The major components of the TRSS include the following: 1. A riser insert with rail guides 2. A clamp and rail attachment device 3. A lifting bail/guide block 4. A remotely detachable crane hook The TRSS utilizes a riser insert with attached rails for hanging equipment as shown in Figure 1. The insert must be constructed of at least 2 sections with each part having a rail section. Figure 1 shows an insert consisting of 2 halves. The insert is installed into an empty riser using a crane. The rails extend into the tank and curve up to be parallel with the tank ceiling. In this way, the failed equipment can be stored away from the riser opening. By doing this, the riser is available for normal tank activities as well as for storage. Figure 1: Rail installation in a riser September 15, 2002 Page 6 of 30

If a pump or other equipment should fail in a riser, the first step is to remove the equipment from the riser. A clamp and rail attachment device or devices must be designed to grip the various sizes of equipment used in riser. As an example, Figure 2 shows a simple 4-inch tube that is to be stored in the tank as failed and contaminated equipment. A clamping device is shown securing the failed equipment. The lifting bail/guide block assembly is attached to handle the failed equipment. The equipment is removed from the riser by using a crane. Figure 2: Riser with 4 tube installed September 15, 2002 Page 7 of 30

The failed equipment cannot extend into the waste as this may cause an interference with tank closure activities. Equipment that is too long will have to be size-reduced. With the failed equipment held by a crane, the clamping device is loosened. The crane can then remove an appropriate length from the tank. The clamp secures the equipment remaining in the tank. The upper section of the failed device is cut as shown in Figure 3 while the lower section is held firmly in place by the clamp. Figure 3: Sectioning equipment to fit inside the tank September 15, 2002 Page 8 of 30

The removed section is monitored for radioactivity. It may or may not be stored in the tank based on the radiological survey. Assuming it is to be put back in the tank, it is temporarily stored on the tank top. The remaining section in the riser is then lifted out of the tank and is cut into smaller sections and surveyed. Once the equipment removal process is complete, the TRSS is installed in the riser as shown in Figure 4. The sections of failed equipment are then ready to be lifted by the crane and returned to the tank. Figure 4: Failed equipment completely removed from tank September 15, 2002 Page 9 of 30

Relocation into the tank will require a crane hook with a remote de-coupling capability as shown in Figure 5. The equipment to be returned is positioned onto the guide rail and lowered into the tank s riser. Figure 5: Inserting failed equipment into a tank using the guide rail system September 15, 2002 Page 10 of 30

The guide block must be hinged to allow the equipment to transition the curved part of the TRSS rail as shown in Figure 6. Figure 6: Lowering failed equipment into the tank September 15, 2002 Page 11 of 30

When the returned equipment reaches the end of the curved section of rail, the crane hook de-couples from it as shown in Figure 7. This process is repeated for all sections being stored in the tank. Figure 7: Failed equipment sections hanging inside the tank September 15, 2002 Page 12 of 30

Once the storage process is completed, new process equipment can be lowered into the riser as shown in Figure 8. Figure 8: New equipment installed September 15, 2002 Page 13 of 30

CONCLUSION The Tank Riser Suspension System would be a great asset to the tank farm operation and is highly recommended. It would allow HLW to store several pieces of equipment and simultaneously use the tank s riser in closure activities. However, working on tank tops and utilizing riser space for hanging multiple components presents significant engineering challenges: Designing the insert and rail system Designing a universal clamping device or a suite of clamping devices Developing a remotely detachable crane hook Many factors and safety issues must be addressed during the development of design requirements. They include: Performing load limit calculations for riser and tank top support of suspended equipment Ensuring that suspended equipment won t interfere with tank closure efforts Ensuring that suspended equipment won t interfere with existing equipment inside the tanks ACKNOWLEDGEMENTS A special thanks to the following team members for their creativity in providing a solution to a problem in HLW tank closure activities: Don Pak, SRTC Jonathan Thomas, HLW/Waste Removal Project Randall Forty, PE&CD/Design Execution Toby Hess, HLW/FTF Waste Removal Project Liaison Wade Faires, PE&CD/Structural Mechanics REFERENCES 1. Pak, D. J., Eberl, K. R., Baseline Technology Report For the Tank Riser Suspension System (U) WSRC-TR-2001-00441, Savannah River Site, Aiken, SC 29808. 2. Pak, D. J., Eberl, K. R., Functions and Requirements for the Tank Riser Suspension System (U) WSRC-TR-2001-00442, Savannah River Site, Aiken, SC 29808. September 15, 2002 Page 14 of 30

Appendix A September 15, 2002 Page 15 of 30

Figure 1A: Type I Waste Tank September 15, 2002 Page 16 of 30

Figure 2A: Type II Waste Tank September 15, 2002 Page 17 of 30

Figure 3A: Type IIIA Waste Tank September 15, 2002 Page 18 of 30

Figure 4A: Type IV Waste Tank September 15, 2002 Page 19 of 30

Appendix B September 15, 2002 Page 20 of 30

Figure 1B: Typical Type I Waste Tank Riser Layout September 15, 2002 Page 21 of 30

September 15, 2002 Page 22 of 30

Figure 2B: Typical Type II Waste Tank Riser Layout September 15, 2002 Page 23 of 30

Figure 3B: Typical Type III Waste Tank Riser Layout September 15, 2002 Page 24 of 30

Figure 4B: Typical Type IV Waste Tank Riser Layout September 15, 2002 Page 25 of 30

Appendix C September 15, 2002 Page 26 of 30

Figure 1C: Telescoping Transfer Jet Pump September 15, 2002 Page 27 of 30

Figure 2C: Telescoping Transfer Pump September 15, 2002 Page 28 of 30

Appendix D September 15, 2002 Page 29 of 30

Figure 1D: Typical Type 1 Riser Cross Section September 15, 2002 Page 30 of 30