Power Blackout in Taif

Similar documents
PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

ABB POWER SYSTEMS CONSULTING

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

CHAPER 5 POWER FLOW STUDY IN THE INTEGRATED GRID NETWORK

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design

Small Electrical Systems (Microgrids)

CHAPTER 5 FAULT AND HARMONIC ANALYSIS USING PV ARRAY BASED STATCOM

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

2015 WDC Disturbance and Protection Standards Overview

Shippensburg University

2013 Grid of the Future Symposium. Utilizing Single Phase Operation Scheme on Untransposed 765kV lines for a Stability-Limited Plant

Seabrook Substation Reliability Improvement Project

Cost Benefit Analysis of Faster Transmission System Protection Systems

Interconnection System Impact Study Report Request # GI

Copyright 2003 Advanced Power Technologies, Inc.

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems

CONNECTION OF NEW GENERATORS IN THE ELECTRICAL POWER SYSTEM OF KOSOVO. Rexhep Shaqiri 1, Bogdanov Dimitar 2.

Safety Design of CHAdeMO Quick Charging System

Decision on Merced Irrigation District Transition Agreement

Review of Electric Utility Hurricane Preparedness and Restoration Actions ORLANDO UTILITIES COMMISSION RESPONSES TO STAFF'S SECOND DATA REQUEST

Aswan high dam - Distributed control system AUTOMATION

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director

Power Grid & Blackouts. Prof. Ramzy R. Obaid

3.2. Current Limiting Fuses. Contents

Guideline for Parallel Grid Exit Point Connection 28/10/2010

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

Use of High-Power Thyristor Technology for Short-Circuit Current Limitation in High Voltage Systems

100 MW Wind Generation Project

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

Agility in energy Ahead of the challenge, ahead of the change

Computer Aided Transient Stability Analysis

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management

INTERCONNECT CHALLENGES IN THE DEVELOPING WORLD S DISTRIBUTED GENERATION INFANCY. David C. Oehl, P.E. President MAVEN POWER

Merger of the generator interconnection processes of Valley Electric and the ISO;

Appendix G Examples and Recommended Methods

The behavior of the cycloconverter fed gearless drive under abnormal electrical conditions

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS

Analysis of Grid Connected Solar Farm in ETAP Software

Project #148. Generation Interconnection System Impact Study Report

Review paper on Fault analysis and its Limiting Techniques.

Rescue operations on dedicated high speed railway lines

/12/$ IEEE. M. Bashir M.Sc student, Student Member, IEEE Ferdowsi University of Mashhad Mashhad, Iran

TECHNICAL SPECIFICATION FOR INDEPENDENT POWER PRODUCERS. NB Power Customer Service and Distribution. June 2008

Health and Safety Executive, Technology and Health Sciences Division, Magdalen House, Bootle.

Selective Coordination Enforcement:

Field Verification and Data Analysis of High PV Penetration Impacts on Distribution Systems

Climate change drivers for a single and smart EU grid

Transforming Transforming Advanced transformer control and monitoring with TEC

B-03 ELECTRICIAN TRAINING SKILL DEVELOPMENT GUIDE

Modeling and Simulation of Battery Energy Storage Systems for Grid Frequency Regulation. X. XU, M. BISHOP, D. OIKARINEN S&C Electric Company USA

Straight Talk. About the Smart Grid. Introduction

Dual Power. Protection. Protection

CRITICAL ISSUES DOWNTOWN CONTINGENCY PORTFOLIO

NC PV DG Program SEPA Presentation. December 15, 2011

Double earth fault in a PSP during back to back launching sequence

Grid Stability Analysis for High Penetration Solar Photovoltaics

Fuzzy based STATCOM Controller for Grid connected wind Farms with Fixed Speed Induction Generators

INTERCONNECTION STANDARDS FOR PARALLEL OPERATION OF SMALL-SIZE GENERATING FACILITIES KILOWATTS IN THE STATE OF NEW JERSEY

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

A TRIAL OF ALTERNATIVES TO DIRECTIONAL OVERCURRENT PROTECTION ON GRID TRANSFORMERS TO IMPROVE THE NETWORK CAPACITY TO ACCOMMODATE REVERSE POWER FLOW

2015 Grid of the Future Symposium

Modular Standardized Electrical and Control Solutions for Fast Track Projects

City of Palo Alto (ID # 6416) City Council Staff Report

Guidelines for connection of generators:

The IAEA does not normally maintain stocks of reports in this series.

