The North Carolina solar experience: high penetration of utility-scale DER on the distribution system

Similar documents
Solar Farms: design & construction

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems

Reactive Power Compensation for Solar Power Plants. Andy Leon IEEE PES Chicago Chapter December 12 th, 2018

Overview of S.L Competitive Energy Solutions for North Carolina

JEA Distributed Generation Policy Effective April 1, 2018

Small Electrical Systems (Microgrids)

The Role of Electricity Storage on the Grid each location requires different requirements

SPIDER Modeling Sub-Group DER Modeling, CAISO Experience

Solar Development in New Jersey, and PV Impacts on the Distribution System Carnegie Mellon Conference on the Electricity Industry - March 9, 2011

Clark W Gellings, P.E. Fellow CEPSI 2014 October 29, Electric Power Research Institute, Inc. All rights reserved.

Considerations for Interconnecting with Renewable Generators

Merger of the generator interconnection processes of Valley Electric and the ISO;

PV Grid Integration Research in the U.S.

Targeted Application of STATCOM Technology in the Distribution Zone

Integrating DER. Thomas Bialek, PhD PE Chief Engineer. Smart Grid & Climate Change Summit October 13, 2015

John Barnick, Industry Solution Executive, Network Control, Enterprise Software

Decision on Merced Irrigation District Transition Agreement

Feasibility Study Report

Interconnecting with Ameren

IEEE-PES Chicago Chapter Presentation November 11, Smart Grid. Mike Born. Principal Engineer, Capacity Planning

Effects of Smart Grid Technology on the Bulk Power System

TRANSMISSION PLANNING CRITERIA

Managing California s Electrical Supply System after the shut down of San Onofre Nuclear Generating Station

Guideline for Using IEEE 1547 for Solar PV Interconnection Page 1

Feasibility Study Report

C PER. Center for Advanced Power Engineering Research C PER

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

Grid Integration Costs: Impact of The IRP Capacity Mix on System Operations

Grid Management Voltage Control Distribution Grid Voltage Regulation with DER. Michael Sheehan, P.E. IREC Pacific Northwest Solar Partnership

Improving DER Interconnection with Updated Standards and Codes, Smart Inverters, and Distribution System Design

Essential Reliability Services From PV Plants

ENERGY STORAGE AS AN EMERGING TOOL FOR UTILITIES TO RESOLVE GRID CONSTRAINTS. June 18, 2015 E2Tech Presentation

Wholesale Power Supply Socorro Electric Cooperative, Inc. Rob Wolaver, P.E. Senior Manager, Energy Resources

Renewable Grid Integration Research in the U.S.

Clark W Gellings, P.E. Fellow National Conference of State Legislators Energy Supply Task Force August 18, 2014

Transmission Planning using Production Cost Simulation & Power Flow Analysis

Inverter-based DER Ride Through and IEEE Standard 1547

Smart Grid and its Role in Reducing Peak Demand and Improving Electricity Delivery

Interconnection and Net Metering Service in Ohio

Distributed Energy Resources

Wind Interconnection and Net-Metering in MA. Tim Roughan - National Grid Joe Feraci - NStar

Feasibility Study Report

SCE Smart Grid. Creating a Cleaner, Smarter Energy Future. Metering, Billing / MDM America Conference. San Diego. March 9, 2010

Net Metering (NEM) Credit Recommendation. June 5, 2018

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management

Interconnection Feasibility Study Report GIP-226-FEAS-R3

RECOMMENDATION: It is recommended that the City Council, following a public hearing, adopt the attached resolution which:

Portland General Electric

Experience on Realizing Smart Grids. IEEE PES conference, Gothenburg

Puget Sound Energy Overview

Distribution System Analysis for Smart Grid

Advanced Inverter Design

MassDOT Highway ROW Solar PV Energy Program. Hongyan (Lily) Oliver Massachusetts Department of Transportation Office of Transportation Planning

Dynamic Control of Grid Assets

Impact of Distributed Generation and Storage on Zero Net Energy (ZNE)

Implementation of Distributed Generation

Distributed Generation and Impacts to Distribution Systems. FMEA Energy Connections Conference 2017

NERC Load Modeling Activities. Ryan D. Quint, PhD, PE Senior Engineer, System Analysis, NERC MRO Fall Reliability Conference November 2016

Airports Going SOLAR! Michael Shonka

U.S. SOLAR ENERGY INDUSTRY: NATIONAL DYNAMICS & STATE-LEVEL IMPACTS

System Impact Study Report

A DOUG s View of Electric Utility Industry MICHAEL SHEEHAN, P.E. FAILTE GROUP NOVEMBER 2014

DG Standard Updates. IEEE 1547, UL 1741 SA, and Rule 21 CHASE SUN GII/PG&E 3/28/18

2015 Grid of the Future Symposium

Large Scale Solar Integration

NW Energy XP Project

Agenda. Industry Rate Trends Summary of Financial Targets Cost of Service Information. Valuation of Solar

PES Cook Islands KEMA Grid Study Final Report

µ-grids Integration to the Puerto Rico Electric System CCPR Puerto Rico Energy Sector Transformation Condado Plaza Hilton San Juan PR

