SERTP rd Quarter Meeting

Similar documents
2013 SERTP. Welcome. SERTP rd Quarter Meeting. 2 nd RPSG Meeting

SERTP rd Quarter Meeting

2010 SERTP. Welcome. SERTP rd Quarter Meeting. 2 nd RPSG Meeting 9:00 AM 3:00 PM

Southeastern Regional Transmission Planning (SERTP)

2011 SERTP Annual l S E S RTP T P S u S mmit 1

SERTP - 1 st Quarter Meeting

System Impact Study Report

Southeastern Region Transmission Planning. 10 Year Transmission Expansion Plan

PSE Attachment K Puget Sound Area Transmission Meeting

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

West Station-West Cañon 115 kv Transmission Project

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

Feasibility Study Report

SERTP Southeastern Regional Transmission Planning

100 MW Wind Generation Project

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Appendix D Black Hills Project Summary

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Sub Regional RTEP Committee Western Region ATSI

Sub Regional RTEP Committee Mid-Atlantic

Supplemental Report on the NCTPC Collaborative Transmission Plan

Feasibility Study Report

Feasibility Study for the Q MW Solar Project

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

New Mexico Transmission Expansion Concepts For Wind Resources

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

Feasibility Study Report

The Long-Range Transmission Plan

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Sheffield-Highgate Export Interface SHEI. VSPC Quarterly Meeting October 18, 2017

Local Transmission Plan. October 11, 2013 Revised August 25, 2014

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Consulting Agreement Study. Completed for Transmission Customer

Donna Painter, Executive Consultant February 27, 2013

Terry Blackwell Page 1 of 5. Education North Carolina State University BS, Electrical Engineering Power Systems emphasis

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

East. Georgia Integrated Transmission System (ITS) Jointly Planned ITS. Dalton Utilities. GTC (Georgia Transmission Corporation)

Merger of the generator interconnection processes of Valley Electric and the ISO;

East. Dalton Utilities. GTC (Georgia Transmission Corporation) MEAG (Municipal Electric Authority of GA) Southern Company Transmission

Falcon-Midway 115 kv Line Uprate Project Report

Overview of ISO New England and the New England Wholesale Power Markets

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC

ERCOT Independent Review of Houston Import RPG Project

Local Transmission Plan. Rev. 1: April 2018

PUD ELECTRIC SYSTEM INTERCONNECTION

Feasibility Study for the Q MW Solar Project

Black Hills Project Summary

Alberta Electric System Operator Saleski Transmission Project Needs Identification Document

Generator Interconnection System Impact Study For

Interconnection System Impact Study Report Request # GI

Southeastern Regional Transmission Planning Process 10 Year Preliminary Expansion Plan Meeting. June 24, 2009

DFO STATEMENT OF NEED REPORT

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

East. Dalton Utilities. GTC (Georgia Transmission Corporation) MEAG (Municipal Electric Authority of GA) Southern Company Transmission

Maddox Creek to Southwest Lima 345kV New Transmission Line November 15, 2016

Illinois State Report

South Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget

Gateway South Transmission Project

APPENDIX F: Project Need and Description

Transmission Planning Attachment K Public Input Meeting

Key to Status Fields in the Project List

TRANSMISSION PLANNING CRITERIA

Cromby Units 1 and 2 and Eddystone Units 1 and 2. Deactivation Study

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

East. Georgia Integrated Transmission System (ITS) GTC (Georgia Transmission Corporation) MEAG (Municipal Electric Authority of GA)

South Carolina Regional Transmission Planning. Stakeholder Meeting. Lake Murray Training Center. Lexington, SC. September 12, 2013

New Jersey State Report

SERTP nd Quarter Meeting

Review Initial Results of Reliability Assessments. Inter-regional. Discuss Alternative Solutions from Stakeholders

National Grid s 2017 Local Transmission Plan

MTEP13 SPM #2- Central Region. March 25, 2013

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Interconnection Feasibility Study Report GIP-369-FEAS-R1

