Power Transmission Division Erlangen, April 29, Siemens Completes Installation of Second HVDC Converter Platform for TenneT

Similar documents
Power Transmission Division Erlangen, April 29, 2014

Power Transmisson Division Erlangen, April 15, Siemens receives major order for BorWin3 North Sea grid connection from TenneT

Background Information

HVDC Innovative Technology for Smart Grids and Super Grids. Wilfried Breuer CEO Power Transmission Solutions, Siemens Energy Sector

The Smart Way. HVDC PLUS One Step Ahead. Answers for energy.

The Smart Way HVDC PLUS One Step Ahead Answers for energy.

Siemens supplies the world s biggest gearless conveyor drive system

Peter Lundberg, ABB HVDC, Nov 2016 HVDC Light - Power from shore. ABB Group November 16, 2016 Slide 1 1JNL A

Power Transmission Solutions Grid Access

OFFSHORE WIND ENERGY CAPACITY REACHES ALMOST 5.4 GW IN 2017

Hywind Scotland status and plans

Background information

Transmission Grid Development & Investment Planning on EHV Level in Germany

Mikael Dahlgren, ABB Corporate Research, 02 December 2011 ABB Technology providers perspective Energidagen Chalmers Energyinitiative

wire 2018: Cables for offshore wind turbines

HOW OFFSHORE WIND CONCERNS THE SECURITY OF SUPPLY

PLUG INTO WAVE ENERGY. John Liljelund CEO AW-Energy // 26 October 2016

Enabling the power of wind. Competence and expertise for wind power customers

Offshore Wind and security of power supply - Energy economic analysis of risk and threat scenarios -

Offshore Wind Connections HVDC for Offshore Grids

Grid Integration of Large Scale Wind and Solar

Wind meets Gas Groningen, September 2017 Ab van der Touw, CEO Siemens Nederland NV. Siemens Nederland 2017

ABB Next Level Big shift in power attractive opportunities

Introduction to Veja Mate Offshore Project

ABB Group August 27, 2010 Slide 1

Pathways to the global grid Answers for energy.

Within the 300 GW total, the Energy Department estimates that 54 GW will be required from offshore wind to feed the large coastal demand centers.

Offshore Wind: Grid Connection & Technology Options. Dietmar Retzmann Focus on. CO 2 Reduction Green Energy Megacities Security of Supply

Page 1 August, Siemens AG / Service Renewables All rights reserved E S SR WP

Dr.-Ing. Ervin Spahi, Wadden Sea Forum, Bremerhaven Electric grid on and off-shore: current status, obstacles and new developments

Automotive financial services in Germany Motor Finance Summit Europe

Wind Energy in the Southeast: Offshore and Land-Based Potential

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

Reliability is our profession

Siemens G2 platform 2.3-MW geared wind turbines. Exceptional performance, proven reliability. Answers for energy.

Capital Markets Day 2007 Kongsberg Maritime 25 September 20O7

GRAND RENEWABLE ENERGY PARK PROJECT DESCRIPTION REPORT. Attachment C. Turbine Specifications

Europe's first blockchain project to stabilize the power grid launches: TenneT and sonnen expect results in 2018

Siemens G2 platform 2.3-MW geared wind turbines. Exceptional performance, proven reliability. Answers for energy.

ABB Wind Power Solution

Oerlikon continues strong profitable sales growth

Totally Integrated Power. A reliable all-rounder. Gas-insulated medium-voltage switchgear 8DJH 36.

WE MAKE POWER SYSTEMS WORK

Vattenfall Capital Markets Day 2009

Peter Lundberg, Global Product Manager, November 2016 ABB Power Systems Offshore wind connection

Background Information

Power From Shore: An introduction to HVDC Light Offshore

Bright outlook for improved profitability. Direct drive wind turbine SWT Answers for energy.

MAN Diesel & Turbo. Engineering the Future since Dionissis Christodoulopoulos Managing Director, MAN Diesel & Turbo Hellas Ltd

ABB Wind Industry Sector Initiative Greengrowth Tallinn, 16 September 2011 Cutting-Edge Wind Energy Solutions Challenges and Solutions ABB Viewpoint

The SGT5-8000H proven in commercial operation

nkt cables Our p assion passion brings power to life

Volkswagen s strategic realignment is delivering

IEEE PES General Meeting, Minneapolis, July 25-29, 2010 HVDC & FACTS Subcommittee. latest Technology Developments and Projects Dietmar Retzmann

Submarine Cable Solutions, Laying and Challenges. Submarine Solutions from the Specialist 15-Apr-11 / 1

European technology leadership to address infrastructure bottlenecks


TetraSpar. Industrialized Floating Foundation

Background Information

Ambra Sannino, ABB FACTS, May 2011 Keynote Speech PCIM 2011 The Role of Power Electronics in Smart Grids and Renewable Integration

Drivers, Building Blocks (Cables, Offshore), EU and US Examples, Grid- Enabled HVDC, LCC-MTDC

E-Mobility in Planning and Operation of future Distribution Grids. Michael Schneider I Head of Siemens PTI

HIGH WIRE ACT. When the lights went out at Kitimat, it was the cue for Rio Tinto Alcan to embark on one of its most complex engineering feats ever.

