Sub : In the matter of determination of Parallel Operation Charges. MPERC, Bhopal - Petitioner

Similar documents
Before the. Case No. 106 of 2009

KERALA STATE ELECTRICITY REGULATORY COMMISSION Thiruvananthapuram. Present : Sri. T. M. Manoharan, Chairman Sri. K. Vikraman Nair, Member OP 11/2016

Wheeling charges, Banking charges & Cross Subsidy Surcharge for Solar Power Generators

POWER FACTOR REBATE-BOLD DECISION FROM REGULATOR

UP Electricity Regulatory Commission Vidyut Niyamak Bhawan, Vibhuti Khand, Gomti Nagar, Lucknow. Public Notice

CASE No. 35 of In the matter of

CASE No. 139 of Coram. Shri. Azeez M. Khan, Member Shri. Deepak Lad, Member. Shri A. W. Mahajan (Rep) ORDER

Policy for Net-Metering based Renewable Energy Applications, Madhya Pradesh, DRAFT

Policy for Net-Metering based Renewable Energy Applications, Madhya Pradesh, DRAFT

Uttar Pradesh Electricity Regulatory Commission, Lucknow

MPSEZ Utilities Private Limited Truing up for FY and Determination of Tariff for FY

Case No. 163 of In the matter of

Case No. 109 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member. Maharashtra State Electricity Distribution Co. Ltd.

JEA Distributed Generation Policy Effective April 1, 2018

Petition No. 1051, 1054 & 1055 of 2015 BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW Date of Order :

Maharashtra Electricity Regulatory Commission (Renewable Purchase Obligation, Its. Regulations, 2016 STATEMENT OF REASONS

Chapter 3.1: Electrical System

Northeastern Rural Electric Membership Corporation Schedule DG-2 Columbia City, Indiana Page 1 of 5

In-House paper on Implementation of Telescopic Tariffs in LMV-6 category

PRESS RELEASE ON 19March, 2018

Reactive Power Requirements and Financial Compensation. Addendum to Draft Final Proposal

Renewable Regulatory Fund (RRF) Mechanism : -

The Role of Electricity Storage on the Grid each location requires different requirements

STATE LOAD DISPATCH CENTRES (SLDC)

216B.164 COGENERATION AND SMALL POWER PRODUCTION.

RULES ENABLING THE NET- METERING PROGRAM FOR RENEWABLE ENERGY

TERMS AND CONDITIONS

IJRASET 2013: All Rights are Reserved

PUNJAB STATE POWER CORPORATION LIMITED REPORT ON OUTCOMEOF THE MOCK TRIALSFOR DESIGN OF TWO PART TARIFF

KERALA STATE ELECTRICITY REGULATORY COMMISSION. NOTIFICATION Dated, Thiruvananthapuram 6 th August,2007

Large General Service Time-of-Use Storage Program

Noble County Rural Electric Membership Corporation

Northeastern Rural Electric Membership Corporation Columbia City, Indiana

is attached to and becomes a part of a agreement dated, 20,

Procedure in the case of connection requests by power plant operators for the purpose of feeding into the Amprion grid

POWER PURCHASE AGREEMENT FOR ROOFTOP SOLAR PV PLANTS WITH NET METERING ARRANGEMENT

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program.

Direct Energy Regulated Services

Tariff Circular & Tariff Schedules

THE PUBLIC SERVICE COMMISSION OF MARYLAND

University of Alberta

Bihar Electricity Regulatory Commission Vidyut Bhawan, J.L.Nehru Marg, Patna

kvah Billing - Frequently Asked Questions (FAQs)

