SunZia Southwest Transmission Project

Similar documents
SunZia Southwest Transmission Project

Arizona Energy Consortium Conference

TransWest Express Transmission AC and DC Project Interregional Transmission Project Submittal

Arizona Transmission Challenges

Merger of the generator interconnection processes of Valley Electric and the ISO;

MILLIGAN SOLAR PROJECT

Proposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in Stakeholder Webconference February 28, 2013

Decision on Merced Irrigation District Transition Agreement

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

THE TRES AMIGAS PROJECT

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

TABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES:

AES Corporation A CLEAN Program Brief

WIRES University Overview of ISO/RTOs. Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool

New Mexico Transmission Expansion Concepts For Wind Resources

CITY OF PASADENA APPLICATION FOR PARTICIPATING TRANSMISSION OWNER STATUS

WestConnect Regional Transmission Service. Presentation to ISAS September 26, 2017

Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions.

Michigan Thumb Loop Transmission Line Project

State Regulatory Affairs and Local Relations Update. ATC Customer Meeting November 19, 2009

Wholesale Power Supply Socorro Electric Cooperative, Inc. Rob Wolaver, P.E. Senior Manager, Energy Resources

best to you all Gail Carbiener Page 1 of 5

Overview of ISO New England and the New England Wholesale Power Markets

WestConnect Regional Planning Update

SPP OVERVIEW. Mike Ross Senior Vice President, Government Affairs and Public Relations

STATE OF MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS FOR THE PUBLIC UTILITIES COMMISSION PUC DOCKET NO. E002/TL OAH DOCKET NO.

HONORABLE CHAIRPERSON AND MEMBERS OF THE AZUSA UTILITY BOARD

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA

City of Palo Alto (ID # 6416) City Council Staff Report

P. Desert Southwest Region Transmission, Transmission Losses, Unreserved Use Penalties, and Ancillary Services Rate Order No.

Presentation to the Senate Committee on Transportation. April 7, Carson City, NV

NERSA PUBLIC HEARING: RENEWABLE ENERGY POWER PLANT LICENCE APPLICATION Riverbank Wind Power (Pty) Ltd: Wesley-Ciskei Wind Project

STATE OF MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS FOR THE PUBLIC UTILITIES COMMISSION PUC DOCKET NO. E002/TL OAH DOCKET NO.

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016

Grid Operations and the Increasing Challenges of Balancing Renewable Energy ALBUQUERQUE QUALITY NETWORK

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04

RENEWABLE ENERGY IN JORDAN What had to be done 8 Oct 2017

Alberta Electric System Operator Saleski Transmission Project Needs Identification Document

Reactive Power Requirements and Financial Compensation. Addendum to Draft Final Proposal

August 15, Please contact the undersigned directly with any questions or concerns regarding the foregoing.

Power Infrastructure. PowerToGrowPHX.com

Peninsula Corridor Electrification Project (PCEP)

Managing California s Electrical Supply System after the shut down of San Onofre Nuclear Generating Station

Western NY Public Policy Transmission Planning Report

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation

REGIONAL TRANSMISSION ORGANIZATIONS / INDEPENDENT SYSTEM OPERATORS AND THE ENERGY IMBALANCE MARKET: AN OVERVIEW OF THE PICTURE IN THE WEST

Terry Blackwell Page 1 of 5. Education North Carolina State University BS, Electrical Engineering Power Systems emphasis

2012 INSTALLERS MEETING UES INSTALLER S MEETING

EASTERN ILLINI ELECTRIC COOPERATIVE REGULATION NO. 26A

March 7, Subject: Southern California Edison 2011 Annual Progress Report

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Southern California Edison Clean Energy Future

Frequently Asked Questions Trico Proposed Net Metering Tariff Modifications

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82

welcome to the BC Hydro community open house

ARIZONA ALTERNATIVE FUEL CORRIDOR NOMINATION FAST ACT 1423

October 17, Please contact the undersigned directly with any questions or concerns regarding the foregoing.

