Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS

Similar documents
Guidelines for connection of generators:

Jemena Electricity Networks (Vic) Ltd

Appendix A2: Technical Requirements for Distributed Generators > 10 kw to be Connected to Kitchener-Wilmot Hydro Inc. s Distribution System

GUIDELINES FOR OPERATING, METERING AND PROTECTIVE RELAYING FOR. NET METERED SYSTEMS UP TO 50 kw AND BELOW 750 VOLTS

Net Metering Interconnection Requirements

Guideline for Parallel Grid Exit Point Connection 28/10/2010

Net Metering Interconnection Requirements. Customer Generation Capacity Not Exceeding 100 kw. Date: Version: 1

SA Power Networks Commissioning Witnessing Checklist

GUIDELINES FOR GRID INTERCONNECTION OF SMALL POWER PROJECTS IN TANZANIA

DER Commissioning Guidelines Community Scale PV Generation Interconnected Using Xcel Energy s Minnesota Section 10 Tariff Version 1.

Standards, Procedures and Policies for Grid Connection

GUIDE FOR MICROGENERATION INTERCONNECTION TO CITY OF MEDICINE HAT ELECTRIC DISTRIBUTION SYSTEM

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

Large Embedded Generation User Guide A

Aurora Energy Limited. Network Connection Requirements (NS5.1)

TECHNICAL SPECIFICATION FOR INDEPENDENT POWER PRODUCERS. NB Power Customer Service and Distribution. June 2008

MICHIGAN ELECTRIC UTILITY

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems

Technical Requirements for Renewable Energy Power System

INTERCONNECTION STANDARDS FOR PARALLEL OPERATION OF SMALL-SIZE GENERATING FACILITIES KILOWATTS IN THE STATE OF NEW JERSEY

Enquiry Form (Non-Registered Generator With Capacity less than 5 MW)

Net +Plus Connection Code

Substation LV AC Supplies. Document Number: 1-11-FR-04

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management

Document Requirements for Engineering Review- PV Systems v1.1 12/6/2018

MICHIGAN ELECTRIC UTILITY

Connecting your business diesel generation

CLP POWER HONG KONG LIMITED. SUPPLY RULES March 2001

Unified requirements for systems with voltages above 1 kv up to 15 kv

Copyright 2003 Advanced Power Technologies, Inc.

Summary of General Technical Requirements for the Interconnection of Distributed Generation (DG) to PG&E s Distribution System

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

Document Requirements for Engineering Review PV Systems v1.0 6/9/2017

Small Electrical Systems (Microgrids)

MICHIGAN ELECTRIC UTILITY

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program.

Louisville Gas and Electric Company

APPLICATION FOR INSTALLATION OF SMALL SCALE EMBEDDED ELECTRICITY GENERATION

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655)

E-15 Uninterruptible Power Systems (UPS)

Electric Networks/Ina Lehto Updated Original 12/2011

DG SYNCHRONIZING &AMF PANEL

RULES FOR CUSTOMER INTERCONNECTION OF ELECTRIC GENERATING FACILITIES

GRID CONNECTION ISSUES FOR DISTRIBUTED GENERATION REVIEW & STANDARDS

3. Customer shall provide space for metering equipment and meter base as per Springville City Power requirements.

Company Directive STANDARD TECHNIQUE: SD4O/1. Standard HV Connection Arrangements

STATE OF NORTH DAKOTA DISTRIBUTED GENERATION INTERCONNECTION REQUIREMENTS TABLE OF CONTENTS

SOUTHERN PUBLIC POWER DISTRICT DISTRIBUTED GENERATION STANDARD

EDS SUBSTATION LVAC SUPPLIES

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Distributed Generation

INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY

Distribution Code Part 4: Distributed Generation Requirements

NORRIS PUBLIC POWER DISTRICT DISTRIBUTED GENERATION (DG) INTERCONNECTION

EC Forum on Model Approaches to Distribution Pricing. June 2009

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

KD LV Motor Protection Relay

DAKOTA ELECTRIC ASSOCIATION DISTRIBUTED GENERATION INTERCONNECTION REQUIREMENTS

APPLICATION ELECTRICITY SERVICES. APPLICATION FOR THE CONNECTION OF SMALL SCALE EMBEDDED GENERATION Page 1

Micro Embedded Generating Units (0-30 kva)

Guideline for Using IEEE 1547 for Solar PV Interconnection Page 1

Interconnection Requirements for Generation Systems

UBC Technical Guidelines Section Edition Commissioning of Electrical Systems Page 1 of 5

Overview of State Distributed Generation Interconnection Rules

INTERCONNECTION for GENERATING FACILITIES Up to 20 MW

Technical Standard - TS 129. Small Inverter Energy Systems (IES) - Capacity not exceeding 30kW. SA Power Networks. Published: November 2017

AS/NZS AS/NZS

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS.

