ABB POWER SYSTEMS CONSULTING

Similar documents
Experience on Technical Solutions for Grid Integration of Offshore Windfarms

ABB Group August 27, 2010 Slide 1

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

STEADY STATE ELECTRICAL DESIGN, POWER PERFORMANCE AND ECONOMIC MODELING OF OFFSHORE WIND FARMS

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Peter Lundberg, Global Product Manager, November 2016 ABB Power Systems Offshore wind connection

HVDC Innovative Technology for Smart Grids and Super Grids. Wilfried Breuer CEO Power Transmission Solutions, Siemens Energy Sector

Offshore Wind Connections HVDC for Offshore Grids

EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Unrestricted. Air Core Reactor Applications Current Limiting Reactors

The Smart Way. HVDC PLUS One Step Ahead. Answers for energy.

Grid code Compliance and Renewable Energy Projects. Mick Barlow, Business Development Director, S&C Electric, United Kingdom

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

Power From Shore: An introduction to HVDC Light Offshore

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Shunt reactors Proven history for future success

100 MW Wind Generation Project

Feasibility Study Report

Targeted Application of STATCOM Technology in the Distribution Zone

Low-Frequency AC Transmission for Offshore Wind Power

EH2741 Communication and Control in Electric Power Systems Lecture 3. Lars Nordström Course map

15 Nelson-Marlborough Regional Plan

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Interconnection Feasibility Study Report GIP-226-FEAS-R3

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

Interconnection System Impact Study Report Request # GI

Black Start capability in the Wind Turbine Market

Relative Power Factor Correction costs

Experiences with Wind Power Plants with Low SCR

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation

Peter Lundberg, ABB HVDC, Nov 2016 HVDC Light - Power from shore. ABB Group November 16, 2016 Slide 1 1JNL A

Interconnection Feasibility Study Report GIP-084-FEAS-R2

New Mexico Transmission Expansion Concepts For Wind Resources

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Research on Transient Stability of Large Scale Onshore Wind Power Transmission via LCC HVDC

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems

OPF for an HVDC feeder solution for railway power supply systems

POWER TRANSMISSION OF LOW FREQUENCY WIND FIRMS

CHAPER 5 POWER FLOW STUDY IN THE INTEGRATED GRID NETWORK

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

Interconnection Feasibility Study Report GIP-157-FEAS-R2

Dynamic Reactive Power Control for Wind Power Plants

Generation Interconnection Facilities Study For

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

Simulated Switching Transients in the External Grid of Walney Offshore Wind Farm

Gunnar Asplund HVDC R&D Manager Sweden. Latest HVDC Light developments. IEEE Montreal

ABB Wind Power Solution

NETSSWorks Software: An Extended AC Optimal Power Flow (AC XOPF) For Managing Available System Resources

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

Rogers Road to Clubhouse 230kV New Transmission Line April 1, 2016

Offshore Wind: Grid Connection & Technology Options. Dietmar Retzmann Focus on. CO 2 Reduction Green Energy Megacities Security of Supply

The Role of Offshore Wind

Drivers, Building Blocks (Cables, Offshore), EU and US Examples, Grid- Enabled HVDC, LCC-MTDC

Power Transmission Solutions Grid Access

Reactive Power Compensation for Solar Power Plants. Andy Leon IEEE PES Chicago Chapter December 12 th, 2018

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY SHORT CIRCUIT ANALYSIS

Chapter 1. Overview of HVDC applications

OPF for an HVDC Feeder Solution for Railway Power Supply Systems

PES Cook Islands KEMA Grid Study Final Report

Review paper on Fault analysis and its Limiting Techniques.

15 Nelson-Marlborough Regional Plan

Standard Battery Energy Storage System (BESS) Connection Arrangements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

OBJECTIVES LCC HVDC SYSTEMS VSC HVDC SYSTEMS COMMON EQUIPMENT DIFFERENT OPTIONS ECONOMIC IMPACTS CONCLUSIONS

Modular Standardized Electrical and Control Solutions for Fast Track Projects

Introduction CONTENT Future of offshore wind energy in Europe Offshore wind energy in Spain Alternatives to the transmission system to the grid Compar

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Short Circuit Analysis with New Generation Proposed by XXXXXXXXXXXXXXXXXXXXXX Pursuant to a Transmission and Facilities Study