Demand Response as a Power System Resource

Battery Energy Storage System addressing the Power Quality Issue in Grid Connected Wind Energy Conversion System 9/15/2017 1

Grid-Friendly Utility-Scale PV Plants

ABB POWER SYSTEMS CONSULTING

WESTERN INTERCONNECTION TRANSMISSION TECHNOLGOY FORUM

Designing and Maintaining a Pollution-Resilient Electric Power System. Managing Pollution Issues

DER101: Distributed Energy Resources basics. May 4, 2017

Grid Stability Analysis for High Penetration Solar Photovoltaics

Interconnection Feasibility Study Report GIP-222-FEAS-R3

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

MILLIGAN SOLAR PROJECT

Product Overview. 1.0 About VRB-ESS. 2.0 System Description. MW-Class VRB-ESS

WIRES University Overview of ISO/RTOs. Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool

Energy Security Electrical Islanding Approach and Assessment Tools. Dr. Bill Kramer Senior Research Engineer Distributed Energy Systems Integration

Presented By: Bob Uluski Electric Power Research Institute. July, 2011

Freeing The Grid Resource for better solar policy

Generation Interconnection Facilities Study For

Battery Energy Storage

Interconnection System Impact Study Report Request # GI

100 MW Wind Generation Project

Wind Energy and Utility Providers

Georgia Power Renewable Update. October 31, 2016 Marc Vinson

Analysis of Impact of Mass Implementation of DER. Richard Fowler Adam Toth, PE Jeff Mueller, PE

Session 8: Distributed Energy Resources Utility Concerns, Grid Impacts and Mitigation Strategies October 21, 2015 Santiago, Chile

EPRI Intelligrid / Smart Grid Demonstration Joint Advisory Meeting March 3, 2010

Planning for Renewables

Workshop on Grid Integration of Variable Renewable Energy: Part 1

Update on State Solar Net Metering Activities Lori Bird, NREL RPS Collaborative Summit Washington, DC September 23, 2014

Smart Grid, Long term planning for a sustainable energy system, from source to socket

Materials Research for Smart Grid Applications

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Transcription:

1 The North Carolina solar experience: high penetration of utility-scale DER on the distribution system John W. Gajda, P.E. Duke Energy IEEE PES Working Group on Distributed Resources Integration

2 High penetration of utility-scale DER North Carolina s solar story, 1978-2017 what does this mean? Discoveries, considerations, requirements Distribution Reliability & Power Quality medium voltage construction transformer energization & transient harmonics Distribution Planning Area planning limitations & substation backfeed Capacity & Losses Policy changes, pre-2014 through to 2017

Duke Energy Progress customers transmission distribution Generating capacity 1.2 million 6,300 miles 67,800 miles 12,900 MW 3

North Carolina s solar story: 1978-2007 PURPA - 1978 NC REPS - 2007 Congress enacted the Public Utilities Regulatory Policy Act (PURPA) in 1978 and FERC enacted PURPA regulations, but state commissions implement them, including calculation of avoided cost. PURPA mandates a must purchase requirement on utilities for renewable output from qualifying facilities at an avoided cost rate. North Carolina s Renewable Energy and Efficiency Portfolio Standard (REPS) NC law signed August 2007 12.5% by 2021 Requires utilities to: Provide a portion of retail energy supply from renewable resources Establish Demand Side Management (DSM) and Energy Efficiency (EE) Programs Includes a cost recovery mechanism and limits impact on customer bills. 4

North Carolina s solar story: 2007-2017 PURPA: NC s 5 MW nonnegotiated PPA ceiling for QFs In place since 1980s Avoided cost rate methodology State tax credit 35%, ended 12/31/15 2007 NC REPS (Renewable Energy Portfolio Standard) Inexpensive land (DEP) Federal ITC 30% through 2019 Declining cost of PV equipment 5

6 North Carolina s solar story: 2017 In the Carolinas (NC & SC), to-date: DER capacity in Duke Energy (Carolinas & Progress) = 2,834 MW (July 2015) Current queue (T&D) = 7,813 MW At end of 2016, NC is #2 in the U.S. in solar capacity (3,016 MW) Most DER not utility-owned today However, Duke Energy accelerating self-built facilities NC House Bill 589 (July 2015) Additional 6,800 MW of solar generation in NC by 2022* Does not include solar growth in South Carolina Currently accelerating at a robust pace

7 1,400 Duke Energy Progress - Interconnected Generation (distribution), 2017 YTD (July) 1,200 1,000 Range (kw) # DER MW 0 20 1,927 9 20 240 94 8 240 950 65 31 950 2,500 67 114 2,500 7,500 197 960 Average = 4.8 MW 878 1,088 1,216 MW 800 7,500 20,000 7 94 2,357 1,216 600 400 200 0 DER totals in DEP, July 2015: Distribution: 1,216 MW Transmission: 825 MW Queue (T&D) = 5,900 MW DEP system peak load ~ 13,000 MW 0 0 1 5 6 9 15 23 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 100 243 458

