Refurbishment & Upgrade of the Celilo HVdc Converter Station

Similar documents
The Upgrade of the Northern Terminal of the Pacific NW-SW HVdc Intertie Celilo Converter Station

2013 Grid of the Future Symposium

B4-114 CIGRE Celilo Pacific DC Intertie Upgrade presentation. K ERIKSSON*, O SAKSVIK, T HOLMGREN Bonneville Power Administration

OBJECTIVES LCC HVDC SYSTEMS VSC HVDC SYSTEMS COMMON EQUIPMENT DIFFERENT OPTIONS ECONOMIC IMPACTS CONCLUSIONS

Refurbishment and Life Extension of Existing Facilities in Vermont

MVDC PLUS Managing the future grid

FINAL FACILITY STUDY. 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1. September 10, 2010

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders

Interconnection System Impact Study Report Request # GI

Transmission Planning. WECC 2014 Progress Report. March 14, 2014

2013 ANNUAL PROGRESS REPORT

Longevity of Power Electronic Solutions in the Macro Grid historical perspective of AC (FACTS) and DC (HVDC) installations

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director

Generation Interconnection Facilities Study For

BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada. IEEE PES Meeting July 2014

A system fault contribution of 750 mva shall be used when determining the required interrupting rating for unit substation equipment.

DC Substation Solutions For Metal Processing Applications

2016 INTEGRATED TRANSMISSION PLAN SCHEDULES SEPTEMBER 2016

SOFE

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G

KONČAR Group. Research and Development

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

Load Modeling for Power System Studies

A 500kV AIS Switchyard Rejuvenation in British Columbia using Hybrids

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS

Appendix 11 RETURN TO APPENDICES LIST. High Voltage Power Supply Upgrade (Welcon Technologies Pty Ltd)

Alternatives for meeting the need for transmission improvement described

Solar Farms: design & construction

Double earth fault in a PSP during back to back launching sequence

EH2741 Communication and Control in Electric Power Systems Lecture 3. Lars Nordström Course map

Final Written Examination.

Four Corners Queue Transmission Interconnection Study

Mechanical, Electrical, Technology Engineering Firm

TRANSPOWER PLANS, BUILDS, MAINTAINS AND OPERATES NEW ZEALAND S HIGH VOLTAGE ELECTRICITY TRANSMISSION NETWORK THE NATIONAL GRID.

ABB Wind Power Solution

Power From Shore: An introduction to HVDC Light Offshore

UBC Technical Guidelines Section Edition Commissioning of Electrical Systems Page 1 of 5

Aswan high dam - Distributed control system AUTOMATION

Latest development in transmission in 800kVDC

Development, innovations and transformer solutions

EPRI HVDC Research. Gary Sibilant, EPRI. August 30, 2011

BHARAT ALUMINIUM COMPANY LTD. SPECIFICATIONS FOR SYNCHRONOUS GENERATOR GENERAL Make : Jinan Power Equipment Factory Type : WX2

Enabling the power of wind. Competence and expertise for wind power customers

Unrestricted. Air Core Reactor Applications Current Limiting Reactors

Functional Specification Revision History

Introduction CONTENT Future of offshore wind energy in Europe Offshore wind energy in Spain Alternatives to the transmission system to the grid Compar

HVDC Solutions. for Integration of the Renewable Energy Resources. Marcus Haeusler HVDC Lead Engineer. siemens.com/energy/power-transmission

Cigre and Trends in Power Electronics for the Grid. Bjarne Andersen Chairman of Cigre Study Committee B4 HVDC and Power Electronics

Comparison of the Performance of HVDC and HVAC Overhead Transmission Lines for the Itaipu System

PUD ELECTRIC SYSTEM INTERCONNECTION

The Application of Power Electronics to the Alberta Grid

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation

The Xiangjiaba-Shanghai 800kV UHVDC project Status and special aspects. V. F. Lescale, U. Åström W. Ma, Z. Liu State Grid Corporation of China

Generator Interconnection System Impact Study For

CITY OF PASADENA APPLICATION FOR PARTICIPATING TRANSMISSION OWNER STATUS

Schedules 1 to 4, Lot B: Extension of the Lessos Substation

ABB Group August 27, 2010 Slide 1

Failure of Transformer Cable box A case study

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04

Variable speed control of compressors. ABB drives control the compressors of the world s longest gas export pipeline

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

Technical Specifications (In-Cash Procurement)

Western Alberta Transmission Line (WATL) HVDC Project

ABB Next Level Big shift in power attractive opportunities

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

Cigre SC B4 Activities Towards HVDC Grids. HVDC Grid Workshop Belgium

Texas A&M Microgrid and Electrical System Study. Cushing Memorial Library & Archives

Reliability Analysis Update

CITIZEN TASK FORCE PRESENTATION

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA PACIFICORP. Direct Testimony of Richard A. Vail

ABB Wind Care Service Offering

Transformer Technology Seminar HV Collector (Power) Transformers

Next Generation of UHVDC System. R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC Sweden

Service and Rehabilitation Electrical Power Systems

Sectionalizing. Rick Seeling. Pete Malamen. Introduction Philosophy. Three Phase Reclosers High-Side Protection Specific Applications