Case Nos. 108 of In the matter of

Noble County Rural Electric Membership Corporation

EXTRA ORDINARY 16 AASHAADHA, 1937(S) BIHAR ELECTRICITY REGULATORY COMMISSION

JAMMU AND KASHMIR STATE POWER DEVELOPMENT CORPORATION LIMITED PUBLIC NOTICE

Madhya Pradesh Policy for Rooftop Renewable Energy Projects, 2016

RIPUC No Cancelling RIPUC No Sheet 1 THE NARRAGANSETT ELECTRIC COMPANY NET METERING PROVISION

POWER DEVELOPMENT DEPARTMENT OF JAMMU AND KASHMIR JANIPUR, JAMMU TEL: FAX: PUBLIC NOTICE

KANSAS CITY POWER AND LIGHT COMPANY P.S.C. MO. No. 7 Fourth Revised Sheet No. 39 Canceling P.S.C. MO. No. 7 Third Revised Sheet No.

M.P.S.C. No. 2 Electric Third Revised Sheet No. 65 (Rate Case) Cancels Second Revised Sheet No. 65

Roof Top Solar Power Net Metering Solution. Guidelines for implementation of Net Metering for Roof Top Solar Power System

GREEN TRANSPORT POLICY EVALUATION STUDY EVIA CONFERENCE, 05-6 DECEMBER 2016 IDC CONFERENCE CENTER, SANDTON

TERMS AND CONDITIONS XXV. NET METERING CUSTOMERS AND SMALL AGRICULTURAL GENERATORS

Interconnection Process for Generation Systems

TRANSMISSION CONNECTION CHARGING METHODOLOGY STATEMENT

Toyota Motor North America, Inc. Grant of Petition for Temporary Exemption from an Electrical Safety Requirement of FMVSS No. 305

Western Electricity Supply Company of Orissa Ltd., Burla, Sambalpur , Orissa

ATTACHMENT 14 RESOLUTION NO. 5888(14) Supersedes Schedule NEM of Resolution No. 5592(09) Schedule NEM NET ENERGY METERING

CUSC Panel 30 September 2016 John Martin National Grid

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

Determination of Average Pooled Purchase Cost for FY

FITCHBURG GAS AND ELECTRIC LIGHT COMPANY NET METERING SCHEDULE NM

Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kva to 10 MVA or less)

S T A F F R E P O R T

GC108: EU Code: Emergency & Restoration: Black start testing requirement

National Electric Power Regulatory Authority Islamic Republic of Pakistan

STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DE LIBERTY UTILITIES (GRANITE STATE ELECTRIC) CORP. d/b/a LIBERTY UTILITIES

CITY OF MINNEAPOLIS GREEN FLEET POLICY

Case No. 141 of Coram. Shri. Azeez M. Khan, Member Shri. Deepak Lad, Member. V/s Maharashtra State Electricity Distribution Co. Ltd.

Alert: Electromobility infrastructure

Application for Commission Approval to Construct a Generating Station Pursuant to Public Utilities Article Section and

GC108: EU Code: Emergency & Restoration: Black start testing requirement

ROLE OF HAREDA IN NET METERING. By : P.C. Sharma Project Officer

CASE No. 86 of In the matter of. Petition of the Brihanmumbai Electric Supply & Transport Undertaking for revision in Service Connection Charges

STATEMENT OF CHARGING METHODOLOGY FOR USE OF THE SOUTHERN ELECTRIC POWER DISTRIBUTION PLC EMBEDDED DISTRIBUTION NETWORKS

BC Hydro writes in compliance with Exhibit A-4 to provide its Final Submission in respect of the Application (Exhibit B-1).

New Ulm Public Utilities. Interconnection Process and Requirements For Qualifying Facilities (0-40 kw) New Ulm Public Utilities

City of, Kansas Electric Department. Net Metering Policy & Procedures for Customer-Owned Renewable Energy Resources

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) )

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS.

