High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

Similar documents
New Mexico Transmission Expansion Concepts For Wind Resources

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

March 2017 to June 2017 Preliminary Interconnection Cluster Window System Impact Study 49.9 MW IA-PNM May 2018

Status of PNM s Completed Transmission Construction Projects 11/30/2017

100 MW Wind Generation Project

MILLIGAN SOLAR PROJECT

Feasibility Study Report

CUSTOMER/ TWIN ARROWS PROJECT

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

System Impact Study Report

Generation Interconnection Facilities Study For

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

Appendix D Black Hills Project Summary

Feasibility Study Report

Verde Transmission, LLC. Verde Project. System Impact Study Report

Interconnection System Impact Study Report Request # GI

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Generator Interconnection System Impact Study For

TABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES:

ABB POWER SYSTEMS CONSULTING

City of Palo Alto (ID # 6416) City Council Staff Report

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Falcon-Midway 115 kv Line Uprate Project Report

All territory within the incorporated limits of the City and land owned or leased by the City.

ATTACHMENT - DFO STATEMENT OF NEED

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

SPN High Value Project PO Route. RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Feasibility Study Report

PREPARED DIRECT TESTIMONY

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation

PUD ELECTRIC SYSTEM INTERCONNECTION

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV

El Paso Electric Company

WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

South Dakota 890 Study

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

Tehachapi Renewable Transmission Project 3.1 OVERVIEW OF PROPOSED PROJECT

DFO STATEMENT OF NEED REPORT

EMERGING REQUIREMENTS

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

SPP Notification to Construct

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection

Black Hills Project Summary

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04

FILED. IN THE MATfER OF THE APPLICATION OF 1 AND CONSTRUCT A 161 KV TRANSMISSION LINE )

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

Sub Regional RTEP Committee Western Region ATSI

Maddox Creek to Southwest Lima 345kV New Transmission Line November 15, 2016

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

15 Nelson-Marlborough Regional Plan

Rogers Road to Clubhouse 230kV New Transmission Line April 1, 2016

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

INTERCONNECTION FACILITIES STUDY REPORT

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

West Station-West Cañon 115 kv Transmission Project

Reliability Analysis Update

15 Nelson-Marlborough Regional Plan

Refurbishment & Upgrade of the Celilo HVdc Converter Station

Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives. Addendum. San Juan Major Project

Q0044 interconnection at

FORTISBC INC. PRUDENCY REVIEW KETTLE VALLEY SUBSTATION EXHIBIT A2 5

System Impact Study Report Request # T MW Firm Point-to-Point Transmission Service Request from Wyoming to Colorado

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Consulting Agreement Study. Completed for Transmission Customer

Project #148. Generation Interconnection System Impact Study Report

Interconnection Feasibility Study Report Request # GI

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT

Sheffield-Highgate Export Interface SHEI. VSPC Quarterly Meeting October 18, 2017

Reliability Analysis Update

Sub-Regional RTEP Committee PJM South

New Mexico Transmission System Overview TRANSMISSION SYSTEM OVERVIEW NETWORK OPERATING COMMITTEE

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION

XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS

Transmission Expansion Advisory Committee

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Clean Line Energy Partners, LLC. Western Spirit Clean Line 345 kv. System Impact Study

The Energy Queensland Group Notice of no non-network options

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company

Interconnection Feasibility Study Report GIP-226-FEAS-R3

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company

SPS Planning Criteria and Study Methodology

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

XXXX. Knob Hill Wind Farm Project. Interconnection System Impact Study

ATTACHMENT Y STUDY REPORT

The Long-Range Transmission Plan

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation

2017 Interim Area Transmission Review of the New York State Bulk Power Transmission System

Transcription:

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM-2006-02) Interconnection Facility Study Final Report November 2, 2007 Prepared by: Public Service Company of New Mexico Electric Services Transmission Operations

Foreword This report was prepared for XXXXXX ( XXX ) by the Transmission Operations Department at the Public Service Company of New Mexico ( PNM ). Any correspondence concerning this document, including technical and commercial questions should be referred to: Gregory C. Miller Lead Director of Transmission Operations Public Service Company of New Mexico Alvarado Square MS-0604 Albuquerque, NM 87158 Phone: (505) 241-4570 Fax: (505) 241-4363 IA-PNM-2006-02 Facilities Study Report i

