Copyright 2003 Advanced Power Technologies, Inc.

Similar documents
Small Electrical Systems (Microgrids)

GUIDE FOR MICROGENERATION INTERCONNECTION TO CITY OF MEDICINE HAT ELECTRIC DISTRIBUTION SYSTEM

Appendix A2: Technical Requirements for Distributed Generators > 10 kw to be Connected to Kitchener-Wilmot Hydro Inc. s Distribution System

DER Commissioning Guidelines Community Scale PV Generation Interconnected Using Xcel Energy s Minnesota Section 10 Tariff Version 1.

Net Metering Interconnection Requirements. Customer Generation Capacity Not Exceeding 100 kw. Date: Version: 1

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems

Net Metering Interconnection Requirements

Interconnection Requirements for Generation Systems

Energy Security Electrical Islanding Approach and Assessment Tools. Dr. Bill Kramer Senior Research Engineer Distributed Energy Systems Integration

STATE OF NORTH DAKOTA DISTRIBUTED GENERATION INTERCONNECTION REQUIREMENTS TABLE OF CONTENTS

GRID CONNECTION ISSUES FOR DISTRIBUTED GENERATION REVIEW & STANDARDS

GUIDELINES FOR OPERATING, METERING AND PROTECTIVE RELAYING FOR. NET METERED SYSTEMS UP TO 50 kw AND BELOW 750 VOLTS

Guideline for Using IEEE 1547 for Solar PV Interconnection Page 1

MOBILE SUBSTATION DESIGN Brad Bozich & Vitor Vieira 2755 Northwoods Parkway Norcross, Georgia

Some of the main objectives of the Smart Grid initiatives in the State of California are:

DAKOTA ELECTRIC ASSOCIATION DISTRIBUTED GENERATION INTERCONNECTION REQUIREMENTS

MICHIGAN ELECTRIC UTILITY

Summary of General Technical Requirements for the Interconnection of Distributed Generation (DG) to PG&E s Distribution System

Adopted: September 24, 2015 Version: Version 1.0

Solar Power Switchgear & Energy Storage Renewable Energy Systems

Technical Guidelines and Requirements for Parallel-Operated Customer-Owned Generation. Interconnecting to the Electric Distribution System

Enabling Smart Grid Interoperability: A System of Systems Approach via IEEE P2030 TM and IEEE 1547 TM

Guidelines for connection of generators:

Technical Requirements for Renewable Energy Power System

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655)

Regenerative Utility Simulator for Grid-Tied Inverters

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS

TECHNICAL SPECIFICATION FOR INDEPENDENT POWER PRODUCERS. NB Power Customer Service and Distribution. June 2008

3.0 Radial Distribution Systems

Requirements For Net Metering

INTERCONNECTION STANDARDS FOR PARALLEL OPERATION OF SMALL-SIZE GENERATING FACILITIES KILOWATTS IN THE STATE OF NEW JERSEY

MICHIGAN ELECTRIC UTILITY

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS.

DISTRIBUTED RESOURCE GENERATION Feed-In-Tariff Single Phase

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

MICHIGAN ELECTRIC UTILITY

Document Requirements for Engineering Review- PV Systems v1.1 12/6/2018

POW ER EN G IN EER S, L LC

GRID INTERCONNECTION AND PERFORMANCE TESTING PROCEDURES FOR VEHICLE- TO-GRID (V2G) POWER ELECTRONICS

1.Power System Infrastructure

DESIGN GUIDELINES LOW VOLTAGE SWITCHGEAR PAGE 1 of 5

MICHIGAN ELECTRIC UTILITY

ADHERING TO UTILITY INTERCONNECTION STANDARDS MAY NOT GUARANTEE DG SECURITY Wayne G. Hartmann Beckwith Electric Co., Inc. Product Manager, Protection

HANDBOOK OF GENERAL REQUIREMENTS FOR ELECTRICAL SERVICE TO DISPERSED GENERATION CUSTOMERS

Designing and Maintaining a Pollution-Resilient Electric Power System. Managing Pollution Issues

Conference Papers. Keith Malmedal P.E., P.K. Sen Ph.D /08/$ IEEE. Paper No. 08 C3

AGRALITE ELECTRIC COOPERATIVE 320 EAST HIGHWAY 12 P.O. BOX 228 BENSON, MN PHONE: (320) FAX: (320)

TECHNICAL REQUIREMENTS FOR PARALLEL OPERATION OF MEMBER-OWNED GENERATION

Impact of Distributed Energy Resources on Transmission System Reliability

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program.

