Power Transmission Division Erlangen, April 29, 2014

Similar documents
Power Transmission Division Erlangen, April 29, Siemens Completes Installation of Second HVDC Converter Platform for TenneT

Power Transmisson Division Erlangen, April 15, Siemens receives major order for BorWin3 North Sea grid connection from TenneT

HVDC Innovative Technology for Smart Grids and Super Grids. Wilfried Breuer CEO Power Transmission Solutions, Siemens Energy Sector

Background Information

The Smart Way. HVDC PLUS One Step Ahead. Answers for energy.

The Smart Way HVDC PLUS One Step Ahead Answers for energy.

Siemens supplies the world s biggest gearless conveyor drive system

Offshore Wind: Grid Connection & Technology Options. Dietmar Retzmann Focus on. CO 2 Reduction Green Energy Megacities Security of Supply

Enabling the power of wind. Competence and expertise for wind power customers

Transmission Grid Development & Investment Planning on EHV Level in Germany

Power Transmission Solutions Grid Access

OFFSHORE WIND ENERGY CAPACITY REACHES ALMOST 5.4 GW IN 2017

HOW OFFSHORE WIND CONCERNS THE SECURITY OF SUPPLY

wire 2018: Cables for offshore wind turbines

Peter Lundberg, ABB HVDC, Nov 2016 HVDC Light - Power from shore. ABB Group November 16, 2016 Slide 1 1JNL A

Grid Integration of Large Scale Wind and Solar

Offshore Wind Connections HVDC for Offshore Grids

Background information

Hywind Scotland status and plans

Mikael Dahlgren, ABB Corporate Research, 02 December 2011 ABB Technology providers perspective Energidagen Chalmers Energyinitiative

Within the 300 GW total, the Energy Department estimates that 54 GW will be required from offshore wind to feed the large coastal demand centers.

Peter Lundberg, Global Product Manager, November 2016 ABB Power Systems Offshore wind connection

ABB Group August 27, 2010 Slide 1

Dr.-Ing. Ervin Spahi, Wadden Sea Forum, Bremerhaven Electric grid on and off-shore: current status, obstacles and new developments

Comprehensive solution with SIHARBOR

Offshore Wind and security of power supply - Energy economic analysis of risk and threat scenarios -

PLUG INTO WAVE ENERGY. John Liljelund CEO AW-Energy // 26 October 2016

Totally Integrated Power. A reliable all-rounder. Gas-insulated medium-voltage switchgear 8DJH 36.

ABB Wind Power Solution

IEEE PES General Meeting, Minneapolis, July 25-29, 2010 HVDC & FACTS Subcommittee. latest Technology Developments and Projects Dietmar Retzmann

Reliability is our profession

Drivers, Building Blocks (Cables, Offshore), EU and US Examples, Grid- Enabled HVDC, LCC-MTDC

Trusted technology for maximum power yield SINAMICS W180 siemens.com/sinamics-w180

HVDC Solutions. for Integration of the Renewable Energy Resources. Marcus Haeusler HVDC Lead Engineer. siemens.com/energy/power-transmission

Pathways to the global grid Answers for energy.

ABB Next Level Big shift in power attractive opportunities

Stationary Energy Storage Solutions 3. Stationary Energy Storage Solutions

Wind meets Gas Groningen, September 2017 Ab van der Touw, CEO Siemens Nederland NV. Siemens Nederland 2017

Ambra Sannino, ABB FACTS, May 2011 Keynote Speech PCIM 2011 The Role of Power Electronics in Smart Grids and Renewable Integration

Application Note. Dynamic PFC: Power Quality at the Docks (China State Shipbuilding Corporation)

Floating Foundations: Opening Up Deeper Waters In the U.S.

PRESS RELEASE. C-Power completes first wind farm in the Belgian North Sea

Siemens G2 platform 2.3-MW geared wind turbines. Exceptional performance, proven reliability. Answers for energy.

