COLORADO SPRINGS UTILITIES RESPONSE TO Xcel ENERGY INTERCONNECTION SYSTEM IMPACT STUDY REQUEST # GI , RESTUDY 1 (August 6, 2009)

Similar documents
Falcon-Midway 115 kv Line Uprate Project Report

Interconnection System Impact Study Report Request # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

100 MW Wind Generation Project

SPS Planning Criteria and Study Methodology

Appendix D Black Hills Project Summary

Generation Interconnection Request # GI Restudy Feasibility and System Impact Study Report

Consulting Agreement Study. Completed for Transmission Customer

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

GENERATOR INTERCONNECTION REQUEST. BHCT-G11 Interconnection System Impact Restudy PREPARED BY BLACK HILLS CORPORATION TRANSMISSION PLANNING

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

Interconnection Feasibility Study Report Request # GI

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014

2012 LOCAL TRANSMISSION PLAN:

PSCo 10-Year Transmission Plan/20-Year Scenario Assessment

APPENDIX F: Project Need and Description

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

New 115 kv Disconnect Switches at Bloomsburg MTS

Feasibility Study Report

Merger of the generator interconnection processes of Valley Electric and the ISO;

Header. Reasonableness Test RT 007/11 Balhannah & Uraidla 66 / 33 kv Substations. RT Balhannah and Uraidla - Final Draft Page 1 of 8

Midway/Monument Area TTC Study

System Impact Study Report Request # T MW Firm Point-to-Point Transmission Service Request from Wyoming to Colorado

West Station-West Cañon 115 kv Transmission Project

Black Hills Project Summary

Supplemental Report on the NCTPC Collaborative Transmission Plan

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

Burlington Lamar 345/230 kv Impact and 2013 Post TPL Assessment Study

CUSTOMER/ TWIN ARROWS PROJECT

15 Nelson-Marlborough Regional Plan

Feasibility Study Report

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

CRYPTOCURRENCY MORATORIUM SMALL MINER RATE IMPACT. September 4, 2018

Feasibility Study for the Q MW Solar Project

Local Transmission Plan. October 11, 2013 Revised August 25, 2014

Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

2015 Grid of the Future Symposium

System Impact Study Report

MILLIGAN SOLAR PROJECT

Feasibility Study Report

DFO STATEMENT OF NEED REPORT

15 Nelson-Marlborough Regional Plan

2011 LOCAL TRANSMISSION PLAN:

Table of Contents. Purpose. Eldorado Intertie and System (Eldorado- Moenkopi) Scheduling at Willow Beach. Operating Procedure

Project #148. Generation Interconnection System Impact Study Report

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Stability Study for the Mt. Olive Hartburg 500 kv Line

APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation

New Mexico Transmission Expansion Concepts For Wind Resources

Transmission Planning for Wind Energy Resources in the Eastern United States. Dale Osborn

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation

Hybrid Wind Solar Generator

GENERAL DIRECTION SOUGHT AND SPECIFIC QUESTIONS TO BE ANSWERED

AQUILA NETWORKS WESTPLAINS ENERGY COLORADO CATEGORY C CONTINGENCY STUDIES

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

Decision on Merced Irrigation District Transition Agreement

Western Area Power Administration Sierra Nevada Region

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT

Public Service Company of Colorado Transmission Projects Status. CCPG May 5, 2016

2016 Load & Capacity Data Report

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Status of PNM s Completed Transmission Construction Projects 11/30/2017

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)

MILESTONE SUMMARY REPORT Project funding provided by customers of Xcel Energy through a grant from the Renewable Development Fund

Overview of State Distributed Generation Interconnection Rules

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV

Energy Storage Interconnection Initiative

Georgia Transmission Corporation Georgia Systems Operations Corporation

300 MW SOLAR PHOTOVOLTAIC PLANT, GENERATOR INTERCONNECTION FEASIBILITY STUDY

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

TRANSMISSION PLANNING CRITERIA

Manitoba Hydro Generation Interconnection Exploratory Study Notice September 28, 2006

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders

Jay Caspary Director Research, Development & Tariff Services

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

Impact of Distributed Energy Resources on Transmission System Reliability

Engineering Study Report: FortisAlberta Inc. Plamondon 353S Capacity Increase. Contents

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company

FINAL FACILITY STUDY. 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1. September 10, 2010

The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027)