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1

South Carolina Regional Transmission Planning. Stakeholder Meeting. Web Conference

MILLIGAN SOLAR PROJECT

Sub Regional RTEP Committee - Southern. August 19, 2011

Southern California Edison Rule 21 Storage Charging Interconnection Load Process Guide. Version 1.1

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

South Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget

Project #148. Generation Interconnection System Impact Study Report

TransWest Express Project

South Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION

Interconnection Feasibility Study Report GIP-157-FEAS-R2

EIPC HIGH LEVEL TRANSMISSION COST ESTIMATION TASK #5: DOE PROJECT NO. DE-OE

Header. Reasonableness Test RT 007/11 Balhannah & Uraidla 66 / 33 kv Substations. RT Balhannah and Uraidla - Final Draft Page 1 of 8

Transmission Expansion Advisory Committee

SPP OVERVIEW. Mike Ross Senior Vice President, Government Affairs and Public Relations

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04

Sub-Regional RTEP Committee PJM South

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT

Transcription:

2014 SERTP SERTP 2014 3 rd Quarter Meeting 2 nd RPSG Meeting September 30 th, 2014 APC Headquarters Birmingham, AL

2014 SERTP Process Information The SERTP process is a transmission planning process. Please contact the respective transmission provider for questions related to real-time operations or OATT transmission service. 2

Purposes & Goals of Meeting 2014 SERTP Preliminary Economic Study Results Regional Modeling Update Order No.1000 Update Next Meeting Activities EIPC Update 3

Preliminary Economic Planning Studies SERTP Preliminary Economic Planning Studies 4

Study Process SERTP Sponsors identify the transmission requirements needed to move large amounts of power above and beyond existing long-term, firm transmission service commitments Analysis is consistent with NERC standards and company-specific planning criteria Models used to perform the analysis incorporate the load forecasts and resource decisions as provided by LSEs Power flow models are made available to stakeholders to perform additional screens or analysis Scoping Meeting held in May Preliminary Economic Planning Studies 5

Five Economic Planning Studies Santee Cooper Border to FRCC Border 300 MW (2017 Summer Peak and Shoulder) FRCC Border to Santee Cooper Border 300 MW (2017 Summer Peak and Shoulder) TVA Border to Southern 500 MW (2019 Summer Peak and Shoulder) TVA Border to Southern Preliminary Economic Planning Studies 1500 MW (2019 Summer Peak and Shoulder) TVA Border to Duke Energy Border 1000 MW (2019 Summer Peak and Shoulder) 6

Power Flow Cases Utilized Study Years: 2017 and 2019 Load Flow Cases: Preliminary Economic Planning Studies 2014 Series Version 2A Summer Peak and Shoulder 7

Preliminary Report Components Thermal Analysis Preliminary Economic Planning Studies Contingency analysis to identify constrained elements/contingency pairs Interface Transfer Capability Analysis Potential Solutions Transmission enhancements and cost estimates 8

Process Information Preliminary Economic Planning Studies The following information depicts recommended enhancements for the proposed transfer levels above and beyond existing, firm commitments. Therefore, this information does not represent a commitment to proceed with the recommended enhancements nor implies that the recommended enhancements could be implemented by the study dates (2017 and 2019). These potential solutions only address constraints identified within the SERTP Sponsors areas that are associated with the proposed transfers. Other Balancing Areas were not monitored which could result in additional limitations and required system enhancements. 9

Preliminary Economic Planning Studies Economic Planning Studies Santee Cooper Border to FRCC Border 300 MW 10

Study Assumptions Santee Cooper to FRCC 300 MW Transfer Type: Load to Load (2017 Summer Peak and Shoulder) Source: Uniform load scale within Santee Cooper Sink: Uniform load scale within FRCC FRCC Source Sink 11

TVA DUKE 9.2% 6.4% 20.6% 41.3% 3.8% 8.3% 17.9% MPC 3.8% APC GA ITS 96.1% 0.7% 0.2% PS 4.4% 0.9% Gulf 1.4% 0.1% 3.9% Source Sink FRCC

