Hardware Testing of Photovoltaic Inverter Loss of Mains Protection Performance

Similar documents
magellan solar export control solutions Magellan Power Solar Gate

Use of Microgrids and DERs for black start and islanding operation

RESEARCH PROJECT VERBUNDNETZSTABIL

magellan solar export control solutions Magellan Power Solar Gate

Regenerative Utility Simulator for Grid-Tied Inverters

4th European PV-Hybrid and Mini-Grid Conference, Glyfada, Greece, May 2008

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS

RESILIENT SOLAR CASE STUDY: SUNY New Paltz NYPA Integrated Grid Pilot

Standards, Procedures and Policies for Grid Connection

Galapagos San Cristobal Wind Project. VOLT/VAR Optimization Report. Prepared by the General Secretariat

Field Verification and Data Analysis of High PV Penetration Impacts on Distribution Systems

Dynamic Study of Bonaire Island Power System: Model Validation and Project Experience

FAULT ANALYSIS OF AN ISLANDED MICRO-GRID WITH DOUBLY FED INDUCTION GENERATOR BASED WIND TURBINE

Introduction. Systems Specifications

Y9. GEH2.3: FREEDM Cost Benefit Analysis based on Detailed Utility Circuit Models

Development of New Megasolar PCS Models and Functions Conforming to Feed-in-Tariff System in Japan

A flywheel energy storage system for an isolated micro-grid

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems

Integrated Plant Control and Q on Demand 24/7 SUNNY TRIPOWER

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

Laboratory Infrastructure

Agility in energy Ahead of the challenge, ahead of the change

Laboratory Scale Microgrid Test-Bed Hardware Implementation

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

IEEE Workshop Microgrids

Jemena Electricity Networks (Vic) Ltd

INTERCONNECT CHALLENGES IN THE DEVELOPING WORLD S DISTRIBUTED GENERATION INFANCY. David C. Oehl, P.E. President MAVEN POWER

CHAPTER 5 FAULT AND HARMONIC ANALYSIS USING PV ARRAY BASED STATCOM

Research Brief. Impact of higher 25kV fault currents. T873 - October Background. Aims

CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM

Power Networks. Professor Graeme Burt Institute for Energy & Environment, University of Strathclyde

3.7 Areas where increasing levels of DER potentially affects operation of the system under Emergency Conditions

Smart Integrated Adaptive Centralized Controller for Islanded Microgrids under Minimized Load Shedding

Journal of American Science 2015;11(11) Integration of wind Power Plant on Electrical grid based on PSS/E

Control System for a Diesel Generator and UPS

Power Generation. PowerStore Renewable microgrid stabilization

MICROGRID SOLUTIONS. Renewable microgrid stabilization PowerStore

Comparative Analysis of Integrating WECS with PMSG and DFIG Models connected to Power Grid Pertaining to Different Faults

SIRFN Capability Summary European Distributed Energy Resources Laboratories (DERlab) e. V.

DYNAMIC BEHAVIOUR OF SINGLE-PHASE INDUCTION GENERATORS DURING DISCONNECTION AND RECONNECTION TO THE GRID

Renewable Energy & Storage Best Practice at TPL and Issues Faced. Murray Sheerin Power Generation Manager, Tonga Power Limited.

Design and Implementation of Reactive Power with Multi Mode Control for Solar Photovoltaic Inverter in Low Voltage Distribution System

GRID CONNECTION ISSUES FOR DISTRIBUTED GENERATION REVIEW & STANDARDS

Battery Energy Storage System addressing the Power Quality Issue in Grid Connected Wind Energy Conversion System 9/15/2017 1

Guidelines for connection of generators:

AN INTRODUCTION TO THE USE OF INVERTER POWER SUPPLIES IN GLOBAR APPLICATIONS HOW TO IMPROVE THE POWER FACTOR OF THE SYSTEM.

Guideline for Using IEEE 1547 for Solar PV Interconnection Page 1

DRAFT. Guidelines on Power quality & safety issues in usage of roof-top solar pv system CENTRAL ELECTRICITY AUTHORITY

Accidental Islanding of Distribution Systems with Multiple Distributed Generation Units of Various Technologies

INTERCONNECTION STANDARDS FOR PARALLEL OPERATION OF SMALL-SIZE GENERATING FACILITIES KILOWATTS IN THE STATE OF NEW JERSEY

Autonomous Voltage and Frequency Control by Smart Inverters of Photovoltaic Generation and Electric Vehicle

