Impact of electric vehicles on the IEEE 34 node distribution infrastructure

Similar documents
Impact Analysis of Fast Charging to Voltage Profile in PEA Distribution System by Monte Carlo Simulation

Electric Vehicles Coordinated vs Uncoordinated Charging Impacts on Distribution Systems Performance

Targeted Application of STATCOM Technology in the Distribution Zone

Impact Analysis of Off-board Charger to Power Quality

EV - Smart Grid Integration. March 14, 2012

An approach for estimation of optimal energy flows in battery storage devices for electric vehicles in the smart grid

Coordinated Charging of Plug-in Hybrid Electric Vehicles to Minimize Distribution System Losses

Adaptive Power Flow Method for Distribution Systems With Dispersed Generation

2015 Grid of the Future Symposium

Assessing Feeder Hosting Capacity for Distributed Generation Integration

INTEGRATING PLUG-IN- ELECTRIC VEHICLES WITH THE DISTRIBUTION SYSTEM

Characterization of Voltage Rise Issue due to Distributed Solar PV Penetration

Impact of Plug-in Electric Vehicles on the Supply Grid

Energy Security Electrical Islanding Approach and Assessment Tools. Dr. Bill Kramer Senior Research Engineer Distributed Energy Systems Integration

STABILIZATION OF ISLANDING PEA MICRO GRID BY PEVS CHARGING CONTROL

United Power Flow Algorithm for Transmission-Distribution joint system with Distributed Generations

Investigation of THD Analysis in Residential Distribution Systems with Different Penetration Levels of Electric Vehicles

New York Science Journal 2017;10(3)

Integrated System Models Graph Trace Analysis Distributed Engineering Workstation

STOCHASTIC ESTIMATION OF FEEDER-SPECIFIC DISTRIBUTED GENERATION (DG) HOSTING CAPACITY

Field Verification and Data Analysis of High PV Penetration Impacts on Distribution Systems

Island Smart Grid Model in Hawaii Incorporating EVs

Renewable Grid Integration Research in the U.S.

International Conference on Advances in Energy and Environmental Science (ICAEES 2015)

DISTRIBUTED GENERATION FROM SMALL HYDRO PLANTS. A CASE STUDY OF THE IMPACTS ON THE POWER DISTRIBUTION NETWORK.

PHEV Design Impacts. Jason Taylor Ph.D. South West Electric Distribution Exchange May 6 th, 2010

Sensitivity Analysis of Photovoltaic Hosting Capacity of Distribution Circuits

Smart Grids and Mobility

Power Balancing Under Transient and Steady State with SMES and PHEV Control

Analysis of Grid Connected Solar Farm in ETAP Software

Grid Impact of Electric Vehicles with Secondary Control Reserve Capability

A Novel Distribution System Power Flow Algorithm using Forward Backward Matrix Method

IEEE Workshop Microgrids

Model-Based Integrated High Penetration Renewables Planning and Control Analysis

LOCAL VERSUS CENTRALIZED CHARGING STRATEGIES FOR ELECTRIC VEHICLES IN LOW VOLTAGE DISTRIBUTION SYSTEMS

Computer Aided Transient Stability Analysis

Grid Management Voltage Control Distribution Grid Voltage Regulation with DER. Michael Sheehan, P.E. IREC Pacific Northwest Solar Partnership

Performance Evaluation of Electric Vehicles in Macau

THE alarming rate, at which global energy reserves are

Potential Impact of Uncoordinated Domestic Plug-in Electric Vehicle Charging Demand on Power Distribution Networks

Optimal Decentralized Protocol for Electrical Vehicle Charging. Presented by: Ran Zhang Supervisor: Prof. Sherman(Xuemin) Shen, Prof.