1. Introduction Public Service Company of New Mexico ( PNM ) preformed this Interconnection Facility Study ( Study ) in response to an interconnection request by XXXXXXXXX ( Customer ). The purpose of the Study is to provide cost and construction schedule estimates for the facilities needed to interconnect the Customer s proposed 100 MW wind power plant ( Project ) located approximately five miles south of the Willard 115 kv station in Torrance County, New Mexico. The proposed Point Of Interconnection is the Willard 115 kv station, which is owned and operated by Tri-State Generation and Transmission Association, Inc. ( TSGT ). The in-service date originally proposed is December 31, 2007. The previously completed Feasibility Study 1 and System Impact Study 2 established the Facility Study components listed below. Figure 1 is a one-line diagram of the transmission system in the vicinity of the Project and facilities impacted. Component 1: Upgrade the Algodones Willard 115 kv line and remove Algodones station terminal equipment limitations to allow the line to be operated at its thermal rating of 119 MVA. Component 2: Upgrade the Belen Willard 115 kv line to be operated at 200 MVA. Component 3: Mitigate the Tome Las Chavez overload on the Person-Tome 46 kv line. Component 4: Mitigate the Belen-Socorro 115 kv line overload. Component 5: Add a sixth bay position at the Willard 115 kv station to interconnect the Project, and remove any Willard station terminal equipment limitations associated with the Algodones Willard and Belen Willard 115 kv line upgrades. Person Algodones Tome Moriarty Belen ~ Valencia Energy Facility 1 Estancia 2 Willard 5 Duran ~ ~ Proposed Project Figure 1: One-Line Diagram 1 IA-PNM-2006-02 100 MW Wind Generation Project Interconnection Feasibility Study Final Repot, September 13, 2006 2 IA-PNM-2006-02 100 MW Wind Generation Project Interconnection System Impact Study Final Repot, May 2007 IA-PNM-2006-02 Facilities Study Report 1

Section 2 summarizes the results of the Study. Additional information is contained in the Exhibits. Cost and construction schedule estimates for Components 1 through 4 were provided by PNM. Cost and construction time estimates for Component 5 were provided by TSGT. 2. Summary of Cost Estimates and Work Schedule The total cost and construction schedule estimates for each component are summarized in Table 1. Schedule is from the date the Customer provides written authorization to proceed, provided all interconnection agreements and funding arrangements are in place. Based on the construction schedule, the Project in-service date originally proposed cannot be met. Table 1: Cost and Construction Schedule Estimates Component Cost (2007 $) Schedule 1 $ 2,113,946 15 months 2 $ 27,454,041 23 months 3 $ 0 NA 4 $ 1,524,258 13 months 5 $ 805,583 11 months Project Total $ 31,897,828 Please note that there is no cost associated with Component 3. PNM s planned San Clemente 115 kv station (projected in-service date of 2013), will address the Person Tome 46 kv line overload. To address this issue on an interim basis, PNM plans to apply an operating procedure that would consist of switching feeder load from the Los Chaves 46 kv station to 1st Street station. The risk is acceptable given the low magnitude of the overload (1% above rating), and the low probability of occurring. The exposure is limited to an N-1 contingency condition during heavy loads, coinciding with high output from the proposed wind Project, and other proposed generation projects in the Willard and Belen areas at full output. Additional planning studies conducted as part of the Study have concluded that the Belen Socorro 115 kv line overload (Component 4) is a pre-existing condition and the Project exacerbates this overload. To address this pre-existing overload condition, PNM is considering one of the following alternatives at Belen on the Belen Socorro 115 kv line: A. Install a 27-ohm series reactor B. Install a phase shifting transformer Cost estimate for Component 4 provided in Table 1 assumes that the series reactor option is pursued to address the pre-existing overload condition. In this case, a second 27-ohm series reactor stage would be needed to mitigate the impact of the Project. The cost estimate shown in Table 1 assumes that the second stage will be constructed adjacent to the first stage. If PNM chooses instead to pursue a phase shifting transformer, cost associated with Component 4 would not be Customer s responsibility. IA-PNM-2006-02 Facilities Study Report 2

