PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G

Similar documents
Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Western Region ATSI

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee South

Reliability Analysis Update

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee South

New Jersey State Report

Sub-Regional RTEP Committee PJM South

Sub Regional RTEP Committee Mid-Atlantic

Reliability Analysis Update

Sub Regional RTEP Committee Mid-Atlantic

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Transmission Expansion Advisory Committee

PJM Regional Transmission Expansion Planning (RTEP) Process

100 MW Wind Generation Project

Generator Interconnection System Impact Study For

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Sub Regional RTEP Committee Mid-Atlantic

DFO STATEMENT OF NEED REPORT

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC

South Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget

Feasibility Study Report

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Transmission Expansion Advisory Committee

Sub Regional RTEP Committee - Southern

South Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

Sub Regional RTEP Committee - Southern. August 19, 2011

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Sub Regional RTEP Committee Mid-Atlantic

Interconnection System Impact Study Report Request # GI

Appendix D Black Hills Project Summary

Alternatives for meeting the need for transmission improvement described

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

2015 Grid of the Future Symposium

MILLIGAN SOLAR PROJECT

Illinois State Report

System Impact Study Report

Rogers Road to Clubhouse 230kV New Transmission Line April 1, 2016

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION

Reliability Analysis Update

Q0044 interconnection at

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

The Energy Queensland Group Notice of no non-network options

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

PJM SRTEP Meeting Questions Pertaining to Proposed Projects & Scopes AEP: Ambler Ridge:

Sub Regional RTEP Committee Mid-Atlantic First Energy MAAC Solution Meeting

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04

Designated Entity Pre-Qualification Materials. Exelon Corporation

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

EXCEPTIONS TO RELIABILITY RULES Revision 11 February 9, 2018

Transmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board

Supplemental Report on the NCTPC Collaborative Transmission Plan

ATTACHMENT - DFO STATEMENT OF NEED

Review of Electric Utility Hurricane Preparedness and Restoration Actions ORLANDO UTILITIES COMMISSION RESPONSES TO STAFF'S SECOND DATA REQUEST

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Black Hills Project Summary

Sub Regional RTEP Committee PJM West

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Transmission Expansion Advisory Committee. Reliability Analysis Update

2017 Indiana State Infrastructure Report (January 1, 2017 December 31, 2017)

CUSTOMER/ TWIN ARROWS PROJECT

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection

PG&E s 2012 Request Window Proposals

South Dakota 890 Study

Reliability Analysis Update

Feasibility Study Report

Surry Skiffes Creek Whealton Modeling and Alternatives Analysis Review

SPP Notification to Construct

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

MTEP13 SPM #2- Central Region. March 25, 2013

FINAL FACILITY STUDY. 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1. September 10, 2010

Generation Interconnection Facilities Study For

Maddox Creek to Southwest Lima 345kV New Transmission Line November 15, 2016

Falcon-Midway 115 kv Line Uprate Project Report

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

ATTACHMENT Y STUDY REPORT

IEEE-PES Chicago Chapter Presentation November 11, Smart Grid. Mike Born. Principal Engineer, Capacity Planning

Impacts of MISO DPP-2016-February (West, ATC, MI, South) Projects on PJM Facilities

A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES. Electrical. Mechanical. Civil. Protection & Control. System Planning

Market Efficiency Update

Feasibility Study Report

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

TRANSMISSION PLANNING CRITERIA

STATE OF NEW JERSEY BOARD OF PUBLIC UTILITIES

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions.

Interconnection Feasibility Study Report GIP-157-FEAS-R2

Feasibility Study for the Q MW Solar Project

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

West Station-West Cañon 115 kv Transmission Project

SECTION 9: ELECTRICAL POWER DISTRIBUTION. ESE 470 Energy Distribution Systems

Mechanical, Electrical, Technology Engineering Firm

Out of Sight Out of Mind Revisited. EEI Transmission, Distribution, & Metering Conference October 14, 2009 Ken Hall Hall Energy Consulting

Robert L. Mitchell CEO and Co-Founder Atlantic Wind Connection

Transcription:

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, 2016 Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G