AEP Ohio Distribution Reliability and Technology Programs

VOLTAGE STABILITY CONSTRAINED ATC COMPUTATIONS IN DEREGULATED POWER SYSTEM USING NOVEL TECHNIQUE

PV and opportunistic electric vehicle charging in a Swedish distribution grid

Y9. GEH2.3: FREEDM Cost Benefit Analysis based on Detailed Utility Circuit Models

Electric Power Research Institute, USA 2 ABB, USA

Implementing Dynamic Retail Electricity Prices

Available online at ScienceDirect. Procedia Technology 21 (2015 ) SMART GRID Technologies, August 6-8, 2015

Electric Vehicle Load Characteristic Analysis and Impact of Regional Power Grid

Impacts of Fast Charging of Electric Buses on Electrical Distribution Systems

INSTALLATION OF CAPACITOR BANK IN 132/11 KV SUBSTATION FOR PARING DOWN OF LOAD CURRENT

Abstract- In order to increase energy independency and decrease harmful vehicle emissions, plug-in hybrid electric vehicles

Autonomous Voltage and Frequency Control by Smart Inverters of Photovoltaic Generation and Electric Vehicle

Underpinning Research Power Electronics in Distribution Networks

Demand Charges to Deal With Net Energy Metering: Key Considerations

American Electric Power s Energy Storage Deployments

Experimental Study on the Effects of Flow Rate and Temperature on Thermoelectric Power Generation

Network Reconfiguration for Loss Reduction and Voltage Profile Improvement of 110-Bus Radial Distribution System Using Exhaustive Search Techniques

Simulation of Voltage Stability Analysis in Induction Machine

Intelligent Energy Management System Simulator for PHEVs at a Municipal Parking Deck in a Smart Grid Environment

Keyword: Power Distribution System, Three-Phase Power Flow, Simplified Model, Distributed Energy Resources, Load Flow.

Fault Analysis on an Unbalanced Distribution System in the Presence of Plug-In Hybrid Electric Vehicles

Electric Vehicle Grid Integration Research Analyzing PHEV Impacts on Distribution Transformers in Hawaii

Analysis of Low Tension Agricultural Distribution Systems

RECONFIGURATION OF RADIAL DISTRIBUTION SYSTEM ALONG WITH DG ALLOCATION

A Novel Hybrid Smart Grid- PV-FC V2G Battery Charging Scheme

Managing EV Load Workplace Charging Project Utility Perspective

IEEE-PES Chicago Chapter Presentation November 11, Smart Grid. Mike Born. Principal Engineer, Capacity Planning

Applied Technology Services Overview

Charging Electric Vehicles in the Hanover Region: Toolbased Scenario Analyses. Bachelorarbeit

IEEE Transactions on Applied Superconductivity, 2012, v. 22 n. 3, p :1-5

Reactive power support of smart distribution grids using optimal management of charging parking of PHEV

RESILIENT SOLAR CASE STUDY: SUNY New Paltz NYPA Integrated Grid Pilot

Optimization of Seat Displacement and Settling Time of Quarter Car Model Vehicle Dynamic System Subjected to Speed Bump

GRAND RENEWABLE ENERGY 2018

Analysis of 440V Radial Agricultural Distribution Networks

The Effect Of Distributed Generation On Voltage Profile and Electrical Power Losses Muhammad Waqas 1, Zmarrak Wali Khan 2

Implementation SVC and TCSC to Improvement the Efficacy of Diyala Electric Network (132 kv).

Methods of reducing power losses in distribution systems

Batteries and Electrification R&D

Optimal Placement of EV Charging Station Considering the Road Traffic Volume and EV Running Distance

Electrification of Domestic Transport

Data envelopment analysis with missing values: an approach using neural network

The Role of Electricity Storage on the Grid each location requires different requirements

USAGE OF ACCUMULATION TO SUSTAIN THE DAILY DIAGRAM OF ELECTRICITY PRODUCTION IN PHOTOVOLTAIC POWER PLANT

Available online at ScienceDirect. Procedia Technology 25 (2016 )

Deploying Power Flow Control to Improve the Flexibility of Utilities Subject to Rate Freezes and Other Regulatory Restrictions

Interconnection System Impact Study Report Request # GI

TransWest Express Project

Advancements in Energy Storage: Utility-Scale Technologies and Demonstration Projects

Performance of Batteries in Grid Connected Energy Storage Systems. June 2018

TRANSNATIONAL ACCESS USER PROJECT FACT SHEET

ScienceDirect. Simulation and Testing of a Typical On-Board Charger for ITB Electric Vehicle Prototype Application

Implementation of Steady-State Power System Visualizations Using PowerWorld Simulator. Dr. Jung-Uk Lim, Department of Electrical Engineering

Smart Grids and Integration of Renewable Energies

Comparing FEM Transfer Matrix Simulated Compressor Plenum Pressure Pulsations to Measured Pressure Pulsations and to CFD Results

