ITER PROJECT J. FARINEAU ITER ORGANIZATION. September 29th, 2010 SOFT PORTO: ITER-ORG 1

Similar documents
EU Procurement of In Vessel Components for ITER

ITER Magnets Update European perspective

THE Gersh Budker Prize PRIZE FOR.THE SUCCESSFUL CONSTRUCTION AND COMMISSIONING OF THE SPALLATION NEUTRON SOURCE

Progress of the JT-60SA Project

PF Coil 2-6 Supply. Main technical aspects. P. Valente

Technical Summary for BOP-Group 5 Installation Works The BOP Group 5 works include installation and commissioning of all the Items included in

Status of ITER at the Transition to Construction

Future opportunities for Industry

The Electron Cyclotron Heating & Current Drive (EC H&CD) Power Supply Procurement. F. Albajar, T. Bonicelli (F4E)

Technical Summary. Contract for Procurement of Manual Valves, Relief Valves, Control Valves, and Valve Actuators (IO/15/CFT/11867/ACS CP/3)

Technical Specifications (In-Cash Procurement)

KSTAR Assembly. National Fusion Research Center, Daejeon, Korea

GENERAL ATOMICS ITER CEnTRal SolEnoId ModulE FabRICaTIon September 2018

ITER Vacuum Vessel Loads. Jake Blanchard October 2011

The Results of the KSTAR Superconducting Coil Test

GENERAL ATOMICS ITER CENTRAL SOLENOID MODULE FABRICATION

Overview of the ITER In-Vessel coil (IVC)

CONFIGURATION DESIGN AND MAINTENANCE APPROACH FOR THE ARIES-CS STELLARATOR POWER PLANT

Presented by B. Nelson for the QPS team QPS Conceptual Design Review June 23-24, 2003 ORNL

GENERAL ATOMICS ITER CEnTRal SolEnoId ModulE FabRICaTIon August 2016

JT-60SA Newsletter. Cryoplant arrives at the JAEA Naka Site. No. 65, 31 May Headline

ITER Shield Blanket Design Activities At SWIP

Approaches to Maintenance. S. Malang

UPDATES ON ARIES-ACT1 POWER CORE CONFIGURATION

Costing of Test Articles Ancillary Equipment and Costing Methodology

SOFE

Neutronic Performance Issues of the Breeding Blanket Options for the European DEMO Fusion Power Plant

INTEGRATION OF THE MODULAR DUAL COOLANT PB-17LI BLANKET CONCEPT IN THE ARIES-CS POWER PLANT

Recent progress on R&D toward Neutral Beam Injector for ITER and JT-60SA

ITER International Partnerships - France & China -

DEMO FUSION CORE ENGINEERING: Blanket Integration and Maintenance

Glendale Water & Power Smart Grid Project

ITER G A0 FDR R1.0

Power converters for ITER

High Availability Remote Maintenance Approach for the European DEMO Breeder Blanket options

Design Description Document: DDD 11 ITER_D_22HV5L v2.2. Magnet

Smarter Network Storage UK first multi-purpose application of grid scale storage. Dr. Panos Papadopoulos, PhD, CEng

Pumping Systems for ITER, FIRE and ARIES

Units of Instruction MISD Pacing Guide Days Date Range Test Date

Vacuum pumps for the ESRF EBS project Michael Hahn

Barcelona, 26/06/2018

No. 64, 30 April 2015

Total Production by Month (Acre Feet)

PRELIMINARY ACT-2 POWER CORE DESIGN DEFINITION

9-O-3A-4 Cryogenic system for the 43 T Hybrid Magnet at LNCMI Grenoble From the needs to the commissioning

Creating a Lean and Productive Processing Facility

Bulk Storage Containers

Commercial-in-Confidence Ashton Old Baths Financial Model - Detailed Cashflow

ELECTRICAL UTILITY COST REDUCTION THROUGH PREDICTIVE CONTROL BACKGROUND

EUROPEAN COMMISSION ENTERPRISE AND INDUSTRY DIRECTORATE-GENERAL

UPDATE ON THE LHC MAIN MAGNETS. Lucio Rossi CERN - LHC MAC 15

Smarter Network Storage: Introduction to grid-scale storage and applications, the DNO perspective