Grid Integration of Large Scale Wind and Solar

2015 Grid of the Future Symposium

Supplement to ISO Transmission Plan. Harry Allen-Eldorado Project Description and Functional Specifications

Jemena Electricity Networks (Vic) Ltd

Essential Reliability Services From PV Plants

XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS

Wind Generators Evolving Technology

Electrical Transmission System Analysis EE 456 project. Team Members Abdulaziz Almarzouqi Hamzah Abeer

Diversifying into Marine Energy. ABB March 2015

Project #148. Generation Interconnection System Impact Study Report

Interconnection System Impact Study Final Report February 19, 2018

Wessel Bakker Business Line Director ETD BMEA DNV KEMA The Netherlands

CHAPTER 5 FAULT AND HARMONIC ANALYSIS USING PV ARRAY BASED STATCOM

Integration of Large Wind Farms into Electric Grids

Platformless DC Collection and Transmission for Offshore Wind

Mikael Dahlgren, ABB Corporate Research, 02 December 2011 ABB Technology providers perspective Energidagen Chalmers Energyinitiative

Wind Turbine. Commissioning Utilizing Mini-Grid Power. Scottish Renewables Onshore Wind Conference & Exhibition Aggreko

Gateway South Transmission Project

Long distance bulk transmission

Pressurized Air Cooled Generators

Transmission s Future Today. High Capacity High Efficiency Low Profile

Final Written Examination.

Raphael Görner, Head of Marketing & Sales, Grid Systems Germany Building bridges with HVDC Solar Energy for Science

FAULT ANALYSIS OF AN ISLANDED MICRO-GRID WITH DOUBLY FED INDUCTION GENERATOR BASED WIND TURBINE

MILLIGAN SOLAR PROJECT

Georgia Transmission Corporation Georgia Systems Operations Corporation

DC Connection of Offshore Wind Power Plants without Platform

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

Transcription:

ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1

Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February 2012 Department: ESC Pages: 28 Authors: Bhargavi Devarajan / Don Martin ABB Consulting 940 Main Campus Drive, Suite 300 Raleigh, NC 27606

Summary Report Introduction ABB has been requested by Dominion Virginia Power to determine the feasibility of designing, constructing, operating, and maintaining submarine cable based interconnection facilities for offshore wind resources along the Atlantic coast so that electric power generation from offshore wind farms can be developed and used by Dominion customers. This report is a follow-up to Dominion s onshore connection study. The report for Dominion s onshore study can be found at http://www.dmme.virginia.gov/de/vowda/dominionoffshorewindstudyreport.pdf The layout for the offshore area identified for wind development is shown in Figure S-1. The total size of the offshore area is approximately 700 sq. km. (35 km x 20 km). An estimate of up to 3,000 MW of power has been proposed in this offshore area. The distance between the closest shore area and the beginning of the offshore area is approximately 45 km (28 miles). The offshore generated power is assumed to be interconnected to the Dominion power system at stations that are up to 15 km (9 miles) inshore from the coast. Figure S-1: Offshore wind area layout for Dominion Virginia Power There are two types of cable system that have been used for submarine connections to offshore wind generation. Both AC and DC cable systems have been used for offshore wind connections to onshore. All cables have much higher capacitance than overhead lines. The high capacitance is due to the small distance from the energized conductor in the middle of the cable to the metallic sheath on the outer edge of the insulating medium. This makes a cable very similar to a capacitor. The longer the cable is the more total capacitance in the cable.

