Derrick Boltt Southern Region Hydro Generation Eskom South Africa
Hydro Power in the S/Region.
History of Hydro in the S/Region. In 198 the former Transkei government financed the development of Hydro power schemes in the Eastern Cape. Four Hydro Electric stations were built between 198 and 1984 in the region. The stations were allocated to the Transkei Electricity Supply Corporation. (Tescor) The Four Facilities were handed over to Eskom Southern Region in April 1995.
The Four Stations Are: Collywobbles on the Mbashe river system approximately3km east of Idutwya. First Falls on the Mthatha river situated approximately 5kM east of Mthatha. Second Falls on the same river about 15kM down stream from First Falls. Ncora on the Tsomo river approximately 5kM west of Engcobo in the North.
Mbashe Hydro Station.
Mbashe From the Air
2 nd Falls Hydro Station.
1 st Falls Hydro Station
Ncora Hydro Station.
Southern Region 6/9/24 1
SOUTHERN HYDRO INTERCONNECTION FLOW PLAN AND ELECTRICAL INTERCONNECTION Tsomo River Gauging weir Ncora Dam Bypass Ncora Irrigation Mgwili River Xuka River Umtata River LEGEND ELECTRICAL SWITCH RIVER Tsomo River Ncora Hydro Mbashe River Hydro WATER VALVE CONTROL ELECTRICAL TRANSMISSION LINE Ncora Load 3.3/22/66kV Municipal Gauging weir 132/66kV Qumbu/Dumasi Line First Falls Balancing Dam 132/66kV First Falls Hydro 11/66kV Butterworth Load Butterworth 132/66kV S/S Port St. Johns Network Mbashe Weir Umtata Load Second Falls Balancing Dam Second Falls Hydro 11/66kV 132kV line from Pembroke Mbashe River Hydro Collywobbles Hydroelectric Scheme 11/66kV Umtata River
NCORA DAM 9 MCu capacity
Over Flow from Ncora Dam
MTHATHA DAM 25 MCu capacity
Mbashe Buffer Dam
Overview of Collywobbles/Mbashe Mbashe has three 14MW units with the provision for a future fourth machine. Penstock is 1.4kM long by 4.6m diameter dual lined tunnel operating at 14 bars. Plant does not have SCO capability due to the design of the draft tube and tail race. Siltation of the dam has significantly reduced the available water reserves. Water consumed on full load is 38m3/sec.
Mbashe Hydro Gens
Salient Pole Rotor and Stator
Mbashe Spare MIV and Penstock
Mbashe Generator Floor
Overview of Second Falls The station has two 5.5MW units with the provision for a future third machine. Penstock is 44m long by 3.5m diameter steel tunnel that operates at 4bars. Water is discharged from 1 ST Falls and reaches 2 nd Falls about eight hours later. Both units are modified for SCO mode. Water consumed on full load is 25m3/sec. Station was totally refurbished in 2.
2 nd Falls Hydro Generators
2 nd Falls From the Road.
Overview of First Falls The station has two 3MW units with the provision for a future third machine. Penstock is 27m long by 2.7m diameter steel pipe that operates at 2bars. Water is discharged at 6m3/sec from Mthatha dam down the river to 1 st Falls. Both units are modified for SCO mode. Water consumed on full load is 28m3/sec. Discharged water flows down to 2 nd Falls.
1 st Falls Hydro Turbines
1 st Falls Hydro Generators
Overview of Ncora Hydro. This station has a single 1.6MW unit and two 4kW slip ring machines. The machines were removed from 1 st and 2 nd Falls when they were upgraded. Penstock is 26m long by 1.6m diameter steel pipe that operates at 4 bars. Water is released from the main Ncora dam via a canal to the holding dam. The plant does not have SCO capabilities. Water consumed on full load is 6m3/sec.
Ncora Hydro Generators
4KW DC Excitation Machine.