Certificate of Conformity self-generation unit

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

RULES ENABLING THE NET- METERING PROGRAM FOR RENEWABLE ENERGY

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Overview of State Distributed Generation Interconnection Rules

Solar Development in New Jersey, and PV Impacts on the Distribution System Carnegie Mellon Conference on the Electricity Industry - March 9, 2011

IEEE SCC21 Overview/Status IEEE Standards Coordinating Committee 21 on Fuel cells, Photovoltaics. Dispersed Generation, and Energy Storage

TRANSMISSION PLANNING CRITERIA

Minnesota Dept. of Commerce, Division of Energy Resources. Distributed Generation Workshop Interconnection Standards

Fully Automated Wind Project: Automating the Substation

REQUIREMENTS FOR GRID INTERCONNECTION OF RENEWABLE GENERATION SYSTEMS

Improving DER Interconnection with Updated Standards and Codes, Smart Inverters, and Distribution System Design

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

Global Standards Development:

Implementing a Microgrid Using Standard Utility Control Equipment

DG Standard Updates. IEEE 1547, UL 1741 SA, and Rule 21 CHASE SUN GII/PG&E 3/28/18

IEEE* American National Standards

Jemena Electricity Networks (Vic) Ltd

NET METERING PROGRAM. Technical Interconnection Requirements

Distributed Generation

INTERCONNECTION STANDARDS FOR COGENERATORS AND SMALL POWER PRODUCERS LA PLATA ELECTRIC ASSOCIATION, INC. DURANGO, COLORADO

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY

3.2. Current Limiting Fuses. Contents

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System

Small Generator Interconnection Program Interconnection Technical Requirements

201 S. Anaheim Blvd. Page No Anaheim, CA RULE NO. 2 DESCRIPTION OF SERVICE

Medium Voltage Standby non-paralleling Control GUIDE FORM SPECIFICATION

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management

Advanced controls of PV for microgrid applications

Definitions. Scope. Customer Generation Interconnection Requirements

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System

ACTION FORM. EXHIBIT #1 Regular Council Meeting of 11/27/2006

Exelon Energy Delivery Interconnection Guidelines for Generators 2 MVA or less

INTERCONNECTION for GENERATING FACILITIES Up to 20 MW

Inverter Advancements in UL1741 and UL 62109

Calculating AC Line Voltage Drop for M215 Microinverters with Engage Cables

Impact of Islanding and Resynchroniza?on on Distribu?on Systems

Distributed Generation Interconnection Policy

6/4/2017. Advances in technology to address safety. Thomas A. Domitrovich, P.E., LEED AP VP, Technical Sales Eaton

Chapter 6 Generator-Voltage System

3. Customer shall provide space for metering equipment and meter base as per Springville City Power requirements.

REQUIREMENTS FOR GRID INTERCONNECTION RENEWABLE GENERATION SYSTEMS

TD-2306B-001, Interconnecting Large 2-20MW Generation Systems. Employees involved with generation interconnection on electric distribution circuits.

SOUTHERN PUBLIC POWER DISTRICT DISTRIBUTED GENERATION STANDARD

Standards, Procedures and Policies for Grid Connection

IEEE Guide for the Design of Low Voltage AC and DC Auxiliary Systems for Substations

WELLS RURAL ELECTRIC COMPANY Adopted: March 1976 Revised: March 21, 2017 Reviewed: August 21, 1998 RULE NO. 2

West Virginia Net Metering Service. Customer Information Package

Transcription:

Overview of the Standard for Interconnecting Distributed Resources with Electric Power Systems, IEEE 1547 and it s potential impact on operation of the Distributed Generation (DG) systems and on the design of the switchgear intended for the transition of the distributed generation resources (DR) to and from grid connected operation. Adoption of the IEEE Standard for Interconnecting Distributed Resources with Electric Power Systems, IEEE Std 1547-2003 presents a significant technical resource for the individuals and organizations involved in interconnection of the distributed generation resources to the utility grid. As stated in the standards abstract IEEE Std 1547 has the potential to be used in federal legislation and rulemaking and state public utilities commission (PUC) deliberations, and by over 3000 utilities in formulating technical requirements for interconnection agreements for distributed generators powering the electric grid. As stated in the Introduction to the standard: There is a critical need to have a single document of consensus standard technical requirements for DR interconnection rather than having to conform to numerous local practices and guidelines. This standard addresses that critical need by providing uniform criteria and requirements relevant to the performance, operation, testing, safety considerations, and maintenance of the interconnection. The intent of this standard is to define the technical requirements in a manner that can be universally adopted. The universality relates not only to the technical aspects, but also to the adoption of this standard as being pertinent across a number of industries and institutions, e.g., hardware manufacturers, utilities, energy service companies, codes and standards organizations, regulators and legislators, and other interested entities. As we can see IEEE Std 1547-2003 attempts to provide all the answers in the complex field of interconnection of the DG resources with aggregate capacity of 10 MVA or less with the utility grid. For the purposes of this report, interconnection is defined as a combination of the equipment and electrical engineering services necessary to implement continuous parallel operation of the DG with the utility grid at one physical location. Continuous parallel operation assumes duration of the electrical connection of the DG to the utility grid for the duration longer than 100 ms. Universal adoption of this standard could substantially reduce typical cost of the interconnection as well as the installation cycle of the grid connected DG. IEEE Std 1547-2003 defines and summarizes brought range of the defined issues identified by the power industry related to the parallel operation of the DG with the utility. The following acronyms are used by the standard: Area EPS -- Area electric power system 1