Progress of GEF-UNDP-China Fuel Cell Bus Demonstration Project

RSB List of Documents and references

EU TF coils status. A.Bonito Oliva F4E Magnets Project Manager

Impact of Medium-Temperature Magnet and 2-FP Configuration on Radial Build

Hall C SHMS Progress

Water side Economizer WC chiller

Making Electricity since December Melody Collis Facilities Engineering Assistant Manager Toyota Motor Manufacturing Canada

Ministério de Minas e Energia. Minister Eduardo Braga. Brazil - Texas Chamber of Commerce - BRATECC May/2015

ELECTRICAL UTILITY COST REDUCTION THROUGH PREDICTIVE CONTROL December 2008 BACKGROUND

NEWS Release. U.S. Manufacturing Technology Orders. Year-to-date U.S. manufacturing technology orders up 4.1% over 2011

OPAL : Commissioning a New Research Reactor. IAEA Conference, Sydney, November 2007

Hinkley Point C our approach to Health and Safety Iain Graham Head of Health & Safety

McNary Northshore Fishway Hydro Project. History & Lessons Learned

Date Event or Holiday :Sun, 2:Mon North Orchard Delong Preschool North Orchard Delong Preschool

Engineers Ireland Site Visit 23 rd March 2010

ASSEMBLY INSTALLATION STUDIES FOR THE ITER CRYOLINE SYSTEM

up the formulas. You can copy/paste the formulas for the days within the same October 2017 Jan 1, 2 & 5 Student Christmas Break April 2018

Algebra II Pacing Guide

Commuter Rail Performance. October

U.S. BACKGROUND IN ITER FUELING SYSTEMS AND FUTURE CONTRIBUTIONS

Low Beta Cryomodule Development at Fermilab. Tom Nicol March 2, 2011

Wheat Marketing Situation

FACILITY DEVELOPMENT AND OPERATIONS

Interconnected Power Systems with Superconducting Magnetic Energy Storage

Status of the DARHT 2 nd Axis Accelerator at Los Alamos National Laboratory

Artesis MCM Case Studies. March 2011

PHASE TWO WET PLANT POWER ENERGISED. Phase Two wet beneficiation plant grid power energised successfully.

Power and Particle Control in JT-60SA to Support and Supplement ITER and DEMO

Satellite and mobile communications HGV tolls in Germany: innovative, environmentally friendly and fair

The Peoples Gas Light and Coke Company

Guidelines on Bus Tendering & Specifications. Mohamed Mezghani Head of Middle-East and North Africa Office

Precision Station Stopping Progress Update

September 2016 Water Production & Consumption Data

RSB ROUNDTABLE ON SUSTAINABLE BIOMATERIALS RSB List of Documents and references. 18 January RSB reference code: RSB-DOC

STAFF REPORT INFORMATION ONLY

Methanol as an Alternative Marine Fuel. 6th Chemical & Product Tanker Conference. London 12th March 2014 Ulf T Freudendahl

Status of the Nuclotron-M project

Dual-Cooled Blanket Modular Replacement Design Approach

FINAL FACILITY STUDY. 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1. September 10, 2010

NBI Systems for DEMO: Status and Prospects Ursel Fantz, Christian Hopf P. Sonato, A. Simonin, R. McAdams, M. Tran,.

PRESENTATION ON STRATEGIC APPROACH TOWARDS WIND SOLAR HYBRID SYSTEMS (SWES) FOR REMOTE TELECOM SITES IN INDIA & CASE STUDY OF RAJASTHAN

2016 UC Solar Research Symposium

PDR Energy Baseline Alternative. Proposal for Discussion October 27, 2015

Fueling System Proposal for KSTAR

Peninsula Corridor Electrification Project (PCEP)

Mu2e Solenoids! Michael Lamm! L2 for the Mu2e Solenoid! July 27, 2015!