Electric Vehicle Cost-Benefit Analyses

Accidental Islanding of Distribution Systems with Multiple Distributed Generation Units of Various Technologies

Smart- Grid Ready PV Inverter

IMPROVEMENT OF LOADABILITY IN DISTRIBUTION SYSTEM USING GENETIC ALGORITHM

Transcription:

International Journal of Smart Grid and Clean Energy Impact of electric vehicles on the IEEE 34 node distribution infrastructure Zeming Jiang *, Laith Shalalfeh, Mohammed J. Beshir a Department of Electrical Engineering, University of Southern California, Los Angeles, CA 90089, USA Abstract With the growing penetration of the electric vehicles to our daily life owing to their economic and environmental benefits, there will be both opportunities and challenges to the utilities when adopting plug-in electric vehicles (PEV) to the distribution network. In this paper, a thorough analysis based on real-world project is conducted to evaluate the impacts of electric vehicles infrastructure on the grid relating to system load flow, load factor, and voltage stability. IEEE 34 node test feeder was selected and tested along with different case scenarios utilizing the electrical distribution design (EDD) software to find out the potential impacts to the grid. Keywords: Electric vehicle, smart grid, grid impact, load, power flow, voltage stability, DEW, IEEE 34. 1. Introduction A distribution system study, power flow, feeder voltage regulation, and short-circuit analysis, becomes necessary for planning and evaluating the suitability and impacts of Plug in Electric Vehicles (PEVs) and Photovoltaic (PV) in the distribution system. This research paper is based on the Los Angeles Department of Water and Power (LADWP) Smart Grid Regional Demonstration Project (SGRDP), which is a leading edge demonstration project intended to support the goal of the DOE Smart Grid Demonstration Project (SGDP) funded under the American Recovery and Reinvestment Act (ARRA) of 2009. The intent of the DOE s SGDP is to explore advanced smart grid systems and evaluate performance for future applications in the electric power industry. To support these DOE SGDP objectives, LADWP and its research partners, the University of Southern California (USC), the University of California at Los Angeles (UCLA) and Jet Propulsion Lab (JPL) are working together under the LADWP SGRDP to demonstrate innovations in key areas of smart grid (SG) technologies. This includes Advanced Meter Infrastructure (AMI), Demand Response (DS), Customer Behaviour (CB), Cyber Security (CS), and Electric Vehicles (EV). The LADWP SGRDP is a five-year, $120 million project that encompasses installation of smart-grid equipment, collection of system data, construction of equipment models, performing power system studies, formulation of operating strategies, and development of software and techniques related to the above-mentioned areas of smart grid. The objective of this paper is to present some early result of the EV demonstration project, specifically the infrastructure impact of EV, including system modelling, power flow studies, and demonstration activities utilizing the IEEE 34 node test feeder as a test system. The EV impact demonstration studies are conducted under different load increment conditions and different system load profiles. The results of these studies will be used to validate and benchmark those obtained from real-time data. This paper first gives an overview of the EV demonstration project activities and describes the IEEE * Manuscript received May 15, 2014; revised July 17, 2014. The research work was conducted under ARRA Smart Grid Regional Demonstration Project and funded by the US Department of Energy and Los Angeles Department of Water and Power. Corresponding author: Zeming Jiang; Tel.: +1 213 618-2127; E-mail address: zemingji@usc.edu. doi: 10.12720/sgce.3.4.417-424