Transmission System Impacts Thermal Constraints Identified: None Santee Cooper to FRCC 300 MW Total Cost (2014$) = $0 13

Preliminary Economic Planning Studies Economic Planning Studies FRCC Border to Santee Cooper Border 300 MW 14

Study Assumptions FRCC to Santee Cooper 300 MW Transfer Type: Load to Load (2017 Summer Peak and Shoulder) Source: Uniform load scale within FRCC Sink: Uniform load scale within Santee Cooper FRCC Source Sink 15

TVA DUKE 9.2% 6.4% 20.6% 41.3% 3.8% 8.3% 17.9% MPC 3.8% APC GA ITS 96.1% 0.7% 0.2% PS 4.4% 0.9% Gulf 1.4% 0.1% 3.9% Source Sink FRCC

Transmission System Impacts Thermal Constraints Identified: None FRCC to Santee Cooper 300 MW Total Cost (2014$) = $0 17

Preliminary Economic Planning Studies Economic Planning Studies TVA Border to Southern 500 MW 18

Study Assumptions Transfer Type: Generation to Generation (2019 Summer Peak and Shoulder) Source: A new generator interconnection to the existing Shelby 500 kv substation (TVA) Sink: Southern Generation TVA to Southern 500 MW Source Sink 19

TVA DUKE 28.4% 32.6% 16.0% 8.0% 21.1% MPC 9.8% APC GA ITS 1.1% 5.2% Gulf 0.2% 0.0% FRCC 0.0% 1.9% PS 0.6% 0.3% Source Sink

Transmission System Impacts Thermal Constraints Identified: Two (2) 230 kv T.L. One (1) 161 kv T.L. TVA to Southern 500 MW Total Cost (2014$) = $135,700,000 21

Significant Constraints TVA to Southern 500 MW Limiting Elements Rating (MVA) Thermal Loading (%) Without Request With Request Fayette Gorgas 161 kv T.L. 193 103.9 (1) 117.8 Lexington Russell 230 kv T.L. 596 98.5 102.8 Clay Leeds 230 kv T.L. 602 97.4 100.6 (1) A current operating procedure is sufficient to alleviate this identified constraint without the addition of the proposed transfer. However, the additional transfer exacerbates the loading on this transmission facility such that the operating procedure becomes insufficient. 22

Significant Constraints TVA to Southern 500 MW APC GA ITS MPC Gulf 23

Significant Constraints TVA to Southern 500 MW Russell Lexington 230 kv 24

Proposed Enhancement TVA to Southern 500 MW (P1) Russell Dam Athena 230 kv 25

Significant Constraints TVA to Southern 500 MW Fayette Gorgas 161 kv Clay Leeds 230 kv 26

Proposed Enhancements TVA to Southern 500 MW (P2) Fayette Gorgas 161 kv (P3) Clay Leeds 230 kv 27

Projects Identified TVA to Southern 500 MW Item Proposed Enhancements Cost ($) P1 Russell Dam Athena 230 kv T.L. - 53 miles of new 230 kv Line - Bundled (2) 1351 ACSR at 100 C $82,000,000 P2 P3 Fayette Gorgas 161 kv T.L. - Rebuild 38.8 miles with 1351 ACSR at 100 C $31,500,000 Clay TS Leeds TS 230 kv T.L. - Reconductor 17.3 miles with bundled (2) 1351 ACSR at 100 C $22,200,000 Total Cost (2014$) = $135,700,000 28

Preliminary Economic Planning Studies Economic Planning Studies TVA Border to Southern 1500 MW 29

Study Assumptions Transfer Type: Generation to Generation (2019 Summer Peak and Shoulder) Source: A new generator interconnection to the existing Shelby 500kV substation (TVA) Sink: Southern Generation TVA to Southern 1500 MW Source Sink 30

