Market Congestion Planning Study (South)- Robustness Analysis. Economic Planning Users Group Meeting August 11 th, 2017

Similar documents
Stability Study for the Mt. Olive Hartburg 500 kv Line

ICT Strategic Transmission Plan (ISTEP) Review and Status Update

1. Administrative Items... SPP. 2. Stakeholder Web-Presentation... ABB

Market Efficiency Planning Study

Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

Entergy Texas, Inc. Transmission Draft Construction Plan Update 1 Projects

100 MW Wind Generation Project

Entergy Louisiana, LLC (South) & Entergy New Orleans, Inc. Proposed Transmission Reliability Projects

Merger of the generator interconnection processes of Valley Electric and the ISO;

MTEP14 South SPM #2. MISO Texas Project Information. April 7, 2014

SPP OVERVIEW. Mike Ross Senior Vice President, Government Affairs and Public Relations

Transmission Planning using Production Cost Simulation & Power Flow Analysis

CIL/CEL Values and Study Timeline

Interconnection System Impact Study Report Request # GI

Impacts of MISO DPP-2016-February (West, ATC, MI, South) Projects on PJM Facilities

Supplemental Report on the NCTPC Collaborative Transmission Plan

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

Decision on Merced Irrigation District Transition Agreement

MTEP13 SPM #2- Central Region. March 25, 2013

High Plains Regional Transmission Summit. Timelines for Planning Processes / Policy

The Transmission Lay of the Land

Market Efficiency Update

Market Efficiency Update

Reliability Analysis Update

Kansas Legislature. Briefing for the. March 6, Paul Suskie & Mike Ross

2015 Grid of the Future Symposium

Falcon-Midway 115 kv Line Uprate Project Report

Transmission Expansion Advisory Committee

Western NY Public Policy Transmission Planning Report

WIRES University Overview of ISO/RTOs. Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool

Draft Results and Open House

Sub Regional RTEP Committee Western Region ATSI

FINAL FACILITY STUDY. 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1. September 10, 2010

Dunvegan Hydroelectric Project. For Glacier Power Limited. Preliminary Interconnection Study

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

System Impact Study PID MW Plant

IMM Quarterly Report: Summer 2017

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

ATTACHMENT Y STUDY REPORT

Project #94. Generation Interconnection System Impact Study Report Revision

Illinois State Report

Donna Painter, Executive Consultant February 27, 2013

The Long-Range Transmission Plan

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

STH 60 Northern Reliever Route Feasibility Study Report

XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

Updates. Pat Reiten President and CEO, PacifiCorp Transmission

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

FACILITIES STUDY TRANSMISSION SERVICE REQUESTS OASIS

SERTP rd Quarter Meeting

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

Generation Deactivation Notification Update

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Proposed FY Capital Improvement Program (CIP) March 5, 2018 Capital Planning Committee 1

System Impact Study Report

Market Efficiency Update

Rogers Road to Clubhouse 230kV New Transmission Line April 1, 2016

SPP Reliability Coordinator TLR 5 Analysis Report for the ICT Reliability Area

New Jersey State Report

CUSTOMER/ TWIN ARROWS PROJECT

TEXAS ECONOMIC STUDY REPORT ICTES INFORMATIONAL ONLY

LLC FACILITIES STUDY TRANSMISSION SERVICE REQUEST

APPENDIX F: Project Need and Description

Draft Results and Recommendations

Business Park North Muskegon County, MI

The Energy Queensland Group Notice of no non-network options

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

The Development of Competitive Renewable Energy Zones in Texas

EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

City of Palo Alto (ID # 6416) City Council Staff Report

Sub Regional RTEP Committee Mid-Atlantic

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Western NY Public Policy Transmission Report

ORANGE COUNTY TRANSPORTATION AUTHORITY. Agreement to Purchase Compressed Natural Gas Articulated Buses. Staff Report

TRANSMISSION PLANNING CRITERIA

PSE Attachment K Puget Sound Area Transmission Meeting

Reliability Analysis Update

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation

Muskegon Waste Water Treatment Site Muskegon County, MI

Transmission and Distribution Substation Projects. Operating Company: Entergy Gulf States - Texas. Customer: PID # 202

