Network. ENMAX Power Corporation Network Planning & Design November 4, 2011

Similar documents
ATTACHMENT - DFO STATEMENT OF NEED

SECTION 9: ELECTRICAL POWER DISTRIBUTION. ESE 470 Energy Distribution Systems

OEB's Appendix 2-B: Fixed Asset Continuity Schedule

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

DFO STATEMENT OF NEED REPORT

Schedules 1 to 4, Lot B: Extension of the Lessos Substation

Agility in energy Ahead of the challenge, ahead of the change

Power Infrastructure. PowerToGrowPHX.com

Building a 21 st Century Electric Grid. February 23, 2018

Rex Healthcare Medium Voltage System Presentation APEC 2015 March 15-19, 2015

PRESENTATION BY ENERGY COMMISSION OF GHANA ON TACKLING POWER SYSTEM LOSSES

Review of Electric Utility Hurricane Preparedness and Restoration Actions ORLANDO UTILITIES COMMISSION RESPONSES TO STAFF'S SECOND DATA REQUEST

Electric Power Delivery To Big Cities

WINNIPEG HYDRO QUICK FACTS

MINIMUM DISTRIBUTION SYSTEM CONCEPTS AND APPLICATIONS. Larry Vogt. Manager, Rates

Customer Requirements Downtown Secondary Network Service

Raising the bar. UHV switchgear and components

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G

EMERGING REQUIREMENTS

Put the Power in Your Hands

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

15 Nelson-Marlborough Regional Plan

IEEE-PES Chicago Chapter Presentation November 11, Smart Grid. Mike Born. Principal Engineer, Capacity Planning

3.0 Radial Distribution Systems

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders

100 MW Wind Generation Project

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

SOUTHWEST CALGARY RING ROAD (SWCRR)

High Voltage Pad-mount Transformer

Exelon Energy Delivery Interconnection Guidelines for Generators 2 MVA or less

SPN High Value Project PO Route. RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN

COMPANY PROFILE DOLCHE ENGINEERING POWER AND ENERGY. Where you get Unlimited Support!

BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada. IEEE PES Meeting July 2014

Margarett Jolly DG Manager, Consolidated Edison Company of New York, Inc

SECTION 27 - PAD-MOUNTED TRANSFORMERS TABLE OF CONTENTS

AIR INSULATED METAL ENCLOSED SWITCHGEAR AND CONTROLGEAR

LIST OF EDD DESCRIPTION/ SPECIFICATION AS 19 TH OCTOBER 2016

2701 INTERTECH DRIVE, YOUNGSTOWN, MAHONING COUNTY, INDUSTRIAL PROPERTY FOR SALE 143,789 SF on ACRES $4,300,000

Switchgear and Distribution Systems for Engineers and Technicians

University of California, San Diego Cal (IT) 2 Technical Assignment #2. Brian Smith

Local Transmission Plan. October 11, 2013 Revised August 25, 2014

CUSTOMER/ TWIN ARROWS PROJECT

Overhead Utilities Presentation Purpose

Generation Interconnection Facilities Study For

TRANSMISSION PLANNING CRITERIA

15 Nelson-Marlborough Regional Plan

Oncor Electric Delivery Distributed Storage and Microgrid Demonstration Projects

TABLE OF CONTENTS. Important Notices Underground Plant Protection Information. Commercial/Industrial Information Sheet

BSCP31 Trading Unit Application for West Burton A&B Power Stations

A comparison of metal-enclosed load interrupter (ME) switchgear and metal-clad (MC) switchgear

Alternatives for meeting the need for transmission improvement described

Diane Lindsey CenterPoint Energy SWEDE 2010

Design Criteria Implementation for the Network Development Plan Hursthill Substation

EH2741 Communication and Control in Electric Power Systems Lecture 3. Lars Nordström Course map

Sub-Regional RTEP Committee PJM South

CITY OF VANCOUVER ADMINISTRATIVE REPORT

Sub Regional RTEP Committee Mid-Atlantic

Max value Max life Range from. ($000) (Years) Pole Type

EDS SUBSTATION LVAC SUPPLIES

Sub Regional RTEP Committee Mid-Atlantic

Title Electrical Technical Maintenance Coding System. Reference Number PMP 01 (RIC Standard: EP SP)

Pretest Module 29 High Voltage Unit 1

8DJ. Maintenance-free for lifetime

2701 INTERTECH DRIVE, YOUNGSTOWN, MAHONING COUNTY, INDUSTRIAL PROPERTY FOR SALE 143,789 SF on ACRES $4,300,000

FEBRUARY 14, 2017 Elastimold Solid dielectric switchgear customer presentation

Pike County Light & Power Company Summer Reliability Outlook

Transmission and Distribution Substation Projects. Operating Company: Entergy Gulf States - Texas. Customer: PID # 202