Background Information

Europe's first blockchain project to stabilize the power grid launches: TenneT and sonnen expect results in 2018


POWER TRANSMISSION OF LOW FREQUENCY WIND FIRMS

Introduction to Veja Mate Offshore Project

Southeast Asia: A Bright Future for Solar

P R E S S R E L E A S E. Balancing heat and cold for improved cruising range, performance, and comfort in electric vehicles

Modular Standardized Electrical and Control Solutions for Fast Track Projects

Stabilized power flows improve transmission grid performance siemens.com/energy/hvdcplus

Brochure. Modular Systems wind portfolio Power Collection and Grid Connection products

STATUS OF LAND-BASED WIND ENERGY DEVELOPMENT IN GERMANY

MAN Diesel & Turbo. Engineering the Future since Dionissis Christodoulopoulos Managing Director, MAN Diesel & Turbo Hellas Ltd

European technology leadership to address infrastructure bottlenecks

Wind Energy in the Southeast: Offshore and Land-Based Potential

TetraSpar. Industrialized Floating Foundation

Insulation Technologies for the Oil & Gas Market. Made in Germany.

Siemens G2 platform 2.3-MW geared wind turbines. Exceptional performance, proven reliability. Answers for energy.

Reliable, economical and safe siemens.com/rail-electrification

Volkswagen s strategic realignment is delivering

Press. Extensive additions to Sinamics G120 portfolio for optimum handling. SPS IPC Drives 2017, Hall 11

Oerlikon continues strong profitable sales growth

In Bulgaria by. Continental Wind Bulgaria EOOD

Background Information

Power From Shore: An introduction to HVDC Light Offshore

Introduction CONTENT Future of offshore wind energy in Europe Offshore wind energy in Spain Alternatives to the transmission system to the grid Compar

Press Newsletter. Division Drive Technologies and Division Industry Automation July 2010

Modular Multilevel Submodules for Converters, from the State of the Art to Future Trends

Robert L. Mitchell CEO and Co-Founder Atlantic Wind Connection

Capital Markets Day 2007 Kongsberg Maritime 25 September 20O7

Contemporary technological solutions

WESTA Leading Ukrainian producer of automotive batteries

Offshore Wind Farm Projects

The SGT5-8000H proven in commercial operation

Challenges to Ethanol Blending in the Southeast

Page 1 August, Siemens AG / Service Renewables All rights reserved E S SR WP

Siemens Gamesa Renewable Energy Unlocking Vietnam s Nearshore Wind Potential

Power Electronics for Medium Voltage Grid Applications Topologies and Semiconductors

Automotive financial services in Germany Motor Finance Summit Europe

PORT OF ROTTERDAM FRONT RUNNER IN ENERGY TRANSITION. Ruud Melieste, Corporate Strategy June 2018

Solutions for Profitable PV Power Plants

Vattenfall Capital Markets Day 2009

SeaGen-S 2MW. Proven and commercially viable tidal energy generation

Bright outlook for improved profitability. Direct drive wind turbine SWT Answers for energy.

Submarine Cable Solutions, Laying and Challenges. Submarine Solutions from the Specialist 15-Apr-11 / 1

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

STATUS OF OFFSHORE WIND ENERGY DEVELOPMENT IN GERMANY

Click to edit title 18. Fachforum Netzbau und Betrieb

Pluggable installation system from Wieland Electric for integrated flexible lighting in the Segmüller megastore in Pulheim.

The impact on the data center Industry

GRAND RENEWABLE ENERGY PARK PROJECT DESCRIPTION REPORT. Attachment C. Turbine Specifications

In Africa. For Africa.

Virginia Offshore Wind Port Readiness Study

Medium Voltage Drives. ABB Value Provider Program Partnership for growth and profit

ABB Fact Sheet Full-year ABB Slide 1

WE MAKE POWER SYSTEMS WORK

HIGH WIRE ACT. When the lights went out at Kitimat, it was the cue for Rio Tinto Alcan to embark on one of its most complex engineering feats ever.