TVA DUKE 28.4% 32.6% 16.0% 8.0% 21.1% MPC 9.8% APC GA ITS 1.1% 5.2% Gulf 0.2% 0.0% FRCC 0.0% 1.9% PS 0.6% 0.3% Source Sink

Transmission System Impacts Thermal Constraints Identified: One (1) 500 kv T.L. Eight (8) 230 kv T.L. Two (2) 161 kv T.L. One (1) 115 kv T.L. One (1) 500/230 kv transformer One (1) 230/115 kv transformer TVA to Southern 1500 MW Total Cost (2014$) = $277,200,000 32

TVA to Southern 1500 MW Significant Constraints Pass 0 Limiting Elements Rating (MVA) Thermal Loading (%) Without Request With Request Oostanaula East Dalton 230 kv T.L. 664 93.8 109.1 Lexington Russell 230 kv T.L. 596 98.5 106.8 South Hall Candler 230 kv T.L. 509 95.9 104.3 Conasauga Bradley 500 kv T.L. (1) 2598 90.2 104.1 Bio Vanna 230 kv T.L. 433 99.6 103.4 Lexington East Watkinsville 230 kv T.L. 602 94.7 102.6 Miller 500/230 kv Transformer 1613 90.7 102.0 East Watkinsville 230/115 kv Transformer 332 90.4 100.3 Vanna New Haven 230 kv T.L. 433 84.2 100.2 (1) The limiting element of this tie-line constraint is located within TVA. 33

TVA to Southern 1500 MW Significant Constraints Pass 0 APC GA ITS MPC Gulf 34

TVA to Southern 1500 MW Significant Constraints Pass 0 Conasauga Bradley 500kV Oostanaula E. Dalton 230kV Bio Vanna New Haven 230 kv S. Hall Candler 230kV E. Watkinsville 230/115 kv Russell Lexington E. Watkinsville 230 kv Miller 500/230 kv 35

TVA to Southern 1500 MW Proposed Enhancements Pass 1 (P1) Widows Creek Bowen 500 kv 36

Significant Constraints Pass 1 Limiting Elements TVA to Southern 1500 MW Rating (MVA) Thermal Loading (%) Without Request With Request Fayette Gorgas 161 kv T.L. 193 103.9 (1) 129.5 Attalla Albertville 161 kv T.L. 193 94.0 107.5 Collins Magee 115 kv T.L. 100 88.9 105.7 Miller Boyles 230 kv T.L. 602 97.8 103.9 Clay Leeds 230 kv T.L. 602 97.4 103.0 (1) A current operating procedure is sufficient to alleviate this identified constraint without the addition of the proposed transfer. However, the additional transfer exacerbates the loading on this transmission facility such that the operating procedure becomes insufficient. 37

TVA to Southern 1500 MW Significant Constraints Pass 1 APC GA ITS MPC Gulf 38

TVA to Southern 1500 MW Significant Constraints Pass 1 Attalla Albertville 161 kv Fayette Gorgas 161 kv Clay Leeds 230 kv Miller Boyles 230 kv 39

TVA to Southern 1500 MW Significant Constraints Pass 1 Collins Magee 115 kv 40

TVA to Southern 1500 MW Proposed Enhancements Pass 2 (P4) Attalla - Albertville 161 kv (P2) Fayette Gorgas 161 kv (P6) Miller Boyles 230 kv (P3) Clay Leeds 230 kv 41

TVA to Southern 1500 MW Proposed Enhancements Pass 2 (P5) Collins Magee 115 kv 42

Projects Identified TVA to Southern 1500 MW Item Proposed Enhancements Cost ($) P1 Widows Creek (TVA) Bowen 500 kv T.L. - 60 miles of new 500 kv Line (Southern s portion) - Bundled (3) 1113 ACSR at 100 C $185,000,000 P2 P3 P4 Fayette Gorgas 161 kv T.L. - Rebuild 38.8 miles with 1351 ACSR at 100 C $31,500,000 Clay TS Leeds TS 230 kv T.L. - Reconductor 17.3 miles with bundled (2) 1351 ACSR at 100 C $22,200,000 Attalla Albertville 161 kv Line - Reconductor 19.6 miles with 1351 ACSR at 100 C $19,500,000 43