City Power Johannesburg: Response to Potential Load Shedding. Presented by : Stuart Webb General Manager : PCM October 2014

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS.

Gas-insulated medium-voltage switchgear. For the metal industry. Answers for energy.

Performance Analysis of Transient Stability on a Power System Network

SECTION 9: ELECTRICAL POWER DISTRIBUTION. ESE 470 Energy Distribution Systems

INTRODUCTION TO SMART GRID

What is Smart Grid? R.W. Beck Inc.

POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 UNIT ON 9 FEBRUARY 2012

Accidental Islanding of Distribution Systems with Multiple Distributed Generation Units of Various Technologies

APPLICATION OF VARIABLE FREQUENCY TRANSFORMER (VFT) FOR INTEGRATION OF WIND ENERGY SYSTEM

Don t Discriminate: The importance of selective coordination in electrical installations

NETSSWorks Software: An Extended AC Optimal Power Flow (AC XOPF) For Managing Available System Resources

OMAR - Power Generation AUTOMATION

Falcon-Midway 115 kv Line Uprate Project Report

Smart Grid Automation and Centralized FISR

NOBERT MATARUTSE TECHNICAL DIRECTOR ESKOM UGANDA LIMITED UGANDA

Development and Operational Advantages of a Solid State Circuit Breaker with Current Limiting

OKLAHOMA CORPORATION COMMISSION REGULATED ELECTRIC UTILITIES 2017 RELIABILITY SCORECARD

System Status Briefing

MEDIUM VOLTAGE PRODUCTS. Fault Current Limiters I S. -limiter and FC-Protector The worldʼs fastest switching devices

Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER

IFC Workshop on Distributed Generation, 13 February 2013, Moscow, Russia

POWER SYSTEM INCIDENT REPORT: TRIP OF NO 1 AND 2 NEW OSBORNE 66 KV BUSBARS ON 26 SEPTEMBER 2010

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

DER Portfolio Optimization and Dispatch, Tertiary Control/Monitoring Strategies

ATTACHMENT - DFO STATEMENT OF NEED

CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM

3.0 Radial Distribution Systems

Selective Coordination

Shunt Capacitor Bank Protection in UHV Pilot Project. Qing Tian

ISLANDING SCHEME FOR STATION DURING GRID BLACK-OUT

Guideline for Using IEEE 1547 for Solar PV Interconnection Page 1

Transcription:

Power Blackout in Taif [Author Name(s), First M. Last, Omit Titles and Degrees] [Institutional Affiliation(s)] Author Note [Include any grant/funding information and a complete correspondence address.]

Abstract On 11 th June, 2014, complete power blackout occurred in Saudi Arabia due to the tripping of relay. In this, the city of Taif witnessed the worst case of blackout at 14:29 hours causing havoc in the region where people were subjected to immense difficulty for unknown time period. Power blackout is not a unique accident of its kind. Many blackout incidents have been reported not only in Saudi Arabia but throughout the Middle East region and across other continents as well. This report presents background, root cause analysis, event description and future recommendations for the above mentioned and other similar mishaps. Keywords: Taif, Blackout

Contents Abstract... 2 Executive Summary... 4 Introduction... 5 Historical Background... 5 Taif Blackout... 6 Overview of Saudi Electricity Company (SEC)... 7 Description... 8 Event... 8 Analysis... 8 Taif Transmission Network... 10 Causes & Solution of Blackout... 12 Lack of System Maintenance:... 12 Lack of System Testing... 13 Power Surges... 13 Impact of Blackout... 14 Future Recommendation... 14 Conclusion... 15 References... 16

Executive Summary Saudi Arabia is one of the hottest countries of the world which means that the demand of energy in this region is greater than the average demand of other countries. Also, this country hosts millions of foreigners during pilgrimage season and round the year therefore, presence of a smooth power network is of utmost priority. This report is about the power blackout incident that occurred in the city of Taif of Saudi Arabia on 11th June, 2014. Initially, the literature review of similar incidents of the past have been investigated of the Arab world. The next section outlines the function of Saudi Electricity Company (SEC). This is then followed by a description of the actual event covering details of the incident and an analysis of the cause behind the event. Furthermore, general causes leading to power outage is discussed. This is then followed by the impact of such events and recommendations to avoid such mishaps in future.

