PRESENTATION BY ENERGY COMMISSION OF GHANA ON TACKLING POWER SYSTEM LOSSES

Similar documents
Building Collaboration Between East African Nations via Transmission Interconnectors

GHANA GRID COMPANY LIMITED Electricity Supply Plan

Agility in energy Ahead of the challenge, ahead of the change

The Grid Link Project. Summary of the Report for the Independent Expert Panel

Estimating the cost of electrification technology options to aid electricity access scale up: The case of Ghana

Presented By: Omane Frimpong President: Association of Ghana Solar Industries 10 th December

Electricity industry structure and capacity growth trends

New 115 kv Disconnect Switches at Bloomsburg MTS

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan

BROCHURE. End-to-end microgrid solutions From consulting and advisory services to design and implementation

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection

EH2741 Communication and Control in Electric Power Systems Lecture 3. Lars Nordström Course map

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

Commercialized storage solutions for enhanced grid operation

HVDC Systems in India

Utility Distribution Planning 101

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

Local Transmission Plan. October 11, 2013 Revised August 25, 2014

Falcon-Midway 115 kv Line Uprate Project Report

SCE's Experience Distribution Volt/VAR Control:

The Energy Queensland Group Notice of no non-network options

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

Targeted Application of STATCOM Technology in the Distribution Zone

DFO STATEMENT OF NEED REPORT

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA

NRECA Cooperative Research Network. Modern Grid Initiative Southeast Summit August 10, 2006 Nashville, TN

Panel Discussion: Planning for Today and Tomorrow

ENERGY STORAGE AS AN EMERGING TOOL FOR UTILITIES TO RESOLVE GRID CONSTRAINTS. June 18, 2015 E2Tech Presentation

The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027)

Next Generation of UHVDC System. R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC Sweden

National Committee Kosovo. SEERC October 2017 Istanbul

Gunnar Asplund HVDC R&D Manager Sweden. Latest HVDC Light developments. IEEE Montreal

100 MW Wind Generation Project

Network. ENMAX Power Corporation Network Planning & Design November 4, 2011

IEEE-PES Chicago Chapter Presentation November 11, Smart Grid. Mike Born. Principal Engineer, Capacity Planning

Electricity industry structure and key players

Presented By: Bob Uluski Electric Power Research Institute. July, 2011

Title of presentation

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

GE Energy Management. GE s electrification and automation business

July 28, 2009 Presentation to the Illinois Statewide Smart Grid Collaborative

Metal enclosed capacitor banks: ABBACUS family

The Role of Electricity Storage on the Grid each location requires different requirements

EUCL AMI Project Experience Share

Slide 1. ABB September 9, 2015

Experience on Realizing Smart Grids. IEEE PES conference, Gothenburg

New Mexico Transmission Expansion Concepts For Wind Resources

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks

Toshiba s Smart Grid technologies and solutions for MV/LV grid

TRANSMISSION PLANNING CRITERIA

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

An Integrated Grid Path for Solar. Thomas Key, EPRI Senior Technical Executive. ISES Webinar. April 22, 2016

Nepal Power Investment Summit Transmission Line Projects

ABB Next Level Big shift in power attractive opportunities

IFC Workshop on Distributed Generation, 13 February 2013, Moscow, Russia

American Electric Power s Energy Storage Deployments

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT

Tackling Power Theft through Meter Data Management and Quality Analysis. Results from NPCL s AMR roll out and AMI trial

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

GRID INNOVATION CAUCUS CO-CHAIRS

Battery Energy Storage

2016 Load & Capacity Data Report

i-pcgrid Workshop 2013 Ecuador s experiences towards a Smart Grid development

Looking Towards the Future: Advantages of 765-kV Transmission Technology

Status of PNM s Completed Transmission Construction Projects 11/30/2017

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Karl Elfstadius, ABB Smart Grid Program Mmanager / SMART GRID TAIWAN, Smart Grid Overview. ABB SG_Presentation_V4.

