Panel Discussion: Planning for Today and Tomorrow

Similar documents
Panel Discussion: Planning for Today and Tomorrow

Burlington to Nanticoke REGIONAL INFRASTRUCTURE PLAN

July 25, Karla Bailey Asset Management & Engineering Manager Thunder Bay Hydro 34 Cumberland St N, Thunder Bay, ON P7A 4L4. Dear Ms.

Utility Administration & Operation of Virtually Net-Metered Generation

Overview of ISO New England and the New England Wholesale Power Markets

Metro Toronto REGIONAL INFRASTRUCTURE PLAN

WIRES University Overview of ISO/RTOs. Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool

March 21, Mr. James F. Brown, P.Eng. Director, Infrastructure EnWin Utilities Inc. 787 Ouellette Avenue, Windsor, Ontario N9A 5T7

Mr. Vince Mauceri General Manager Transportation Operations and Technology

November 28, Jim Klujber Manager of Operations Wellington North Power Inc. 290 Queen Street West, P.O. Box 359 Mount Forest, ON N0G 2L0

CONNECTING THE REGION

May 20 th Mark Van de Rydt Supervisor Engineering Greater Sudbury Hydro Inc. 500 Regent Street P.O Box 250 Sudbury, ON P3E 3Y2

SERVICES INNOVATION. Montreal Symposium March 29, Jack Simpson Director, Generation & Capacity Planning

GO Transit s deliverable: the 2020 Service Plan

ERCOT Overview. Paul Wattles Senior Analyst, Market Design & Development. Solar Energy Industries Association July 11, 2012

April 8 th Brenda L. Pinke Regulatory/CDM Manager InnPower Corporation 7251 Yonge Street Innisfil, Ontario, L9S 0J3. Dear Ms.

New 115 kv Disconnect Switches at Bloomsburg MTS

April 28, Doug Curtiss Chief Executive Officer Grimsby Power Inc. 231 Roberts Road Grimsby, ON L3M 5N2. Dear Mr. Curtiss:

SPP OVERVIEW. Mike Ross Senior Vice President, Government Affairs and Public Relations

Effects of Smart Grid Technology on the Bulk Power System

Kansas Legislature. Briefing for the. March 6, Paul Suskie & Mike Ross

2018 OPERABILITY ASSESSMENT

ENERGY STORAGE AS AN EMERGING TOOL FOR UTILITIES TO RESOLVE GRID CONSTRAINTS. June 18, 2015 E2Tech Presentation

Western NY Public Policy Transmission Planning Report

ENERGY STORAGE DEPLOYMENTS IN ONTARIO APPRO NOVEMBER 18, 2014 TORONTO

Electricity industry structure and key players

NYISO Market Initiatives

CONNECTING THE REGION

Year Built: ,972 sq. ft. (including basement) Roof: Replaced in drive-in doors and 1 dock-door. Yes partial wet system (basement)

Western NY Public Policy Transmission Report

Roadmap for high RES penetration in Greek Non Interconnected Islands

Impact of Energy Efficiency and Demand Response on Electricity Demand

Transportation Electrification Public Input Workshop. August 3, 2016

PSE Attachment K Puget Sound Area Transmission Meeting

Building Collaboration Between East African Nations via Transmission Interconnectors

Distributed Generation

Office of Electric Transmission and Distribution. Transforming the Grid to Revolutionize Electric Power in North America

TORONTO TRANSIT COMMISSION REPORT NO.

ABB Next Level Big shift in power attractive opportunities

Energy Plan. Public Forum Presentation January 25, 2011

Alfen acquires Elkamo in Finland A platform for expansion in the Nordics

ADB Knowledge Partnership Week. Hirokazu Yamaguchi May, 2015

Illinois State Report

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

ISO on Background. Energy-efficiency forecast. Anne George. Stephen J. Rourke VICE PRESIDENT, SYSTEM PLANNING DECEMBER 12, 2012

PRESENTATION BY ENERGY COMMISSION OF GHANA ON TACKLING POWER SYSTEM LOSSES

Looking Towards the Future: Advantages of 765-kV Transmission Technology

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT

CREATING CONNECTIONS IN THE TOWN OF NEWMARKET

2016 Load & Capacity Data Report

The Regional Transportation Plan PLAN BUILD OPERATE

Terry Blackwell Page 1 of 5. Education North Carolina State University BS, Electrical Engineering Power Systems emphasis

Accommodating High Levels of Variable Generation. EPRI Managing Complexity for Safety and Reliability September 14-15, 15, 2009

Electric Power Infrastructure Services Duke Austin, President & Chief Executive Officer B.J. Ducey, Senior Vice President Operations

Efficiency Challenges for the European Utilities A view from Enel

Northwest Ontario REGIONAL INFRASTRUCTURE PLAN

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

Decision on Merced Irrigation District Transition Agreement

Share with the GHSEA. Smart Energy Initiatives. Collaboration and a partner eco-system to achieve results

The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027)