Sub Regional RTEP Committee - Southern. August 19, 2011

Feasibility Study Report

MILLIGAN SOLAR PROJECT

Waco Rapid Transit Corridor (RTC) Feasibility Study

SERTP rd Quarter Meeting

VIRGINIA RAILWAY EXPRESS MANASSAS PARK STATION PARKING EXPANSION. Site Evaluation & Recommendation. October 18, 2016

DFO STATEMENT OF NEED REPORT

Interconnection and Net Metering Service in Ohio

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)

Donna S. Painter Record of Litigation Experience

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1

The North Carolina solar experience: high penetration of utility-scale DER on the distribution system

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION AND FACILITIES STUDY. Short Circuit Analysis

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Transcription:

Market Congestion Planning Study (South)- Robustness Analysis Economic Planning Users Group Meeting August 11 th, 2017

Key Takeaways The benefit calculations were updated due to a flowgate rating correction (all scenarios/futures) Chisholm Road to Sabine 230 kv Three projects in the WOTAB/Western focus area are still considered for potential recommendation to Board of Directors Alternate configurations of the WOTAB Economic Project have been evaluated for economic and reliability impact 1 Economic Planning User Group Meeting, August 11th 2017

MTEP17 MCPS Scope & Study Progress Nov - Dec 2016 Jan - May 2017 June - Aug 2017 Flowgate Identification Project Candidate Identification Robustness Testing Review Historical Congestion Transmission Development Robustness Analysis Congestion Analysis Identify Top Congested Flowgates Screening Analysis Present Value (PV) Analysis Establish Project Candidate(s) Reliability Analysis MISO Scoping Level Cost Estimation Best Fit Solution(s) 2 Economic Planning User Group Meeting, August 11th 2017

WOTAB Economic Project Alternatives Alternative 1 Alternative 2 Alternative 3 Description of Project Alternative Discussed at the July EPUG New Hartburg Sabine 500 kv transmission line New Sabine 500/230 kv transformer Expand Hartburg and Sabine substations Tap the existing Sabine McFadden and Sabine Nederland 230 kv transmission lines into a new substation New Hartburg New substation 500 kv transmission line New substation 500/230 kv transformer New Hartburg Sabine 230 kv transmission line New Hartburg 500/230 kv transformer Expand Hartburg and Sabine 230 kv substations Meets MEP voltage and cost criteria? Yes Yes No 3 Economic Planning User Group Meeting, August 11th 2017

WOTAB Economic Project Alternative 1 Project Description New 500kV line from Hartburg to Sabine Expand existing Sabine and Hartburg substations New 500/230kV 1200 MVA Transformer at Sabine substation Location Texas In-Service Year: 2023 Texas Louisiana MISO Scoping Level Cost Estimate (Million$-2017): 135 Note: This image is for illustrative purposes only and does not represent line routing Map represents the transmission system with voltages 230kV and above, in MISO 4 Economic Planning User Group Meeting, August 11th 2017

WOTAB Economic Project Alternative 1 Full outage contingency of the future load pocket CCGT units for VLR commitments: Generation Scenario Benefit to Cost Ratios EF* PR* AAT* Weighted* 20-yr Present Value Benefit ($M) Emergency Energy Contribution to Project Benefits (%) 1 (Base) 0.95 0.88 2.50 1.23 203 25 2 13.94 13.63 9.76 12.98 2,141 74 3 2.81 1.71 1.08 2.03 334 44 Partial outage contingency of the future load pocket CCGT units for VLR commitments: Generation Scenario Benefit to Cost Ratios EF* PR* AAT* Weighted* 20-yr Present Value Benefit ($M) Emergency Energy Contribution to Project Benefits (%) 1 0.95 0.96 2.10 1.18 195 25 3 1.30 0.84 0.73 1.00 166 36 * Note: MTEP17 Futures and associated weights are included in the appendix 5 Economic Planning User Group Meeting, August 11th 2017