Gateway South Transmission Project

Energy Policy Implications: PJM Planning

Project #148. Generation Interconnection System Impact Study Report

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

BSCP31 Trading Unit Application for West Burton A&B Power Stations

IEEE PES Panel Discussion

SERTP rd Quarter Meeting

BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada. IEEE PES Meeting July 2014

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY

Relative Power Factor Correction costs

Interconnection System Impact Study Report Request # GI

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Increasing PV Hosting Capacity in Distribution Networks: Challenges and Opportunities. Dr Andreas T. Procopiou

SILICONES GLOBAL SOLUTIONS

Ergon Energy s experience in meeting the challenges of increasing peak demand and customer expectation.

Building a 21 st Century Electric Grid. February 23, 2018

Presentation of the European Electricity Grid Initiative

B-4: Reducing Peak Demand through Distributed Grid Edge Control

Accelerate your grid modernization with smart RMUs. Ring main units with smart grid-ready feeder automation

Analysis of options for the future allocation of PV farms in South Africa

Shunt reactors Proven history for future success

TECHNICAL TERMS AND ABBREVIATIONS

MILLIGAN SOLAR PROJECT

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

(1) Current State and Issues of the Electricity Sector in Indonesia

System Status Briefing

µ-grids Integration to the Puerto Rico Electric System CCPR Puerto Rico Energy Sector Transformation Condado Plaza Hilton San Juan PR

Transcription:

PRESENTATION BY ENERGY COMMISSION OF GHANA ON TACKLING POWER SYSTEM LOSSES 1

PRESENTATION OUTLINE Generation System Demand Outlook Existing Generation Resources Transmission System National Interconnected Transmission System State of the Transmission Grid Transmission Losses Strategies to reduce Transmission losses Distribution System Existing Distribution Utilities Distribution System Losses Strategies to reduce system losses Expected Benefits of loss reduction strategies 2

GENERAL POWER SYSTEM OUTLOOK GENERATION SYSTEM Demand Outlook Over the long term (2011 2021) demand is projected to grow at an average of about 6.9%. VALCO demand is assumed to be at 2 pot lines from mid 2012 to 2021 Energy consumption is projected to increase from 11,337 GWh in 2011 to 23,236 GWh in 2021 Demand is projected to grow from 1,677 MW in 2011 to 3,264 MW in 2021. 3

EXISTING GENERATION RESOURCES Plant Installed capacity Fuel Type Akosombo and Kpong GS 1180 Water Takoradi International Company(TICO)- VRA 330 LCO/Gas Takoradi Power Company(TAPCO) - IPP/VRA 220 LCO/Gas Tema Thermal 1 Power Plant - VRA 110 LCO/Gas Mines Reserve Plant - VRA 80 Diesel Tema Thermal 2 Power Plant - VRA 49.5 Gas Sunon-Asogli Power Plant (SAPP)-IPP 200 Gas Total 2169.5 4

TRANSMISSION SYSTEM TRANSMISSION SYSTEM 5

STATE OF THE TRANSMISSION GRID SYSTEM LOSS RECORD System Operation & Performance Inadequate generation capacity resulting sometimes into load-shedding Low system voltages due to inadequate reactive power support and overloaded lines and transformers Higher than PURC Standard of 3.5% losses System in alert state rather than normal state and cannot support the N-1 reliability criteria 6

TRANSMISSION LOSSES Statistics of Transmission Losses 2003 2004 2005 2006 2007 2008 2009 2010 2011 Transmission loss as % of Net Generation 5.9 3.0 3.3 3.5 3.8 3.7 3.8 3.7 4.7 7 Transmission loss as % of Net Generation 6 5 4 3 2 Transmission loss as % of Net Generation 1 0 2003 2004 2005 2006 2007 2008 2009 2010 2011 7

STRATEGIES TO REDUCE TRANSMISSION LOSSES Road Map to address System Challenges The following Documents have been developed: Transmission Systems Master Plan Study for Ghana (2010-2020) Generation Systems Master Plan Study for Ghana (2010-2025) Annual Reliability Assessment Studies (2010 and 2011) Protection Review Study 8

STRATEGIES TO REDUCE TRANSMISSION LOSSES Projects to address critical system challenges Substations Upgrade Project Capacitor Banks Project Accra-Tema 4th Circuit and Volta-Tema Lines Upgrade Transmission Lines Upgrade projects System Rehabilitation Projects Substations Reliability Enhancement Project Replacement of MV Indoor Equipment 9

DISTRIBUTION SYSTEM Existing Distribution Utilities Electricity Company of Ghana Northern Electricity Distribution Company Enclave Power Company 10