Floating Foundations: Opening Up Deeper Waters In the U.S.

Solar Farm Electrical Control Buildings & Substation Build Project

Trusted technology for maximum power yield SINAMICS W180 siemens.com/sinamics-w180

PRESS RELEASE. C-Power completes first wind farm in the Belgian North Sea

Background information

Siemens Gamesa Renewable Energy Unlocking Vietnam s Nearshore Wind Potential

Press Newsletter. Division Drive Technologies and Division Industry Automation July 2010

Medium Voltage Drives. ABB Value Provider Program Partnership for growth and profit

Stationary Energy Storage Solutions 3. Stationary Energy Storage Solutions

Offshore Wind China 2010 Bergen, 15th March Olivier Angoulevant Nexans Norway AS

Peter Lundberg, Product Manager HVDC Light, Guangzhou, Sept New Solutions for Transmission Systems HVDC Light ( 轻型直流 )

Kontakt. Turnkey solutions for hydropower plants An overview of the ABB portfolio

Presentation of the Baltimore Metro System

New dimensions. Siemens Wind Turbine SWT Answers for energy.

Comprehensive solution with SIHARBOR

Enabling Utility Scale PV: Challenges for Glass Makers

Matthew Knight, Director Business Development UK Offshore Wind. The future of offshore renewables

Hva er utsiktene for flytende vindturbiner til havs? Klimafrokost, Bergen 15/ Simen Moxnes, Statoil. Statoil ASA

POWER-GEN Africa 2012

Robert L. Mitchell CEO and Co-Founder Atlantic Wind Connection

In Bulgaria by. Continental Wind Bulgaria EOOD

STATUS OF LAND-BASED WIND ENERGY DEVELOPMENT IN GERMANY

Annual General Meeting Infineon Technologies AG

Siemens Power System Consulting

MindSphere The IoT operating system for smart cities. Hakan Olcay, Energy Efficiency Coordinator at Siemens

SeaGen-S 2MW. Proven and commercially viable tidal energy generation

Siem Offshore Contractors Your Partner for Submarine Cable & Floating Wind Installation Works. The Leading Provider and Most Attractive Employer

Press. Extensive additions to Sinamics G120 portfolio for optimum handling. SPS IPC Drives 2017, Hall 11

Synchronous condenser solutions siemens.com/energy/facts

Getting Smart Evolution to the Smart Grid April 2008

Karl Elfstadius, ABB Smart Grid Program Mmanager / SMART GRID TAIWAN, Smart Grid Overview. ABB SG_Presentation_V4.

Control & monitoring system for Siemens gas engines & gen-sets siemens.com

WESTA Leading Ukrainian producer of automotive batteries

ABB POWER SYSTEMS CONSULTING

ENERGY STORAGE DEPLOYMENTS IN ONTARIO APPRO NOVEMBER 18, 2014 TORONTO

Brochure. Modular Systems wind portfolio Power Collection and Grid Connection products

Siemens G4 platform 3.6-MW and 4.0-MW geared wind turbines. The offshore workhorse redefined. Answers for energy.

Transcription:

Energy Sector Press Power Transmission Division Erlangen, April 29, 2014 Siemens Completes Installation of Second HVDC Converter Platform for TenneT Major step forward for the offshore expansion of the German power grid North Sea platform can transmit wind power to supply more than 800,000 German households using efficient direct current technology Siemens has installed the BorWin2 offshore platform in the North Sea northwest of the island of Borkum. This marks Siemens' achievement of the second crucial milestone in the German grid connection projects under contract with the German- Dutch network operator TenneT. Siemens had already erected its first converter platform for the HelWin1 connection off Heligoland in the North Sea in August 2013. The BorWin2 transmission capacity of 800 megawatts (MW) is enough to meet the power demand of some 800,000 German households. On the platforms, the alternating current generated by the wind turbines is transformed into low-loss direct current for transmission to the mainland using Siemens technology. The BorWin2 onshore converter station, likewise supplied to TenneT by Siemens, is located in Diele. There the electric power from the connected wind farms is converted back into the alternating current required to feed into the power grid. Once more we have mastered the challenging offshore installation part. We are now in the final stretch to achieve commissioning in the first half of 2015, as promised. When the two platforms yet installed by us go on line, they will be able to supply more than 1.3 million households, states Karlheinz Springer, CEO of the Power Transmission Division within the Energy Sector of Siemens AG. We are proud of having successfully tackled these highly complex tasks, says Lex Hartman, member of TenneT management. We are set to make major progress in expanding our offshore capacity in the coming months, continues Hartman, "and that brings the German government's offshore expansion targets within reach. Siemens AG Wittelsbacherplatz 2, 80333 Munich, Germany Communications and Government Affairs Head: Stephan Heimbach Reference number: EPT201404.039e wp Energy Sector Power Transmission Division Freyeslebenstr. 1, 91058 Erlangen Page 1/5