It is not anticipated that load-side generation is required to support the transmission system for these construction outages. However, PNM reserves the right to recover those costs in the event that they are incurred. The following general assumptions apply to all PNM cost estimates: 1. For all estimates, pricing is based on 2007 unit costs. With likely fluctuations in the price of raw materials, fuel, and labor, actual costs may vary in future years. 2. Cost estimates are considered to be within +/- 20%. 3. Estimates include, rights-of-way, governmental permitting, design, materials, construction, construction management, and internal utility loads. 4. Project schedules are considered reasonably accurate but can be affected by permitting delays, equipment deliveries, weather, availability of workforce, and availability of outage clearance for construction. Exhibit A contains itemized cost estimates as well as assumptions specific to each component. IA-PNM-2006-02 Facilities Study Report 3

Exhibit A Component 1: Upgrade Algodones Willard 115 kv line (AW line) and Algodones station upgrades Assumptions This is the upgrade of the AW line to allow the facility to operate at a higher capacity. Approximately 83 spans require clearance improvements to allow the conductor to operate at its full thermal capacity. Phase Raising technology will be the preferred method to make improvements. Where this technology is not appropriate, structures may be replaced or added. Improvements on the steel pole section of the line plan to be accomplished by changing our suspension insulators to a post configuration. The estimate also includes replacement of the AW relays at Willard. Much of the work can be done with the transmission line energized. However, short outages will be needed for structure replacements. The Algodones station will be upgraded to match the new AW line rating. Work includes bus and related equipment. The estimate also includes one temporary tie line and the replacement of the Algodones relays for the AW line. Estimate assumes that outages can be taken on various station equipment and transmission lines as needed. Outages may be limited to off-peak periods such as spring or fall. Outages may also be limited until the construction of the new Belen-Willard 115kV line is complete and can provide full backfeed to the Moriarty area. Transmission costs $1,365,088 Station/Relays $ 615,671 Right-of-Way $ 25,356 Environmental and Regulatory permits $ 107,831 Total $2,113,946 Component 2: Upgrade Belen Willard 115 kv line (WL line) Assumptions An extended WL line outage cannot be taken to rebuild this line. Therefore, a new line (approximately 50 miles) will be built paralleling the existing line. The existing line will be removed once the line is energized. Estimate assumes new right-of-way is acquired paralleling the existing line, including permitting of Federal land. The final design of this line will evaluate alternate routes. Estimate and schedule assumes that short outages will be available on the existing WL line to make cutovers to the new line. Outages may be limited to off peak periods such as spring or fall. Estimate assumes that the WL line relays at Willard will be upgraded prior to this interconnection. IA-PNM-2006-02 Facilities Study Report 1

Transmission costs $21,727,915 Station/Relays $ 0 Right-of-Way $ 5,336,802 Environmental and Regulatory permits $ 389,324 Total $27,454,041 Attachment 1 has the detail line cost estimate, which does not include environmental, regulatory permits, and right-of-way cost estimates. Right-of-way costs will be dependent on several factors including number of owners, willingness to provide land or easement, width of needed easement, etc. Where reasonable, PNM will consider utilizing public rights-of-way. Direct purchase of land is estimated at fair market value. Component 4: Address Belen-Socorro 115 kv line overload by installing a second series reactor at Belen. PNM may pursue the installation of a phase shifting transformer at Belen to address this overload as discussion in Section 2 of this Report. The estimate assumes PNM will install the first series reactor which includes most of the site civil work. Estimate assumes TSGT, owner of the Belen-Socorro 115kV line, is in agreement with the proposed system reinforcement. Short outages on this line will be needed to cut-in the series reactor. Please see Attachment 2 for additional information. Transmission costs $ 0 Station/Relays $1,503,886 Right-of-Way $ 13,747 Environmental and Regulatory permits $ 6,626 Total $1,524,258 Component 5: Expansion of the Willard station and removal of station limitations for the WL and AL line upgrades. Design and Construction $631,407 Overheads $100,941 Contingency $ 73,235 Total $805,583 Please see the Attachment 3 for the assumptions and details cost for component 5. IA-PNM-2006-02 Facilities Study Report 2