Introduction Being a developed nation, Saudi Arabia faces the problem of power outage as well. Although this phenomena is usually part of the third world countries but states with large number of manufacturing plants suffer from this similar cause. In such scenarios, it has been a common practice to save energy and meet energy shortfalls occurring in distribution to the allocated network. Consumers make sure to store power back-up for long and unpredictable hours of power outage. Even after taking the above mentioned measures, power outage can occur in developed countries due to unforeseen circumstances. One such case was reported in Saudi Arabia on 11th June, 2014 when due to the tripping of relay, the city of Taif witnessed the worst case of blackout at 14:29 hours causing havoc in the region where people were subjected to immense difficulty for unknown time period. Historical Background Power outage is not an uncommon incident in Saudi Arabia. Since, Saudi Arabia hosts the world largest gathering during Haj season and also is one of the hottest countries of the world therefore, incidents of blackout have been observed in the previous years as well. According to the Committee of Interconnected Arab Networks (CIAN) report of March 2006 Major Interruptions Blackout Study, number of power fault records reported in Arab countries till 2005 is given below (Committee of Interconnected Arab Networks, 2006):

Figure 1 Number of Power Interruptions in Arab Countries till 2006 (Committee of Interconnected Arab Networks, 2006) Out of the above mentioned records, 42 percent of these were reported to be 100 percent blackout in which the system was incapable of enduring any load. Majority of these incidents occurred as a result of malfunctioning or mishandling of the system or the equipment. The outage duration lasted from 28 minutes to 10-12 hours (Committee of Interconnected Arab Networks, 2006). A brief overview of one of the similar incident that happened in Taif is given below: Taif Blackout On April 4, 2014, the city of Taif witnessed a power breakdown. At 19:00 hours, the 110 kv network of Taif was caught with a partial blackout. However, after 3 minutes the 110 kv bus station completely tripped due to over-current caused by over load. After almost half an hour that is at around 19:31 hours, AD 10 feeding to AD 05 AMT tripped due to high thermal load. WRCC then opened AD09 TPS2 at 20:57 hours for power flow management which lead to the tripping of AD07 at HVT due to overloading. When WRCC tried to restore the system then at 21:59 hours AD13 tripped by overloading

(ABDULRAHEEM, 2014). After analysis it was found out that Taif s 110 kv network was run by a 380/110 kv 500MVA power transformer. The power flow was balanced by starting the AD09 at TPS2 substation. Following this, AD07 at HVT linked to AD07 of NGD tripped due to overload. In this situation, both lost their connection and hence, all feeders present at HVT substation and connected to BB 2B & BB1 were deprived of power. It was later found out that bus section AD13 was off. Due to overcurrent in relay. This was the reason why all feeders connected to BB2B and BB1 were then fed from TPS2 and NGD. When WRCC took the decision to switch off AD 09 at TPS 2, all the feeders lost their excitation power (ABDULRAHEEM, 2014). Overview of Saudi Electricity Company (SEC) Saudi Electricity Company (SEC) was established in 2000 which is 81 percent owned by government out of 74 percent is contributed by the government itself and 7 percent is owned by Saudi Aramco. It is responsible for generation, transmission and distribution of power across the country and ensuring 100 percent quality customer satisfaction. The main function of SEC is to provide economical and reliable energy network throughout the region (AL DEKHAYL, 2012). The Subsidiaries of SEC are as follows: Four Generation Companies (GENCO s) One Transmission Company (National Grid) One Distribution Company (DISTCO) The purpose of all these sub sections is to collaborate and work in junction to generate the required amount of energy for consumption and provide rapid solution in case of any emergency situation.