PUBLIC UTILITIES COMMISSION

Research RES LEGAL Grid issues Country: Hungary

Buy All Sell All Rider for Interconnection of Renewable Generation

STATE OF NEW YORK PUBLIC SERVICE COMMISSION

CUSC Modification Proposal Form CMP270

RATE ORDER 2015 UNIFORM ELECTRICITY TRANSMISSION RATES January 08, 2015

18/10/2018. Mr Peter Adams General Manager, Wholesale Markets Australian Energy Regulator. By

PRESS NOTE. Distribution Tariff for Maharashtra State Electricity Distribution Company Limited (MSEDCL) applicable with effect from 1 June, 2015

ENERGY STRATEGY FOR YUKON. Net Metering Policy DRAFT FOR CONSULTATION

Western Alberta Transmission Line (WATL) HVDC Project

A. Basic Customer Charge: $ B. Energy Charge: $.09316/kWh

Gujarat Energy Transmission Corporation Limited (GETCO)

BOOT/OPEX/Pay As You Use Model for Rooftop Solar Projects Workshop on Getting Started on Energy Management & Solar

TARIFF DECISION FOR SASOL OIL (PTY) LTD S SECUNDA TO NATREF INTEGRATED (SNI) PIPELINE

STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DE PUBLIC SERVICE COMPANY OF NEW HAMPSHIRE

Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 25 kw to 10 MVA or less)

Case Nos. 12 & 48 of 2009

DEPARTMENT OF TRANSPORTATION. National Highway Traffic Safety Administration. [Docket No. NHTSA ; Notice 2]

Transcription:

MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION, BHOPAL Sub : In the matter of determination of Parallel Operation Charges. Suo-Motu Petition No. 73/2012 ORDER (Date of order 31 st December, 2012) MPERC, Bhopal - Petitioner The MP Power Transmission Co. Ltd., Jabalpur had filed a petition no. 50/2010 in the matter of determination of parallel operation charges in case of intra-state generating units. The Commission had decided that a study for determination of parallel operation charges be conducted through an independent agency and, thereafter, following the procedure, the process for determination of parallel operation charges to be levied in MP, be initiated. Accordingly, the Electrical Research and Development Association (ERDA), Vadodara was awarded the contract for providing consultancy services for evaluation of parallel operation charges. 2. By letter No. ERDA/ESPC/26195 dated 21.02.2012 ERDA submitted a discussion paper on Evaluation of Parallel Operation Charges. In the discussion paper, it was concluded that due to harmonic generation, negative phase sequence currents, reactive power from grid etc., the captive power plants (CPPs) loads are harmful for smooth and efficient operation without the help of utility grid. Therefore, grid support charges/parallel operation charges are necessary to be recovered from bulk consumers with CPP. ERDA recommended evaluation of parallel operation charges by Base MVA support method. 3. In the report, ERDA worked out the parallel operation charges (Grid Support Charges) @ Rs. 53.32 per KVA. This report of ERDA was placed in the public domain and also uploaded on the website of the Commission. A public notice was issued on 26.05.2012 for obtaining comments from various stakeholders by 20.06.2012. A public hearing was also held on 10.07.2012. The following comments were received:

(A) MP Transmission Power Transmission Co. Ltd., Jabalpur (i) (ii) (iii) (iv) (v) The studies and the findings of ERDA exactly substantiate the submission made by the MPPTCL in its petition for determination of parallel operation charges. Therefore, there is every justification for imposing the parallel operation charges on the CPPs/Private Generating Sets. The generation does not bridge the demand-supply gap in the state. The utility does not get advantages of demand charges whereas the CPPs run their generator at optimum load at optimum fuel efficiency. At high voltage the saving in losses of service line is negligible. The power exported to the grid by CPPs does not give any relief to the utility. Therefore, the formula may be modified as under by deleting the component of Power export to the Grid. Factor B = Installed Capacity Contract Demand. (vi) The parallel operation charges should be uniform for all CPPs on the basis of installed capacity and the contract demand with the utility. (B) (C) MP Electricity Consumers Society, Indore and M/s Grasim Industries Ltd., Nagda Any levies in addition to purchase of RECs to fulfil the RPO may threaten survival of the captive plants which is against the provisions of the Electricity Act, 2003. Transmission charges fixed and approved by the Commission against each year in ARR include charges incurred on paralleling of captive consumers. Thus levy of charges on captive consumers is an extra income, which cannot be allowed once the ARR for the year is approved. The working made by ERDA indicates that some of the charges arise because of the nature of industries, like ARC furnace, etc. and not due to