WOTAB Economic Project Alternative 2 Project Description New 230kV substation tapping the existing Sabine McFadden and Sabine Nederland 230 kv transmission lines New 500kV line from Hartburg to New Substation New 500/230kV 1200 MVA transformer at the new substation Location Texas Texas Louisiana Note: This image is for illustrative purposes only and does not represent line routing Map represents the transmission system with voltages 230kV and above, in MISO In-Service Year: 2023 MISO Scoping Level Cost Estimate (Million$-2017): 129.7 6 Economic Planning User Group Meeting, August 11th 2017

WOTAB Economic Project Alternative 2 Full outage contingency of the future load pocket CCGT units for VLR commitments: Generation Scenario Benefit to Cost Ratios EF* PR* AAT* Weighted* 20-yr Present Value Benefit ($M) Emergency Energy Contribution to Project Benefits (%) 1 (Base) 1.01 1.01 2.72 1.35 214 23 2 14.69 14.36 10.20 13.66 2,162 74 3 2.97 1.87 1.08 2.15 341 43 Partial outage contingency of the future load pocket CCGT units for VLR commitments: Generation Scenario Benefit to Cost Ratios EF* PR* AAT* Weighted* 20-yr Present Value Benefit ($M) Emergency Energy Contribution to Project Benefits (%) 1 1.01 1.10 2.19 1.28 202 24 3 1.36 0.94 0.77 1.07 170 35 * Note: MTEP17 Futures and associated weights are included in the appendix 7 Economic Planning User Group Meeting, August 11th 2017

WOTAB Economic Project Alternative 3 Project Description New 230kV line from Hartburg to Sabine New 500/230kV 800 MVA transformer at Hartburg substation Location Texas In-Service Year: 2023 Texas Louisiana MISO Scoping Level Cost Estimate (Million$-2017): 99.4 Note: This image is for illustrative purposes only and does not represent line routing Map represents the transmission system with voltages 230kV and above, in MISO 8 Economic Planning User Group Meeting, August 11th 2017

WOTAB Economic Project Alternative 3 Full outage contingency of the future load pocket CCGT units for VLR commitments: Generation Scenario Benefit to Cost Ratios EF* PR* AAT* Weighted* 20-yr Present Value Benefit ($M) Emergency Energy Contribution to Project Benefits (%) 1 (Base) 1.08 0.97 2.68 1.36 165 28 2 17.14 16.22 11.43 15.63 1,898 74 3 3.28 1.66 1.00 2.18 265 44 Partial outage contingency of the future load pocket CCGT units for VLR commitments: Generation Scenario Benefit to Cost Ratios EF* PR* AAT* Weighted* 20-yr Present Value Benefit ($M) Emergency Energy Contribution to Project Benefits (%) 1 1.08 1.08 2.14 1.29 157 27 3 1.49 1.01 0.85 1.17 142 34 * Note: MTEP17 Futures and associated weights are included in the appendix 9 Economic Planning User Group Meeting, August 11th 2017

Alternatives 2 & 3 produce a Benefit-to-Cost ratio greater than 1.25 in all generation siting scenarios Alternati ve # 1 Generation Scenario Benefit to Cost Ratios EF* PR* AAT* Weighted* 20-yr Present Value Benefit ($M) Emergency Energy Contribution to Project Benefits (%) 1 0.95 0.88 2.50 1.23 203 25 2 13.94 13.63 9.76 12.98 2,141 74 3 2.81 1.71 1.08 2.03 334 44 1 1.01 1.01 2.72 1.35 214 23 2 2 14.69 14.36 10.20 13.66 2,162 74 3 2.97 1.87 1.08 2.15 341 43 3 1 1.08 0.97 2.68 1.36 165 28 2 17.14 16.22 11.43 15.63 1,898 74 3 3.28 1.66 1.00 2.18 265 44 * Note: MTEP17 Futures and associated weights are included in the appendix 10 Economic Planning User Group Meeting, August 11th 2017