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director

Submission to the IESO re: RDGI Fund Virtual Net Metering Investigation Topic

15 Nelson-Marlborough Regional Plan

Da Afghanistan Breshna Sherkat

CREATING CONNECTIONS IN EAST GWILLIMBURY

Regional Market Trends Forum April 21, 2016 Hartford, CT. Mike Dirrane Director, Northeast Marketing

Journey to Excellence. Building Markham s Future Together. Development Services Committee. Transit. Update. June 23, 2015

LONDON!!!!!!!!!!!!!!!!!! Regional Infrastructure Plan 09 January London Area REGIONAL INFRASTRUCTURE PLAN

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

OVERVIEW OF UNIFORM TRANSMISSION RATES

The Role of Electricity Storage on the Grid each location requires different requirements

July 28, 2009 Presentation to the Illinois Statewide Smart Grid Collaborative

The role of Transmission System Operator in Belgium and in Europe. Vlerick Alumni Event 26 January 2016

Developments in Electrification and Implications for the United States Electric Industry U.S. Department of Energy Perspective

Electric Transportation and Energy Storage

2018 Load & Capacity Data Report

GTA West Corridor Planning and EA Study Stage 1

Presentation Context. Major Mackenzie & 48 Land Owners Group. Presentation on Behalf of the. Development Services Committee.

Impact of Distributed Energy Resources on Transmission System Reliability

General Overview. Ernesto Macias ARE President MUNICH Copyright Alliance for Rural Electrification. All rights reserved.

WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017

Energy Policy Implications: PJM Planning

Metrolinx: Transforming the Way We Move - A Network Wide Approach. Greg Percy, Chief Operating Officer November 1, 2016

Overview of Electricity Trade Agreement between Québec and Ontario. May 10, 2017 For Information Purposes Only

The impact on the data center Industry

Energy Outlook for Asia and the Pacific

Ron Schoff Senior Program Manager, EPRI. USEA Energy Supply Forum Washington, DC October 2, 2014

Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA

Deloitte Utility Electric Vehicle Survey

Review of U.S. market reforms for renewable integration, flexibility, and storage

Mississauga Moves: A City in Transformation icity Symposium Hamish Campbell

Grid Operations and the Increasing Challenges of Balancing Renewable Energy ALBUQUERQUE QUALITY NETWORK

Envisioning Future Energy Technologies Aaron Melda Tennessee Valley Authority

Lennox GS Deregistration Analysis

Microgrid solutions Delivering resilient power anywhere at any time

21st Century Power Grids: Reliable, Controllable and Resilient

LDC 2.0 EVs, DER, Transactive Energy

DFO STATEMENT OF NEED REPORT

Power Systems Fundamentals

Transcription:

Panel Discussion: Planning for Today and Tomorrow Moderator: Chuck Farmer, Director, Stakeholder and Panelists: Public Affairs, IESO David Short, Power System Assessments, IESO Ahmed Maria, Senior Manager, Transmission Integration, IESO Angelo Boschetti, Supervisor, Engineering Department: Generation and Capacity Planning, Toronto Hydro Robert Reinmuller, Director, System Planning, Hydro One

GTA and Central Ontario Regional Forum Operations Perspective David Short Director, Power System Assessments December 11, 2017

Overview 2

Operating challenges Under peak load conditions, this area can be exposed to low voltages and thermal overloads requiring capacitors to be placed into service and generation to be dispatched. On occasion, load transfers may be required in Metro Toronto region. Under light load periods this area can be exposed to high voltages. 500 kv circuits along the Bowmanville SS to Lennox TS corridor have had to be taken out of service as a control action. Under high imports from New York Niagara interconnection, 230 kv circuits with the Hamilton to Burlington area may become congested. 3

Toronto Zone Historical Operating Conditions 2014-2017 Summer Total Energy (June-Aug) Summer Peak Demand Annual Energy 2014 2015 2016 2017 13.1 TWh 13.2 TWh 14.3 TWh 12.9 TWh 8723 MW 9229 MW 9649 MW 8619 MW 51.5 TWh 51.2 TWh 51.4TWh - 4

Greater Toronto and Central Ontario Near-term Outlook Transmission transfer capability in Toronto and Central area is expected to be sufficient for the purpose of serving load, with sufficient margin to allow for planned outages. Metro Toronto Manby East or Manby West TS loading Copeland TS is expected to be completed in 2018 GTA North Increased Vaughan loads GTA East Clarington TS will help improve the reliability of central and eastern GTA once Pickering retires High voltages are an issue during low transfer levels on the 500 kv transmission system 5

Toronto Zone Summer 2018 Capacity and Energy Picture Capacity Picture - Normal peak demand forecast for July 2018 is 9,414 MW - Internal supply for July 2018 is 6,712 MW Energy Picture - Energy demand forecast for July 2018 is 4,644 GWh. - Internal energy capability for July 2018 is 4,789 GWh. 6

Appendix: Peak Demand in Toronto Zone Annual Peak Toronto Zonal Demand (MW) 7

Appendix Toronto Zonal Demand 2014 to 2017 8

Planning of the Ontario Electricity System Ahmed Maria, IESO December 11, 2017

Ontario s Electricity Sector Participants Regulation Transmission Planning, Market & System Operation Five Nations & others Ontario Electricity System and its Customers Distribution Generation Customers & other generators Hydro One Distribution & other local distribution utilities Residential Commercial Industrial 2