Science Applications International Corporation

Clean Hydrogen in European Cities (256848) Monika Kentzler EvoBus GmbH

Transcription:

ITER PROJECT J. FARINEAU ITER ORGANIZATION September 29th, 2010 SOFT PORTO: ITER-ORG 1

Contents ITER Context and Background ITER Technical Systems ITER: Organization & Contractual Rules New ITER Project Baseline ITER Progress status and next CFT s September 29th, 2010 SOFT PORTO: ITER-ORG 2

ITER CONTEXT AND BACKGROUND September 29th, 2010 SOFT PORTO: ITER-ORG 3

Fusion powers the sun and the stars Prometheus stole the fire from the heaven On Earth, fusion could provide: Essentially limitless fuel, available all over the world No greenhouse gases Intrinsic safety No long-lived radioactive waste Large-scale energy production September 29th, 2010 SOFT PORTO: ITER-ORG 4

Moscow Beijing Daejeon ITER Oak Ridge Ghandinagha r Barcelona Naka September 29th, 2010 SOFT PORTO: ITER-ORG 5

ITER, is the result of a very long experience in Fusion Principales installations (Tokamak) Plasma edge effect ITER specific issues: Dust tritium invento TRIAM, J EAST, China September 29th, 2010 SOFT PORTO: ITER-ORG 6

Staffing (Feb 2010) September 29th, 2010 Professional staff Support staff Total CN 16 2 18 EU 180 115 295 IN 15 14 29 JA 23 6 29 KO 20 5 25 RU 20 2 22 US 24 8 32 Total 297 153 450 SOFT PORTO: ITER-ORG 25 Different nationalities7

Now we are firmly on ITER (the way) September 29th, 2010 SOFT PORTO: ITER-ORG 8

The Roadmap Beyond ITER 2005 2010 2015 2020 2025 2030 2035 2040 2045 2050 Today s expts. upgrade, construction Operation ITER Des. Construction H D DT Test/Optimise Blanket 2nd DT Op. Phase IFMIF Design Construction Qualify DEMO Materials Optimise Materials DEMO Design Construction Initial Operation Reliability demo Alternative Confinement Schemes Commercial Power Plants Concept Design Construction Op. September 29th, 2010 SOFT PORTO: ITER-ORG 9

ITER TECHNICAL SYSTEMS September 29th, 2010 SOFT PORTO: ITER-ORG 10

Feeders (31) (NbTi) ITER Tokamak Cryostat (29 m high x 28 m dia.) Toroidal Field Coils (18) (Nb3Sn) Poloidal Field Coils (6) (NbTi) Thermal Shield (4 sub-assemblies) Vacuum Vessel (9 sectors) Correction Coils (18) (NbTi) Feeders (NbTi) In-vessel Coils Central Solenoid (6) (Nb3Sn) Divertor (54 cassettes) Blanket (440 modules) September 29th, 2010 SOFT PORTO: ITER-ORG 11

Magnet System 6 PF Coils (EU & RF) 9 Pairs of Correction Coils (CN) 18 TF Coils (EU & JP) Facts 48 superconducting coils - ~9800 tons - ~187 km of conductor 11.8 T (peak TF field) 68 ka (peak current) Stored energy 51 GJ 31 Feeders (CN) CS Coils Stack of 6 (US) September 29th, 2010 SOFT PORTO: ITER-ORG 12

Vacuum Vessel Facts - First safety barrier for ITER - SS 316 LN-IG - ~5300 tons (VV, ports, shielding only) - 19.4 m (63 ft) torus outer diameter - 11.3 m (37 ft) torus height - 9 Sectors assembled in triplets September 29th, 2010 SOFT PORTO: ITER-ORG 13

Remote Handling Systems Blanket RH System (JA) Transfer Cask Systems (EU+CN) Multi Purpose Deployer Hot Cell RH Equipment Cassette Toroidal Mover In-Vessel Viewing System September 29th, 2010 SOFT PORTO: ITER-ORG 14

ITER Remote Handling / Hot Cell PBS 23-5 NB RH PBS 23-6 Hot Cell RH Tokamak building Hot Cell building PBS 23-3 Transfer cask September 29th, 2010 SOFT PORTO: ITER-ORG 15