Alternative 2 (500kV) fully relieves the congestion in Sabine/Port Arthur area and provides higher VLR makewhole payment relief compared to Alternative 3 (230kV) Alternative 2 (500kV) Alternative 3 (230kV) Congestion Relief Inland Orange McLewis Chisholm Sabine 230kV (100% Congestion Relief) Marshall Mossville 138kV (98% Congestion Relief) Inland Orange McLewis Chisholm Sabine 230kV (98% Congestion Relief) Marshall Mossville 138kV (80% Congestion Relief) Voltage & Local Reliability (VLR) Make whole payment (MWP) reduction in WOTAB (Nominal - $) 2021 - $1.5-13.3 Million 2026 - $0.8-18.3 Million 2031 - $0.9-6.3 Million 2021 - $1.0-8.7 Million 2026 - $0.3-16.5 Million 2031 - $0.0-4.7 Million 11 Economic Planning User Group Meeting, August 11th 2017

Sam Rayburn to Fork Creek to Doucette 138 kv Network Upgrade Project Description Replace 26 transmission structures on the Sam Rayburn to Fort Creek to Turkey Creek to Doucette 138kV transmission line Rating increases to 137MVA from 112MVA Location Texas In-Service Year: 2020 Texas MISO Planning Level Cost Estimate (Million$-2017): 2.8 Note: This image is for illustrative purposes only and does not represent line routing Map represents the transmission system with voltages 100kV and above, in MISO 12 Economic Planning User Group Meeting, August 11th 2017

Sam Rayburn to Fork Creek to Doucette 138 kv Network Upgrade is a robust transmission solution under all scenarios evaluated Full outage contingency of the future load pocket CCGT units for VLR commitments: Generation Scenario Benefit to Cost Ratios EF* PR* AAT* Weighted* 20-yr Present Value Benefit ($M) Emergency Energy Contribution to Project Benefits (%) 1 (Base) 0.64 9.49 22.27 8.51 33 26 2 1.88 8.94 9.81 6.29 24 61 3 53.56 23.08 31.10 36.88 141 45 Partial outage contingency of the future load pocket CCGT units for VLR commitments: Generation Scenario Benefit to Cost Ratios EF* PR* AAT* Weighted* 20-yr Present Value Benefit ($M) Emergency Energy Contribution to Project Benefits (%) 1 (Base) 0.64 9.58 16.48 7.38 28 25 3 1.67 7.71 21.33 8.01 31 8 * Note: MTEP17 Futures and associated weights are included in the appendix 13 Economic Planning User Group Meeting, August 11th 2017

Substation Equipment Upgrade at Carlyss Louisiana Project Description Replace two air break switches (17549 and 17551) at Carlyss 138 kv to a minimum of 1600 A The 138 kv bus and the line bay bus at Carlyss (138 kv autotransformer line bay) will also be upgraded to at least 1600 A Rating on Carlyss 230/138kV transformer increases to 300MVA from 243MVA Location Louisiana In-Service Year: 2020 Note: This image is for illustrative purposes only and does not represent line routing Map represents the transmission system with voltages 100kV and above, in MISO MISO Planning Level Cost Estimate (Million$- 2017): 0.5 14 Economic Planning User Group Meeting, August 11th 2017

Substation Equipment Upgrade at Carlyss is a robust project under all scenarios evaluated Full outage contingency of the future load pocket CCGT units for VLR commitments: Generation Scenario Benefit to Cost Ratios EF* PR* AAT* Weighted* 20-yr Present Value Benefit ($M) Emergency Energy Contribution to Project Benefits (%) 1 (Base) 14.19 (9.05) 130.96 28.25 19 45 2 1.54 262.19 332.19 171.93 113 90 3 309.38 79.04 61.51 167.67 110 66 Partial outage contingency of the future load pocket CCGT units for VLR commitments: Generation Scenario Benefit to Cost Ratios EF* PR* AAT* Weighted* 20-yr Present Value Benefit ($M) Emergency Energy Contribution to Project Benefits (%) 1 (Base) 14.19 (7.98) 3.45 3.18 2 100 3 1.40 18.06 (1.92) 7.40 5 12 * Note: MTEP17 Futures and associated weights are included in the appendix 15 Economic Planning User Group Meeting, August 11th 2017