A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES. Electrical. Mechanical. Civil. Protection & Control. Transmission & Distribution

Arc-Flash Mitigation Technologies. Dennis Balickie

Title High Voltage and 1500 System Earthing References and Definitions. Reference Number PDS 02 (RIC Standard: EP SP)

Transformer Technology Seminar HV Collector (Power) Transformers

FUSES. Safety through quality

Q0044 interconnection at

THE WAY WE MOVE LRT FOR EVERYONE

ABB Next Level Big shift in power attractive opportunities

SWITCHGEAR DIVISION PRODUCT PROFILES

North Oregon Coast Area Study. Adam Lint

Cobra-S. Catalog Cobra-S

Power Voltage Transformers for Air Insulated Substations

Wisconsin Public Utility Institute. June 28, Minimum Distribution Charges. Larry Vogt. Director, Rates Mississippi Power

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1

A system fault contribution of 750 mva shall be used when determining the required interrupting rating for unit substation equipment.

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Overview Gas Insulated Switchgear Modular and flexible, kV. ABB Group April 17, 2009 Slide 1

V03. APTA Multimodal Operations Planning Workshop August Green Line LRT

MILLIGAN SOLAR PROJECT

Q64. Photovoltaic Solar Generation Project Interconnection. Facilities Study. APS Contract No

Development and Operational Advantages of a Solid State Circuit Breaker with Current Limiting

ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE

Modular integrated transportable substation (MITS)

Overview Gas Insulated Switchgear Modular and flexible, kV. ABB Group May 15, 2013 Slide 1

Local Transmission Plan. Rev. 1: April 2018

3 Existing National Grid

i-pcgrid Workshop 2013 Ecuador s experiences towards a Smart Grid development

ABB POWER SYSTEMS CONSULTING

The Energy Queensland Group Notice of no non-network options

S C ELECTRIC EUROPE LTD. Excellence Through Innovation. Harnessing the Wind. November 2011 Descriptive Bulletin E

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

Transcription:

Network ENMAX Power Corporation Network Planning & Design November 4, 2011

ENMAX Fast Facts Service area of 1,044 square kilometers 1,738MVA Peak load (2009) Transmission System 266 km overhead 15km underground 36 substations Distribution System 2,387km overhead 5,136km underground 64,554 utility poles 48,321 transformers

Network Service Boundary

ENMAX Network History 1910 Started installing conduit & manholes prior to paving 1912 Substation # 1 built to supply downtown load 1934 City council approves installation of a secondary network 1935 Secondary network started 1937 First 3-phase network transformer installed 1939 Secondary network expanded and 1 st in western Canada

ENMAX Network Section Secondary Network supplied via 3 major substations 13kV primary system, 56 feeders 3 voltages available 120/208v general street voltage 277/480v medium density loads 347/600v high density loads Remote Secondary Networks 3 major malls are supplied via secondary Network systems. Consist of 54 transformers with a load of 27 MVA. 25Kv High Voltage System 30 high density buildings supplied with a preferred and alternate 25kV feeder 2 substations supply the downtown 25kV system via 16 feeders. System configured such that a break before make transfer occurs within customer owned switchgear

ENMAX Network Fast Facts Secondary Network System Peak load of 230 MVA Service area of 8 square kilometers 875 transformers (500MVA installed capacity) 272 km underground primary HV cables (13.2kV) NO overhead primary 32kM secondary overhead cable 988 utility poles 1549kM underground conduit 653 km secondary system cable 343 street vaults 1300 manholes 410kM 3 rd party communication cable 25kV Downtown System Peak load of 130 MVA 30 major customers 50kM underground primary cables Secondary Spot Networks 3 large shopping malls (Chinook, North Hill and Westbrook) Peak load of 27MVA Supplied via distribution substations

What & Why a Secondary Network System Why Designed for high density loads Densely populated area s (impact of a power outage creates large scale socioeconomic impacts) Higher degree of reliability (n-2) is required or expected (Banking & Data centers) Permits equipment outages without impact to customers or switching operations What Composed of multiple transformers interconnected on the low voltage side Multiple primary feeders supplying the transformers Customers are supplied from the low voltage secondary interconnected grid Provides n-2 reliability (loss of any 2 components does not impact service)