PSE&G System Characteristics New Jersey utility characterized by densely populated load areas, limited space for expansion, particularly in northern New Jersey. 69kV Facilities In service in 1970s and later. Established tie with other TOs Adds more flexibility in transmission planning. Higher capacity equivalent to more than four (4) 26kV circuits Uses wood pole construction on city streets. More reliable less vegetation impact because of higher poles networked construction as opposed to radial 26kV With the continued conversion of 138kV to higher voltages, 69kV acts as a new transition/sub transmission system between the 230kV/345kV and the distribution system. 26kV Facilities In service since early 1900s; near end of their useful life cycle. Looped nature of system makes it difficult to arrange outages and transfer out loads to other switching stations in a heavily loaded station/area. Limited capacity for future growth. City streets are congested. Limited ability to construct additional 26kV circuits on city streets. Circuits do not have the required capacity to supply large commercial customers (e.g.. data centers) 2

PSE&G Supplemental Projects Philosophy Projects that are not the result of violations to NERC TPL standards, PJM or PSE&G reliability criteria, but address problems that impact PSE&G reliability performance and standards, subject to an exception for certain 69kV facilities. Maintaining reliability to the PSE&G 138kV and sub transmission network. Addressing PSE&G s maximum allowable load drop. Addressing equipment condition. Improving and maintaining a reliable supply to the distribution system. Modernizing the system to improve operational performance (e.g. optical fiber, telemetry upgrades). 3

PSE&G Supplemental Projects Philosophy PSE&G criteria includes both transmission and distribution system violations. We classified certain 69kV projects as supplemental given that the drivers for these projects are primarily distribution related, including 26kV aging infrastructure, reliability criteria violations and insufficient capacity. 4

PSE&G Aging Infrastructure Projects Identified and prioritized based on analysis of the following metrics: Age of Asset Asset health and condition SAIDI/ CAIDI/ MAIFI Industry standards/guidelines Wood structures: 35 55 years Conductor and connectors: 40 60 years Porcelain insulators: 50 years 5

PSE&G Aging Infrastructure Projects For the projects being reviewed today, PSE&G did consider system performance with the facility removed from service. PSE&G considers the current rating specification of the equipment and lines, as well as future system requirements in determining the ratings and specifications of replacement facilities. e.g.: 69kV line rated for 95MVA summer normal and 131.5MVA summer emergency 69kV transformers are rated for 300MVA summer normal and 350MVA summer emergency. 69kV system is networked and acts as sub transmission, provides additional reliability, and is planned for ultimate transmission/distribution system needs. 6

PSE&G Future Load Growth Projects 69kV solution most cost effective solution. Alternative considered: Alternative of upgrading switching stations was not as cost effective. 69kV facilities are operated as part of the networked system. 7

138kV Project 8

138kV Overloaded Circuit Circuit is overloaded Damaged and exposed control cables includes 26kV substation protection Five (5) overstressed 138kV breakers Bergen Gen Unit 1 Existing Topology 138 kv Straight Bus 60P 80P N.O. Bus 3 Bus 2 Bus 1 65P 55P 90P F-1306 R-1344 E-1305 40P 50P 30P M-1339 Existing Control Cables NJ Turnpike overloaded circuit 1P40 40P70 Unit 1 STG XFMR 1112 1314 1 1 1 1 ST1 ST2 CT1 CT2 CT3 CT4 9

Proposed Solution Rebuild/Reconductor 138kV ckt (1 mi) Upgrade control cables using OPGW Relocate and upgrade breakers Estimated Cost $6.5M PSE&G $12.7M Generation Owner Schedule IS Date Fall 2016 Project Status Conceptual 15P NJ Turnpike Unit 1 STG XFMR ST1 90P ST2 1P40 16P Bergen Gen Unit 1 Proposed 138 kv Ring Bus Bus 3 Bus 1 14P 13P 12P 11P 2P40 90P60 1112 1112 1 T2H70 1 CT1 CT2 40P60 40P70 T1P70 1314 1314 1 1 CT3 CT4 10