418 International Journal of Smart Grid and Clean Energy, vol. 3, no. 4, October 2014 34 node test feeder (Section 2). Section 3 presents an overview of different study scenarios and base cases, while Section 4 describes the results and analysis of those cases. Finally, the conclusions based on this analysis and suggestions for potential future work are presented in Section 5. 2. Overview of the System Used 2.1. Technology and system utilized To analysis and evaluate the impact of EV to the grid, the following activities are under taken: An IEEE 34 bus test system reflecting an industry standard distribution test model was selected to enable analysis of EV distribution effects as described above. Distribution system modeling software Distribution Engineering Workstation (DEW) by Electrical Distribution Design, Inc. (EDD) is to be used to model the distribution network, which enables the construction of a complete working model for the entire power grid, from the transmission level through primary and secondary distribution networks. The EDD models and the system representations allow the attachment of multiple EV-charger loads of various classifications The EDD models and the system representations are designed to reveal the aggregate effect of the multiple EV-charger loads at substation connections to the transmission grid A sensitivity analysis are setup on the test systems with the goal of revealing the substations within the LADWP territory that have the greatest impact on the transmission grid when they are similarly subjected to EV loads. The sensitivity studies conducted are discussed in Section III. 2.2. Configurations of the smart grid systems, subsystems and components The network configurations of the test systems and the system modeling considerations are discussed in this section. The actual system test results are provided in Section 4. The distribution system under consideration is the IEEE34 node test feeder. This feeder is an actual feeder located in Arizona. Due to its size, data of the test feeder can not be made available in this paper. The IEEE 34 node test feeder one-line diagram configuration is shown in Fig 1 below. 848 822 846 820 844 818 864 842 802 806 808 812 814 850 824 826 816 858 834 860 836 840 800 810 832 852 888 890 862 838 828 830 854 856 Fig. 1. One-line diagram of IEEE34 node test system The feeder s nominal voltage is 24.9 kv. It is characterized by: Three phase 4-wire and single phase, 2-wire overhead lines arranged in different configurations. Very long and lightly loaded. Two in-line regulators required to maintain a good voltage profile. An in-line transformer reducing the voltage to 4.16 kv for a short section of the feeder. Unbalanced loading with both spot and distributed loads. Distributed loads are assumed to be connected at the center of the line segment.

Zeming Jiang et al.: Impact of electric vehicles on the IEEE 34 node distribution infrastructure 419 Shunt capacitors modeled as constant susceptance. Loads are comprise of three-phase (balanced or unbalanced) and single phase systems. Three-phase loads are connected in Y or D while single-phase loads are connected line-to-ground or line-to-line. All loads can be modeled as constant kw and kvar (PQ), constant impedance (Z) or constant current (I) depending based on the actual system load. Electric Distribution Design (EDD) software is used to perform power flow solution. The power flow equation is employing Newton-Raphson method with constant P & Q at 1000 maximum number of iterations. Fig. 2 shows the IEEE34 node test feeder system after it has been implemented in EDD software. The base case system conditions are given in Table 1. Table 1. Power flow results of IEEE 34 node test feeder Characteristic EDD Result Standard kw 2043.17 2042.872 Total feeder flow kvar 292.14 290.258 kva 2063.95 2063.389 kw 273.41 273.049 Total losses kvar 36.96 34.999 kva 275.90 275.283 Ph-A 54.15 51.58 Bus current flow Ph-B 46.81 44.57 Ph-C 42.98 40.93 Fig. 2. IEEE34 node test system in EDD. 3. Description of the Methodologies and Algorithms Utilized As described in Section II, IEEE34 node test feeder representation is provided with the EDD modeling. The methodologies used and the scenarios selected are to meet some of the key EV project objectives are described below. 3.1. Distribution system load level consideration In order to define the load level to study, a consideration need to be made on the varying nature of the power system load. Due to the daily and season changes of the power system loads, certain simplifying assumptions need to be considered when analysis system issues that depend as well as impact the system loading and capabilities. A typical summer season load curve for the California Independent System Operator (CAISO) is shown Fig. 3. In developing a simplifying consideration, the load curve is represented with three load levels or periods: peak, intermediate, and off-peak as shown in Fig. 4. These load periods are defined as follows: Period 1: Peak load (100%), Period 2: Intermediate load (55%),

420 International Journal of Smart Grid and Clean Energy, vol. 3, no. 4, October 2014 Period 3: Off-peak load (30%) The estimate in the percentage of the peak load for the Periods 2 and 3, consideration is made the impact of the daily changes to the summer peak load condition that is the basis for Period 1. Fig. 3. CAISO s summer load curve as a representative loading for the development of the load periods. Fig. 4. Load period definition. 3.2. EV load integration scenarios Three EV load increase scenarios (Cases) are been analyzed. These cases are defined as follows: Case 1: Random EV Load Increase: Increase each load (spot or distributed) until bus or system limit (transformer loading, voltage, and line limit) is reached Case 2: 10% System Incremental increase Per Spot Bus Increase 10% (or higher) circuit or system incremental starting from the far end of the circuit Case 3: Distributed Incremental Increases Increase loads throughout the system in percentage proportion to the load at the bus (spot load only)