Projects Identified (cont.) TVA to Southern 1500 MW Item Proposed Enhancements Cost ($) P5 Collins Magee 115 kv T.L. - Reconductor 8.5 miles with 795 ACSR at 100 C $3,000,000 P6 Miller Boyles 230 kv T.L. - 6.2 miles of new 230 kv line with 1351 ACSS at 200 C $16,000,000 Total Cost (2014$) = $277,200,000 44

Preliminary Economic Planning Studies Economic Planning Studies TVA Border to Duke Energy Border 1000 MW 45

Study Assumptions TVA to Duke Energy 1000 MW Transfer Type: Generation to Load (2019 Summer Peak and Shoulder) Source: A new generator interconnection to the existing Shelby 500kV substation (TVA) Sink: Uniform load scale within Duke Energy Source Sink 46

TVA DUKE 12.5% 20.8% 22.9% 11.2% 6.2% 17.3% 6.3% MPC 6.2% APC GA ITS 0.9% 1.0% 0.0% PS 1.4% 0.3% Gulf 0.9% 0.6% 0.9% Source Sink FRCC

Transmission System Impacts Thermal Constraints Identified: One (1) 230 kv T.L. One (1) 161 kv T.L. TVA to Duke Energy 1000 MW Total Cost (2014$) = $53,700,000 48

Significant Constraints TVA to Duke Energy 1000 MW Limiting Elements Rating (MVA) Thermal Loading (%) Without Request With Request Fayette Gorgas 161 kv T.L. 193 103.9 (1) 130.8 Clay Leeds 230 kv T.L. 602 97.4 103.9 (1) A current operating procedure is sufficient to alleviate this identified constraint without the addition of the proposed transfer. However, the additional transfer exacerbates the loading on this transmission facility such that the operating procedure becomes insufficient. 49

Significant Constraints TVA to Duke Energy 1000 MW APC GA ITS MPC Gulf 50

Significant Constraints TVA to Duke Energy 1000 MW Fayette Gorgas 161 kv Clay Leeds 230 kv 51

Proposed Enhancements TVA to Duke Energy 1000 MW (P1) Fayette Gorgas 161 kv (P2) Clay Leeds 230 kv 52

Projects Identified TVA to Duke Energy 1000 MW Item Proposed Enhancements Cost ($) P1 Fayette Gorgas 161 kv T.L. - Rebuild 38.8 miles with 1351 ACSR at 100 C $31,500,000 P2 Clay TS Leeds TS 230 kv T.L. - Reconductor 17.3 miles with bundled (2) 1351 ACSR at 100 C $22,200,000 Total Cost (2014$) = $53,700,000 53

2014 SERTP SERTP Regional Modeling Update 54

Regional Modeling Update Exchanged the latest transmission models for the ten year planning horizon with FRCC. FRCC models will be incorporated into subsequent base cases. SERC Regional Model Development 2014 SERTP Data Bank Update ( DBU ) May 20 May 22 2014 Series SERC LTSG models completed Linear Transfers and AC verification performed Currently compiling the results into the SERC LTSG Report 55

2014 SERTP SERTP Order No.1000 Update 56

2014 SERTP Order No.1000 Update Prequalified Transmission Developer Applications Deadline for application submittal was August 1 st, 2014 for the 2015 planning cycle. No prequalification applications were submitted. Regional Planning Analysis Version 2 SERTP Regional Models available on SERTP Website. SERTP Sponsors currently performing analysis on regional models including assessment to identify and evaluate potential regional transmission projects. 57

Next Meeting Activities 2014 SERTP Annual Transmission Planning Summit Location: TBD Date: December 2014 Purpose: Final Economic Planning Study Results Order 1000 Implementation Update Regional Transmission Plan Assumptions Input Session 58

2014 SERTP Questions? 59