Earthsafe Systems, Inc. Emergency Power Fuel Systems Recommended System Standard

Similar documents
Earthsafe Systems, Inc. Page 1

ESS.DG.HT611 Life Safety Earthsafe Systems, Inc. Page 1

As diesel fuel ages it degrades in 2 ways: particulate formation, and biological growth.

Updated: October 2012

PEI/RP Recommended Practices for Installation of Bulk Storage Plants

Code Requirements on Aboveground Storage Tanks Dispensing Fuels At Motor Vehicle Fuel-Dispensing Stations

How to Design a Genset Fuel System With Gen Evo (Franklin) ATG

Code Requirements for ASTs at Motor Vehicle-Dispensing Stations

earth safe Fuel Systems for Critical Power

Code Requirements for ASTs at Motor Vehicle-Dispensing Stations

CONTENTS. Foreword...iii. 1. Introduction...1

Reliant Series Systems Fuel Tanks DAY TANKS FILTRATION TANKS SPECIALTY TANKS

Model C230 Pump Controller

Generator Fire Safety: Generator assemblies should be located outside the building.

CF50.0 CRITICAL FUEL SYSTEMS For Fuel Storage Up To 250,000 Gallons (946,000 liters)

THE KEY RELATIONSHIPS BETWEEN FIRE CODES, NEW YORK AST REGULATIONS AND SPCC PLANS

M20 Duplex Pump Data C8 Controller Data Sheet

Climas y Proyectos Leyco, S.A. de C.V.

SECTION VEHICLE FUEL DISPENSING EQUIPMENT

SECTION DOMESTIC-WATER PACKAGED BOOSTER PUMPS

Fuel Management Systems

Winning Bid US Petroleum Equipment Walts Petroleum Northwest Petroleum Petro-Chemical Systems Kimberly Green Bay Wausau Fond Du Lac

Call us now: (+44) Fuel Polishing And Filtration Equipment. Page 1

Auxiliary Equipment. Option #397-12A Single Remote Pumping Unit (with Standard Pump & Motor) Duplex Remote Pumping Unit Option #397-12B

.4 Emergency and normal vents and terminations. .1 CAN/CSA-B139-09, Installation Code for Oil Burning Equipment.

SECTION DOMESTIC-WATER PACKAGED BOOSTER PUMPS

STS SERIES. Enclosed Automated Fuel Maintenance Systems (STS)

ADDENDUM #1. A. Alternate Bid Item #3A - The procurement and installation of a new 12,000 gallon UL 2085 rated AGT tank for

earth safe Fuel Systems for Critical Power

Fuel Storage Dec 2016

Installation Manual. Automated Fuel. Maintenance. System FUEL TECHNOLOGIES INTERNATIONAL LLC

9.21 Tank Program Guide NYS Office of Mental Health Tank System Installation Guide

Ground Mount / Piping / Electrical Quick Reference ECS Membrane Processor: PMC and ISD

Installation Manual FTI-10A & FTI-20A SINGLE TANK. Automated Fuel Maintenance System FUEL TECHNOLOGIES INTERNATIONAL

SECTION (15444) - DOMESTIC WATER PACKAGED BOOSTER PUMPS

Underground Storage Tank Annual Compliance Inspection (Revised 1/2015)

W-PFS range of advanced fuel polishing systems. Rev1501

Understanding the Colorado Annual Compliance Package. William Holman & Robert Schlegel Inspectors Division of Oil and Public Safety

earth safe DEF Systems for Critical Power

(Please type or use black ink)

Installation Manual. Automated Fuel Maintenance System FTI-5A FUEL TECHNOLOGIES INTERNATIONAL

SEASONAL MAINTENANCE CHECKLISTS Johnson Controls

A. Motors shall be designed, built, and tested in accordance with the latest revision of the following standard documents.

Aboveground Tank Equipment. Presenter: Steven Allwein Northeast Regional Sales Manager Morrison Bros. Co.

Mizer Single Pump and Starter Box

Industrial Generator Set Accessories

Advantage-D. Operating Instructions and Maintenance Manual. Central Vacuum Systems (Expandable/Modular Models) (Ver.