C1000 Series Automatic Cap Bank

A Distribution Network Operator s View of Connecting Microgeneration For RegenSW - South Devon College 07 September 2011

ELECTRICAL SERVICE TECHNICIAN EXAMINATION 16 September 2017 QUESTION AND ANSWER BOOKLET

NRS 097-series / Grid Code Discussion:

A TRIAL OF ALTERNATIVES TO DIRECTIONAL OVERCURRENT PROTECTION ON GRID TRANSFORMERS TO IMPROVE THE NETWORK CAPACITY TO ACCOMMODATE REVERSE POWER FLOW

Model ESV Uninterruptible Power System 1.5 KVA/KW KVA/KW Single Phase

Technical Guidance for Customer Export Limiting Schemes

ATyS d M Remotely operated Transfer Switching Equipment from 40 to 160 A

Technical Requirements for Export Limiting Schemes

Renewable sources of electricity a brief overview

E-15 Uninterruptible Power Systems (UPS)

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Marina Bay Sands Guidelines for Electrical and Wiring Service

IFC Workshop on Distributed Generation, 13 February 2013, Moscow, Russia

INTERCONNECTION REQUIREMENTS POLICY

Interconnection Feasibility Study Report GIP-084-FEAS-R2

TECHNICAL REQUIREMENTS FOR PARALLEL OPERATION OF MEMBER-OWNED GENERATION

Comparison of Indian Electricity Rules, 1956 Vs CEA (Measures relating to Safety and Electric Supply) Regulations, 2010

Effective discrimination of protective devices

University of Houston Master Construction Specifications Insert Project Name

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

Construction and Connection of Street Light Assets

NORTH CAROLINA INTERCONNECTION REQUEST APPLICATION FORM. Utility: Duke Energy Progress

SUBSTATION INTERLOCKING SCHEMES

SECTION MOTOR CONTROL

NET METERING PROGRAM. Technical Interconnection Requirements

TD-2306B-001, Interconnecting Large 2-20MW Generation Systems. Employees involved with generation interconnection on electric distribution circuits.

AS/NZS :2016. Grid connection of energy systems via inverters AS/NZS :2016. Part 1: Installation requirements

MICHIGAN ELECTRIC UTILITY

90.2 Scope. The installation of electrical conductors, equipment and raceways for:

Enquiry Form for Micro and Small Generators 5MW and Less

Exelon Energy Delivery Interconnection Guidelines for Generators 2 MVA or less

Transcription:

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS 1. PURPOSE AND SCOPE OF THIS DOCUMENT... 3 2. DEFINITIONS... 3 3. CONNECTION METHODS... 3 4. NETWORK CAPABILITY ISSUES... 3 4.1. Network Congestion... 3 4.2. Power Factor... 4 4.3. Upstream Voltage Regulators... 4 4.4. Ripple Signal Absorption... 4 5. GENERAL REQUIREMENTS... 4 5.1. Fault Levels... 4 5.2. Voltage Regulation... 4 5.3. Voltage Fluctuations... 4 5.4. DC Injection... 4 5.5. Harmonics... 4 5.6. Means of Isolation... 5 5.7. Synchronising... 5 5.8. SCADA Monitoring... 5 6. ISLANDING... 5 7. EARTHING... 6 7.1. Direct Connected Generators... 6 7.2. Generators connected via a Transformer.... 6 8. PROTECTION... 6 8.1. Protection Objectives... 6 8.2. Mandatory Protection Requirements... 7 8.3. Direct Connected LV Generation... 7 8.4. Generators Connected via Transformers... 7 8.5. Vector Shift Protection... 8 8.6. HV Fuse Switch Intertrip... 8 8.7. Reclosing Coordination... 8 8.8. Short Term Paralleling... 8 8.9. Protection Location and Indication... 8 8.10. Protection Relay Standards... 8 8.11. Trip Circuit Supervision... 8 8.12. DC Trip Supply... 9 9. TESTING... 9 10. METERING... 9 Page 1 of 10