ITER Project Site Layout: 3-D graphics view September 29th, 2010 SOFT PORTO: ITER-ORG 16

ITER Buildings and Facilities PF Winding Building ~250 m (820 ft) x 45 m (148 ft) Tokamak & Assy building 6 levels @ 166 m x 81 m x 57 m high (~36000 m 2 ) Cryoplant 65 kw at 4.5 K & 1300 kw at 80 K Second largest in world Magnet power convertors buildings (~1000 MW output power) Tritium building 7 levels @ 25 m x 80 m (~14000 m 2 ) Largest throughput in world (~300 kg/yr). Hot cell 60 m x 70 m Area - 60 hectares (~150 acres) September 29th, 2010 SOFT PORTO: ITER-ORG 17

ITER Organization & Contractual Rules September 29th, 2010 SOFT PORTO: ITER-ORG 18

In-Kind Contributions (Credit Values) EU Buildings & Excavation PA s 377 kiua (~580 Million ) EU VV & Magnet & Divertor PA s 297 kiua (~460 Million ) JA Magnet& Divertor PA s 310 kiua (~466 Million ) 400 300 200 In-Kind Credit - Status 44 PA s signed to date 1729 kiua (~ 2.7 Billion ) ~ 60% of total in-kind PA value 100 0 EU CN IN JA KO RF US IO Machine core Internal auxiliaries External auxiliaries Heating, Diagnostics, Control Buildings September 29th, 2010 SOFT PORTO: ITER-ORG 19

Integration between IO and DAs - Basic Roles and Responsibilities - Planning / Design* Integration / QA / Safety / Licensing / Schedule Installation Testing + Commissioning Operation ITER Organization Seven Members (Domestic Agencies, DA) Detailing / Designing* Procuring / Manufacturing Delivering Supporting installation Conformance * Depending on type of specification - Functional: Functional requirements by IO and design by DAs - Detail Design: Conceptual design by IO and detailed design by DAs - Build-to-print: Detailed design by IO and fabrication/shop design by DAs September 29th, 2010 SOFT PORTO: ITER-ORG 20

Responsibilities between ITER Organization / Domestic Agencies ITER Organization (IO) As owner and Nuclear Operator, ITER Organization, created through an International treaty signed by 7 members, is in charge of: - Design; - Specifications; - Assembly; - Operation of the ITER Machine. Domestic Agencies European Agency: Fusion for Energy - (F4E) Based in Barcelone, the European Agency contributes to 45.46 % of total cost of the project: - Design and construction of all buildings (39) on ITER site -Equipments for the Vacuum Vessel, poloidal field coils (35 à 45%) F4E has created an antenna in Cadarache for follow-up of Buildings construction. This team, including technical assistance, will be composed of 200 people in 2010. Other Domestic Agencies The 6 other members are responsible for each of them of 9.09% of total investment. Domestic Agencies are in charge of Manufacturing of various equipments and of Delivery to ITER September 29th, 2010 SOFT PORTO: ITER-ORG 21

Relationship IO-DA s-suppliers IN 8.08 % PA s IKD s CN 7.97 % PA s IKD s US 7.85 % Suppliers EU 41.04 % IKD s PA s IKD s PA s JP 8.07% IO 10.95 % PA s IKD s In Cash IO Suppliers PA s IKD s PA s IKD s KO 7.96 % RF 8.08 % Suppliers PA: Procurement Arrangements IKD: In Kind Deliveries September 29th, 2010 SOFT PORTO: ITER-ORG 22

NEW ITER PROJECT BASELINE September 29th, 2010 SOFT PORTO: ITER-ORG 23

New Baseline Schedule for 2019 First Plasma First Plasma ITER Construction 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 TF Coils (EU) 2021 2022 2023 Case Winding Mockups Complete TF10 TF15 CS Coil CS Final Design Approved CS3L CS3U CS Ready for Machine Assembly Vacuum Vessel (EU) VV Fabrication Contract Award VV 05 Buildings & Site Construction Contract Award Tokamak Bldg 11 RFE Tokamak Assembly Start Machine Assembly VV09 VV07 In Vessel Assembly New Project Baseline Approved by IC in July 2010 First Plasma Date Nov 2019 DT operation to begin March 2027 Tokamak Basic Machine Assembly Start Install CS Start Cryostat Closure Ex Vessel Assembly Assembly Phase 2 Assembly Phase 3 ITER Operations Pump Down & Integrated Commissioning Plasma Operations September 29th, 2010 SOFT PORTO: ITER-ORG 24