Electric Coil [Make-Up Air / Displacement Ventilation / Space Heating] System

NOW UL LISTED. Patented

New UST Installation Inspection Checklist

A. Provide variable frequency drives to operate variable torque loads as shown on the Drawings and as specified herein.

Industrial Generator Set Accessories

Table Summary of Sprinkler System Inspection, Testing, and Maintenance. Reference. Inspection , ,

A. This Section includes ac, enclosed controllers rated 600 V and less, of the following types:

Automatic Roof Door Vents

EXHAUST FANS CUD & CUB UPBLAST FANS

Packaged Pump Sets FOR DIESEL FUEL OIL APPLICATION. Packaged Pump Sets for Diesel/Fuel Oil Application Page 1

Tank Filling Systems. for Petroleum Products

Industrial Generator Set Accessories

A. The latest published edition of a reference shall be applicable to this Project unless identified by a specific edition date.

PUMPS AND FILTRATION

Franklin Fueling Systems

Submersible Pumping Systems. Product Catalog

Tank Filling Systems for Petroleum Products

SECTION HVAC POWER VENTILATORS

Pumps and Filtration

SECTION ENCLOSED CONTROLLERS

ROGERS MACHINERY COMPANY, INC

13,000 Watt Diesel Generator AGi13P E

8,000 Watt Diesel Generator

WARREN COUNTY, N.Y. M/E REFERENCE A. Submit manufacturer's product data on all motors and adjustable speed drives.

Custom Shipyard and Military Facility Products

BUREAU OF STANDARDS. Effective Date: 8/19/2016 Section No. 4. Version: 1.2 Procedure No. 3

10,000 Watt Diesel Generator AGi9P E

SECTION ENCLOSED SWITCHES AND CIRCUIT BREAKERS

Farm & Residential Tanks Angle skids

Liebert CSU3000 DISCONTINUED PRODUCT. CSI Mainframe Cooling Systems. CT(Three Module) Model 20, 30 & 37 ton Mainframe Chiller

Wilo CO-Helix Pressure Boosting Systems. Engineering Specification

Direct Gas-Fired Heating

Changes to EPA s AST & UST Rules. Mott-Smith Consulting Group, LLC

A. Products shall be designed, manufactured, tested, and installed in compliance with the following standards:

Industrial Generator Set Accessories

DESIGN GUIDELINES FANS PAGE 1 of 7

SECTION FUEL-OIL DISTRIBUTION (APPLIES TO FUEL TANKS FOR GENERATORS)

Changes to EPA s AST & UST Rules. Mott-Smith Consulting Group, LLC

SECTION FACILITY FUEL OIL PIPING

Industry best 5 year fan housing warranty, 1 year motor warranty

Industrial Generator Set Accessories

Users Manual Professional Series Direct Drive Pump.25-2 GPM Series Safety, Operating, Installation, and Maintenance Instructions

GENERAL AVIATION FUELING Arkansas Airport Operators Association Annual Meeting

University of Houston Master Construction Specifications Insert Project Name

Inspection, Testing, and Maintenance Fire Pumps NFPA 25, Chapter 8 as amended by CCR, Title 19 Page 1 of 8

Diesel Engines for Fire Protection Applications

SECTION FACILITY FUEL SYSTEMS

.2 Section Waste Management and Disposal..5 Section Thermometers and Pressure Gauges Piping Systems.

Industrial Generator Set Accessories

SECTION AXIAL HVAC FANS

P.O. Box 435 Saratoga Springs, NY 12866

1) Activity Description: Management of Petroleum Storage Tanks and Containers

Inspecting Airport Fueling Systems

Transcription:

Copyright 2008 Earthsafe Systems, Inc. This information is provided to consulting engineers and prospective customers for the purpose of specifying Earthsafe Emergency Power Fuel Systems. Reproduction or use for other purposes is prohibited without the consent of Earthsafe Systems, Inc. Section 1: Section 2: Section 3: Section 4: Section 5: Section 6: Section 7: Section 8: Mechanical Environmental Fire Safety Electrical Controls Monitoring Other Equipment Earthsafe Systems, Inc. Page 1