Diversifying into Marine Energy. ABB March 2015

Transcription:

Energy Sector Press Power Transmission Division Erlangen, April 29, 2014 Siemens Completes Installation of Second HVDC Converter Platform for TenneT Major step forward for the offshore expansion of the German power grid North Sea platform can transmit wind power to supply more than 800,000 German households using efficient direct current technology Siemens has installed the BorWin2 offshore platform in the North Sea northwest of the island of Borkum. This marks Siemens' achievement of the second crucial milestone in the German grid connection projects under contract with the German- Dutch network operator TenneT. Siemens had already erected its first converter platform for the HelWin1 connection off Heligoland in the North Sea in August 2013. The BorWin2 transmission capacity of 800 megawatts (MW) is enough to meet the power demand of some 800,000 German households. On the platforms, the alternating current generated by the wind turbines is transformed into low-loss direct current for transmission to the mainland by using Siemens technology. The BorWin2 onshore converter station, likewise supplied to TenneT by Siemens, is located in Diele. There the electric power from the connected wind farms is converted back into the alternating current required to feed into the power grid. Once more we have mastered the challenging offshore installation part. We are now in the final stretch to achieve commissioning in the first half of 2015, as promised. When the two platforms yet installed by us go on line, they will be able to supply more than 1.3 million households, states Karlheinz Springer, CEO of the Power Transmission Division within the Energy Sector of Siemens AG. We are proud of having successfully tackled these highly complex tasks, says Lex Hartman, member of TenneT management. We are set to make major progress in expanding our offshore capacity in the coming months, continues Hartman, "and that brings the German government's offshore expansion targets within reach. Siemens AG Wittelsbacherplatz 2, 80333 Munich, Germany Corporate Communications and Government Affairs Manager: Stephan Heimbach Reference number: EPT201404039e fp Energy Sector Power Transmission Division Freyeslebenstr. 1, 91058 Erlangen Page 1/6

In mid-2010 the grid operator TenneT had placed the order for the BorWin2 offshore grid connection with a consortium comprising Siemens and the Italian cable specialist Prysmian. In all, Siemens is realizing five North Sea grid link-ups for TenneT: HelWin1 (576 MW) and HelWin2 (690 MW) off Heligoland, BorWin2 (800 MW) and BorWin3 (900MW) off Borkum, and SylWin1 (864 MW) off Sylt. The first four platforms HelWin1 and HelWin2, BorWin2 and SylWin1 are to commence commercial operation in rapid succession between the second half of 2014 and the first half of 2015. In April 2014, Siemens won the order for the fifth grid connection in the North Sea., BorWin3, in a consortium with Petrofac. It is scheduled to go on line in 2019. Once commissioned, the grid connections installed by Siemens will have a total transmission capacity of over 3.8 gigawatts (GW). Thanks to Siemens' efficient high-voltage direct current (HVDC) technology, transmission losses per link are less than three percent, not including cable losses. The converter technology used by Siemens is called HVDC Plus, and is essentially a voltage-sourced converter of the modular multi-level converter type (VSC MMC). Siemens is a leading pioneer of VSC MMC technology in this field. By contrast with the conventional HVDC version, which can only be used in networks with sufficient short-circuit capacity, systems using HVDC Plus make it possible to start up island networks from scratch. This is an important prerequisite for operation of the offshore network. The modular VSC technology reduces complexity and thus the space required for the installations an essential precondition precisely for use on offshore platforms. What is more, HVDC Plus ensures a nearly ideally sinusoidal AC voltage and a smooth voltage in the DC circuit. This eliminates the need for harmonic filters. For the installation the platform was towed into position directly above the substructure, which Siemens had already installed in the North Sea, 39 meters deep at that point, in 2013. This substructure consists of six steel pilings of up 2.5 meters in diameter and with a wall thickness of eight centimeters, anchored around 50 meters deep in the seabed. With a length of up to 83.5 meters, these pilings are only ten meters shorter than the Statue of Liberty in New York, including its base. Once the platform is aligned immediately above the substructure, the two parts have to be meshed perfectly with each other. This is the most critical part of the whole installation sequence: it calls for a very calm sea and cannot be done in poor weather. Once this has been achieved, the platform is raised using a hydraulic device in an activity known as jacking up. To protect it against giant waves, the Reference number: EPT201404039e fp Page 2/6