11. OPERATIONAL REQUIREMENTS... 9 11.1. Operating Personnel... 9 11.2. Communications... 9 11.3. Reconnection... 9 11.4. Isolation... 9 11.5. Power factor... 10 12. RECORDS AND INFORMATION... 10 12.1. GIS Information... 10 12.2. Schematic Diagrams... 10 12.3. Manuals... 10 12.4. Protection Settings... 10 12.5. Test Results... 10 12.6. System Operator (Transpower) Notification... 10 Issued: 10 August 2009 Expires: 10 August 2011 Page 2 of 10

1. PURPOSE AND SCOPE OF THIS DOCUMENT This document covers Aurora s technical requirements for electrical generators that can connect to, and operate in parallel with the Aurora distribution network. It includes standby generators designed to synchronise with the Aurora network, for a short time, to facilitate a no-break transfer of load on network supply restoration. Generators at installations that are not designed to operate in parallel with the Aurora network shall have changeover facilities that comply with the requirements of AS/NZS 3010 which will ensure such generators cannot be connected to the Aurora network. 2. DEFINITIONS (DG) Distributed Generation: - Electrical generation facility capable of operating in parallel with the Aurora network. (EGR): - Electricity Governance Rules (NVD): - Neutral Voltage Displacement (PCC) Point of Common Coupling: - Is the point in the network electrically nearest to the consumer/generator at which other consumers are or may be connected. (SM-EI) Safety Manual Electricity Industry: - This document defines the requirements for safety in New Zealand Electricity Generation Transmission and Distribution Industry. 3. CONNECTION METHODS Only induction generators and inverter connected generation with a capacity up to 30kVA is permitted to connect directly to the Aurora low voltage network. All other connections shall be to the EHV or HV networks via a transformer. Connections greater than 10kVA shall be three phase. Synchronous generators can connect to the HV network either directly or via a transformer. Direct HV connection is not recommended due to the possibility of excessive generator damage if the generator should develop an earth fault. All connections to the 33kV and 66kV networks must be via transformers. All DG installations connected to the Aurora network, where the primary purpose is to export energy into the Aurora network, shall be connected via a circuit breaker on the Aurora side of any generation transformers. 4. NETWORK CAPABILITY ISSUES 4.1. Network Congestion Aurora will determine if the connection of the proposed DG will result in thermal ratings of Aurora s equipment being exceeded under all expected operating conditions. If equipment ratings will be exceeded then network upgrades will be required to accommodate the DG or alternatively it may be possible to avoid equipment overloads by imposing operating constraints on the DG e.g. restricting generator output during circuit outages or under particular loading conditions. Issued: 10 August 2009 Expires: 10 August 2011 Page 3 of 10

4.2. Power Factor Distributed generation may reduce the load power factor at Transpower grid exit points. This can result in penalty charges from Transpower and non-compliance with the EGR. If the power factor is unacceptable then the cost of Transpower penalty charges or the cost of installing power factor correction will be allocated to the generators that are causing the problem. 4.3. Upstream Voltage Regulators If the DG site has an HV neutral earth reference and is connected to a three phase HV feeder supplied by voltage regulators, then the voltage regulator must consist of a three phase regulator or three single phase units controlled to have each unit on the same tap. This is necessary to avoid circulating zero sequence currents that can cause the mal-operation of earth fault protection. 4.4. Ripple Signal Absorption Aurora operates ripple injection systems on its network. Generation can result in a reduction in the ripple signal level. If ripple signal reduction to an unacceptable level results from the connection of new generation then the owner of the generation will be required to fund mitigation measures. 5. GENERAL REQUIREMENTS 5.1. Fault Levels The connection of DG shall not result in the fault rating of any Aurora equipment being exceeded. The normal design fault level on Aurora s 6.6kV, 11kV, 33kV and 66kV networks is 25kA but in certain 11kV and 6.6kV areas there may be equipment with a lower rating (usually dropout fuses with a 13kA rating). The equipment within the DG installation must be capable of withstanding the fault current supplied by the DG and the Aurora network. 5.2. Voltage Regulation The DG shall not actively regulate the voltage at the PCC. The DG shall not cause the voltage to other installations on the Aurora s network to go outside the range specified in the Electricity Regulations. 5.3. Voltage Fluctuations The DG shall not create objectionable flicker for other customers connected to the Aurora network. Flicker is considered objectionable if the limits prescribed in AS/NZS 6100 are exceeded at the PCC. 5.4. DC Injection The DG and its interconnection system shall not inject a dc current greater than 0.5% of the full rated output current of the generation at the point of DG connection. 5.5. Harmonics The harmonics introduced into the Aurora network by any generation installation shall not exceed the limits defined in NZECP36 New Zealand Code of Practice for Harmonic Levels The harmonic current limits of inverter connected generation shall comply with the requirements of AS477.2 (2005) Clause 4.5. Issued: 10 August 2009 Expires: 10 August 2011 Page 4 of 10