Section 1: Mechanical 1-01 Fuel Storage Capacity Total fuel storage capacity shall be sufficient to run the primary generators at full load for 72 hours, based on 90% full tanks. The system shall include a minimum of (2) bulk storage tanks. 1-02 Fuel Transfer The fuel system shall include as a minimum (2) fuel pumps, and (2) independent fuel supply pipes from the bulk storage tanks to the generator tanks. Submersible fuel pumps are preferred. Systems shall be designed to allow for the regular exercise of fuel transfer pumps by alternating duplex pumps and / or continuos operation. 1-03 Fuel Piping Aboveground fuel piping shall be carbon steel primary pipe with butt weld or socket weld connections. Underground fuel piping shall be UL listed fiberglass pipe. Fuel piping shall be contained within secondary piping. The secondary pipe shall be UL listed fiberglass pipe underground and carbon steel pipe (minimum 10 gauge) aboveground. 1-04 Fuel Valves Valves for fuel piping shall be carbon steel. Where required by local code valves shall be FM approved fire safe valves. 1-05 Piping Design Piping systems shall be checked for low head loss, absence of fluid hammer, accommodation of expansion / contraction, thermal expansion relief, and isolation from vibration. Pipe supports shall be designed for required loads, shall be located at required spacing, and shall be seismic restrained where required. 1-06 Filtration / Polishing Fuel systems shall include filtration / polishing systems for both bulk storage and generator tanks over 1000 gallon capacity. Filtration shall include separation and coalescing cartridges to remove both dirt and water. The filtration / coalescing system shall be designed to filter the entire fuel inventory at least once per week. The system shall include a means of introducing a biocide for protection against bacterial and algae growth. Bulk storage tanks shall be monitored by the tank level gauge for water accumulation in the bottom of the tank. 1-07 Fill Systems Underground tanks shall be filled by gravity drop from delivery trucks. Aboveground tanks shall be equipped with systems to allow filling of tanks from the ground. Where fuel delivery by pump equipped trucks is not readily available, the fill systems shall include a truck unloading pump. Earthsafe Systems, Inc. Page 2

Section 2: Environmental 2-01 Secondary Containment Tanks and piping systems shall be designed with a minimum 100% capacity secondary containment and as required by local codes. Pump and filter systems at tanks shall be enclosed within secondary containment sumps with allowance for connection of double wall piping. 2-02 Spill Containment Spill containment shall be provided as a minimum 15-gallon capacity at all fill hose connections to storage tanks. 2-03 Overfill Protection Tanks shall be designed for redundant overfill protection. Primary control devices shall prevent filling of tanks to over 90% capacity. Secondary devices shall prevent filling at 95% capacity. A mechanical overfill prevention valve is preferred as a secondary device. Alarms shall be provided to signal an overfill condition. Return piping to tanks shall include an overfill prevention valve where an overfill condition is possible. Generator tanks shall have a gravity return overflow pipe to the main storage tank where practical. Multiple bulk storage tanks shall be connected by an overflow pipe. 2-04 Leak Detection Continuous electronic leak sensors shall monitor secondary containment tanks, piping, sumps, and enclosures. The sensors shall be integrated with the electronic level gauging system. 2-05 Corrosion Protection Underground tanks and piping shall be protected from corrosion by non-metallic exterior protection. 2-06 Anti-siphon Protection Piping from aboveground tanks shall be equipped with anti-siphon devices. 2-07 Stormwater Quality Stormwater systems from tank and generator yards shall be equipped with oil water separation devices. 2-08 SPCC Plans A licensed engineer shall provide spill Prevention, Control, and Countermeasure (SPCC) plans for all facilities. Facilities shall be equipped with spill response equipment to handle small spills. Earthsafe Systems, Inc. Page 3

Section 3: Fire Safety 3-01 General Fuel systems shall be designed in accordance with NFPA requirements 3-02 Isolation from Buildings Fuel systems shall be designed to assure isolation from buildings. This includes an assurance that leaks from tanks and piping would flow away from buildings. Tank fill points shall be separated from building openings by a minimum of 15 feet. Tank vents shall be isolated from building openings air intake locations. 3-03 Fire Rated Tanks Outside bulk storage tanks shall be underground or fire rated (UL2085) aboveground tanks. 3-04 Lightning Protection Tanks shall be ground for lightning protection at (2) points with a minimum 4/0 cable. Earthsafe Systems, Inc. Page 4

Section 4: Electrical 4-01 General Electrical work shall be in accordance with NEC requirements and local codes. 4-02 Materials Conduit shall be rigid galvanized steel conduit. Conduit accessories shall be cast aluminum. Wire shall be THHN unless otherwise noted. Maximum 3 feet lengths of seal-tight conduit may be used for connection to devices. 4-03 Power Fuel systems shall be designed for 120 / 208 VAC single phase power. The fuel system shall include (2) independent power distribution panel. Power to the panels shall be provided from independent sources in the building. 4-04 Isolation Control wire shall be isolated from motor loads. Intrinsically safe wiring for level gauging and leak detection shall be installed in conduit independent of non-intrinsically safe wires. Communication wire and cable shall be isolated in separate conduit. 4-05 Area Classification Diesel fuel systems shall be classified as ordinary electrical areas, unless required to be hazardous electrical areas by local codes. Heating systems for tanks, piping, filters and associated enclosures shall be rated as Class 1 / Division 2 4-06 Control Power Control power shall be 120 VAC 4-07 Motors Motors shall be protected by overload protection devices. Motors starters shall be capable of manual operation. Disconnect devices shall be located as required for shutoff and lockout of power for motor maintenance. Motors over 0.75 HP shall be 208 VAC single phase. 4-08 Surge Suppression Electrical systems shall include surge suppression from motor starters, solenoid valves, contactors, and other devices. Earthsafe Systems, Inc. Page 5