2013 Transportation Technology Deployment Report:

U.S. System Summary: ARIZONA/SOUTHWEST

Selling PFIFFNER in the UK. Paul Haines

Updates. Pat Reiten President and CEO, PacifiCorp Transmission

Consumers Energy Net Metering

Updates and Modifications to Report

Attachment A Page 1 of 149 ARIZONA PUBLIC SERVICE COMPANY TEN-YEAR TRANSMISSION SYSTEM PLAN. Prepared for the Arizona Corporation Commission

Workshop on International Good Practices of Sustainable Energy Technologies. Beirut Energy Forum 9-11 Sep 2015

Interconnecting with Ameren

Net Metering & Compensation Seminar

MILESTONE SUMMARY REPORT Project funding provided by customers of Xcel Energy through a grant from the Renewable Development Fund

Alternatively Financing Energy Projects Fort Campbell s Lessons Learned

Michigan Renewable Energy Case Study

Metropolitan Domestic Water Improvement District Board of Directors Meeting. August 8, July 2011 Report

Re: Comments on the 12/7/09 Dynamic Transfer Stakeholder Meeting

CUSTOMER/ TWIN ARROWS PROJECT

Mystic to Woburn Line Project. Town of Winchester Board of Selectmen Lincoln School Auditorium February 11, 2016

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

Neighborhood Fire Stations

TOT1A: Metering Point Relocation Comprehensive Progress Report (WECC Path 30)

What s Up with City of Tucson Solar?? Bruce Plenk, City of Tucson Solar Energy Coordinator Office of Conservation and Sustainable Development

Contents. Solar Select TM Frequently Asked Questions

SPP Notification to Construct

January 18, Docket: ER Energy Imbalance Market Special Report Transition Period September 2018 for Idaho Power Company

SPS Planning Criteria and Study Methodology

Updates and Modifications to Report

Microgrids A Regulatory Perspective

Participation of Beacon Power s Flywheel Energy Storage Technology in NYISO s Regulation Service Market

(2) Scope. 220 CMR applies to all Distribution Companies subject to the jurisdiction of the Department.

100 MW Wind Generation Project

congestion management program

Supplemental Report on the NCTPC Collaborative Transmission Plan

Purple Line Light Rail P3 Project

PUBLIC SERVICE COMPANY OF COLORADO SENATE BILL DESIGNATION OF ENERGY RESOURCE ZONES AND TRANSMISSION PLANNING REPORT PROCEEDING NO.

MENARD ELECTRIC COOPERATIVE POLICY MANUAL. SECTION IV Operating Rules for Cooperative Members

Considerations for Municipal Solar Projects. Ben Frevert Larsen Engineers November 16, 2016

MassDOT Highway ROW Solar PV Energy Program. Hongyan (Lily) Oliver Massachusetts Department of Transportation Office of Transportation Planning

Transmission from East to West Transmission Policy Institute The History, Present and Future Of Electric Transmission Planning

ORANGE COUNTY TRANSPORTATION AUTHORITY. Agreement to Purchase Compressed Natural Gas Articulated Buses. Staff Report

JEA Distributed Generation Policy Effective April 1, 2018

Four Corners Queue Transmission Interconnection Study

D.P.U A Appendix B 220 CMR: DEPARTMENT OF PUBLIC UTILITIES

Re: California Independent System Operator Corporation

Transcription:

SunZia Southwest Transmission Project SunZia Project Update for the Southern Arizona Economic Development Group September 12, 2017 SUNZIA SOUTHWEST TRANSMISSION PROJECT SEPTEMBER 12, 2017 0

SouthWestern Power Group Independent developer of utility-scale generation and transmission in the Desert Southwest Project Manager/Developer of SunZia Based in Phoenix, staff of ten: 175 years of experience, in business for 17 yrs Major References:» 2,400 MW CCGT Panda Gila River power plant (in operation)» 1,000 MW CCGT Bowie Power Station (permitted)» 600 MW Lignite CFB Rockdale Power Plant (in operation)» 200 MW (DC) Solar PV power project (in operation) Owned by MMR Group of Baton Rouge, LA SUNZIA SOUTHWEST TRANSMISSION PROJECT SEPTEMBER 12, 2017 1

MMR Group Construction services firm based in Baton Rouge, LA 22 offices in USA, Canada & overseas In business +25 years; owned by senior management Approximately 5,000 employees One of the largest electrical contractors in the US Industrial markets only: power, oil & gas, process, etc. Built over 40,000 MWs of generation SUNZIA SOUTHWEST TRANSMISSION PROJECT SEPTEMBER 12, 2017 2

SunZia: 500kV Project delivering NM Wind to the Palo Verde Hub Central NM Wind Region Proposed SunZia Transmission Line Pinal Central Willow SunZia East 3 rd Party Transmission Service SunZia South SUNZIA SOUTHWEST TRANSMISSION PROJECT SEPTEMBER 12, 2017 3