Cost Allocation for WOTAB Economic Project Alternative 2

Market Efficiency Project (MEP) - Cost Allocation Methodology Based on Attachment FF-6 of MISO Tariff During the 5 year cost allocation transition period, costs of Market Efficiency Projects located solely in MISO South are allocated only to MISO South Overview of Market Efficiency Project Cost Allocation Methodology 20% of the project costs are allocated to each pricing zone based on load ratio share 80% of the project costs are allocated to pricing zones based on the distribution of APC savings to the Local Resource Zones (LRZ) with positive APC savings (see table and map on next slide) If the total future weighted APC saving for an LRZ is negative then the LRZ is not allocated a portion of the 80% 17 Economic Planning User Group Meeting, August 11th 2017

APC Benefit Distribution for WOTAB Economic Project Alternative 2 LRZ State Weighted Present Value of APC Benefit ($M) Local Resource Zone Share of APC Benefits 8 8 AR (1.9) 0% 10 9 LA, TX 217.9 100% 10 MS (2.4) 0% 9 18 Economic Planning User Group Meeting, August 11th 2017

WOTAB Economic Project Alternative 2: Cost Allocation Pricing Zone Pricing Zone - Abbr. Local Resource Zone (LRZ) Local Resource Zone Distribution of Benefits [1] [2] [3] Pricing Zone Load Ratio Share of Local Resource Zone See Note 1 MISO South Load Ratio Share [5] 20% Postage Stamp Component [6] = 20% * [5] 80% Local Resource Zone Component [7] = 80% * [3] * [4] Total Pricing Zone Cost Allocation (%) [8] = [6] + [7] Entergy Arkansas EATO 8 0.00% 100.00% 20.50% 4.10% 0.00% 4.10% Entergy Louisiana ELTO 9 100.00% 63.71% 41.49% 8.30% 50.96% 59.26% Entergy Mississippi EMTO 10 0.00% 81.97% 11.78% 2.36% 0.00% 2.36% Entergy Texas ETTO 9 100.00% 19.24% 12.53% 2.51% 15.39% 17.89% Cleco Power CLEC 9 100.00% 9.37% 6.10% 1.22% 7.49% 8.71% Cooperative Energy SME 10 0.00% 18.03% 2.59% 0.52% 0.00% 0.52% [4] Lafayette City- Parish Consolidated Entergy New Orleans LAFA 9 100.00% 2.12% 1.38% 0.28% 1.70% 1.97% ENTO 9 100.00% 5.57% 3.63% 0.73% 4.46% 5.18% Note 1: Calculated by dividing the load of applicable pricing zone by the total load of applicable Local Resource Zone 19 Economic Planning User Group Meeting, August 11th 2017

Appendix

MTEP17 Futures and Future Weights for MCPS South study MTEP17 Future Future Weight (%) Existing Fleet (EF) 40 Policy Regulation (PR) 40 Accelerated Alternative Technologies (AAT) 20 Revised future weights based on the discussion at the March 2017 Planning Advisory Committee (PAC) meeting 1 were utilized for MCPS South Study 1 MTEP17 Weighting discussion at the March 15 th, 2017 PAC: https://www.misoenergy.org/library/repository/meeting%20material/stakeholder/pac/2017/20170315/20170315%20pac%20ite m%2002a%20mtep17%20weighting.pdf 21 Economic Planning User Group Meeting, August 11th 2017

Load pocket generation siting scenarios were studied for robustness analysis Scenario 1 Base Futures Scenario 2 RRF Generation sited outside South load pocket(s) Scenario 3 RRF Generation sited at Entergy s RFP proposals Transmission Network upgrades identified from MISO DPP SIS Phase 1 Study were included RRF Regional Resource Forecast; DPP Definitive Planning Phase of MISO generation queue; RFP Request for Proposals; SIS System Impact Study 22 Economic Planning User Group Meeting, August 11th 2017