New ITER Organization Structure September 29th, 2010 SOFT PORTO: ITER-ORG 25

ITER PROGRESS STATUS AND NEXT CFT s September 29th, 2010 SOFT PORTO: ITER-ORG 26

Jacketing Lines Status CN, JA and RF have set up their jacketing lines; EU and US will award contracts in oncoming 2 months; KO is negotiating with JA. CN Jacketing Line JA Jacketing Line RF Jacketing Line at ASIPP at NSE at UNK September 29th, 2010 SOFT PORTO: ITER-ORG 27

TF Conductor Production Status JA has completed jacketing of 760 m Cu dummy cable and first three superconducting cables (100m and 2 x 420m). Welding & Leak Checking Cable Insertion Compaction & Spooling September 29th, 2010 SOFT PORTO: ITER-ORG 28

Roads Upgrades Complete TF Coil ~360 t 16 m Tall x 9 m Wide VV Sector ~400 t 12 m Tall x 9 m Wide PF1 Coil ~200 t 9.4 m Dia Heavy Component on Road (TF Coils, VV Sectors, & PF1 Coil) September 29th, 2010 SOFT PORTO: ITER-ORG 29

ITER Construction Site ITER Tokamak PF Coil Winding Building (first building on site) Main platform-leveling work is complete (~40 acres) Handover of the ITER site from CEA to the IO in June 2010; Tokamak Excavation started in July 2010 Construction of the PF Coil Winding Building & ITER Office building began in July 2010 September 29th, 2010 SOFT PORTO: ITER-ORG 30

ITER Construction Site September 29th, 2010 SOFT PORTO: ITER-ORG 31

PF COILS Facility Construction September 29th, 2010 SOFT PORTO: ITER-ORG 32

PF COILS Facility Construction September 29th, 2010 SOFT PORTO: ITER-ORG 33

PF COILS Facility Construction September 29th, 2010 SOFT PORTO: ITER-ORG 34

Key Technologies Superconductive Coils (Nb 3 Sn and NbTi) Welded steel structures (TIG, NG-TIG, MIG, EB, Laser, ) High-Vacuum technologies High heat flux technologies Insulating coatings Neutral Beam Power Supplies and High Voltage Components ( of the order of 1 MV) High Power, High Frequency Transmission Lines and Sources (in the ranges 5-8 GHz and 120-180 GHz) Electrical Power Supplies September 29th, 2010 SOFT PORTO: ITER-ORG 35

Key Technologies Remote Handling Tools Vacuum Cryopumps Mechanical Pumps and Cooling Water Systems Tritium Handling and Atmosphere Detritiation and Tritium Compatible Valves Materials for tritium breeding blankets including ceramic breeder and beryllium pebbles and permeation barriers Buildings and Infrastructure September 29th, 2010 SOFT PORTO: ITER-ORG 36

PA s to be signed by end of March 2011 1 PA REFERENCE 5.3.P6.JA.01 NB H&CD Power Supply for Heating Neutral Beam 2019 IPS DATE 22-Feb-10 PROJECTION DATE September 2010 SLIDE # 12 2 5.1.P4.IN.01 IC H&CD Radio Frequency Power Supply 31-Mar-10 November 2010 11 3 1.1.P3A.RF.01 PF Magnet 1 31-Mar-10 4 1.1.P5A.CN.01 Magnet Feeders 16-Apr-10 5 5.3.P9.EU.01 NBTF Components 05-May-10 September 2010 December 2010 September 2010 5 6 13 6 2.4.P1A.IN.01 Cryostat 25-Jun-10 October 2010 7 7 4.1.P2.CN.01 AC/DC Converters 13-Jul-10 PAs that can be signed at next MAC or IC December 2010 *PA will be split in 2 parts with the value of the 1st part being 22.622 - but this does not change the global KIUA value. 2nd part will be signed in 2013. September 29th, 2010 SOFT PORTO: ITER-ORG 37 17