DG -- distributed generation DR -- distributed resources EPS -- electric power system I -- current IL -- load current ISC -- short circuit current Local EPS -- Local electric power system PCC -- point of common coupling TDD -- total demand distortion TRD -- total rated-current distortion Copyright 2003 Advanced Power Technologies, Inc. The following are the major sections of the Interconnection technical specifications and requirements of the standard: 4.1 General requirements 4.2 Response to Area EPS abnormal conditions 4.3 Power quality 4.4 Islanding General requirements section specifies that the interconnected DG installation shall follow common power systems design practices and meet the requirements of the other applicable ANSI/IEEE standards as it relates to the voltage regulation, surge withstand, flicker and electromagnetic interference. There is a requirement to provide connection status monitoring, real power, reactive power and voltage metering for the DG installations of 250 kva or more. The requirement of the section 4.1.4.2: Connection of the DR to the Area EPS is only permitted if the Area EPS network bus is already energized by more than 50% of the installed network protectors. may need to be further clarified by the standard. Without complete understanding of the intent, it seems that depending on the power system configuration, this requirement may not be essential, but very costly to meet. Another requirement of the section 4.1.4.2 is: The network equipment loading and fault interrupting capacity shall not be exceeded with the addition of DR. The reason for this requirement is illustrated below in Figures 1, 2 and 3. 2

Utility Grid 52U3 Load current 52U2 TR1 Other utility customers 52U1 DG Source(s) To site loads Figure 1. The transformer TR1, network protectors 52U1, 52U2, 52U3 and corresponding power cables should be checked for adequate load rating, before DG sources can be added to the system. 3

Utility Grid Fault current 52F1 52F2 DG Source(s) Additional fault current To site loads circuit Short fault Figure 2. New system fault study needs to be performed. The interrupting ratings of the network protectors 52F1 and 52F2 should be verified and compared with the new calculated available fault currents. 4

Utility Grid Fault current Additional fault current 52F1 52F2 Other utility customers Short circuit fault DG Source(s) To site loads Figure 3. New system fault study needs to be performed. The interrupting ratings of the network protectors 52F1 and 52F2 should be verified and compared with the new calculated available fault currents. 5

Response to Area EPS abnormal conditions section defines interconnection protection requirements. The protective functions addressed are over/under voltage and over/under frequency protection and reconnect enable time delay. The following are the interconnection protection setpoint ranges according to the standard: Table 1 Interconnection system response to abnormal voltages Voltage range Clearing time(s) b (% of base voltage a) V< 50 0.16 50 V< 88 2.00 110 < V < 120 1.00 V 120 0.16 a Base voltages are the nominal system voltages stated in ANSI C84.1-1995, b DR 30 kw, maximum clearing times; DR > 30kW, default clearing times. Table 2 Interconnection system response to abnormal frequencies a DR 30 kw, maximum clearing times; DR > 30 kw, default clearing times. In addition to the over/under voltage and over/under frequency protection the standard defines the following essential requirements to the interconnection protection in sections 4.2 and 4.4: 4.2.1 Area EPS faults The DR unit shall cease to energize the Area EPS for faults on the Area EPS circuit to which it is connected. 4.2.2 Area EPS reclosing coordination The DR shall cease to energize the Area EPS circuit to which it is connected prior to reclosure by the Area EPS. 6

4.4.1 Unintentional islanding For an unintentional island in which the DR energizes a portion of the Area EPS through the PCC, the DR interconnection system shall detect the island and cease to energize the Area EPS within two seconds of the formation of an island. Operation of the utility distribution reclosures is one of the common cases of unintentional islanding, Figure 4. Typical utility non time delayed reclosing takes 200 300 ms, from the time the main contacts open to the time they reclose. This means that if the utility company uses non time delayed reclosing, despite the 2 seconds requirement of paragraph 4.4.1, the DG disconnection time shall be less than 200 ms. Utility Grid Automatic reclosure (Open) Fault current limited by distribution system and fault impedences Short circuit fault Other utility loads energized by the DG as a result of islanding. Load current DG Source(s) To site loads Figure 4. 7

The requirement of the paragraph 4.2.1: The DR unit shall cease to energize the Area EPS for faults on the Area EPS circuit to which it is connected. generically describes the main purpose of the interconnection protection. One of the ways to meet this requirement is to rely on the utility company s protective relaying to detect faults in the utility power system and trip the appropriate network protectors. At this time if DG is still connected to the grid, an unintentional islanding condition will be created. Interconnection over/under frequency and voltage relaying will be in the position to detect the unintentional island and disconnect the DG from the grid. For the fast detection of the unintentional island condition by the interconnection over/under frequency and voltage relaying it is typically necessary that the total load connected to DG during unintentional island is greater or less than the DG load levels immediately before the unintentional island condition by at least 5-8% of the DG rating. Additional protective functions used to disconnect the DG from the grid, upon fault in the utility grid system are: Time overcurrent protection, device 50/51 Time overcurrent protection with voltage restraint or control, device 50/51V Directional current protection, device 67 Directional power protection, device 32 Distance protection, device 21 Ground fault protection, device 50/51G and 59G Transfer tripping 8