8 Make it work: sustainable? PURPA s approach incremental in nature did not contemplate interconnections at large scale Common interconnection considerations for utilityscale DER on distribution: system protection, voltage & thermal impacts At large scale, however: many other considerations System balancing (duck curves & ramps, too much for today!) Distribution reliability (medium voltage construction) Power quality (harmonics from large transformer inrush, other) Distribution planning (policies on volt/var control integration, use of existing infrastructure, ROW) Transmission & distribution system integration (modeling challenges, reactive power flows)

9 Distribution Reliability & Power Quality: Medium voltage construction quality February 2016 Clearance issue caused circuit to trip Industrial customer on adjacent circuit experiences multiple production interruptions due to voltage sag

10 No lightning arresters on any dip poles After this, several random site inspections??? Missing extension link Crossarm brace bolts without lock washers Weak ground connections

Magnetizing inrush harmonics impacts 5/2/2016, reconnection of 20 MW solar farm to circuit: Extended harmonic distortion impressed voltage impacts upon the substation bus, and on industrial customer on adjacent feeder (VSDs & PLCs shut down; product lost). 11

All transformers energized at once = New requirements: evaluation of harmonics risk as part of interconnection study Possible requirement to switch transformer blocks on in stages Significant new design task for utility s distribution protection engineers Staging of generating site reconnections 12 Typical one-line diagram, large distributionconnected solar farm Nine 2.2 MVA transformers

13 Area Planning Ignoring Mr. Ohm: a favorite pastime. But with DER? 135 MW More generation than load in northeast NC Expected load growth Much distribution-connected DER being located away from load centers. Not quite distributed, depending upon your perspective.

Duke Energy Progress, Lagrange 115 kv / 12 kv Substation near LaGrange, NC: August 4 & 5, 2013 Afternoon ramp ~ 0.7 MW / hour MW MVAR No solar DER on any of the three distribution feeders yet 0400 1200 2000 0400 1200 2000 One-minute real & reactive power flow measured at distribution bus, 48 hour period 14

Duke Energy Progress, Lagrange 115 kv / 12 kv Substation near LaGrange, NC: October 4 & 5, 2014 MW 2 x 5 MW solar DER on one distribution feeder MVAR ~100% penetration (compared to peak) Afternoon ramp ~ 3 MW / hour 0400 1200 2000 0400 1200 2000 One-minute real & reactive power flow measured at distribution bus, 48 hour period 15

Utility-scale DER solar farm operations: capacity impacts 16 Unchanged peak loading Additional note: Losses on the distribution system found to increase with the growth of utility-scale DER on distribution, due to backfeed

17 Evolution of planning requirements (pre-2014) Prior to fall 2014, system scale was not a consideration interconnection studies included allowance for DER reactive power import to help control voltage rise and flicker Downward adjustment of voltage regulator band center also an option. As scale grew, realization that centralized volt/var control system may not be able to resolve distribution load variability vs. intermittent generation when running power flow solutions Further questions arose on scalability of significant dynamic reactive flows from the transmission to distribution system, with reverse real power flows

Evolution of planning requirements (2014-2017) Voltage regulator band center adjustment impacts As the number of interconnections grew further, realization that Duke Energy Progress volt/var control system, known as DSDR (Distribution System Demand Reduction dispatchable 300 MW demand reduction resource), was being negatively impacted 18 Fall 2014 policy changes DER required to operate at unity PF Substation voltage regulator bandcenters to remain unchanged Utility-scale interconnections must be located electrically ahead of all line voltage regulators

19 Evolution of planning requirements (2017) Capacity planning impacts As the number of interconnections grew yet further, capacity planning engineers noted the loss of valuable right-of-way (ROW) & double-circuit path options for future planning Early 2017 policy changes Interconnections must still be electrically located ahead of all line voltage regulators, but distribution upgrades cannot utilize utility ROW or double-circuiting methods For many multi-mw DER, this means acquisition of new ROW for delivery path to the grid New substations may be required to connect these DER

20 EXAMPLE: Evolution of planning requirements (pre-2014) reg is location of existing line voltage regulator. DG is a proposed interconnection point. R DG Load patterns drive decisions on voltage regulator placement reg

21 EXAMPLE: Evolution of planning requirements (2014-2017) R The red line shows a partial double circuit created to serve the generator site. DG Load patterns drive decisions on voltage regulator placement reg

22 Load growth has now occurred at point D, and the utility is not necessarily able to integrate the partial double circuit with a newly required full double circuit (dashed line). One reason amongst many: R you may need a new regulator somewhere ahead of the DG site on the new circuit. Hence, new rightof-way must be sought for the necessary line extension. EXAMPLE: Evolution of planning requirements (2017) D DG Load patterns drive decisions on voltage regulator placement reg

23 Evolution of planning requirements (beyond 2017) Steps being taken to better manage real & reactive power flow at the substation NC HB 589 calls for: 10 MW limit for interconnection to the distribution system Aggregate DER capacity behind substation to not exceed transformer nameplate (OA/ONAN) capacity Seeking better modeling methods for T/D interface, with respect to DER