Generation Siting Scenario 2 - Siting Changes in the MISO South Load Pockets for the AAT Future Powerbase Name Scenario 1 Scenario 2 RRF MISO CC:001 Little Gypsy 230 kv Wrightsville 500 kv RRF MISO CC:006 Nelson 230/138 kv Lake Catherine 115 kv RRF MISO CC:060 Nine Mile 230 kv Holland Bottoms 500 kv RRF MISO CT:007 Sabine 138 kv Hot Springs 115 kv RRF MISO CT:010 Hartburg 230kV Hinds 230 kv RRF MISO CT:011 Hartburg 230kV Hinds 230 kv RRF MISO CT:016 Nine Mile 115 kv Big Cajun 230 kv Hartburg RRF MISO CT:090 Sabine 230 kv Couch 115 kv 23 Economic Planning User Group Meeting, August 11th 2017

Generation Siting Scenario 2 - Siting Changes in the MISO South Load Pockets for the EF Future Powerbase Name Scenario 1 Scenario 2 RRF MISO CC:001 Little Gypsy 230 kv Wrightsville 500 kv RRF MISO CT:007 Sabine 138 kv Baxter Wilson 115 kv RRF MISO CT:023 Sabine 138 kv Baxter Wilson 115 kv RRF MISO CT:048 Nine Mile 230 kv Rodemacher 230 kv RRF MISO CT:053 Sabine 230 kv Gerald Andrus 230 kv RRF MISO CT:058 Nine Mile 230 kv Gerald Andrus 230 kv RRF MISO CT:066 Nelson 138 kv Baxter Wilson 115kV RRF MISO CT:067 Nelson 138 kv Franklin 500 kv RRF MISO CT:090 Sabine 230 kv Rodemacher 230 kv 24 Economic Planning User Group Meeting, August 11th 2017

Generation Siting Scenario 2 - Siting Changes in the MISO South Load Pockets for the PR Future Powerbase Name Scenario 1 Scenario 2 RRF MISO CC:001 Little Gypsy 230 kv Franklin 500 kv RRF MISO CC:006 Nelson 230/138 kv Holland Bottoms 500 kv RRF MISO CC:039 Sabine 138 kv Sterlington 500 kv RRF MISO CT:014 Nine Mile 230 kv Bailey 115 kv RRF MISO CT:015 Nine Mile 230 kv McClellan 115 kv RRF MISO CT:016 Nine Mile 115 kv Teche 138 kv RRF MISO CT:023 Sabine 138 kv Teche 138 kv RRF MISO CT:053 Sabine 230 kv Rex Brown 115 kv 25 Economic Planning User Group Meeting, August 11th 2017

Generation Siting Scenario 3 Siting changes in MISO South load pockets Siting Location Capacity (MW) In-Service Year AAT EF PR Little Gypsy 230 kv 1,000 2019 Nelson 230/138 kv 1,000 2020 Lewis Creek 230/138 kv 1,000 2021 Michoud 115 kv 250 2019 Generation siting in the load pocket is replaced with Entergy RFP generation in Scenario 3 Total Generation inside the load pocket is similar to Generation Siting Scenario 1 Transmission Network upgrades identified from MISO DPP SIS Phase 1 Study were included RRF Regional Resource Forecast; DPP Definitive Planning Phase of MISO generation queue; RFP Request for Proposals; SIS System Impact Study 26 Economic Planning User Group Meeting, August 11th 2017

Make Whole Payment reduction for WOTAB Economic Project Alternative 1 Generation Scenario 1 2 3 1 (Partial Outage) 3 (Partial Outage) 2021 2026 2031 Load Pocket EF PR AAT EF PR AAT EF PR AAT WOTAB + Western 0.9 2.6 11.3 0.1 4.2 17.0 0.8 (1.2) 6.8 WOTAB 0.7 1.9 11.3 0.1 4.2 17.0 0.8 (0.8) 6.8 WOTAB + Western 2.9 5.4 13.3 (0.3) 1.6 4.1 5.2 1.8 1.7 WOTAB 0.8 1.7 11.0 (0.4) 1.4 4.4 5.2 1.1 1.9 WOTAB + Western 3.6 7.4 16.2 3.8 7.3 6.9 8.1 9.8 2.5 WOTAB 2.4 4.7 15.6 3.6 6.3 6.7 7.8 7.7 2.2 WOTAB + Western 0.0 5.5 13.2 0.0 5.6 19.1 0.0 0.8 1.8 WOTAB 0.0 1.8 11.0 0.0 5.2 20.3 0.0 (0.8) 2.2 WOTAB + Western 1.8 4.7 12.5 1.5 5.6 9.0 2.1 6.4 1.5 WOTAB 0.9 2.7 12.1 1.4 4.4 8.4 1.9 4.0 1.2 27 Economic Planning User Group Meeting, August 11th 2017