For AC cables, the alternating voltage results in capacitive current flowing into the cable to charge the cable alternating from positive to negative voltage. The longer the cable the more capacitive current or charging current in the cable. At longer distances, the charging current will use the entire current capability of the cable just to carry this charging current. Therefore, there are limits to the distance that AC submarine cables can be used. DC cables have a constant voltage and only experience the charging current in the first few milliseconds that the cable is energized. This leaves the entire current capability of the cable to transmit power. DC cable systems have no limit on distance; however, they are generally not as practical at shorter distances because of the additional costs of the converter stations, one which must be mounted on a platform. The following section gives more details on these alternatives. System Alternatives The wind power generated offshore can be transported to the shore using both AC and DC cables. The performance characteristics and feasibility of both HVDC and AC transmission for the Virginia interconnection facilities are reviewed in this report for completeness. However, based on the characteristics and location of the Virginia offshore wind resources, AC transmission is a more economical and, therefore, the recommended alternative. AC System Possible AC export cable ratings considered to connect the offshore system to the onshore system are: 550-kV cable 345-kV cable 230-kV cable 115-kV cable Higher cable voltages result in higher charging currents, which in turn result in more capacitive reactive power generated by the cable system. The charging current also increases with the length of the cable system. Due to the high level of charging current for 550-kV cables and the required length of the offshore interconnection system, the 550-kV export cable option is not practical for the Virginia interconnection facilities. Another consideration for choosing an appropriate voltage rating is the number of cables that will need to be laid in parallel underwater. For export submarine cables, about half of the construction cost is typically in the freight and installation. If 115-kV cable circuits are used for this project, it will require sixteen cable circuits to transport 2.6 GW of this wind generation. If either 230-kV cables or 345-kV cables are used, eight circuits will be sufficient and the 230-kV cable was optimized for about 325 MW of power which results in the capability to transmit 2,600 MW with eight cables. More cables and platforms can be built to accommodate additional power if more wind generation is installed. The cost of 115-kV cable is not significantly cheaper than 230-kV cable, but the

additional circuits will increase the cost of the 115-kV cable option well above the cost of the 230- kv option; therefore, the 115-kV cable option is not as economically feasible as 230-kV. Comparison between the 230-kV and 345-kV cable alternatives A more detailed look at the comparison between 230-kV cables and 345-kV cables: The 345-kV cable will have approximately 36% higher charging current than a 230-kV cable of the same length. (That is, approximately 393 MVAr versus 283 MVAr for the length of the Virginia system) The 345-kV cable option will require eight circuits totally, the same number as for the 230-kV cable option. The onshore station has 230-kV as an existing voltage. If 345-kV cable is used, transformers will be required to connect the offshore area to the onshore system. Another consideration in choosing a cable is the number of cables that will need to be laid underwater. If three single phase cables are installed as opposed to one tri-core cable, then the installation cost of the three single core cables will be almost two to three times higher than the one tri-core cable. The installation costs make tri-core cable the economical choice to consider. Both 345-kV and 230-kV cables are available as tri-core cables. Based on the above considerations, the tri-core, 230-kV cable option appears to be the optimum cable design for the Virginia project. For this study, the offshore area is divided into zones with one platform in each zone. Each platform is assumed to house one 34.5/230 kv wind farm collector system. With more platforms, there is more flexibility to phase the equipment installation. If the design was limited to fewer platforms, there would be less opportunity to phase the installation of the equipment. Even more important are the technical challenges with fewer platforms. The impact of having just one platform in the offshore area is listed below. Impact of the One Platform Concept The length of some of the 34.5-kV collector system cables would exceed 25 km to reach the farthest wind turbines. The single platform would need to bring seventy-two 34.5-kV feeders and eight 230-kV cables onto the platform. Finding space to lay all of these cables and bringing them up to the platform would be very challenging even if it were possible. If an event on the platform were to shut down the platform, up to 2,600 MW of generation could be lost during one disturbance. If the one platform was built and only part of the wind generation was installed, the platform could be considerably overbuilt for the offshore wind generation. Based on providing a reasonable design that is technically feasible, the proposed solution is to divide the wind farm area into four zones with a central substation platform for the collection system in each zone. Each platform will have eighteen 34.5-kV feeders connected to it. This general arrangement will allow the collector system to use 34.5-kV submarine cables with reasonable lengths. It is proposed that two 230-kV export cable circuits will be used to connect each

substation platform to the onshore Dominion power system. This proposed arrangement is illustrated in Figure S-2. Each zone represents one phase of construction. When a platform is built and installed, all of the offshore substation equipment needed for the development of that project phase must be installed with the platform. Each project phase will involve completing one platform entirely. Other platforms can be developed as needed. CONCEPT Four Platforms Two cable circuits from each platform to the onshore system Figure S-2: Propos ed Wind farm Zones HVDC System HVDC Light is ABB s trade name for the voltage source converter technology. HVDC Light systems have the ability to operate well with weak AC systems (low short circuit levels) and to provide black start support to the power grid. Voltage source converter based HVDC (HVDC Light ) for this application is commercially available for circuit capacity ratings up to around 1,100MW using two cables, one +320 kv and one - 320 kv. Figure S-3 shows the concept with three HVDC circuits with a combined capacity to transmit up to 3,000 MW from the offshore wind farms.