In all, Siemens is realizing five North Sea grid connections for TenneT. The first four are to commence commercial operation one after the other between the second half of 2014 and the first half of 2015 and will have a total transmission capacity of over 2.9 gigawatts. The new and fifth connection BorWin3, ordered in the middle of this month, is scheduled to be operational by 2019. After one day in transit at sea and two days of installation on site, the BorWin2 platform has now been safely anchored at its final position northwest of the island of Borkum. Siemens had already installed the platform s support substructure at this location in the 39-meters-deep North Sea in 2013. Six steel pilings measuring up 2.5 meters in diameter and with a wall thickness of eight centimeters were anchored around 50 meters deep in the seabed. With a length of up to 83.5 meters, these pilings are only ten meters shorter than the Statue of Liberty in New York City, including its base. To protect it against giant waves, the platform is installed 20 meters above sea level. BorWin2 is designed for decades of operation in the rugged North Sea. The platform is equipped with a helipad and was built under contract to Siemens by Nordic Yards at its shipyard in Warnemünde. Nordic Yards has been contracted by Siemens to fabricate three HVDC platforms in all. At 12,000 tons, the BorWin2 platform weighs more than 20 loaded and fully tanked Airbus A380 super airliners. With a length of 72 meters and a width of 54 meters, its surface area is more than half the size of a soccer field. The platform s seven decks, spanning a total height of 25 meters, house not only all the technology and equipment required for highvoltage direct current (HVDC) transmission, but also living quarters. Up to 100 employees at a time will be active on the platform for the next phase of the project in the North Sea. They will first re-open the doors and panels previously welded closed for transportation, and remove other transport safety fixtures and ballast weights. They will then commission the maritime systems such as the position lights and radio installations, and start up the air conditioning and water treatment systems. A self-propelled jack-up platform - a kind of mobile logistics and accommodation island - will provide on-site catering and living quarters for the crew. The platform is fully automated and, once commissioned, the systems can be monitored and controlled from land, with cameras and sensors providing a complete Reference number: EPT201404.039e wp Page 2/5

overview of the current operating status. The crews quarters on the platform can be used when maintenance work is required. Siemens has been contracted by TenneT for maintenance of the grid connection for an initial period of five years. The special circumstances and challenges posed by such projects called for appropriate risk hedging. The insurance concepts for grid connection projects in the North Sea are individually tailored, with the Siemens Financial Services insurance unit (SFS Insurance) actively involved in the development of these concepts. These insurance solutions cover material damage to the platform and to the installations during construction and shipping, and within the warranty period. HVDC solutions and the associated services are part of Siemens Environmental Portfolio. Green products and solutions account for about 43 percent of the Group's turnover. This makes Siemens one of the world's largest providers of environmentally compatible technology. Offshore platform for BorWin2 North Sea grid connection successfully installed at sea Siemens installed the offshore platform for the BorWin2 grid connection at sea in April 2014. BorWin2 is scheduled to go into operation in 2015. The platform is designed for decades of operation in the rugged North Sea and, once commissioned, will be remotely monitored and controlled from the mainland base. Reference number: EPT201404.039e wp Page 3/5

German wind farms with HVDC grid connections To reliably convey the power from offshore wind farms to the mainland over long distances, the German-Dutch grid operator TenneT counts on low-loss high-voltage direct current (HVDC) transmission. Siemens is implementing a total of five of the nine HVDC offshore grid connections in the North Sea ordered to date, and thereby helping to make Germany's energy transition a success. HVDC grid connection links numerous wind farms to the mainland High-voltage direct current (HVDC) technology enables the alternating current generated by the wind farms to be converted into low-loss direct current. First, a number of transformer platforms arranged around the wind farm transform the alternating current before it is converted into direct current on a HVDC platform. It is transported to land via a submarine cable and then converted back into alternating Reference number: EPT201404.039e wp Page 4/5

current for onward transmission. HVDC technology is usually used when transmission cable lengths reach 80 km and longer. Contact for journalists: Torsten Wolf, phone: +49 9131 18-82532 E-mail: torsten.tw.wolf@siemens.com This press release, press pictures and further information are available under: www.siemens.com/press/x-win Follow us on Twitter at: www.twitter.com/siemens_press The Siemens Energy Sector is the world s leading supplier of a broad spectrum of products, services and solutions for power generation in thermal power plants and using renewables, power transmission in grids and for the extraction, processing and transport of oil and gas. In fiscal 2013 (ended September 30), the Energy Sector had revenues of EUR26.6 billion and received new orders totaling approximately EUR28.8 billion and posted a profit of approximately EUR2 billion. On September 30, 2013, the Energy Sector had a work force of approximately 83,500. Further information is available at: www.siemens.com/energy. Reference number: EPT201404.039e wp Page 5/5