Ncora Hydro Splitter Weir
Upgrading of Mbashe. The tunnel was fitted with an extra 7m of steel lining to seal cracks in the concrete. The three Boving turbines and the Main Inlet valves were refurbished in 21. The auto voltage regulators and generator protection controls were all upgraded. The plant cooling was replaced with closed loop towers to minimized the down times. Scada and Telemetry systems improved.
Mbashe Tremor. 1985 Cracks in the first 5m of concrete penstock. Water pressure in hillside results in landslides. Bore holes are established on the hillside to prevent pressure build-up but is only semi-successful. Access pit at station. To Hydro s - Steel section. To Weir - Concrete section. 6/9/24 32
Generator Protection Relay.
Unitrol Auto Voltage Relay
Closed Loop Cooling Towers
Control Desk at Mbashe
Upgrading of 2 nd Falls The station was flooded in 1998 when one of the Main Inlet Valve was damaged. Renovations in 1999 has made the station the most modern facility in the region. Most of the mechanical plant including the generators were salvaged and re-used after being refurbished on site. Both the Turbines were recently rebuilt. Fiber optic communications was installed.
Damaged Main Inlet Valve.
PLC controllers at 2 nd Falls
2 ND Falls Gen Control Panels
Plant Capabilities. Both 1 st and 2 nd Falls were modified for synchronous condenser operation. (SCO) The new control relays allow for maximum reactive power support to the network. The units produce real power during peak times and remain in SCO when off peak. The change from MW to MVARs is a simple process and is done in a few minutes. Protection is calibrated for Reverse Power.
Plant Capabilities cont.. Different modes of voltage regulation is available.(voltage, Power Factor & MVar) The most stable of these modes is to operate the machines in voltage control. The large increase in network loading at Peak times has an effect on Plant stability. A unique system of controls and settings have been applied to optimize all the network and plant conditions.
Protection challenges The control relay parameters are often revised to facilitate the dynamic network conditions to keep the plant on load. The network generated negative phase sequence is high with low peak voltages. Islanding of the plant does often occur. Remote tripping of the three stations optimized the safe restoration of supply.
Connecting to the Grid. Second Falls is the only plant where the synchronization process is fully automated The other stations have a manual close facility via a common synch check panel. Keeping the plant synchronized to the grid under all conditions is still a challenge. Local network conditions are dynamic with variations in network loading and Voltages
Network Loading in the Region The 7MVA of connected Hydro power was sufficient in the 9s to supply the 5MVA of loading in the region. (ex Tescor) Electrification of the area soon changed that and by 1998 the load had doubled with an additional 132kV line from Natal. The huge increase in power made the contribution by the Generators essential for network stability during peak times.
12 1 8 6 4 2 Evening Peaks 46 22/1/21 : 22/1/21 6: 22/1/21 12: 22/1/21 18: 23/1/21 : 23/1/21 6: 23/1/21 12: 23/1/21 18: 24/1/21 : 24/1/21 6: 24/1/21 12: 24/1/21 18: 25/1/21 : 25/1/21 6: 25/1/21 12: 25/1/21 18: 26/1/21 : 26/1/21 6: 26/1/21 12: 26/1/21 18: 27/1/21 : 27/1/21 6: 27/1/21 12: 27/1/21 18: 28/1/21 : Date and time Load in MVA
14 12 1 8 6 4 2 Load Profile UMTATA DISTRICT Load Profile - 22 January 23 TOTAL LOAD GENERATION LINES 6/9/24 47 : :4 1:2 2: 2:4 3:2 4: 4:4 5:2 6: 6:4 7:2 8: 8:4 9:2 1: 1:4 11:2 12: 12:4 13:2 14: 14:4 15:2 16: 16:4 17:2 18: 18:4 19:2 2: 2:4 21:2 22: 22:4 23:2 Time MVA
Costing and Availability Data. The average cost per MWH at the stations varies monthly and is rainfall dependant. Plant utilization and availability in summer is high to maximize power production. The cost per MWH has varied from R68 in 27 to R153 per MWH in 29. The present cost per MWH in July was low due to the recent high rainfall in the area. The following graphs will provide detail.