Three Levels of Electricity Planning Bulk System Planning Regional Planning Distribution Network Planning Long-term Energy Plan, Ontario Planning Outlook Integrated Regional Resource Plan, Regional Infrastructure Plan Distribution System Plan

Regions in GTA and Central Ontario 5 regions: 1. GTA West 2. GTA North 3. Toronto 4. GTA East 5. South Georgian Bay/Muskoka 4

Planning Considerations Infrastructure is aging In some regions, forecasted growth is exceeding supply capability In some regions, reliability of supply is a concern Expansion into greenfield areas away from electricity infrastructure is expected to occur Non-wire solutions may be an option to address electricity needs Municipal and community plans should be factored in There may be opportunities to maximize the use of existing assets 5

Panel Discussion: Planning for Today and Tomorrow Moderator: Chuck Farmer, Director, Stakeholder and Panelists: Public Affairs, IESO David Short, Power System Assessments, IESO Ahmed Maria, Senior Manager, Transmission Integration, IESO Angelo Boschetti, Supervisor, Engineering Department: Generation and Capacity Planning, Toronto Hydro Robert Reinmuller, Director, System Planning, Hydro One

Central Ontario Regional Forum December 11, 2017

Our Role Hydro One s Role in the Electric System TRANSMISSION DISTRIBUTION Electricity Generation Sources Transformer Transmission (Increased to System Higher voltage) Transformer (Decreased to Medium voltage) Distribution System 98% of capacity 75% of geography and 25% of end use customers Percentage of Ontario Market Transformer (Decreased to Lower voltage) Industrial, Residential, Commercial Customers 2

One of North America s Largest Electric Utilities Service Territory Pure electric transmission and distribution utility 30,000 circuit KMs of transmission lines across 98% of Ontario, home to 38% of Canadian population Largest local distribution company (LDC) in Ontario with 1.3 million end customers 99% of revenue from regulated operations Service area is larger than France or the State of Texas Combined transmission and distribution rate base of $17.83 billion Common shares traded on the TSX under ticker symbol H 3

Planning Considerations IESO LDC IESO TRANSMITTER 4

Major Transmission Projects Completed in Central Ontario Legend 500 kv 230 kv 115 kv Hearn SS, Leaside TS & Manby TS Switchyard (2013 & 2014) Manby TS: Reconfiguration (2014) Lakeshore Cable Refurbishment (2015) Midtown Tx Reinforcement (2016) YEC generation (2012) GATR (2016) Thornton Tx (2015) Kingston: Solar CGS (2015) Gardiner TS: T3/T4 (2009) Sidney TS: breakers (2017) Jarvis & Caledonia TS: Reactors (2012-13) Nebo TS: Breakers (2013) Burlington TS: Breakers (2016) TX replacement: Brantford TS (2013), Kenilworth TS (2014), Dundas TS (2015), Brant TS (2016) Clarington 5

Major Future Transmission Projects in Central Ontario Legend 500 kv 230 kv 115 kv Metrolinx Stations: Burlington Barrie Cityview Mimico Oshawa Scarborough Vaughan MTS #4 (2017) Holland breakers (2017) Markham MTS #5 (2023 Clarington TS (2018) Enfield TS (2019) Seaton MTS (2019) Amherst Island CGS (2018) Loyal Solar CGS (2018) Connect Napanee GS (2018) M20D/M21D Switches (2017) Brant 115 kv SS (2019) Kenilworth TS: EOL Tx (2021) Beach TS: HV Breakers/ Tx (2019) Middleport TS: HV breakers (2022) Nanticoke TS: HV breakers (2021) Gage TS: Reconfigure/EOL Tx (2019) Elgin TS: Reconfigure/EOL Tx (2019) Clarington Copeland MTS (2018) Runnymede TS New DESN K x W Line Upgrade (2018) Horner TS (2020) R x K Transmission (2022) Beck 1-2022 Beck 2-2021 Clarington 6

Goals Safe, Reliable, Efficient Facilitate the delivery of the Long Term Energy Plan Comply with stringent Reliability Standards Meet Customer Needs Meet Regional Planning Obligations Expand on System Monitoring and Analysis Continued Collaboration with Indigenous Communities Engagement and Transparency for all Customers Continue Innovation 7

Operational Excellence CANADIAN-BASED CHAMPION & LEADING NORTH AMERICAN UTILITY OPERATIONS 2020 VISION: Establish a culture of operational excellence with industry leading safety to deliver cost effective, reliable service for our customers. Create a repeatable platform for growth as the leading owner and operator of grid infrastructure in North America. Be an industry leader in SAFETY & ENVIRONMENT for our employees, contractors, and the public Deliver improved RELIABILITY to our customers, incorporating their input and priorities Provide COST EFFECTIVE service to our customers by improving our productivity Always be there for our CUSTOMERS with a seamless experience in all operations interactions Foundational OPERATING MODEL enabled by people, process, and technology 8