5.6. Means of Isolation Every DG plant must have a means of isolation that is capable of disconnecting the generating plant in-feed from the Aurora network. The isolation switch or circuit breaker must be suitably labelled and lockable, in the open position, with a standard Aurora padlock. Access to the points of isolation must be kept clear and unobstructed. Aurora s authorised contractors shall have access to the means of isolation without undue delay. 5.7. Synchronising Automatic synchronising must be provided at the generator circuit breakers. Check synchronising or interlocks shall be fitted to any other breaker that could connect the DG to the Aurora network. 5.8. SCADA Monitoring When the primary purpose of the generation is to inject energy into the Aurora network it shall be monitored by the Aurora SCADA system. This will require the installation of an appropriate SCADA RTU and communication facilities. The minimum information to be telemetered via the RTU is: Status of circuit breakers Voltage at the PCC or other agreed location The kw and kva output of the generation for each generation type (e.g. wind, hydro, pv) Status of protection relay outputs 6. ISLANDING Normally Aurora does not provide for intentional islanding and distributed generators are not required to design their systems to supply islanded sections of the Aurora network. Protection and switching operations can result in distributed generators attempting to supply an islanded section of the Aurora network. This is an undesirable because; Voltage and frequency provided to consumers supplied from the islanded section of the network will be unpredictable creating the possibility of damage to consumer equipment. Islanding may cause a hazard to maintenance workers or the public by causing a circuit to remain energised when it has been assumed to be disconnected from all energy sources The generators connected to the island could be damaged when the island is reconnected to the Aurora network. An out-of-synchronism reconnection may also result in further outages on the Aurora network. Islanding may interfere with the restoration of normal service to neighbouring Aurora consumers. Aurora requires that DG must disconnect for faults on the Aurora circuit that the generation is connected to within three seconds of the fault occurring. If the formation of an island is possible for faults upstream of the circuit the generation is connected to, then special operating procedures or protection inter-tripping may be required. DG must not, under any circumstances, re-energise parts of the Aurora network that have been disconnected from the rest of Aurora s network. Issued: 10 August 2009 Expires: 10 August 2011 Page 5 of 10

7. EARTHING 7.1. Direct Connected Generators The earthing of generators directly connected to the Aurora LV network shall be in accordance with the requirements of AS/NZS 3000:2007. Generators connected directly to the Aurora HV network shall have the generator neutral earthed via a suitable resistor or reactor. 7.2. Generators connected via a Transformer. The earthing requirements for generators connected via a transformer are dependent on the generator category and are detailed below. Category 1 - Export required When the DG will export energy into the Aurora network then the DG installation must provide a neutral earth reference or neutral voltage displacement (NVD) protection on the Aurora side of the transformer used to connect the generator to the Aurora network. The choice between neutral point earthing and NVD protection will depend on the network configuration and protection systems in the vicinity of the DG connection. Neutral earth references on the 33kV and 66kV networks supplied from the Cromwell, Clyde or Frankton grid exit points shall include neutral earthing resistors to minimise the magnitude of earth fault currents. Category 2 - No export and unable to sustain an island When the distributed generation is connected to the LV side of a standard consumer distribution transformer and there is no requirement to export energy into the Aurora network and it is not likely the generator can supply a viable island, then an HV earth reference shall not to be provided. The formation of a viable island is considered unlikely if the generator maximum output is less than half the minimum load on the HV feeder supplying the DG installation. Category 3 - No export but can sustain an island When the distributed generation is connected to the LV side of a standard consumer distribution transformer and there is no requirement to export energy into the Aurora network and it is possible for the generation to supply a viable island then an effective HV earth reference shall not be provided. However if the generator is going to operate in parallel with the Aurora network for more than 500 hours per year NVD protection shall be provided. 8. PROTECTION 8.1. Protection Objectives Aurora requires protective equipment to be fitted to the DG to achieve the following objectives: Inhibit connection of the generator to the Aurora network unless all phases of Aurora supply are energised and within acceptable frequency and voltage limits. Disconnect the generator from the Aurora network when a system abnormality results in an unacceptable deviation in voltage or frequency at the connection point. Disconnect the generator from the Aurora network for faults on the Aurora network. Issued: 10 August 2009 Expires: 10 August 2011 Page 6 of 10