Year-On- Year Production in MWH: 49
Percentage Utilisation of Generators: 211/9/23 5
Generators percentage Availability:
Average Cost in Rand per MWH.
Future long Term Planning. A de-siltation study has recently been completed on the Mbashe dam system. Refurbishment of the main inlet valves and the associated service seals. Generator stator and winding repairs. Maintenance to the Penstock and intake tunnel with all the sealing gates. Repairs to the four Hydro dam walls.
Mbashe Dam (Full)
Mbashe Dam Siltation 55
Scouring at Mbashe Dam 6/9/24 56
Strategic Value of Generation. The Generators are needed in Peak times of the day to reduce the high demand which occurs twice a day in the region. The Hydro generators ensure network stability for the regional grid in the area. The stations provide emergency power on demand - when & If required in a few minutes. The Hydro Stations have the ability to Black start and energize the 132kV Backbone. 57
Strategic Importance cont.. Eliminates the need to Load shed large portions of the local network during the winter Peak. Reduces the MVA max demand logged on the Transmission in feed to Distribution. The reduction in demand reduces the high costs actually paid to Tx by S/Region Dx. The ability to run in S.C.O. for some of the units provides Network stability without the use of water. 58
The need for the Hydros. The max demand in the Eastern area is a typical domestic load that increases drastically by 6h to 9h and again 17h to 21h. Without the Gen availability during those times the 132kV system is strained to the point in winter where load shedding may be done to prevent possible network instability If any of the main feeds are down the gens have to support the grid for the full outage duration. 59
MTATA AREA LOAD 18 17 16 15 14 13 Estimated return to service - 2h Max gen required - 63MVA. Requirement f rom Mbashe varied. 12 11 1 9 MVA 8 Pembroke/Kei 132kV safe transfer limit Requirement f rom 1 and 2 Falls continuous. 7 6 5 4 3 2 1 6
The Importance of Hydro The Hydro Gens play a important role in security of supply in the Southern Region. By providing instant additional MW power. They do have the ability to black start in minutes and Island feed small towns in the area. Provide system stability when in SCO mode. The power generated is deemed to be renewable energy Green Power. 61
18 16 14 12 1 8 6 4 2 : 4:2 6:3 2:1 8:4 1:5 13: 15:1 17:2 19:3 21:4 23:5 2: 4:1 6:2 8:3 1:4 12:5 15: 17:1 19:2 21:3 23:4 1:5 4: 6:1 8:2 1:3 12:4 14:5 17: 19:1 21:2 23:3 1:4 3:5 6: 8:1 1:2 12:3 14:4 16:5 19: 21:1 23:2 Typical Gen loading in 24hrs FF G1 MVA MB G3 MVA MB G2 MVA MB G1 MVA SF G2 MW
To Summarize in Short The Hydro Gens in the Southern Region are critical to Ensure the following: Network and grid stability to the Region during specific times of the day. The Gens allow some flexibility to take out Main 132kV linking lines into the Region. The Gens provide a large reduction in Max demand from Tx which saves costs. 63
In Conclusion. All four of the Hydro Gen sites in the S/Region are required for the business. The Government & Eskom has committed to the renewable energy source protocol. Green power at present is the Buzz word at all energy conferences in the world. We have this green resource available. It is a nice to have and a must to keep. 64
Future Hydro Sites in the Region A few additional Hydro generation sites have been identified in the Region. The existing site at Teebus on the Orange Fish river Tunnel near Gariep dam. Tsitsa Falls on the Umzimvubu river North of Mthatha on the N2 towards Kokstad. An additional site on the Umzimvubu River down stream from Tsitsa Falls. 65
Existing Turbine at Teebus
Spare MIV at Teebus
Future Tsitsa Falls Site.
Future Umzimvubu Site.
Mbashe River.
Thank You. Questions? 6/9/24 71