The Long-Range Transmission Plan

Similar documents
TRANSMISSION PLANNING CRITERIA

The Long-Range Transmission Plan Transmission Planning Department Consolidated Edison Company of New York, Inc.

The Long-Range Transmission Plan Transmission Planning Department Consolidated Edison Company of New York, Inc.

EXCEPTIONS TO NYSRC RELIABILITY RULES

EXCEPTIONS TO RELIABILITY RULES REVISION 4 MAY 8, 2015

EXCEPTIONS TO RELIABILITY RULES Revision 11 February 9, 2018

EXCEPTIONS TO RELIABILITY RULES Revision 10 August 11, 2017

Local Transmission Plan. October 11, 2013 Revised August 25, 2014

2017 Interim Area Transmission Review of the New York State Bulk Power Transmission System

2016 Load & Capacity Data Report

LOCAL TRANSMISSION PLAN

100 MW Wind Generation Project

MINIMUM OIL BURN/AUTOMATIC FUEL SWAPPING CAPABILITY

COST ALLOCATION OF NEW INTERCONNECTION FACILITIES TO THE NEW YORK STATE TRANSMISSION SYSTEM

DFO STATEMENT OF NEED REPORT

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

Western NY Public Policy Transmission Report

Interconnection System Impact Study Report Request # GI

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

Feasibility Study Report

Interconnection Feasibility Study Report GIP-222-FEAS-R3

MILLIGAN SOLAR PROJECT

2013 CARIS Phase 1 Report

Feasibility Study Report

Western NY Public Policy Transmission Planning Report

2013 Intermediate Area Transmission Review Of the New York State Bulk Power Transmission System (Study Year 2018) DRAFT REPORT

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

Transmission Expansion Advisory Committee

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Sub Regional RTEP Committee Western Region ATSI

Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any

Supplemental Report on the NCTPC Collaborative Transmission Plan

Falcon-Midway 115 kv Line Uprate Project Report

CUSTOMER/ TWIN ARROWS PROJECT

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Feasibility Study Report

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

System Impact Study Report

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Local Transmission Plan. Rev. 1: April 2018

SERTP rd Quarter Meeting

15 Nelson-Marlborough Regional Plan

Hurricane Sandy. Preparations, Response & Recovery. Wes Yeomans Vice President Operations Management Committee Meeting November 2, 2012

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

North Oregon Coast Area Study. Adam Lint

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

2014 Intermediate Area Transmission Review Of the New York State Bulk Power Transmission System (Study Years 2015, 2019, 2024)

NYCA LOLE Violations (Methods D and E )

XXXX. Knob Hill Wind Farm Project. Interconnection System Impact Study

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT

Updates and Modifications to Report

Margarett Jolly DG Manager, Consolidated Edison Company of New York, Inc

Connection Engineering Study Report for AUC Application: AESO Project # 1674

Gateway South Transmission Project

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Consulting Agreement Study. Completed for Transmission Customer

SERTP rd Quarter Meeting

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

National Grid s 2017 Local Transmission Plan

Interconnection Feasibility Study Report GIP-157-FEAS-R2

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA

City of Palo Alto (ID # 6416) City Council Staff Report

2015 Preliminary Weather Normalized MW and 2016 ICAP Forecast (V3)

Seabrook Substation Reliability Improvement Project

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

15 Nelson-Marlborough Regional Plan

The Energy Queensland Group Notice of no non-network options

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY

The North Carolina solar experience: high penetration of utility-scale DER on the distribution system

Merger of the generator interconnection processes of Valley Electric and the ISO;

New Jersey State Report

Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

Illinois State Report

Appendix D Black Hills Project Summary

Project #94. Generation Interconnection System Impact Study Report Revision

SPS Planning Criteria and Study Methodology

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

Black Hills Project Summary

Project #148. Generation Interconnection System Impact Study Report

Transmission Planning using Production Cost Simulation & Power Flow Analysis

Retro-commissioning for Peak Electric Demand Reduction in New York City. Kim Lenihan , ext.

GridView An Analytic Tool for. ABB Inc. Electric Systems Consulting. Market Simulation & Asset Performance Evaluations. ABB Inc.