Reliability Difference Total Outage Minutes Since 1994 #1 Substation 349 minutes Chevron fire (2002) 149 minutes, 26MVA load loss Century Gardens fire (2002) 121 minutes, 25MVA load loss Mission Gas Line (2005) 15 minutes, 23MVA load loss Miscellaneous substation incidents #5 Substation 9 minutes Miscellaneous substation incidents #8 Substation 60 minutes Miscellaneous substation incidents

Downtown Secondary Network Sub 8 Sub 5 8 Feeders 8 Feeders 8 Feeders 8 Feeders 13.2kV Q Buss 37 MVA 13.2kV R Buss 18 MVA 13.2kV 13.2kV Teens Buss 23 MVA 13.2kV Twenties Buss 25 MVA K Buss 40 MVA 13.2kV J Buss 32 MVA 8 Feeders 8 Feeders Sub 1 8 Feeders 13.2kV L Buss 44 MVA

Secondary Network - Sub 5 Example 138kV West Bus 138kV East Bus Street Grid 13.2kV Bus 21 22 25 26 27 28 23 24 Street Grid Street Grid 23 2 27 3 7 22 24 Man Hole 26 28 Street Grid 208V Customer Load STREET VAULT Customer Load STREET VAULT < 1200A Load Customer Load STREET VAULT STREET GRID Secondary voltages tied

Spot Network North Hill Mall Example Sub - 20 Sub - 003 Distribution Feeder: 8.20-18 Switchgear Distribution Feeder: 8.3-11 1A 2 3 208V 21B 7 1A 1A 1B 1B 1A 1B Switchgear Pad-mounted Designed to source spot network from one feeder at a time Upon loss of service to the primary feeder, control system is designed to transfer the spot network to the alternate source via a break-beforemake scheme. Customer Load STREET VAULT Customer Load STREET VAULT Customer Load STREET VAULT Note: Secondary's not tied together like a Street Grid

25kV High Voltage Radial System Open Sub 8 X3 feeders X3 feeders Preferred Alternate 25kV Customer Load 25kV Customer Load Preferred Alternate Alternate Preferred 25kV Customer Load 25kV Customer Load Alternate Preferred X3 feeders X3 feeders Sub 5 Open Sub 1

Network Servicing & Guidelines

Design & Records Tools Cost estimates produced utilizing Storms Design tool Byers MapViewer also used as a locating tool P&D enhanced the tool with the ability to view digital images as part of the records system. Microstation/Byers used for records and construction maps. Bubble system utilized to identify current construction projects Digital Grid used to determine current system status and load profiles for existing infrastructure

Network Monitoring System Originally installed in the early 1980 s System designed to monitor equipment status such as transformer load, voltage, power factor protector status (Open or Closed) water level, heat, smoke, temperature sensors SF6 gas pressure in system switches Operational staff utilize system to identify potential safety issues whenever a high voltage cable is de-energized to confirm if potential backfeed conditions exist Provides backup data for Engineering staff to develop Capital Maintenance programs. Assist design staff in identifying if a vault as sufficient capacity for additional customer loading

Screen shot of NCS viewer

NETWORK Field Pictures

Pre-Cast Vault & Installation

Street Vault Fancy Top

Street Vault Standard Top

Street Vault Fancy Top, Brick

Street Vault Fancy Top, Cement

Pre-Cast Manhole

Manhole High Voltage Connections (BLR)

Manhole High Voltage Connections (Splice)

Emergency Disconnect Switches E.D.D. (Emergency Disconnect Device) - 15kV switchgear which contains SF6 (Sulphurhexaflouride) - increased protection for equipment located inside the customer building - minimize impact of an event in the customer indoor vault on the system - enhanced safety for staff (Kill Push Button to de-energize vault in emergency)

25kV SF6 Switches

Network Major Office Tower Projects 8 th ave Place 16MVA @ 480-volt (2 Indoor Vaults) Encana (The Bow) 20MVA @ 600-volt (2 Indoor Vaults)

Door Signs on our Customer Owned Vaults

Postless Bus I-Beams

480 Volt Indoor Vault

600V Bus The Bow

Secondary HRC Fuse Boxes

Customer Service Fuseboards

Moles, close up

ENMAX Network Section Fibre Optics in the Network

Network Fiber Optic History 1990 1996 1999 installation of 1st fibre optic cable for Trans Alta Utility Shaw Fibrelink project starts in September and 36kM of backbone fiber installed in 4 months. ENMAX Network section performed all the fiber cable route planning and installation. GT Fiber project started an 12kM of 432 fiber backbone cable installed. ENMAX Network section performed all the fiber cable route planning and installation. Today ENMAX Network system contains over 110 km of fiber optic cable. We have a reputation for high quality work from design to installation.

Communication Cable Tagging

Network 101 Questions?

enmax.com