PA REFERENCE 2019 IPS DATE 8 4.1.P2.KO.01 AC/DC Converters 13-Jul-10 9 4.1.P3.RF.01 Switching Network, Fast Discharge Units, DC Busbar & Instrumentation 19-Jul-10 10 4.1.P2.CN.02 RPC-HF 08-Oct-10 11 12 5.3.P9.IN.01 Spider 100 KV PS and Calorimeter 2.3.P1.JA.01 In-Vessel remote Handling Blanket 14-Oct-10 13 3.4.P1.EU.01 Cryoplant 07-Dec-10 14 PA s to be signed by end of March 2011 2.3.P2.EU.01 In-vessel remote Handling Divertor PROJECTIO N DATE December 2010 December 2010 December 2010 September 2010 SLIDE # 18 19 20 14 15-Oct-10 March 2011 9 December 2010 21 21-Dec-10 May 2011 10 September 29th, 2010 SOFT PORTO: ITER-ORG 38

PA s to be signed by end of March 2011 PA REFERENCE 2019 IPS DATE PROJECTI ON DATE SLID E # 15 2.4.P1B.IN.01 VVPSS 04-Jan-11 8 16 5.3.P9.JA.01 NBTF Components 04-Jan-11 15 17 3.4.P2.IN.02 Cryolines Late Delivery 10-Feb-11 22 18 4.1.P1B.CN.01 Pulsed Power Electrical Network 21-Feb-11 23 19 4.1.P8C.US.01 SSEN Components 21-Feb-11 24 20 3.1.P4.US.01 Vacuum Auxiliary Systems Early Delivery 04-Mar-11 25 21 5.2.P3.RF EC Gyrotrons 23-Mar-11 16 September 29th, 2010 SOFT PORTO: ITER-ORG 39

Next CFT s 2010-2011 (1) Development Equipments and Design activities for CODACS HCD IC & EC: R&D and Design activities Many types of activities for Diagnostics Systems IT activities: Maintenance, SAP Assistance, general support and consultancy Tokamak: Materials & Welding qualification testings Tokamak: Heat Flux testing Component mechanical testing Welding performance under irradiation Mechanical test Magnet support In Vessel Coils interface trial Thermo-Mechanical tests on Blanket Quench Detection Instrumentation Studies Blanket & Divertor R. H. activities Remote Handling R&D Remote Handling Procedures Validation Hot Cell remote Handling Technology September 29th, 2010 SOFT PORTO: ITER-ORG 40

Next CFT s 2010-2011 (2) Vacuum Vessel Field Joint Welding Control (Tender closed) Framework Contract on Engineering support to Machine Assembly & Plant Installation (tender closed) Framework Contract on Access Control, Security Design and Procurement Support Framework Contract on Human factors Software System for Support of Assembly & Installation work Package Engineering & Planning Cryogenic Plant (Liquid Helium, 65 kw) Final Design of Detritiation System Cable Engineering Tritium Plant (elements of) Support to the owner for Electrical Engineer Leak localization: Water or Helium leaks in Cryostat or in Torus HTWP Design Proof of Design for DS Scrubber columns to replace molecular sieves September 29th, 2010 SOFT PORTO: ITER-ORG 41