Make Whole Payment reduction for WOTAB Economic Project Alternative 2 Generation Scenario 1 2 3 1 (Partial Outage) 3 (Partial Outage) 2021 2026 2031 Load Pocket EF PR AAT EF PR AAT EF PR AAT WOTAB + Western 3.5 5.7 13.3 0.8 4.3 18.3 0.9 1.6 6.3 WOTAB 1.3 2.0 11.3 0.8 3.9 19.3 0.9 0.0 6.7 WOTAB + Western 3.5 5.4 13.3 0.1 2.1 4.1 5.2 0.6 0.8 WOTAB 1.3 1.7 11.3 0.1 1.9 4.5 5.1 (0.1) 1.1 WOTAB + Western 3.6 7.4 14.8 3.7 7.6 6.6 8.4 9.9 1.2 WOTAB 2.4 4.7 14.7 3.5 6.6 6.2 8.2 7.7 1.0 WOTAB + Western 0.0 5.6 13.2 0.0 5.6 18.7 0.0 1.6 2.0 WOTAB 0.0 1.9 10.8 0.0 5.2 19.9 0.0 0.0 2.6 WOTAB + Western 1.6 4.7 12.3 1.3 5.3 8.8 2.3 7.5 0.5 WOTAB 0.7 2.7 12.0 1.1 4.1 8.2 2.1 5.1 0.2 28 Economic Planning User Group Meeting, August 11th 2017

Make Whole Payment reduction for WOTAB Economic Project Alternative 3 Generation Scenario 1 2 3 1 (Partial Outage) 3 (Partial Outage) 2021 2026 2031 Load Pocket EF PR AAT EF PR AAT EF PR AAT WOTAB + Western 1.0 2.2 8.7 0.3 3.1 16.5 (0.2) 1.3 4.7 WOTAB 0.8 1.8 8.7 0.3 3.1 16.5 (0.2) 1.4 4.7 WOTAB + Western 3.0 5.3 8.7 (0.7) 1.6 4.8 4.9 1.7 1.1 WOTAB 0.8 1.6 8.7 (0.7) 1.3 4.9 4.8 0.9 1.6 WOTAB + Western 3.2 7.2 9.8 2.3 5.5 6.3 5.9 6.3 1.4 WOTAB 2.0 4.5 9.5 2.2 4.5 6.3 5.7 4.2 1.2 WOTAB + Western 0.0 5.4 8.3 0.0 5.2 12.7 0.0 2.9 3.0 WOTAB 0.0 1.7 8.4 0.0 4.8 13.6 0.0 1.4 3.2 WOTAB + Western 1.5 3.7 6.3 1.0 5.1 7.3 2.1 6.7 1.3 WOTAB 0.6 1.6 6.0 0.8 4.0 7.1 1.9 4.3 1.0 29 Economic Planning User Group Meeting, August 11th 2017

Minimum Project Design Criteria Minimum project requirements for the Market Efficiency Projects (MEP) are specified in BPM-029 Some design requirements are solution specific and are determined through additional analysis 30 Economic Planning User Group Meeting, August 11th 2017

Minimum Design Criteria Selection for WOTAB Economic Project 500kV Transmission Line Line Rating 3000A (Default Minimum Transmission Circuit Ampere Ratings) Sabine Substation 500/230kV Transformer Impedance: >7% Rating: 1200MVA (3-phase) 230kV Breaker Symmetrical Interruption Rating (ka) 63kA 31 Economic Planning User Group Meeting, August 11th 2017