8.2. Mandatory Protection Requirements All DG installations shall have the following protection External system over and under voltage External system over and under frequency External system phase unbalance Overcurrent External system voltage and phase balance shall be monitored immediately adjacent to the circuit breaker making the parallel connection to ensure the supplies are healthy at that point. The protection specified in this document is to ensure Aurora s network is adequately protected. It is the responsibility of the DG owner to ensure DG assets are appropriately protected. 8.3. Direct Connected LV Generation Installations with LV generation that is directly connected to the Aurora LV network will be connected via LV HRC fuses rated to carry the capacity of the connection. Anti islanding protection of inverter connected generators shall be in accordance with the requirements of AS 4777.3 The specific requirements for the direct connection of an induction generator have yet to be established. 8.4. Generators Connected via Transformers The protection required for generation connected via transformers depends on the generation category and is detailed below. Category 1 - Export Required When export of energy onto the Aurora network is required the generation connection is required to have either an effective earth reference or provide NVD protection as per the requirements of Section 7.2 When an effective earth reference is provided, residual current operated earth fault protection shall be fitted. Where no effective earth reference is provided then NVD protection shall be provided. NVD protection shall only be the backup method of clearing earth faults on the Aurora circuit supplying the DG installation. The primary method of clearing earth faults shall be provided by other means such as inter-tripping. Additional protection may be required at the DG site or at other locations on the Aurora network to maintain the pre-existing standard of network reliability and security. Category 2 - No export and cannot sustain an island In the situation where the DG is used to supply customer load, is never required to export and the minimum load the generator will attempt to pickup if the DG becomes islanded is twice the rating of the generator then the following protection is required: Reverse Power Vector Shift with minimum import control (see Section 8.5) OR HV fuse switch inter-trip (see Section 8.6) Category 3A - No export, can sustain an island and annual operating hrs <500 When the DG is used to supply customer load, is never required to export and the minimum load the generator will attempt to pickup if it becomes islanded is less than twice the rating, and the generator will operate in parallel with the Aurora network for less than 500 hrs per year then the protection required can be the protection specified for either a Category 2 or Category 3B situation. Issued: 10 August 2009 Expires: 10 August 2011 Page 7 of 10

Category 3B - No export, can sustain an island and annual operating hrs >500 When the DG is used to supply customer load, is never required to export and the minimum load the generator will attempt to pickup if it becomes islanded is less than twice the rating, and the generator will operate in parallel with the Aurora network for more than 500 hrs per year then the following protection is required: Reverse Power NVD Protection. 8.5. Vector Shift Protection When utilising vector shift protection, the load change on the generator generally needs to be between 10% and 20% of the generator rating to ensure appropriate operation. To ensure this load shift will occur, it is normally necessary to operate the generator with a minimum import. 8.6. HV Fuse Switch Intertrip In situations where DG is connected to the LV side of a distribution transformer protected by an HV fuse switch one method of ensuring the generation will be disconnected for faults between the fuse switch and the transformer or the transformer HV windings is to provide an intertrip signal from an auxiliary switch on the fuse switch to the consumers incoming LV circuit breaker. 8.7. Reclosing Coordination Where the DG is connected via a circuit subject to auto reclosing it is important that the DG disconnect from the network before a reclose is attempted. An out-of-synchronism reclose can cause serious damage to rotating generators and motors. Most Aurora reclosers have a dead time setting of three seconds but the exact setting for each location requires confirmation. Modern field reclosers normally have a live line blocking facility which can be enabled if DG is supplied from the recloser. This facility shall only be considered as a backup to anti-islanding protection. 8.8. Short Term Paralleling At sites where the purpose of the DG connection is to only allow infrequent transfer of load from a generator to the Aurora network then reduced protection requirements can apply at the discretion of Aurora but will not be less than the requirements specified in Section 8.2. The paralleling time shall be automatically controlled to a maximum of 5 minutes. 8.9. Protection Location and Indication Protective equipment must be located in a suitable cabinet that affords immediate access by the DG operator but is secure from interference by unauthorised personnel. Protection systems shall indicate the reason for all protection operations that result in a circuit breaker trip. 8.10. Protection Relay Standards All protection relays associated with DG installations that have voltage and current inputs derived from a primary source rated greater than 415 volts shall be distribution quality relays compliant with IEC 60255. Protection devices monitoring 230/400 volt primary quantities can be industrial grade relays or the protection functions can be provided by a micro-processor generator controller. 8.11. Trip Circuit Supervision Any HV circuit breakers required to disconnect DG from the Aurora network shall be fitted with trip circuit supervision. Issued: 10 August 2009 Expires: 10 August 2011 Page 8 of 10