Zeming Jiang et al.: Impact of electric vehicles on the IEEE 34 node distribution infrastructure 421 3.3. Load flow, load factor and stability limits Load flow analysis using EDD program was conducted for each of the cases by incrementally increasing EV or other storage loads until system limits are reached. The limits for consideration typically are the equipment limits and other system based limits, such as voltages, load factors, and system stability. For distribution systems of the nature we are studying, system stability issues are not a consideration. Thus, the only issues we are dealing with are power and current flow, and voltage level consideration. Specifically, these are the limiting conditions that are monitored for the system studies. Transformer Loading Limit: current rating of 100% (normal), current rating of 225% (emergency) Voltage limit: 114-126V (normal); 110-127V (emergency) Line Loading Limit: 100%. The above criteria are used in determining the level of incremental EV or other storage devices that can be connected to the test systems. 4. Summary of Results The study results related to the system studies are presented in this section. First, summary of the study results is given. Then the results are discussed and analyzed. 4.1. Summary of result plots Nine cases where run using the three case scenarios and three load levels (periods). The study run cases have already been described in Section III. The study results of these cases are summarized below, Fig 5 Fig. 13: Fig. 5. Result for IEEE 34 node test CASE 1.1. Fig. 6. Result for IEEE 34 node test CASE 1.2. Fig. 7. Result for IEEE 34 node test CASE 1.3. Fig. 8. Result for IEEE 34 node test CASE 2.1. Fig. 9. Result for IEEE 34 node test CASE 2.2 Fig. 10. Result for IEEE 34 node test CASE 2.3

422 International Journal of Smart Grid and Clean Energy, vol. 3, no. 4, October 2014 Fig. 11. Result for IEEE 34 Node Test CASE 3.1. Fig. 12. Result for IEEE 34 Node Test CASE 3.2. Fig. 13. Result for IEEE 34 Node Test Feeder CASE 3.3. 4.2. Analysis of the CASE results In this section s analysis, we assume that each electric vehicle charging in level 1 has capacity of 2 kw (20A) at 120V with 12 hours to be fully charged. Level 2 charging has capacity of 8 kw (32A) at 240V with 6 hours to be fully charged. The load flow analysis has been run for all three cases and the system has been checked for voltage and current violations. The limits for 120-volt base is set from 110-127V, as has already been mentioned in Section III. The result of Case 1 shows that: For load bus 840, 860, 848, 844 under peak load condition, around 377 kw more load can be attached, which is equivalent to 186 PHEVs in level 1 charging or 47 PHEVs in level 2 charging. While for load period 2 and 3, nearly 1580 kw and 2090 kw more demand can be added, respectively. For load bus 890 under peak load condition, only 27 kw more load can be added, which is equivalent to 13 PHEVs in level 1 charging or 3 PHEVs in level 2 charging. While for load period 2 and 3, almost 750 kw and 870 kw more demand can be attached, respectively. For load bus 830 under peak load condition, 512 kw can be increased to reach the voltage limit, which is equivalent to 256 PHEVs in level 1 charging or 64 PHEVs in level 2 charging. While for load period 2 and 3, nearly 1880 kw and 2450 kw more demand can be increased, respectively. The result of Case 2 shows that: Under period 1 (peak load), the system will reach its voltage limit when the three load buses (840-860- 848) increase their kw demand by 10%, and the voltage limit will occur at the node bus 814. The results also show that we can increase 615 kw more to the whole system, which is equivalent to 307 PHEVs in level 1 charging or 76 PHEVs in level 2 charging. Under period 2 (intermediate load), the system will reach its voltage limit after all the load buses increase their kw demand by 10%, while load bus 840 and 860 increase 20%, and the voltage limit will occur at the node bus 814. The results also show that we can increase 1640 kw more to the whole system, which is equivalent to 820 PHEVs in level 1 charging or 205 PHEVs in level 2 charging.