platform is installed 20 meters above sea level. BorWin2 is designed for decades of operation in the rugged North Sea. The platform is equipped with a helipad and was built under contract to Siemens by Nordic Yards at its shipyard in Warnemünde. The shipyard has been contracted by Siemens to fabricate three HVDC platforms in all. At 12,000 tons, the BorWin2 platform weighs more than 20 loaded and fully tanked Airbus A380 super airliners. With a length of 72 meters and a width of 54 meters, its surface area is more than half the size of a soccer field. The platform s seven decks, spanning a total height of 25 meters, house not only all the technology and equipment required for highvoltage direct current (HVDC) transmission, but also living quarters. Up to 100 employees at a time will be active on the platform for the next phase of the project in the North Sea. They will first re-open the doors and panels previously welded closed for transportation, and remove other transport safety fixtures and ballast weights. They will then commission the maritime systems such as the position lights and radio installations, and start up the air conditioning and water treatment systems. A self-propelled jack-up platform - a kind of mobile logistics and accommodation island - will provide on-site catering and living quarters for the crew. The platforms are fully automated and, once commissioned, the systems can be monitored and controlled from land, with cameras and sensors providing a complete overview of the current operating status. The crews quarters on the platform can be used when maintenance work is required. Siemens has been contracted by TenneT for maintenance of the grid connection for an initial period of five years. The special circumstances and challenges posed by such projects called for appropriate risk hedging. The insurance concepts for grid connection projects in the North Sea are individually tailored, with the Siemens Financial Services insurance unit (SFS Insurance) actively involved in the development of these concepts. These insurance solutions cover material damage to the platform and to the installations during construction and shipping, and within the warranty period. HVDC solutions and the associated services are part of Siemens Environmental Portfolio. Green products and solutions account for about 43 percent of the Group's Reference number: EPT201404039e fp Page 3/6

turnover. This makes Siemens one of the world's largest providers of environmentally compatible technology. Offshore platform for BorWin2 North Sea grid connection successfully installed at sea Siemens installed the offshore platform for the BorWin2 grid connection at sea in April 2014. BorWin2 is scheduled to go into operation in 2015. The platform is designed for decades of operation in the rugged North Sea and, once commissioned, will be remotely monitored and controlled from the mainland base. German wind farms with HVDC grid connections To reliably convey the power from offshore wind farms to the mainland over long distances, the German-Dutch grid operator TenneT counts on low-loss high-voltage direct current (HVDC) transmission. Siemens is implementing a total of five of the Reference number: EPT201404039e fp Page 4/6

nine HVDC offshore grid connections in the North Sea ordered to date, and thereby helping to make Germany's energy transition a success. HVDC grid connection links numerous wind farms to the mainland High-voltage direct current (HVDC) technology enables the alternating current generated by the wind farms to be converted into low-loss direct current. First, a number of transformer platforms arranged around the wind farm transform the alternating current before it is converted into direct current on a HVDC platform. It is transported to land via a submarine cable and then converted back into alternating current for onward transmission. HVDC technology is usually used when transmission cable lengths reach 80 km and longer. Contract person for journalists: Sabrina Martin, Phone: +49 (0)9131 18-7032 E-mail: sabrina.martin@siemens.com This press release is available under www.siemens.com/press/pi/ept201404039e Further press pictures, graphics and information are available under: www.siemens.com/press/x-win Follow us on Twitter: www.twitter.com/siemens_press Reference number: EPT201404039e fp Page 5/6

Siemens Energy Sector is the world s leading supplier of a complete spectrum of products, services and solutions for power generation in thermal power plants and using renewables, power transmission in grids and for the extraction, processing and transport of oil and gas. In fiscal year 2012 (ended September 30), the Energy Sector had revenues of EUR 27.5 billion and received new orders totaling approximately EUR 26.9 billion, posting a profit of more than EUR 2.2 billion. On September 30, 2012, the Energy Sector had a workforce of more than 86,000. Further information is available at: www.siemens.de/energy Reference number: EPT201404039e fp Page 6/6