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

Stability Study for the Mt. Olive Hartburg 500 kv Line

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

New Mexico Transmission Expansion Concepts For Wind Resources

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation

BC Hydro System 2011 Annual Progress Report

Reliability Analysis Update

EIPC HIGH LEVEL TRANSMISSION COST ESTIMATION TASK #5: DOE PROJECT NO. DE-OE

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

XXXX. Kokish River Hydroelectric Project. Interconnection System Impact Study

2013 ANNUAL PROGRESS REPORT

Guideline for Parallel Grid Exit Point Connection 28/10/2010

Transcription:

The Long-Range Transmission Plan 2015 2025 Matt Koenig Presentation to ESPWG / TPAS October 29 th, 2015

Long-Range Transmission Plan Driver of the Plan is to maintain local reliability 10-year planning horizon extending through the year 2025 Order 890 compliance Criteria, assumptions and methodology posted at: http://www.coned.com/tp/transmission_planning_process.asp Plan posted on the Con Edison website at: http:///www.coned.com/tp/ltp-2015-2025.pdf 2

NY PSC Order for EE/DR/CHP As part of the Transmission Owner Transmission Solutions (TOTS) projects in response to the Indian Point Contingency Plan, the NY PSC, effective November 4, 2013, ordered Con Edison and NYSERDA to implement a DSM program in Zone J. In the 125 MW Revised EE/DR/CHP Program, Con Edison and NYSERDA, in consultation with NYPA, proposed a suite of new EE and DR projects designed to achieve 100 MW of peak demand reduction by the summer of 2016. NYSERDA will achieve 25 MW of CHP. Progress reports are provided to the PSC on a quarterly basis. The most recent Q2 2015 status report indicates that so far 6.5 MW have been achieved, 83.5 MW have been committed, and 40.4 MW are in process. These reports and other related documents can be found at the New York State Department of Public Service website: http://documents.dps.ny.gov/public/mattermanagement/casemaster.aspx?matter CaseNo=12-E-0503 Con Edison s program details can be found at this website: http://www.coned.com/energyefficiency/demand_management_incentives.asp 3

Assessments System Performance Transmission Load Area (TLA) Transmission Substation Interconnection of New Generation / Transmission Resources 4

System Performance Thermal Voltage Short Circuit Stability Transient Switching Surge and Lightning Withstand Capabilities Extreme Contingencies 5

6

Transmission Load Area (Generic) G 345/138 Kv AutotransformerS Transmission Substation Phase Angle Regulator To Other Transmission Substations 138 KV 345 KV Ties to Other Utilities 138 KV Phase Angle Regulator 13.8 or 27 KV Area Substations Transmission Load Area Containing Load, Internal Generation, and Ties to Surrounding Stations 13.8 or 27 KV Area Substations Transmission Load Areas (TLA) are specified portions of the transmission system designated to facilitate the analysis in studying the reliability of the system. 7

17 Actual Transmission Load Areas Transmission Load Areas Contingency Level 1 New York City - 345 kv 2 2 West 49th Street - 345 kv 2 3 New York City - 138 kv 2 4 Astoria - 138 kv 2 5 East 13th Street - 138 kv 2 6 Astoria East / Corona - 138 kv 2 7 Astoria West / Queensbridge - 138 kv 2 8 Vernon - 138 kv 2 9 East River - 138 kv 2 10 Greenwood / Staten Island- 138 kv 1 11 Corona / Jamaica - 138 kv 1 12 Bronx- 138 kv 1 13 Eastview - 138 kv 1 14 Staten Island - 138 kv 1 15 Dunwoodie North / Sherman Creek - 138 kv 1 16 Dunwoodie South - 138 kv 1 17 Millwood / Buchanan - 138 kv 1 8

TLA Assessments Thermal Power, in terms of MVA, on a transmission path must not exceed its applicable emergency rating (LTE or STE, as applicable) and be able to be returned to normal levels for that path post contingency First and second (if TLA is designated second contingency) Voltage Bus voltages must not exceed their limits either above or below their nominal ratings Short-Circuit 3 phase, 2 phase to ground or single phase to ground faults create a short-circuit flow on a transmission path that should not exceed the appropriate short-circuit rating of any of the breakers that are necessary for the isolation of that transmission path 9