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

Connection Engineering Study Report for AUC Application: AESO Project # 1674

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation

Verde Transmission, LLC. Verde Project. System Impact Study Report

Interconnection and Net Metering Service in Ohio

SERTP rd Quarter Meeting

Electricity industry structure and capacity growth trends

PSE Attachment K Puget Sound Area Transmission Meeting

SEPA Grid Evolution Summit: Rethinking Rate Design

2018 Load & Capacity Data Report

Western Area Power Administration Sierra Nevada Region

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Reactive Power Compensation for Solar Power Plants. Andy Leon IEEE PES Chicago Chapter December 12 th, 2018

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

Transcription:

COLORADO SPRINGS UTILITIES RESPONSE TO Xcel ENERGY INTERCONNECTION SYSTEM IMPACT STUDY REQUEST # GI-2007-12, RESTUDY 1 (August 6, 2009) On June 15, 2009 Xcel Energy released a restudy of a System Impact Study evaluating the effect of a 250 MW wind power injection at Jackson Fuller substation (GI-2007-12). Colorado Springs Utilities (SU) was identified in that study as an affected party, with a total of four lines overloaded under contingency. Additionally, the Xcel restudy found several SU owned lines to be benchmark overloaded without the proposed injection at Fuller substation. This study will reevaluate the SU overloads in light of new SU load forecast data and a revised generation dispatch profile for Colorado Springs Utilities. BASE CASE CHANGES AND STUDY SCOPE SU evaluated the 2011 summer peak base case used by Xcel to perform the Impact Study, and decided that there were two significant changes that should be made to the SU model. The changes were as follows: (1) SU completed a new, revised distribution system load forecast in June 2009. The new forecast was based upon the approved 2009 SU corporate forecast. Load projections were reduced, and the location of new load growth was modified based on recent trends. Loads in the model were revised. The table in Appendix C details the changes made to SU loads in the Xcel base case. (2) The local generation dispatched by Colorado Springs Utilities was modeled in the Xcel base case as approximately 185 MWs above expected requirements. Generation levels were reduced in the model. The largest reduction in generation was at Front Range Power, and reflects the fact that the Front Range Power Purchase Agreement with PSCo expires in 2009. There is no firm transaction to replace it. The balance of the dispatch level reduction was made so that SU generation plus imports would match projected SU load. The table in Appendix B details the changes made to generator output levels in the Xcel base case. Both changes above are consistent with SU s annual transmission modeling process. After the base case was modified, studies were run with and without injection at Fuller, for both the case with and the case without the Midway to Waterton 345kV line in service. A single contingency analysis was run for zones 700, 704, 752 and 757. 1521 Hancock Expressway P.O. Box 1103, Mail Code 1821 Colorado Springs, CO 80947-1821 http://www.csu.org

Monitored elements included all Colorado Springs Utilities facilities as well as all SU tie lines. RESULTS With the modifications to the base case completed, all SU benchmark overloads were eliminated for both the case with and the case without the Midway to Waterton line in service. The case with the Midway-Waterton line in service and a 250MW injection at Fuller substation also resulted in no overloads on the SU system. For the case with the Midway-Waterton line not in service, a 250MW injection at Fuller resulted in significant overloads on four SU owned lines. Appendix A includes a tabular comparison of the loading in the Xcel study versus the loading in the SU revised study. CONCLUSIONS It is apparent that the Midway to Waterton project is critical to accommodating the proposed 250MW injection at Fuller substation without overloading the SU system. There are therefore two possible scenarios: (1) The Midway to Waterton line is in service before the injection begins. There are no overloads identified on the Colorado Springs Utilities system in the modified base case if the Midway to Waterton project is completed before the 250MW injection at Jackson Fuller substation begins. Colorado Springs Utilities believes that the 250 MW injection will not adversely impact the SU system in this scenario. (2) The Midway to Waterton line is delayed until after the injection begins. Without a completed Midway to Waterton line, there are significant overloads on four SU owned lines. Among the options available to the wind developer in this scenario would be to: (a) (b) (c) Postpone generation until the line is completed. Limit generation to a level which mitigates overloads. Fund improvements to the SU lines as insurance against possible delays in the construction of the Midway to Waterton line. Colorado Springs Utilities requires that mitigation of any overloads created on the SU system by the 250MW wind injection be made a condition of approval of the LGIA. 2