Description Event On June 11, 2014 at around 14:29 pm, the city of Taif witnessed blackout with a power loss of 783 MW for 38 minutes ("TRIPPING IN 380 KV TAIF SUBSTAION IN TAIF AREA", 2014). The mishap brought the area s life to a halt since power outage is an unusual activity in the region so the residents are generally unprepared for such interruptions. Students preparing for examinations were deprived of this basic necessity while the general public was left helpless with no power back-up. Day-to-day activities of the people was disturbed like parties, events and etc. forcing them to postpone their plans till life became normal. Being one of the world s hottest region, the unplanned outage took the people by surprise in season of heat wave leaving them helpless and unable to cope with the unexpected situation that arose following the power fault ("TRIPPING IN 380 KV TAIF SUBSTAION IN TAIF AREA", 2014). Analysis After investigation it was found that operating Siemens 380KV Bus Bar differential relay type 7SS522 system one and system two both tripped all 380KV lines connected to BB1 and BB2B (AC008, AC04, AC07 and AC09 feeders) at HVT substation of Taif. The network is designed in such a way that 380KV feeder AC08 is located on BB 2B. WRCC closed Q1 of AC08 in order to shift the feeder to BB1. When both the isolators of AC08 are closed then tripping and opening of AC05 bus coupler and AC06 bus section is blocked. Since all three; AC05, AC06 and AC08 are closed therefore, the load is shared on AC09 and AC03 ("TRIPPING IN 380 KV TAIF SUBSTAION IN TAIF AREA", 2014). In the above mentioned blackout, WRCC issued the open command to Q2 of AC08. Within a couple of seconds after the execution of this command, AC05 and AC06 both tripped

due to earth fault that caused overcurrent in relays. At the time of investigation, it was intimated that time delay for earth fault did not contribute to tripping process since the two seconds delay mentioned above of AC05 and AC06 had already been minimized to zero seconds due to the energization requirement of AC10. Around 14:30:05 pm bus section AC06 and bus coupler AC05 were tripped and the circuit breaker along with isolators of AC08 were working as coupler. It was then doubted that during the opening of Q2 of AC08 which usually requires a few seconds either it was unable to tolerate the current produced during this process or physical contact of Q1 of AC08 was loose. With regard to either of the situations mentioned before, differential current of 16 ka for 50 ms was generated in L1 which caused 380 kv BB differential relays (BB1 and BB2B) to trip the 380KV feeders connected to bus bars during their operation ("TRIPPING IN 380 KV TAIF SUBSTAION IN TAIF AREA", 2014). Figure 2 describes the sequence of event that took place as explained above that ultimately resulted in blackout in the region ("TRIPPING IN 380 KV TAIF SUBSTAION IN TAIF AREA", 2014).

Figure 2 Sequence of events leading to Taif Blackout ("TRIPPING IN 380 KV TAIF SUBSTAION IN TAIF AREA", 2014) Taif Transmission Network Following figure 3 shows the 380 / 110 kv transmission network of Taif ("TRIPPING IN 380 KV TAIF SUBSTAION IN TAIF AREA", 2014). Figure 4 shows the single line diagram of HVT Substation ("TRIPPING IN 380 KV TAIF SUBSTAION IN TAIF AREA", 2014).

Figure 3 380 / 110 kv transmission network of Taif ("TRIPPING IN 380 KV TAIF SUBSTAION IN TAIF AREA", 2014)

Figure 4 Single line diagram of HVT Substation ("TRIPPING IN 380 KV TAIF SUBSTAION IN TAIF AREA", 2014) Causes & Solution of Blackout According to Committee of Interconnected Arab Networks, 2006, two major causes have been identified for power interruptions: 1. Human Error 2. Equipment Error Equipment error is further divided into two sub category: malfunctioning and wrong settings. It has been researched that almost 100 percent of power blackout incidents are the result of equipment faults while a small portion of this share are caused by human mismanagement (Committee of Interconnected Arab Networks, 2006). In the above case of Taif incident, the main causes are described below: Lack of System Maintenance: In the historical event of Taif, it was found out that the bus section AD 13 relay tripped due to current exceeding the threshold value. Therefore, the protection engineering department

should regularly monitor the relay settings of all bus stations and bus couplers present in the grid station and should take rectification measures in case of any faults (ABDULRAHEEM, 2014). Electric circuits, wires and switch boards should be prevented from exposure to moisture since, it may lead to short circuit. In case of a weak transmission network, poor relay settings, frequent and unexpected tripping of generators, power faults are usual and should be avoided ("Causes of Power Failures & Power Outages Diesel Service", 2016). Lack of System Testing It was found out that two possible reasons lead to the tripping of feeder AC 08. Firstly, either Q1 of this feeder deteriorated and was unable to make proper contact. Or Q2 was not capable of carrying the current generated during this process. This problem requires that proper testing of Q1 and Q2 should be done before the working process so that tripping of the feeder could be avoided ("TRIPPING IN 380 KV TAIF SUBSTAION IN TAIF AREA", 2014). The process of opening and closing that is adapted while the working of bus couplers and bus stations in these transmission networks like AC05 and AC006 respectively can lead to wear and tear thus, causing an increase in time delay. This means that this switching process will require more operational time. Hence, it is important that this procedure is regularly monitored and any undesirable delays should be reported ("TRIPPING IN 380 KV TAIF SUBSTAION IN TAIF AREA", 2014). Power Surges Power surges are abnormal high voltages that can affect the working of electrical equipment. It can cause fast and frequent overheating of the system resulting in unfortunate events. Also if operational maintenance is not carried out regularly then electrical lines may