Figure S-3: HVDC Light Concept The offshore wind interconnection point will require a platform to mount the HVDC Light converter and AC cable collection station. Figure S-4 shows the overall concept for HVDC based offshore wind interconnection. Figure S-4: Off-Shore HVDC LIGHT Concept Figure S-4: Multi-story converter designs for platform applications. If an HVDC system was developed, the collector system would still be an AC system. The offshore wind would be collected using cable feeders at 34.5-kV or an equivalent voltage and would be brought to the platform and connected to an AC bus. The voltage would be stepped up to 138 kv, 230 kv or any other appropriate voltage and connected to the HVDC converter via AC transmission cables. The converter will be connected to the shore using DC cables. Both the AC and HVDC Light equipment would be designed to be compact and as light weight as technically and economically feasible. A single line diagram for the HCDC Light system is shown in Figure S-5.

Figure S-5: Simplified Single-line Diagram for HVDC Light As shown in the figure above, an HVDC Light system consist of two cables; one with a positive voltage and one with a negative voltage. Both cables are operated together as one circuit. There is no stray dc current or emergency earth return operation. HVDC Light becomes the preferred option to transmit offshore wind power when the distances become too long for AC cables to be feasible. For example, the 230-kV AC cable produces 9.4 amps of charging current per kilometer. The current rating of the cable to the farthest platform is 876 amps. A cable about 90 km long would use the entire ampacity rating of the cable for charging current. This limits the practical distance for AC cable transmission. Although an HVDC Light alternative requires only 6 export cables to be laid instead of 8 cables for the 230-kV AC alternative, there are significant additional costs in the offshore and onshore converter stations. There will be one converter station at each end of the three circuits and the offshore converter must be completely installed on a platform. For shorter distances where AC cables are feasible, the converter costs of HVDC Light systems generally make the HVDC offshore option significantly more expensive than an AC option. Therefore, since the Virginia offshore zones are relatively close to the shore and feasible to interconnect with 230-kV AC export cables, HVDC is not an economical option for radial connection of the offshore wind farms to Dominion s onshore substations, which are located relatively close to the coast. Note that HVDC Light could become a feasible option if the Virginia system was to be networked to other offshore wind systems. HVDC would permit long cables and also control of the power flow. Such power flow control would be needed if low impedance offshore cables were paralleled with higher impedance onshore overhead lines and would permit the system operator to appropriately balance power transfer over the cables and the onshore overhead lines.

Offshore collector system modeling Figure S-6 shows the anticipated basic feeder configuration for the offshore collection system. The following assumptions were used for the development of the system: Each zone is divided into a number of smaller areas with dimensions approximately 5 km x 5 km each. Each wind turbine generator (WTG) is assumed to be rated 6 MW at 0.95 pf (±1.972 MVAr). It is assumed that the WTG has the capability to supply/absorb all of the ±1.972 MVAr when generating different levels of power. Each WTG is assumed to have a 0.69/34.5-kV, 8.33 MVA, 11% impedance transformer to transform the generator voltages to the 34.5-kV level. Every six wind turbine generators in each area form one collector circuit (36 MW, ± 11.8 MVAr capacity). This lumped output of the six generators is connected to the collector system using a 3 x 1750 kcmil cable with 42 MVA capacity at 34.5-kV. Collector systems in each zone are assumed to be connected to a maximum of 18 circuits. As seen in Figure S-6, the output of every three generators is collected by one cable in each circuit. Hence, each such cable carries up to 18 MW. A 3 x 250 kcmil cable with 20 MVA capacity at 34.5-kV is used to interconnect the WTGs. Figure S-6: Off-Shore Feeder Concept Steady state simulation results Capacitance of underground/submarine cables is typically much higher per mile than that of overhead transmission lines because in overhead lines, the capacitance is between phases and between each phase and earth, while in cables the capacitance is between each phase conductor and its shield. Capacitance causes charging currents to flow through the cable. As the cable length increases, more charging current is generated by the cable as capacitance is distributed along the cable. Capacitive charging current also increases with the voltage. Thus,