Grid Impact of Electric Vehicles with Secondary Control Reserve Capability

Grid Stability Analysis for High Penetration Solar Photovoltaics

Document Requirements for Engineering Review- PV Systems v1.1 12/6/2018

Legal Name of the Customer (or, if an individual, individual's name): Name: Contact Person: Mailing Address: Physical Address: City: State: Zip Code:

Power Systems Trainer

DC Microgrids and Distribution Systems for Residences

Compliance of Solar PV Installation with the New Renewables SA Grid Code Jimmy Goulding, Electrical Technologist, Aurecon, South Africa

APPLICATION NOTE USING A MODEL 3060-MS AS A REGENERATIVE AC SOURCE FOR PV INVERTER TEST APPLICATIONS. Abstract. Introduction. Dissipative Load Bank

CHAPTER 6 POWER QUALITY IMPROVEMENT OF SCIG IN WIND FARM USING STATCOM WITH SUPERCAPACITOR

PSO project EaseWind Enhanced ancillary services from Wind Power Plants. Anca D. Hansen DTU Wind Energy

Electrical Test of STATCOM Valves

INSTALLATION AND SET-UP MANUAL FOR THE NEW: AVR-07. A CONTROLPAK AVR Automatic Voltage Regulator for three-phase and single-phase alternators

1 EASY COMMISSIONING GUIDE FRONIUS PV-SYSTEM CONTROLLER

Technical Information Control of the Active Power Feed-In at the Grid-Connection Point with the SMA CLUSTER CONTROLLER

INCREASING electrical network interconnection is

Power Quality and Power Interruption Enhancement by Universal Power Quality Conditioning System with Storage Device

SP PRO ABB Managed AC Coupling

Use of STATCOM for Improving Dynamic Performance of Wind Farms Connected in Power Grid

Accelerating the realisation of key interface technologies in transport and energy - the PNDC

Copyright 2003 Advanced Power Technologies, Inc.

REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION

STABILIZATION OF ISLANDING PEA MICRO GRID BY PEVS CHARGING CONTROL

PV inverters in a High PV Penetration scenario Challenges and opportunities for smart technologies

Black Start capability in the Wind Turbine Market

Integration of DER: Grid Support Functions and Connectivity

Implementation of FC-TCR for Reactive Power Control

Power Conditioning of Microgrids and Co-Generation Systems

A TRIAL OF ALTERNATIVES TO DIRECTIONAL OVERCURRENT PROTECTION ON GRID TRANSFORMERS TO IMPROVE THE NETWORK CAPACITY TO ACCOMMODATE REVERSE POWER FLOW

Small Electrical Systems (Microgrids)

The ABB Medium Scale Power Transmission Test Case

SA Power Networks Commissioning Witnessing Checklist

Remote Area Hybrid Solar-Diesel Power Systems in Tropical Australia

Implementing a Microgrid Using Standard Utility Control Equipment

TRANSNATIONAL ACCESS USER PROJECT FACT SHEET

A STUDY ON ENERGY MANAGEMENT SYSTEM FOR STABLE OPERATION OF ISOLATED MICROGRID

Guideline for Parallel Grid Exit Point Connection 28/10/2010

PROPOSAL FOR STORAGE CONNECTION REQUIREMENTS

A study of the power capacity of regenerative inverters in a DC electric railway system

SIMULTANEOUS CONTROL OF VOLTAGE AND POWER OF MICRO-TURBINE IN DISTRIBUTION NETWORK

NORTH CAROLINA INTERCONNECTION REQUEST APPLICATION FORM. Utility: Duke Energy Progress

Hilton Hunkin Senior Application Engineer SMA Solar Technology South Africa

Surabaya Seminar Ferdinand Sibarani, Surabaya, 30 th October Power Quality

A Transient Free Novel Control Technique for Reactive Power Compensation using Thyristor Switched Capacitor

Distributed Energy Resources

PESC 2004 ABSTRACT. Tel Fax

Integration of Large Wind Farms into Electric Grids

2 MW Flywheel System Integration

TECHNICAL SPECIFICATION FOR INDEPENDENT POWER PRODUCERS. NB Power Customer Service and Distribution. June 2008

Targeted Application of STATCOM Technology in the Distribution Zone

Transcription:

Hardware Testing of Photovoltaic Inverter Loss of Mains Protection Performance I Abdulhadi*, A Dyśko *Power Networks Demonstration Centre, UK, ibrahim.f.abdulhadi@strath.ac.uk University of Strathclyde, UK, a.dysko@strath.ac.uk Keywords: Photovoltaic inverters, loss of mains protection, grid resilience, hardware testing. Abstract This paper presents the findings from hardware testing of photovoltaic inverters in a realistic low voltage network setting. The objective of the tests was to evaluate the performance of inverter built-in loss of mains protection. The evaluation focuses on ensuring that this protection operates as expected during islanding situations, while avoiding spurious tripping during severe grid disturbances. 1 Introduction Failure of Loss of Mains (LoM) protection to detect an unintended islanding condition of distributed generation (DG) can increase the risk of exposing personnel to safety hazards as well as cause damage to generators [1]. An equally undesirable behaviour of LoM protection may occur during grid wide disturbances which may cause spurious tripping of LoM protection. This presents a challenge for selecting a suitable LoM setting or implementing a reliable LoM algorithm. A particular challenge presents itself with inverter interfaced generation where the behaviour of the inverter is not very well understood under islanding or grid disturbance conditions and can vary widely between different manufacturers. Furthermore, there is no widely accepted model of behaviour for these inverters controllers or built-in protection algorithms. Currently the connection requirements for such inverters specified in the engineering recommendation G83/2 [3] only guarantees the inverter connection stability under system disturbances with rates of change of frequency up to 0.2 Hz/s. To this end, physical testing of inverters under anticipated future conditions reaching outside of G83 requirements becomes more favourable. As such, this paper presents the results of network testing of low voltage (LV) photovoltaic () inverters to determine the performance under islanding and grid disturbances, specifically: To establish the existence and quantify the non-detection zone (NDZ) of inverter LoM protection; To assess the stability of inverter connection to the grid during frequency and voltage phase shift disturbances, which may be compromised by the inverter LoM protection or controls. A range of commercially available inverters were tested to ensure that a representative behaviour is observed. Tested inverters are compliant with the UK engineering recommendations G59 and G83 for the connection of generation to the distribution network [2, 3]. The testing was conducted at the Power Networks Demonstration Centre (PNDC) [4]. The outcomes of these tests feed into the UK joint transmission/distribution code review panel activities, which assesses the impact of large disturbances on system frequency [5]. Such impact will become more pronounced with more generation being connected to the grid via inverter interfaces and overall lowering of system inertia. It is, therefore, crucial that the continuity of power generation from small scale inverters during system wide events is preserved. Through hardware testing of typical inverters under realistic system conditions this paper aims to establish any potential risks associated with high penetration levels of inverter connected generation. 2 Test setup Table 1 lists the inverters that were tested at the PNDC. Some of the inverters can have G83 or G59 settings activated as required. However, the table shows the active settings during testing. Phases Single Phase Three Phase Inverter ABB I- 5000-TL- OUTD* SMA Sunny Boy 5000TL* Kaco Powador 6002 Fronius IG Plus 30 V-1 SMA Tripower 10000TL* Maximum AC Power Rating Active settings during testing 5.56 kva G59/3 5.0 kva G59/3 5.0 kva G59/2 3.0 kva G83/1 10.0 kva G59/3 Table 1: List of inverters under test (*inverters marked have a transformer-less interface to the LV grid) 1