Zeming Jiang et al.: Impact of electric vehicles on the IEEE 34 node distribution infrastructure 423 Under period 3 (off-peak load), the system will reach its voltage limit almost when all the six load buses increase its kw demand by 20%, and the voltage limit will occur at the node 852. The results also show that we can increase 2255 kw more to the whole system, which is equivalent to 1127 PHEVs in level 1 charging or 281 PHEVs in level 2 charging. The result of Case 3 shows that under period 1 (peak load), the system will reach its voltage limit when all the six load buses increase its kw demand by 50% with respect to themselves, and the voltage limit will occur at the node bus 814. The results also show that we can increase 523.5 kw more to the whole system, which is equivalent to 261 PHEVs in level 1 charging or 65 PHEVs in level 2 charging. While under period 2 and period 3, the system will run into voltage limit issue when all the six buses are added their demand by 140% and 163%, which is equivalent to 1465.8 kw and 1675.2 kw, respectively. 5. Conclusion This paper presents a detailed analysis based on SGRDP to evaluate the impact of electric vehicles infrastructure on the grid relating to system load flow, load factor, and voltage stability. IEEE34 Node Test Feeder was selected and tested under different case scenarios in the EDD to assess the potential impacts to the grid. The IEEE34-bus system was tested at 100%, 55% and 30 % capacity to evaluate the maximum loading capability by running three case scenario tests. Firstly, we find out the maximum load increase at each load bus on the system. Secondly, we tested the system ability to handle 10% kw demand increment of the IEEE 34-bus system at each load simultaneously and stop when the systems reaches the limit. Finally, we increase all the load buses by 5-20% each time with respect to the load buses and find out the maximum loading capability. Transformers that are attached ahead of the load buses were encountered current limit issue when testing CASE 2 and CASE 3. The current limit was chosen to be neglected and keep testing until reach the next violation. Larger size transformers are needed to solve this problem. The next step of this research is to update the current data obtained from the smart meters including the EV charging information, add Distribution Generator (DG) and PV panels into the IEEE34 node test feeder to give a more accurate analysis of the EV impacts to the grid. Furthermore, the vehicle to grid (V2G) technology will also be tested to understand the potential impact on IEEE 34 bus system when charging and discharging EVs at different time and loading scenarios. References [1] Wynne J. Impact of plug-in hybrid electric vehicles on California s electricity grid. Nicholas School of the Environment of Duke University, North Carolina, 2009. [2] Li N, Huang M. Analysis on harmonics caused by connecting different types of electric vehicle chargers with power network. Power Supply Technology, 2011; 35(1):170-174. [3] Clement K, Haesen E, Driesen J. Stochastic analysis of the impact of plug-in hybrid electric vehicles on the distribution grid. In: Proc. of the 20th International Conference on Electricity Distribution, 2009:1 4. [4] Bradley T, Quinn C. Analysis of plug-in hybrid electric vehicle utility factors. Journal of Power Sources, 2010; 195(16):5399-5408. [5] Rastegar M, Safdarian A, Fotuhi-Firuzabad M, Aminifar F. Impacts of plug-in hybrid electric vehicle uncertainty and grid unavailability on home load management. In: Proc. of the International Conference on Environment and Electrical Engineering, 2012:693-698. [6] Hadley S.W. Impact of plug-in hybrid vehicles on the electric grid. Technical report ORNL/TM-2006/554. Oak Ridge National Laboratory, 2006. [7] Hartmann N, demir ED. Impact of different utilization scenarios of electric vehicles on the German grid in 2030. Journal of Power Sources, 2011; (196):2311-2318. [8] Yang H.M, Xiong L.C, Liu B.P. Analysis of charging and discharging for plug-in hybrid electric vehicles. Journal of Electric Power Science and Technology, 2010; 25(3):8-12. [9] Denholm P, Short W. An evaluation of utility system impacts and benefits of optimally dispatched plug-in hybrid electric vehicles. Technical Report. National Renewable Energy Laboratory, 2006.

424 International Journal of Smart Grid and Clean Energy, vol. 3, no. 4, October 2014 [10] Acha S, Green T, Shah N. Effects of optimized plug-in hybrid vehicle charging strategies on electric distribution network losses. In: Proc. of IEEE Conference and Exposition on Transmission and Distribution, 2010:1 6. [11] Putrus G, Suw A, Johnston P. Impact of electric vehicles on power distribution networks. In: Proc. of IEEE Vehicle Power and Propulsion Conference, Dearborn, USA; 2009:827-832. [12] Taylor M.J, Alexander A. Evaluation of the impact of plug-in electric vehicle loading on distribution system operations. In: Proc. of IEEE Power & Energy Society General Meeting, Calgary, Canada, 2009:1-6.