APPENDIX A COMPARISON OF OVERLOADS AS REPORTED IN XCEL AND CSU STUDIES MIDWAY TO WATERTON 345kV PROJECT ASSUMED IN SERVICE WITHOUT GI-2007-12 WITH GI-2007-12 MONITORED BRANCH BRANCH RATING (MVA) OWNER Xcel STUDY CSU STUDY Xcel STUDY CSU STUDY CONTINGENCY 73393 CTTNWD S/ 73389 BRIARGATE 73414 MONUMENT/ 73477 FULLER 230/ 159 (1) CSU 109.8% 79% 124.1% 93.2% 168 (2) CSU 111.3% 80.8% 126.9% 96% 159 CSU 82.5% 73.2% 104% 82.2% 156 (3) CSU 84.8% 68.6% 109% 87.1% 100 TSG&T 92.1% 86.4% 114.6% 107.4% 73389 BRIARGAT/ 73393 CTTNWD S (1) This rating is 150 MVA in the Xcel study. (2) This rating is 159 MVA in the Xcel study. (3) This rating is 142 MVA in the Xcel study. 3

COMPARISON OF OVERLOADS AS REPORTED IN XCEL AND CSU STUDIES MIDWAY TO WATERTON 345kV PROJECT NOT IN SERVICE WITHOUT GI-2007-12 WITH GI-2007-12 MONITORED BRANCH BRANCH RATING (MVA) OWNER Xcel STUDY CSU STUDY Xcel STUDY CSU STUDY CONTINGENCY 73393 CTTNWD S/ 73389 BRIARGATE 73414 MONUMENT/ 73477 FULLER 230/ 159 (1) CSU 113.9% 92.5% 128.8% 110.3% 168 (2) CSU 115.7% 95.1% 131.9% 114.2% 159 CSU 88% 92% 110.3% 118.3% 156 (3) CSU 91% 82.9% 116% 114.6% 100 TSG&T 96% 98.2 119.1% 122.7% 73389 BRIARGAT/ 73393 CTTNWD S (1) This rating is 150 MVA in the Xcel study. (2) This rating is 159 MVA in the Xcel study. (3) This rating is 142 MVA in the Xcel study. 4

APPENDIX B COMPARISON OF GENERATION DISPATCH IN Xcel AND CSU BASE CASES GENERATOR BUSS # DISPATCH IN Xcel MODEL DISPATCH IN CSU MODEL BIRDSAL1 73381 12.8 0.0 BIRDSAL2 73382 12.8 0.0 BIRDSAL3 73383 20.2 0.0 RD_NIXON 73418 183.4 208 TESLA1 73424 22.5 28 DRAKE 5 73427 42.2 46 DRAKE 6 73428 69.7 77 DRAKE 7 73429 119.2 131 NIXONCT2 73434 27.5 0.0 NIXONCT1 73435 27.5 0.0 FTRNG1CC 73507 137.5 100 FTRNG2CC 73508 137.5 100 FTRNG3CC 73509 165 102.6 TOTALS: 977.8 792.6 NOTE: SU meets load requirements with the local generation dispatched in the CSU model as shown above, supplemented by imports from WAPA and the City of Fountain s contracted supply from MEAN. 5

APPENDIX C COMPARISON OF CSU LOADS IN Xcel AND CSU BASE CASES BUSS # NAME KV CSU LOAD IN Xcel MODEL CSU LOAD IN CSU MODEL 73380 CLAREMNT 230 12.6 8.7 73385 BIRDSALN 34.5 37.8 48.7 73386 BIRDSALS 34.5 36.3 47.5 73387 BIRDSALW 115 22.8 19.5 73388 BRADLEY 115 60.4 60.8 73389 BRIARGAT 115 51.7 28.9 73391 CTTNWD N 115 26.8 20.7 73393 CTTNWD S 115 24.6 17.9 73395 CTTNWD S 34.5 2.8 26.4 73396 DRAKE E 34.5 34.8 53.8 73398 DRAKE S 115 19.0 26.8 73399 DRAKE W 34.5 61.5 28.1 73404 FOUNTAIN 115 52.4 54 73408 KELKER E 115 25.5 34.4 73409 KELKER W 115 23.6 19.3 115 38.5 26.2 73411 FONTERO 115 22.4 25.1 73417 RD_NIXON 115 3.4 1.9 73420 ROCKISLD 115 44.5 45.4 73421 STETSON 230 32.4 24.7 73423 TESLA 34.5 17.7 0.0 73425 WOODMEN 115 40.7 40.1 73430 FAIRVWCS 115 16.9 16.9 73490 RAMPART 115 45.4 40.7 73496 ATMELSUB 115 22.6 21.6 73564 KETTLECK 34.5 16.1 22.3 73565 KELKER 34.5 44.8 65.7 73566 ROCKISLD 34.5 70.93 57.4 115 10.6 9.2 73601 SANTA FE 115 22.5 10.0 TOTAL: 942.03 902.7 NOTE: Power factor of all loads is 97% 6