69kV Projects 11

Kearny 69kV breaker station 12

Kearny 69kV breaker station Problem Statement: Increased load growth in Harrison St (projected to be overloaded by 2018) and Clay St. areas (projected to be overloaded by 2025). 26kV service not sufficient to provide adequate capacity for the increased load. Harrison station has been in service since 1912 and Clay street has been in service since 1941. PSEG is addressing the aging 26kV infrastructure in Harrison St and Clay St and also the station overload problems by 69kV conversion. In additional to addressing overloads, this also ensures adequate capacity for future growth. Proposed Solution: Build a new 230 69kV switching station in the area to provide added capacity. Build a three bay breaker and a half 69kV switching station. This new 69kV station will be in a central location to serve the load and also provide adequate capacity for future growth in the area. Build a new line from Kearny to Madison 69kV. Alternative Considered: Upgrading existing substations is not feasible solution. It would require a larger equipment footprint than is available at the station. No additional property is available for station expansion. This area is also extremely congested and expanding the current 26kV will be very difficult. Estimated Cost: $125.1 M (Desktop Estimate Includes 50% Risk and Contingency) Scheduled IS Date: 12/31/2018 Project Status: Conceptual 13

Madison 69kV breaker station 14

Madison 69kV breaker station Problem Statement: Increased load growth in Jersey City area. Current Marion 26kV switching station that feeds Madison St and Marshall St stations will exceed its capacity by 2019. 26kV service not sufficient to provide adequate capacity for the added load. Madison and Marshall stations have been in service since 1955 and 1948 respectively, and reaching the end of their life cycles. Equipment damaged due to hurricane Sandy (entire station flooded at both Madison St and Marshall St stations). PSEG is addressing the aging 26kV infrastructure at Madison and Marshall St stations and the 26kV switching station overload problem at Marion 26kV station by 69kV conversion. In additional to addressing overload, this also ensures adequate capacity for future growth. Proposed Solution: Build a new 230 69kV Madison switching station. Build a 8 breaker 69kV ring bus and install four 69 4kV transformers. Build a new 69kV line from Madison 69kV to Union City 69kV. This will ensure that there is capacity for future growth and will address the overloaded condition in Marion 26kV switching station. Alternative Considered: Upgrade existing switching station and rebuild 26kV circuits. This will be more costly compared to the proposed solution. Estimated Cost: $124.627 M (Desktop Estimate Includes 50% Risk and Contingency) Scheduled IS Date: 12/31/2018 Project Status: Conceptual 15

New Milford 69kV Breaker Station 16

New Milford 69kV breaker station Problem Statement: Increased load growth in Teaneck, Englewood and Dumont areas. Violation of PSEG N 1 1 criteria for Teaneck 69kV and Dumont 69kV. Introduces a new source station in the area to support future load growth. PSEG is addressing the aging 26kV overload problem in the New Milford area by 69kV conversion. This not only addresses aging infrastructure, but also ensures adequate capacity for future growth. Proposed Solution: Build a new 230 69kV New Milford switching station. Install a new 230 69kV transformer. Build a new six(6) breaker 69kV ring bus. Build a new line from New Milford 69kV to Teaneck 69kV. Build a new line from New Milford 69kV to Dumont 69kV. Alternative Considered: Re build the station and build a new switching station in the Teaneck, Englewood and Dumont vicinity. Some of the 26kV circuits will also need to be rebuilt to provide additional capacity. This would result in higher cost than the proposed solution. Estimated Cost: $79.7 M (Desktop Estimate Includes 50% Risk and Contingency) Scheduled IS Date: 12/31/2018 Project Status: Conceptual 17

Kingsland, Harrison and Van Winkle 69kV 18

Kingsland, Harrison and Van Winkle 69kV Problem Statement: Increased load growth in Harrison and Van Winkle areas. Harrison St sub has been in service since 1912 and Van Winkle station has been in service since 1942. Current East Rutherford 26kV switching station that feeds Van Winkle station will be above its capacity by 2019. Currently there is a temporary 69kV in Kingsland. PSEG N 1 1 criteria violation at Harrison St substation. PSEG is addressing the 26kV overload problem in East Rutherford by 69kV conversion where deemed appropriate. This not only addresses overloads, but also ensures adequate capacity for future growth. Proposed Solution: Build a new 230 69kV switching station. There is currently already a temporary 69kV station in Kingsland. This project will make it permanent. Build a new 69kV breaker and a half Van Winkle substation. Build a new 69kV line from Kingsland to Harrison. Build a new 69kV line from Kingsland to Van Winkle. Build a new 69kV line from Van Winkle to East Rutherford. Alternative Considered: Upgrade existing switching station and rebuild 26kV. This would be more costly compared to the proposed solution. Estimated Cost: $138.5M (Desktop Estimate Includes 50% Risk and Contingency) Scheduled IS Date: 06/01/2019 Project Status: Conceptual 19