5 kw Chroma 62050H [6] emulators were used to drive the inverters. The emulators output the desired DC power according to EN50530 to achieve maximum power point tracking (MPPT) [7]. Two emulators were used to drive up to two single phase inverters simultaneously. The following subsections describe the tests performed which are grouped into three test categories. 2.1 Test category 1: islanding sensitivity Figure 1 shows the network configuration for conducting genuine islanding tests. The network is supplied via a motorgenerator (M-G) set at 11 kv. The inverters are connected to the LV network where a controllable resistive-inductive (RL) load bank is also connected. Islanding of the inverters and load bank is achieved by opening a switch designated as the point of common coupling (PCC). A calibrated power quality meter is used to measure the current and voltage at the PCC and inverter outputs. The purpose of this test is to ensure that the LoM protection of the inverters operates successfully, especially when the pre-lom power flow across the PCC is very small. The power flow through the PCC is reduced to the lowest possible value by adjusting both the power output of the inverters and the load bank power consumption. M M-G set PCC C RL load bank B Figure 1: Network configuration for test category 1 A 2.2 Test category 2: stability against RoCoF disturbances The purpose of this test is to ensure that the inverters do not spuriously disconnect from the grid during a severe rate of change of frequency (RoCoF) event. A 1 Hz/s (accelerating and decelerating) RoCoF event is achieved by controlling the speed set point of the M-G set (refer to Figure 2). The network is instrumented as in test category 1 to monitor the behaviour of the inverters during this test. Frequency Control M M-G set C RL load bank B Figure 2: Network configuration for test category 2 A Typical frequency profiles during accelerating and decelerating RoCoF tests are shown in Figure 3 and Figure 4 respectively. Note that the frequency bands containing the RoCoF events are selected to ensure that the inverters over and under frequency protection does not operate. Figure 3: Frequency profile during accelerating RoCoF test Figure 4: Frequency profile during decelerating RoCoF test In order to verify that the obtained frequency profile does indeed produce the desired RoCoF, a sample of measured instantaneous voltage was injected into a commercial RoCoF protection relay. The relay reported 1.35 Hz/s on average from two sample voltage injections. This is deemed acceptable for the testing. 2.3 Test category 3: stability against simultaneous voltage phase shift and RoCoF disturbances The purpose of this test category is to ensure that the inverters remain synchronised to the grid during a simultaneous RoCoF and voltage phase shift event. Such disturbance emulates a grid event where large loss of generation is accompanied by a change in grid bus voltage angle which is typical of the locations in the proximity of a major transmission system fault. Figure 5 shows the network configuration during this test category. The M-G speed is controlled to initially introduce a drop in frequency at a rate of 0.5 Hz/s. After 0.5s of initiating the frequency drop, a phase-phase LV fault is introduced to the system. Introducing this fault aims to produce sufficient step change in reactive power flow in the system to create a sudden shift in voltage phase angle together with the network frequency drop. A typical frequency profile obtained during this test is shown in Figure 6. The obtained RoCoF and voltage phase shift was verified as in test category 2. The LoM relay reported an average phase shift of 6.5 from two sample voltage 2

injections. The measured RoCoF increased after the introduction of the LV fault to 5.5 Hz/s. Frequency Control M M-G set C RL load bank LV Fault thrower B A Figure 5: Network configuration for test category 3 Figure 6: Typical frequency profile during category 3 tests Figure 7 shows the physical test setup at the PNDC where the inverters are connected to the facilitiy s LV network. inverters exporting a minimum amount of reactive power while generating, as well as the combined reactance of the cable and overhead line circuits in the test network. All inverters disconnected successfully for LoM tests. This holds for both tests where inverters were connected individually or in pairs to the LV network. The pre-lom event power flows and average disconnection times are summarised in Table 2. The direction of power flow across the PCC is positive for active and reactive power flow towards the load. The disconnection time is defined as the period between the opening of the PCC and the tripping of the inverter. The latter is determined from the collapse of the inverter output current to zero. The average times are calculated from two measurements. Inverter 1 Inverter 2 PCC power flow prior to islanding Active Reactive Power Power (W) (VAr) Average inverter disconnection time (s) ABB -10-10 0.406 Kaco 20 10 0.9 Fronius -2 143 0.275 SMA (1 SMA (3 0-10 0.123-40 40 0.126 ABB SMA (1 0-50 0.324 ABB Kaco 0 20 0.493 Fronius Kaco 0-160 0.465 Kaco SMA (1-10 30 0.458 Table 2: Summary of category 1 test results Figures 8 to 10 show the output voltage and current of the ABB, Fronious and SMA (3- inverters during the islanding test. The period between LoM initiation and inverter disconnection is marked with vertical black lines on the waveforms. The behaviour of the inverters varies slightly between a sudden or gradual collapse of output voltage. Figure 7 Inverter testing setup at the PNDC 3 Inverter performance evaluation The main findings from the tests are presented in this section. Due to the lack of space, only a selection of the recorded measurements will be presented to enforce the main findings. 3.1 Test category 1 results and evaluation Active power flow achieved through the PCC for all tests was less than 1% of the connected inverter kva rating. The reactive power flow was more difficult to minimise due to the Figure 8: Output of ABB inverter during islanding test 3