Study Year Long Range Plan Assumptions 2015 Con Edison Load (Coincident Peak) = 13,775 MW Con Edison Load (Coincident Peak) = 14,350 MW 2020 Transfer 70 MW of load from Brownsville (served from Farragut) to Glendale (served from Vernon) Consistent with Public Service Commission order, establish 100 MW of Energy Efficiency improvements, allocated system-wide. 2025 Con Edison Load (Coincident Peak) = 15,050 MW Gowanus Transmission Station expanded to support future area stations 10

TLA Assessment Results Three TLAs show need for system reinforcements: Astoria East / Corona 138 kv TLA Queens Corona / Jamaica 138 TLA Queens Greenwood / Staten Island 138 kv TLA Brooklyn and Staten Island 11

Areas Served by the Astoria East / Corona 138 kv TLA (in Blue / Green), and the Corona /Jamaica 138 kv TLA (in Green-Yellow) Long Island Sound B-Q Expy Nassau County Line Brooklyn Jamaica Bay 12

Astoria East / Corona 138 kv TLA Geographic Coverage Design Criteria Planned Changes In Load Area Queens Second Contingency 2019 Establish new 138 kv transmission line with transformer and Phase Angle Regulator connecting Rainey and Corona Substations Assessment 2015 2020 2025 First Contingency Loss of Astoria Energy I No deficit Second Contingency Loss of Astoria Energy I, followed by loss of feeder 34091 and Astoria Unit 2 No deficit First Contingency Loss of Astoria Energy I No deficit Second Contingency Loss of Astoria Energy I, followed by loss of feeder 34091 and Astoria Unit 2 No deficit First Contingency Loss of Astoria Energy I No deficit Second Contingency Loss of Astoria Energy I, followed by loss of feeder 34091 and Astoria Unit 2 No deficit Operational Remediation Planning Solution 2015 Utilize 300 hour ratings for feeders 34051/52 and 701/702 until new transmission line established in 2019 2020 None required 2025 None required 2015 None required See Operational Remediation 2020 None required See Planned Changes in Load Area 2025 None required Short Circuit Considerations None 13

Corona / Jamaica 138 kv TLA Geographic Coverage Design Criteria Planned Changes In Load Area Queens First Contingency 2019 Establish new 138 kv transmission line with transformer and Phase Angle Regulator connecting Rainey and Corona Substations 2015 First Contingency Bus fault resulting in the loss of feeder 901, 702 and transformer bank 4 at Jamaica 138 kv No Deficit Assessment 2020 First Contingency Bus fault resulting in the loss of feeder 901, 702 and transformer bank 4 at Jamaica 138 kv No Deficit 2025 First Contingency Bus fault resulting in the loss of feeder 901, 702 and transformer bank 4 at Jamaica 138 kv No Deficit Operational Remediation 2015 None required 2020 None required 2025 None required Planning Solution 2015 None required 2020 None required 2025 None required Short Circuit Considerations None 14

Area Served by Greenwood / Staten Island 138 kv TLA 15

Greenwood / Staten Island 138 kv TLA Geographic Coverage Design Criteria Brooklyn and Staten Island First Contingency Planned Changes In Load Area 2018 Establish Breaker 3N (at Greenwood 138 kv substation), to separate feeder 42232 from feeder 42G13 (GTs 1&3) 2015 First Contingency Bus Fault with Stuck Breaker #4N results in loss of Gowanus GTs 1&3, Narrows GT2, Feeder 42232. No deficit Assessment 2020 First Contingency Bus Fault with Stuck Breaker #4S results in loss of Gowanus GTs 2&4, NYPA GTs, Feeder 42231. No deficit 2025 First Contingency Bus Fault with Stuck Breaker #4S results in loss of Gowanus GTs 2&4, NYPA GTs, Feeder 42231. No deficit Operational Remediation 2015 None required 2020 None required 2025 None required Planning Solution 2015 None required 2020 None required 2025 None required Short Circuit Considerations None 16

Transmission Substations Expansion of the Gowanus Transmission station for the support of area stations is anticipated in the year 2025. No additional Transmission connections are planned for this station. 17

New Merchant Generation and Transmission Proposals New York City continues to attract significant amounts of new generation and transmission capacity NYISO s interconnection queue listing, dated 9-30-15 shows Proposed Generation Facilities: 2,743 MW Proposed Transmission Facilities (including HVDC): 4,675 MW 18

Contact Information Parties interested in commenting on Con Edison s Transmission Planning Process can e-mail comments and suggestions to: TPTeam@coned.com 19