along with the load current, the cable also has to carry charging current. This puts a voltage and length dependent limit on the load carrying capability of an AC cable circuit. Steady-state powerflow simulations were run under different generation conditions to evaluate the loading on the cables. For different generation conditions, the cable loading and the amount of reactive power to be absorbed at the shore end to maintain 1 p.u. at the onshore end are shown in the table below: CASE All generators disconnected Maximum generation Zero generation WTG V term (p.u.) MVAr absorbed onshore Line loading N.A. 2,544.20 Uneven; cables heavily loaded at shore end with reactive power. 1 1,171.60 Almost even split of reactive power to shore and platform; cables heavily loaded. 1 2,099.50 Uneven; medium loading on cables. Highest voltage at 230-kV side of platforms (p.u.) 1.0386 1.0260 0.95 1,030.40 1.0230 1.0260 0.95 1,620.50 1.0140 From the above table, it can seen that if the WTG terminal voltage is lowered to 0.95 p.u. from 1 p.u., the reactive power to be absorbed at the shore end reduces as more reactive power is now absorbed by the WTGs. The voltages at the 230-kV platform end are seen to lie within limits even in the case with all generators disconnected. On an open ended cable, the charging current can cause the voltage at the open end to rise due to Ferranti effect. Conclusions and Recommendations The proposed concept with four (4) offshore substation platforms and two 230-kV cables per platform can be developed in phases with each substation platform and associated collection and export cables representing one phase of 648 MW. When a platform is built and installed, all of the equipment needed for the total development should be installed with the platform. There is no easy or economical way to add substation equipment to the platform at a later time. This limits the development phase to completing one platform at a time as needed. Submarine cables are then added to the platform as the development of the wind farms in the associated wind zone progresses. Since the Ferranti effect which raises the voltage on an open-ended circuit is low for 3-core submarine cables (the circuit inductance is low because of the close proximity of the conductors), the study results demonstrated that all of the shunt reactors needed to absorb the cable charging can be put on shore. This will reduce the weight and therefore the cost of the offshore substation platforms. In the maximum generation cases, the reactive power absorbed onshore can be reduced by lowering the terminal voltage of the WTG. Steady-state simulations show that with the 230-kV cable open-ended, the maximum voltage on the offshore platform system due to Ferranti effect goes up to 1.044 p.u. on the 34.5-kV collector system.

Under maximum generation conditions, the MVA loading on the cables was high but it was within limits. The generators are absorbing reactive power at or close to their reactive power limit. The wind turbine units help to absorb the reactive power generated by the cables under all generation conditions unless they re disconnected. The onshore system would need to absorb the remaining MVAr generated by the cables. If the onshore system doesn t have the capability of absorbing the MVAr, reactors will need to be connected to the system. Cost Estimate for Recommended 230-kV AC System The preliminary construction cost for the 230-kV AC interconnection system was estimated for each platform. The indicative estimate for one 648 MW platform system is as follows: I. Offshore platform (topside and offshore substation) -- $250 million II. 230-kV cable system, 2 72 km $389 million III. 230-kV onshore variable shunt reactors (2 x 300 MVARs) including installation, -- $9 million IV. Two three-breaker bays in a breaker and a half scheme to terminate two cables and two shunt reactors -- $ 4 million Thus, the total indicative estimate for one 648 MW platform and 230-kV cable installation is $652 million. Note: The above indicative estimate is for planning, conceptual engineering and study purposes only and neither the data, its associated commercial terms nor any past or future action, course of conduct or failure to act by either ABB or Dominion Virginia Power (the Parties ) regarding the proposed offshore wind integration project will give rise to or serve as a basis for any obligation or other liability on the part of the Parties or any of their affiliates. Neither Party shall be obligated to enter into any further agreement with the other Party. Any commitment, agreement or binding obligation with respect to the proposed offshore wind integration project would only arise and would be subject to, among other things, the negotiation, due execution and delivery by the Parties of a Definitive Agreement regarding the project. Typical Schedule for Offshore Installations The typical time to complete an offshore project with a platform and cables is shown in Figure S- 7 on the next page. Prior to the start of Project Execution there will be some period of developing some conceptual and preliminary designs to help define the project and project requirements. This preliminary work leads up to the award of the project. The manufacturing schedule of the cable will depend on the total length of cable to be provided and the factory loading. If several platforms are done simultaneously this could affect the schedule. It might take longer to manufacture the cable, but all of the cable can be transported and laid at one time.

Figure S-7 - Typical Schedule in Months for Offshore System i ABB Grid Systems Consulting DOMINION VIRGINIA POWER