Ironbound 69kV 20

Ironbound 69kV Problem Statement: Ironbound station has been in service since 1931. Existing equipment has reached the end of their life cycle. Spare/Replacement parts are difficult to acquire because of the equipment's age. Replace low capacity 26kV to ensure adequate capacity for future growth. Proposed Solution: Build a new Ironbound 69kV station. Build a new 69kV station from Ironbound St. to Federal Square. Build a new 69kV station from Ironbound St to Foundry St. Alternative Considered: Eliminate existing station by doing conversions. This option would be far more expensive than the proposed solution and will also result in possible neighboring station capacity violations. Estimated Cost: $75M (Desktop Estimate Includes 50% Risk and Contingency) Scheduled IS Date: 06/01/2019 Project Status: Conceptual 21

13kV Projects 22

Locust St. 69-13kV Transformers 23

Locust St. 69-13kV Transformers Problem Statement: Due to the proposed load growth as a result of the state economic development initiative for the Camden area, the existing Locust St. substation (located in a central location with respect to the future proposed customers) will not be able to accommodate the expected load growth. Currently, there are over 30 large commercial/industrial projects planned for this area. PSE&G has received load letters from several customers with an expected load of around 20 MW. The minimum expected load as a result of this load development is around 30 MW and the projected maximum load is in excess of 60 MW. All customers are expected to be in service before June 2018. Existing Locust St. station and feeders are either at their maximum capacity or expected to be overloaded by 2018 (not including any new customers expected load). All other nearby stations and feeders are either at their maximum capacity or expected to be overloaded by 2018 (not including any new customers expected load). Proposed Solution: Replace the existing limiting Locust Street two 69/4kV and three 69/13kV unit transformers with two 45/60 MVA 69/13kV transformers. (s1023) Alternative considered: Since all the five substations in the vicinity of Locust St. are either at their maximum capacity or will be overloaded if they were to be utilized to supply the new projected customers (existing Locust St. unit transformers will be severely overloaded as well), replacing the limiting transformers at Locust St. was the most cost effective solution. Otherwise, major reinforcement will be needed for all nearby substations and circuits. Estimated Cost: $14.82 M (Desktop estimate including 50% risk & contingency) Scheduled IS Date: 12/2017 Project Status: Conceptual 24

Transformers 25

Transformers PSE&G s Transformer Life Cycle Replacement Program is designed to maintain system reliability through appropriate replacement of equipment as directed by condition assessment. Selection of replacement candidates is based on engineering review of transformer condition as part of our Condition Based Maintenance Program with consideration of Computerized Maintenance Management System (CMMS) Condition Assessment scores, the physical condition of the transformer, maximum and average age in each Peer Group and impact on customers and/or system in the event of failure. 26

Transformers 27

Transformers Projects PJM # Costs Age Comments West Caldwell T1/T3 138/13 s1007 9.8M 45 years T1 & T 3 transfomer Doble test results below acceptable limit for continued operations along with loading, Winding Temp >80 Deg C, insulation deterioration. East Rutherford Sub T 10 /20 s1008 9.8M 45 years T1 & T 3 transfomer Doble test results below acceptable limit for continued operations along with loading, Winding Temp >80 Deg C, insulation deterioration. System Spare transformer for system reliability BLC spare 750 MVA 345/138 s1010.3 & 4 22M System Spare transformer for system reliability System Spare transformer for system reliability300 MVA 345/69, 150 MVA 345/26/13.8 345/13.8 kv 45 MVA Trenton Switch: The elimination of the 440 volt auxilary power system. It is in poor condition and is being transferred to a new system at the station with capacity to handle the loads required. Edison Switch: Build control house to house protective relaying and other operational controls due to the retirement of Edision Generating Station in June of 2015 s1010.5, 6,7 19.9M System Spare transformer for system reliability s1014 2.2M 1937 vintage De commission whole 440 v system transferring loads to new Control House power. s1018 10M Eliminate reliance of third paty generation power system that was retired in June of 2015. Emergency repsonse was compromised during Sandy due to sharing of light and power. 28

Questions? 29