September 29th, 2010 SOFT PORTO: ITER-ORG 42

BACK-UP SLIDES September 29th, 2010 SOFT PORTO: ITER-ORG 43

As of today, 45 Procurement Arrangements have been signed. REFERENCE Signature date 1 1.1.P6A.JA.01 TF Conductors 28 November 2007 2 1.1.P6A.EU.01 TF Conductors 18 December 2007 3 1.1.P6A.RF.01 TF Conductors 12 February 2008 4 1.1.P6A.KO.01 TF Conductors 07 May 2008 5 1.1.P6A.CN.01 TF Conductors 16 June 2008 6 1.1.P1A.EU.01 TF Magnet Windings 20 June 2008 7 1.1.P6C.CN.01 PF Conductors 10 October 2008 8 1.1.P1B.JA.01 TF Magnet Windings 19 November 2008 9 1.1.P2B.JA.01 TF Magnet Structures 19 November 2008 10 6.2.P2.EU.01 PF Coil Winding Facility 19 November 2008 11 1.5.P1A.KO.01 Main Vessel 19 November 2008 12 1.5.P2A.KO.01 Equatorial and Lower Ports 19 November 2008 September 29th, 2010 SOFT PORTO: ITER-ORG 44

REFERENCE Signature date 13 6.2.P2.EU.02 Architect Engineering Services 4 May 2009 14 6.2.P2.EU.03 Tokamak Pit Excavation and Drainage 4 May 2009 15 6.2.P2.EU.04 Seismic Isolation Pads 4 May 2009 16 5.3.P7A.IN.01 Diagnostic neutral Beam Power Supply 19 April 2009 17 1.1.P6C.EU.01 PF Conductors 4 May 2009 18 1.7.P2C.RF.01 Divertor Dome 9 June 2009 19 1.5.P2B.RF.01 Upper Ports 9 June 2009 20 1.7.P2A. JA.01 Divertor Outer Vertical Target 17 June 2009 21 1.1.P6A.US.01 TF Conductors 18 June 2009 22 2.6.P1A-1B.US.01 Tokamak Cooling Water System 18 June 2009 23 1.1.P3A-B.EU.01 PF Magnets 2,3,4,5,6 (EU) 19 June 2009 24 As of today, 45 Procurement Arrangements have been signed. 5.3.P6.EU.01 Power Supply for Heating Neutral Beam ( Low Voltage) 13 July 2009 September 29th, 2010 SOFT PORTO: ITER-ORG 45

As of today, 45 Procurement Arrangements have been signed. REFERENCE Signature date 25 2.2.P2A.KO.01 Machine Assembly Tooling 3 August 2009 26 1.5.P1B.IN.01.0 VV In-Wall Shielding Block Assemblies 24 September 2009 27 1.1.P6C.RF.01 PF Conductors 2 October 2009 28 4.1.P1A-P8B.EU.01 SSEPN and PPEN Detailed System Engineering Design 26 October 2009 29 1.5.P1A.EU.01.0 VV Main Vessel 7 sectors 19 November 2009 30 1.1.P6B.JA.01 Central Solenoid Conductor 8 December 2009 31 5.1.P3.IN.01.0 IC H&CD RF Power Sources 5 February 2010 32 1.7.P2D.RF.01 PFC HHF Tests 23 February 2010 33 1.1.P4A-B.US.01 Central Solenoid Magnet 12 March 2010 34 1.7.P2B.EU.01.0 Divertor Inner Vertical Targets 12 March 2010 35 5.3.P7B.IN.01 Diagnostic Neutral Beam Line 22 March 2010 September 29th, 2010 SOFT PORTO: ITER-ORG 46

36 REFERENCE 2.6.P2A.IN.01 Component Cooling Water System (CCWS) Chilled Water System (CHWS) and Heat Rejection System (HRS) Signature date 22 March 2010 37 5.1.P2.US.01 IC Transmission Lines 30 April 2010 38 1.1.P3C.CN.01 Corrections Coils 11 May 2010 39 1.1.P2C.CN.01 Magnet Supports 11 May 2010 40 1.1.P6C.CN.02 Conductors for CC and Feeders 11 May 2010 41 As of today, 45 Procurement Arrangements have been signed. 5.2.P2.US.01 Electron Cyclotron Main Transmission Lines 12 May 2010 42 1.1.P2A.EU.01 Pre compression rings 12 May 2010 43 6.2.P2.EU.05 Buildings Construction 14 May 2010 44 2.7.P1.KO.01.0 Thermal Shield 17 May 2010 45 3.4.P2.IN.01 Lower Pipe Chase Cryolines 10 June 2010 September 29th, 2010 SOFT PORTO: ITER-ORG 47