reduction of active power is illustrated Figure 13. Further testing determined that a minimum disturbance of 0.7 Hz/s over a frequency band of 1.5 Hz is required before the ABB inverter starts exhibiting this power drop (see Figure 14). Otherwise, with lower RoCoF values, the active power output of the inverter remains largely stable (see Figure 15 for a 0.6 Hz/s disturbance). This drop in active power output may only be a cause of concern if a large number of them were connected to the grid and experience a frequency drop of around 1.5 Hz (i.e. down to 48.5 Hz) at a rate of 0.7 Hz/s. At this point, low frequency load shedding would operate to recover the system frequency. Figure 9: Fronius inverter output during islanding test Figure 11: SMA 1-phase inverter output during +1 Hz/s test Figure 10: SMA 3-phase inverter output during islanding test 3.2 Test category 2 results and evaluation During this test, all inverters remained synchronised to the grid. However, the behaviour of the inverters in terms of power output during this test varies. Transformer-less inverters exhibit a momentary change in reactive power output. A positive RoCoF event results in the inverter absorbing reactive power, while additional reactive power is exported during a negative RoCoF event. The extent and duration of this change depends on the inverter and severity of the RoCoF event. Figure 11 shows an example of this where the SMA (1-phase inverter) absorbs around 1 kvar during at +1 Hz/s disturbance. Note that the power measurements provided by the power quality meter are 0.25 s averages. Inverters with a transformer interface (i.e. Kaco and Fronious) do not exhibit a significant change in reactive power output. An example of this is depicted in Figure 12 which shows the power output of the Kaco inverter during a +1 Hz/s event. In addition to the reactive power output change, the ABB inverter active output is reduced under certain circumstances. It was observed that the active power output of the inverter is reduced to zero for 1 s when a system RoCoF of 1 Hz/s is applied over a 2 Hz band (e.g. between 51-49 Hz). This Figure 12: Kaco inverter output during +1 Hz/s test Figure 13: ABB inverter output during -1 Hz/s RoCoF test 4

The inverter also contributes a small amount of fault current. Quantifying the fault current contribution of the inverters is out with the scope of this paper. Figure 17 shows the output of the ABB inverter during the same test. Similar voltage and current phase shifts can also be observed. 400 30 300 20 Figure 14: ABB inverter output during -0.7 Hz/s RoCoF over a 1.5 Hz band test Voltage (V) 200 100 0-100 -200-300 10 0-10 -20 Current (A) -400 48.45 48.5-30 48.55 Time (s) Figure 17 ABB inverter output during a category 3 test All inverters remained synchronised to the grid during this test category. 4 Conclusion Figure 15: ABB inverter output during -0.6 Hz/s RoCoF test 3.3 Test category 3 results and evaluation Figure 16 shows the voltage and current output of the Kaco inverter during this test. The voltage phase shift and subsequent shift in current phase during the fault inception can be observed in the figure. A change in inverter power factor is also observed prior to the fault due to the change in reactive power output during the initial frequency drop as shown in category 2 tests. Based on the testing conditions, tested inverters and observations, it can be concluded that there is no NDZ associated with the inverters during islanding. However, it is difficult to generalise this finding onto a network with a large number of inverter interfaced generation, especially when mixed with other generating technologies. This warrants further investigation where multiple inverters could be connected to the LV test network. The tests have confirmed that the inverters are able to remain synchronised with the grid under RoCoF events of up to 1.35 Hz/s measured over a 2 Hz frequency deviation band. Introducing a voltage phase shift of up to 6.5 during an initial 0.5 Hz/s grid frequency drop did not result in inverter disconnection either. Some variations in inverter output during testing implies subtleties in implemented inverter controls. These manifest themselves in the way inverter output voltage collapses after islanding and in changes in the active and reactive power output during RoCoF disturbances. However, none of these small control implementation differences seem to have a notable impact on the sensitivity of LoM detection or stability under other tested disturbances. Acknowledgements Figure 16: Kaco inverter output during a category 3 test The Authors would like to thanks the Energy Networks Association and particularly the UK National Grid for their funding and support while conducting this project. 5

References [1] Energy Networks Association, "ENA ETR 139: Recommendations for Setting of Loss of Mains Protection Relays," 2009. [2] Energy Networks Association, "Engineering Recommendation G59, Issue 3: Recommendations for the Connection of Generating Plant to the Distribution Systems of Licensed Distribution Network Operators," 2013. [3] Energy Networks Association, "ER G83/2: Recommendations for the Connection of Type Tested Small-scale Embedded Generators (Up to 16A per Phase) in Parallel with Low-Voltage Distribution Systems," 2012. [4] C. D. Booth, F. Coffele, and G. M. Burt, "The Power Networks Demonstration Centre: An environment for accelerated testing, demonstration and validation of existing and novel protection and automation systems," in DPSP 2014, 2014, pp. 1-6. [5] National Grid, GC0035 / GC0079 Frequency Changes during Large Disturbances and their effect on the total system - Phase 1 & 2. Available: http://goo.gl/h2zmvr [6] Chroma, "Programmable DC Power Supply with Solar Array Simulation: Model 62000H-S Series Data Sheet," Available: http://www.chromaate.com [7] British Standards, "BS EN 50530:2010+A1:2013 Overall Efficiency of Grid Connected Photovoltaic Inverters," 2013. 6