Section 5: Controls 5-01 Manual Control Pump controls shall be capable of manual operation. Actuated valves shall have a manual control or a manual bypass. 5-02 Redundancy Independent control modules shall be provided for each duplex pump set, each generator tank, each filter / polishing set, and each tank manifold control. 5-03 Secondary Devices Failure of any fuel system primary device shall cause control systems to automatically activate the secondary device 5-04 Pump Control Pump controls shall allow for the alternation of duplex pump sets. Pumps shall be monitored by a flow or pressure sensor. Failure of the primary pump shall cause activation of the secondary pump. 5-05 Generator Tank Level Control Generator tanks shall include (2) independent control vales at the fuel inlet. The automatic valves shall be equipped with a manual bypass. The generator tank level shall include (5) points approximately 90 % High Level, 85% Fill Stop, 75% Fill Start, 65% Low Level, 25% Critical Low Level. The low alarm shall activate the secondary fill system. The high alarm shall activate an alarm and overflow pumps if provided. 5-06 Overfill Protection Where mechanical devices are not practical independent level sensors and devices shall be provided for tank overfill protection. 5-07 Control Equipment Control systems shall be constructed of components by manufacturers with worldwide distribution and support Earthsafe Systems, Inc. Page 6

Section 6: Monitoring 6-01 General The fuel system controls shall include continuos monitoring which shall interface with the primary building management system (BMS) through a Network Interface Module (NIM). The NIM shall provide a Modbus interface or other protocol as determined by Exodus. The NIM shall also provide (30) output contacts programmable for specific conditions or events. 6-02 Fuel Inventory Bulk fuel tanks shall be equipped with electronic level gauging devices to provide inventory information. The level gauge shall also monitor for excessive water accumulation in the bottom of the tanks. The inventory monitor shall interface with the BMS through the fuel system NIM. 6-02 Leak Detection Leak sensors shall be monitored through the Fuel Inventory system or local control module. 6-03 Tank Level Tanks shall be monitored for high and low level. 6-04 Pump Activation Pumps shall be monitored for activation and low flow / pressure alarms. 6-05 Filter / Polishing Filters shall be monitored for differential pressure and water accumulation Earthsafe Systems, Inc. Page 7

Section 7: Other 7-01 Signage / Marking System designs shall include appropriate nameplates, color coding, flow direction indicators, wire markings, safety signs, and posted instructions 7-02 Cold Weather Systems shall be designed for cold weather operation where required. Cold weather protection shall include heating for tanks, piping, filters, mechanical enclosures, and electronic enclosures. 7-02 Design Documents Design documents shall include sitework, concrete, mechanical, electrical, and control drawings in sufficient detail. A standard specification for fuel system construction shall be provided. Equipment data manuals shall be included. 7-02 Commissioning Plan A detailed fuel system commissioning plan shall be prepared and executed. 7-03 Operation Manuals Operation and Maintenance manuals shall be prepared including as-built drawings, spare parts lists, and service contacts. Earthsafe Systems, Inc. Page 8

Section 8: Equipment / Manufacturer 8-01 Underground Tanks UL Listed dual steel walls with fiberglass exterior cladding. Make: STI ACT 100 8-02 Aboveground Tanks UL 2085 Listed double wall fire rated tanks with access ladders and ground mounted fill. Make: STI Fireguard 8-03 Fuel Pumps Submersible type preferred. Make: Red Jacket Gear Pumps where required. Make: Viking Centrifugal Pumps where required. Make ITT Gould 8-04 Filtration / Polishing Filters and housings. Make: Racor Controls. Make: Earthsafe 8-05 Tank Level Gauge / Leak Detection Electronic continuous monitoring with communication functions. Make / Model: Veeder Root TLS 350 8-06 Containment Piping Fiberglass pipe UL listed for fuel service. Make: Ameron. Primary pipe schedule 40 steel pipe with centralizer supports 8-07 Power Distribution Square D 8-08 Controls Based on Allen Bradley Micrologic / SLC 500 controllers and components. Make: Earthsafe 8-09 Monitoring Single panel connection for BMS interface to include Modbus and 30 point output module. Make: Earthsafe Earthsafe Systems, Inc. Page 9