Project Summary 515 mile independent transmission project in New Mexico and Arizona Two 500 KV AC lines providing 3,000 MW of transfer capacity to AZ and CA Brings high-quality renewable energy to western markets Pattern Energy was selected in August 2016 as the anchor customer for the first 500 kv transmission line Obtained Declaratory Order from FERC in May 2011 for negotiated rate authority WECC granted SunZia an Accepted Rating of 3,000 MW for two 500kV AC lines in March 2011; rating was re-confirmed in January 2015 Plan of Development is being prepared; NTP from BLM expected Q1 2018 Construction Start in mid-2018 Commercial operation by end-2020 SUNZIA SOUTHWEST TRANSMISSION PROJECT SEPTEMBER 12, 2017 4

BLM Selected Route in the ROD SUNZIA SOUTHWEST TRANSMISSION PROJECT SEPTEMBER 12, 2017 5

SunZia and Permits Started permitting activity in September 2008 Completed NEPA with BLM in January 2015 (Record of Decision) Executed ROW Grant Agreement with BLM September 2016 Received an AZ state permit in February 2016 (Certificate of Environmental Compatibility) Will apply for the following permits this year: Locational permit with NM Public Regulation Commission Section 404 permit with US Army Corps of Engineers SUNZIA SOUTHWEST TRANSMISSION PROJECT SEPTEMBER 12, 2017 6

Engineering and Construction Engaged Burns & McDonnell in May 2016 for design & engineering of SunZia Line 1 for Final Plan of Development Engaged Power Engineers as Owners Engineer in May 2017 Design is 40% complete; targeting 70% complete by Oct 2017 EPC contractor will be joint venture of Kiewit Power + MMR Ongoing discussions with potential suppliers of key items Towers, Underground + Overhead Cable, Series Compensation Expect to construct line in 4 segments, with 2 to 4 major subcontractors working concurrently Construction schedule is 30 months SUNZIA SOUTHWEST TRANSMISSION PROJECT SEPTEMBER 12, 2017 7

SunZia and Rights of Way Federal ROW Grant with BLM signed September 2016 AZ State NM State AZ Private ROW application submitted; Target completion in Q4 2017 Will submit application in Q3 2017 with an expected 9 months to process Acquisition underway; 50% complete by miles NM Private Acquisition underway; 35% complete by miles SUNZIA SOUTHWEST TRANSMISSION PROJECT SEPTEMBER 12, 2017 8

Summary of Rights of Way Category Entity AZ NM Total Miles Number Status Federal BLM 50 134 184 1 ROW Grant signed State Arizona 134 134 1 ROW Application submitted New Mexico 90 90 1 ROW Application pending Private Arizona 16 16 39 In-progress New Mexico 92 92 93 In-progress Aerial Crossings Various 89 In-progress Total 200 315 515 SUNZIA SOUTHWEST TRANSMISSION PROJECT SEPTEMBER 12, 2017 9

Customers and PPAs SunZia selected Pattern Energy in August 2016 as the anchor tenant (pursuant to our FERC Order) SunZia awarded Pattern 1,500 MW of capacity (100% Line 1) and await FERC approval Pattern s Corona Wind Project is SunZia s customer and it will pay SunZia to use our transmission capacity Pattern will sell Corona Wind s energy to utilities under long-term power purchase agreements (PPAs) Pattern and SunZia are meeting with utilities, corporates and others in AZ and CA to market Corona Wind energy Pattern has significant interest from a variety of potential customers and is negotiating proposals with several parties SUNZIA SOUTHWEST TRANSMISSION PROJECT SEPTEMBER 12, 2017 10

Summary of Line Miles in Arizona AZ County BLM AZ State Trust Private Total Miles Notes Cochise 0 51 7 58 Graham 26 8 0 34 Willow Substation proposed Greenlee 9 0 0 9 Pima 0 16 0 16 Pinal 15 59 9 83 50 134 16 200 Interconnects at Pinal Central Substation SUNZIA SOUTHWEST TRANSMISSION PROJECT SEPTEMBER 12, 2017 11

2012 Economic Impact Assessment Jointly prepared by: Economic and Business Research Center Eller College of Management The University of Arizona Tucson, Arizona Arrowhead Center, Inc. New Mexico State University Las Cruces, New Mexico SUNZIA SOUTHWEST TRANSMISSION PROJECT SEPTEMBER 12, 2017 12

Economic Impacts during Construction Note: Jobs are expressed in man-years SUNZIA SOUTHWEST TRANSMISSION PROJECT SEPTEMBER 12, 2017 13

Economic Impacts during Operation SUNZIA SOUTHWEST TRANSMISSION PROJECT SEPTEMBER 12, 2017 14

David Getts General Manager SouthWestern Power Group dgetts@southwesternpower.com SUNZIA SOUTHWEST TRANSMISSION PROJECT SEPTEMBER 12, 2017 15