DISTRIBUTION SYSTEM Electricity Company of Ghana The Electricity Company of Ghana(ECG) Networks cover the six (6) southern regions of Ghana except for the Free Zone area in Tema. The Networks comprise about 14,177 circuit km of 33 kv network, 15,521 circuit km of 11 kv distribution network and approximately 1,458,355 km of LV Distribution network (O/H and U/G cables). ECG receives power from the national transmission grid through twenty six (26) Bulk Supply Points (BSPs). From these BSPs, power distribution is done through ninety eight (98) primary (33/11kV) substations and about nine thousand (9550) secondary (33/0.4kV and 11/0.4kV) substations. 11

DISTRIBUTION SYSTEM LOSSES Historical Record of ECG Losses 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 ECG System Losses (%) 26.04 25.65 26.54 25.44 24.26 24.03 25.58 25.6 24.4 25.1 27 26.5 26 25.5 25 24.5 24 23.5 23 22.5 ECG System Losses (%) 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 ECG System Losses (%) 12

DISTRIBUTION SYSTEM LOSSES Causes of ECG Commercial Losses The causes of the commercial losses have been identified to be due to illegal connections, metering problems, billing challenges, and collection challenges 13

DISTRIBUTION SYSTEM LOSSES Causes of ECG Technical Losses The technical losses are caused mainly by inadequate equipment capacity old and obsolete cables. 14

DISTRIBUTION SYSTEM LOSSES 2011 ECG Losses Statistics 1st Quarter 2011 2nd Quarter 2011 3rd Quarter 2011 4th Quarter 2011 Technical Distribution Losses (%) 12 15 15 15 Commercial Distribution Losses(%) 9.34 15.37 7.03 15.11 Distribution System Losses(%) 21.34 30.37 22.03 30.11 15

#

DISTRIBUTION SYSTEM DISTRIBUTION SYSTEM Northern Electricity Distribution Company Northern Electricity Distribution Company (NEDCo) operations cover largely the northern part of Ghana comprising the Brong-Ahafo, Northern, Upper East and Upper West regions. The Distribution network consists of 5,488 km of medium voltage lines and 7,832 km of low voltage (415V) lines connecting 24 Bulk Supply Points (BSPs). The NEDCo system has transformer installed capacity of 200 MVA compared to its average peak load of 130 MVA. 17

DISTRIBUTION SYSTEM Historical Record of NEDCo s Losses 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 NED System Losses (%) 29.10 31.40 30.10 27.3 25.5 20.20 18.8 18.5 19.8 20.2 35 NED System Losses (%) 30 25 20 15 NED System Losses (%) 10 5 0 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 18

DISTRIBUTION SYSTEM LOSSES The major challenges facing NED are: Long networks serving low customer population density communities; illegal connections, metering problems, billing challenges, and collection challenges 19

STRATEGIES TO REDUCE DISTRIBUTION SYSTEM LOSSES Commercial Loss Reduction Re-routing of concealed service tails and the use of meter enclosures to secure meters Deployment of consultants to monitor service connections of the 10,000 largest customers Strengthening of the Loss Control Unit to monitor energy consumption of customers areas Establishment of utility courts to prosecute energy theft Automation of Commercial Management Systems Installation of remote meter reading and meter database management systems Use of smart metering technologies/ applications 20

STRATEGIES TO REDUCE DISTRIBUTION SYSTEM LOSSES Technical loss reduction Pilot Implementation of High Voltage Distribution System (HVDS) Shunt Capacitor Compensation at substations and on feeders across operational areas Reconstruction of the Low Voltage (LV) network using aerial bundled conductors Construction of additional primary substations to reduce transmission over long lines which results in line losses 21

EXPECTED BENEFITS OF LOSS REDUCTION STRATEGIES Execution of the listed strategies are expected to: Reduce system losses to regulated levels of 21% set by the PURC; Improve voltage levels to achieve 230V 10%; Make available additional active power to meet customer demand Relieve the existing network of excessive overloading Reduce investment into generation as demand is relatively reduced Reduce investment into distribution network upgrade Reduce outage levels to achieve regulated levels of 48hours per customer per year as set in the Legislative Instrument 1816, Electricity Supply And Distribution( Technical and Operational ) Rules, 2005. 22

THANK YOU 23