captive plants. Such charges need to be levied in the tariffs to the industries and not as captive plants paralleling charges. The advantage of full loading the captive plant in parallel operations is offset by minimum charges levied in the tariff and slab charges based on load factor. Thus the captive consumer is paying much higher charges per unit for the power availed from the utility than the average charges recovered through tariff and is already paying a levy. In the above context, additional charges on captive plants for parallel operations are not justified and are against the spirit of the Electricity Act, 2003. (D) M/s HEG Ltd., Mandideep. The part of harmonics and zero sequence current gets absorbed by CPPs which help the grid by reducing the pollutant load. The parallel operations help in improving the CPPs plant load factor. The facility is only extended if requested by way of stand-by support, and otherwise utility is under no obligation to extend support. The proposed methodology is based on hypothesis. ERDA recommendations to recover parallel operation charges on the basis of BASE MVA support is commercially and technically not acceptable. As such, there is no need to impose any charges for operating the plant in parallel with grid, since it is against the spirit of Section 9(1) of the Electricity Act, 2003. 4. A Suo-Motu Petition No. 73/2012 was registered for determination of parallel operation charges. The due date for submission of comments was 30.10.2012. A public hearing was also held on 06.11.2012. The following comments were submitted:

(i) M/s Grasim Industries Ltd., Nagda (e) (f) (g) The captive power plant is not running in parallel with the grid and, therefore, the impact at the point of connection is unknown. Hence, parallel operation charges in this case may not be levied. Additional transmission system and transformation capacity will be required if the CPP did not exist and the load were to be supplied by the utility. Additional losses on the existing system will take place if CPPs did not exist. The impact of power shortage due to CPP supply not being available i.e. purchase of expensive power, payment of UI charges etc., has to be kept in mind. The proposed charges are higher compared to those in other State. The charges in Chhatisgarh are Rs. 16.6 per KVA whereas M.P. has very few CPPs associated with steel furnace polluting the system. Wind farms cannot be considered as part of CPPs as these are not located within the premises of any industry. The levy of parallel operation charges is not justified. (ii) M.P. Power Transmission Company Ltd., Jabalpur Parallel operation charges are not applicable if the CPPs are not connected with the grid. The proposal to levy parallel operation charges @ Rs. 53.32 per KVA is agreed to. (iii) M/s HEG Ltd.,Mandideep Supply affording charges and standby charges are also being charged. Duplication of levy may be removed.

(e) A mere study of two to four hours in respect of fluctuation/harmonics cannot lead to conclusive findings. The sample size is small. The proposed parallel operation charges are too high. It can be a part of transmission charges. 5. On considering the submissions of the respondents, the Commission is of the view that : The parallel operation charges shall not be applicable if the CPPs are not connected with the grid. The purposes of levying supply affording charges and standby charges are different. These are not related to the parallel operation of the CPPs with the grid. Parallel operation charges cannot be made a part of transmission charges as these charges cannot be levied on all consumers. Auxiliary consumption of captive generating plants as a parameter may be deducted from the installed capacity of the plant for computation of parallel operation charges. 6. The Commission also finds that the object of the Electricity Act, 2003 is to delicense generation and to freely permit CPPs. In order to promote CPPs and looking to the facility being availed by CPPs from the grid, the Commission has come to the conclusion that it would be appropriate that parallel operation charges be levied at the rate of Rs. 20/- per KVA per month on the capacity of CPP (after deducting load pertaining to auxiliary consumption) connected to the grid. Ordered accordingly, (Rakesh Sahni) Chairman