malfunction. Hence, power protection circuits should be implemented and verified regularly ("Causes of Power Failures & Power Outages Diesel Service", 2016). Impact of Blackout The impact of power blackout is vast and effects each and everything happening in its vicinity. Every kind of business and trade is effected and due to power breakdown, the industries are unable to meet their required production level and hence, pose a negative impact on the economy of the country (Setrana, 2016). The outage will also effect traffic flow since traffic signal and street lights operated through commercial power will be effected and will stop working, creating a havoc on roads. Since Saudi Arabia heavily depends on water treatment plants for drinking and water for other purposes therefore, this will affect the working of these plants as well. Cooling systems are a necessity in Middle East countries because of their extremely high temperatures. Therefore, cooling systems will stop working causing a halt in the routine of the people. Lastly, all types of communication will be disturbed since they energy required to power them will not be available ("Long Term Power Outage", 2016). Future Recommendation Every year the average hours for which power outage occurs is increasing. Although Middle East has a vast share of gas reserves but due to lack of planning, corruption, mismanagement and poor coordination amongst the Arab world in term of trade, these reserves are not being properly utilized. However, the use of gas instead of petroleum as a source of fuel will result in a cleaner environment free of any pollution. Other renewable resources can also be utilized. For example, Saudi Arabia has excess of solar energy that can be easily used as an alternative of energy source (Khoudouri, 2016).

Existing working transmission networks should have better reactive power as it contributes to blackout. Regions that frequently suffer from power blackout should be provided with SVC for voltage regulation. New shunt reactors should be installed and power back-up with an automatic on/off procedure should be made available all the time. Operational planning trainings should be held in order to revise and follow up the regulations followed in the system. The network working and methods should be analyzed accurately using professional tools and software. Any upgradation required should be carried out precisely. Also, the input source and output load should be verified vigilantly according to the threshold set among all nodes that is generation, transmission and distribution. System settings should be set according to the requirements of routine work or any special activity taking place (Committee of Interconnected Arab Networks, 2006). Conclusion The blackout that occurred in Taif was a source of huge disturbance fot the country economically, socially and personally. Preventive measures should be taken in order to minimize such accidents in the future which are a source of problem for all fields. Error-free and reliable energy network should be made available so that in case of any unavoidable situations, routine tasks are not affected and the network functions smoothly.

References Al-Hamid, N. (2014). Residents of Al-Marwa outraged at power outage. Arab News. Retrieved 22 October 2016, from http://www.arabnews.com/node/583032 Causes of Power Failures & Power Outages Diesel Service. (2016). Dieselserviceandsupply.com. Retrieved 2 November 2016, from http://www.dieselserviceandsupply.com/causes_of_power_failures.aspx Khoudouri, W. (2016). Few solutions to Arab world s power outages. Al-Monitor. Retrieved 2 November 2016, from http://www.al-monitor.com/pulse/business/2015/07/arabworld-electricity-power-outage-energy-lebanon-iraq.html AL DEKHAYL, S. (2012). SAUDI ELECTRICITY COMPANY (SEC). Orlando. Retrieved from http://www.us-sabc.org/files/public/powergen2012presentation.pdf Committee of Interconnected Arab Networks. (2006). Major Interruptions (blackouts) Study. Retrieved from http://www.auptde.org/article_files/234.pdf TRIPPING IN 380 KV TAIF SUBSTAION IN TAIF AREA. (2014) Setrana, F. (2016). Electricity Outages In Ghana: Causes, Effects & Solutions. Ghanahomesblog.com. Retrieved 3 November 2016, from http://www.ghanahomesblog.com/2015/05/electricity-outages-in-ghana.html Long Term Power Outage. (2016). In-a-pickle.org. Retrieved 3 November 2016, from http://www.in-a-pickle.org/long-term-power-outage.html ABDULRAHEEM, S. (2014). PARTIAL BLACK OUT IN TAIF NETWORK. National Grid SA Company.