8.12. DC Trip Supply All protection functions shall operate with a dc voltage down to 80% of the nominal dc voltage. If there is a failure of any supplies to protective equipment which will inhibit its correct operation the generation shall be automatically disconnected and shutdown or at sites where there is competent supervision, initiate an audible or visual alarm. 9. TESTING All testing and associated costs are the responsibility of the DG owner. Aurora reserves the right to have a representative witness the testing. All commissioning tests shall be carried out in accordance with a written test plan and procedures that have been approved by Aurora prior to commissioning. The commissioning tests shall include a full functional test of the auto synchronisation equipment prior to the first synchronisation. All protection functions shall be tested including all interlocks and the facilities to ensure the generator is disconnected from the Aurora network in the event of an Aurora supply failure. The owner of the DG shall keep written records of test results and protection settings and a copy of these records shall be sent to Aurora. Periodic tests shall be carried out to verify the settings and serviceability of the protection. These tests shall be carried at out at intervals not exceeding three years. The results of these tests shall be available for inspection by Aurora. 10. METERING Metering of the DG injection must be certified and comply with the requirements of the EGR. DG installations that export more than 500kW shall provide meter pulses to the Aurora SCADA RTU at the site. The meter pulses will be used for load management purposes by Aurora. 11. OPERATIONAL REQUIREMENTS 11.1. Operating Personnel The DG owner shall designate persons to operate their generation. These operators shall be competent and appropriately trained. They shall follow written operating instructions and the sections relating to interfacing with the Aurora network shall be approved by Aurora. 11.2. Communications There shall be adequate, reliable and documented means of communication between Aurora s System Controllers and the operators of DG. 11.3. Reconnection After the DG has been disconnected from the Aurora network due to a network disturbance, it shall not reconnect to the Aurora network until the voltage and frequency at the PCC have been within acceptable limits for 5 minutes or when authorised by the Aurora System Controller 11.4. Isolation When work is carried out on Aurora s equipment in the vicinity of the DG plant, the generating plant shall be isolated from the Aurora network in accordance with Aurora s safety procedures. Issued: 10 August 2009 Expires: 10 August 2011 Page 9 of 10

All assurances on the state of the DG plant shall comply with the requirements of the SM-EI The DG owner and Aurora may have to agree on scheduling of real and reactive power output into the Aurora network to ensure Aurora s network is within its capacity and voltage limits. 11.5. Power factor It is preferred that generators connected to the Aurora network export reactive power kvar when operating in parallel with the Aurora network. When the generation is associated with consumer load, and there is no export of energy, the generation shall be operated to maintain the power factor at the consumers connection point greater than 0.95. For generators not associated with consumer load the power factor at the generation PCC should be between 0.85 and 0.9 leading subject to network voltages remaining within acceptable limits. 12. RECORDS AND INFORMATION Aurora is responsible for ensuring its plans and records of DG installations are maintained at its control rooms so contractors working on the Aurora network can be advised appropriately. 12.1. GIS Information The DG owner shall provide all necessary information required to facilitate the recording the location and attributes of all DG plant and associated, switchgear, lines and cables on the Aurora geographic information system (GIS). 12.2. Schematic Diagrams The DG owner shall have available at all times at the DG site an up to date single line diagram and protection schematic of the DG plant. Aurora shall be supplied with copies of these diagrams. 12.3. Manuals The owner of the DG shall have manuals on the installation, operation and maintenance of the DG equipment. 12.4. Protection Settings Records shall be kept on protection setting values with details of calculations and logic used to select the settings. 12.5. Test Results The DG owner shall maintain test records as required by Section 9. 12.6. System Operator (Transpower) Notification The EGRs require Aurora to notify the System Operator of the existence of any generators connected to the Aurora network with a maximum capacity greater than or equal to one MW. The DG owner is responsible for providing the System Operator with details of the generation that the System Operator requires. Issued: 10 August 2009 Expires: 10 August 2011 Page 10 of 10