Wind Power Services. One Standard for Safety, Quality & Repairs Across North America INTEGRATED POWER SERVICES

Renewables from a TSO Perspective. M.BENA, SmartGrids Director, RTE, French TSO Vienna, 18 May 2015

SECTION 27 - PAD-MOUNTED TRANSFORMERS TABLE OF CONTENTS

Wind Power Services. One Standard for Safety, Quality & Repairs Across North America INTEGRATED POWER SERVICES

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Raphael Görner, Head of Marketing & Sales, Grid Systems Germany Building bridges with HVDC Solar Energy for Science

Small Electrical Systems (Microgrids)

Power Electronics. Motor brake relay GA 9031 ministop

ATTACHMENT - DFO STATEMENT OF NEED

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

INTERCONNECTION FACILITIES STUDY REPORT

Q0044 interconnection at

Live-line transmission lines upgrade projects. First-in-Africa project

HVDC / FACTS Highlights

Chapter 1. Overview of HVDC applications

Switchgear and Distribution Systems for Engineers and Technicians

The Electron Cyclotron Heating & Current Drive (EC H&CD) Power Supply Procurement. F. Albajar, T. Bonicelli (F4E)

Offshore Wind: Grid Connection & Technology Options. Dietmar Retzmann Focus on. CO 2 Reduction Green Energy Megacities Security of Supply

ELECTRICAL UTILITY COST REDUCTION THROUGH PREDICTIVE CONTROL BACKGROUND

Transcription:

1 Refurbishment & Upgrade of the Celilo HVdc Converter Station Mark A Reynolds, PE Sr. Project Manager, POWER Engineers mark.reynolds@powereng.com Karl A Mitsch, P.E. Sr. Project Manager USDOE Bonneville Power Administration kamitsch@bpa.gov

2 Presentation Topics BPA Decision Replace or Refurbish Typical Life of HVdc Equipment Project Approach Consideration and Timeframe Develop Risk exposure

3 Factors Effecting Equipment Life MW load factor of HVdc link Maintained to HVdc OEM recommendations Design specification for equipment Fault and external stresses on equipment Overload stresses on equipment

4 Typical Equipment Life Equipment Life (years) Thyristor Valves + Electronics 35+ Converter Transformer 35+ (varies on MW Loading) Filters 35+ Control & Protection 15+ Cooling Equipment 35+ Smoothing Reactors 35+

Controls Lifecycle (Ideal) 1 5 yrs Under OEM support 6 12 yrs Mid life of controls 13 14 yrs Replacement planning 15 17 yrs Procure and replace controls 5

6 BPA Decision Replace or Refurbish Equipment condition & maintainability Increasing failure rate suggesting end of life Significant increases in maintenance costs Spare parts not available Availability of HVdc OEM support

7 BPA Decision Replace or Refurbish Outage Considerations Replace Build adjacent, cutover (minimize outage time) Refurbish Multiple projects over time (look at collective outage impacts) Provide incentives to minimize outage time Refurbish and operate in monopole configuration to reduce outage impact Replacement power can be very expensive

8 The BPA Decision & Scope Owners Decision Replace HVdc Terminal Facilities at the Northern Terminal (Celilo) Upgrade Link Capacity by Current & Voltage Increases (3410 Amperes, at 560 kv, 3800 MW (Ultimate Rating), 3100 Amperes, at 556 kv, 3450 MW (Phase 1-Rerate)) Transmission Insulation Upgrade by insulator bell additions ( 2~3 bells on 804 structures) Controls Replacement (pre-replacement) control telecommunications changes (analog MW to Digital)

9 BPA Project Approach Define Project & Funding Get HVdc OEM cost estimates Life Cycle Cost of Replace vs. Refurbish Current and future operating expenses Down time or outages needed (replacement power costs)

10 Project Approach Technical Details Establish New Converter Ratings (step plan for rerating) MW transmission line ultimate rating (3800 MW) Develop a separation and cutover plan

Insulator I-String Additions 11

Design & Manufacturing of New HVdc Apparatus 12 Converter Transformers Converter Valves (Thyristor) Control Systems Cooling Plant Instrument Transformers Air Core Smoothing Reactors Other Equipment

Transformer Production 13

New Thyristor Valve Under HV Testing 14

Existing Converter 1 & 2 Switchyard Demolition 15

Movement & Installation of New Converter Transformers (430 Ton Transport Weight) 16

New Converter Transformer Installation 770 MVA, 3-Winding, 1,270,000 pounds 17

New Switchyard Installation 18

New Thyristor Valve Tower Installation 19

20 Controls Systems Testing MACH-3 Factory System Testing in Ludvika Sweden

Celilo Project Schedule 21

Installation Testing & Commissioning Program 22 Subsystem Testing & cable checks Pre-Energization control checks including Interlocks and sequence checks Finalize Energization Sequence& Outage Coordination Planning Partial Load Testing Full Load Testing Staged Line Faults and Performance Testing 30-Day Trial Operation (90 Day Maximum) Commercial Acceptance & Celebration

23 Detailed Commissioning Milestones 9/13/15 Connect new converters to 500 kv AC system and perform Back to Back testing** 10/3/15 Start of PDCI Outage for DC Line Upgrades and reconnection of DC line to new converters 11/3/15 End of PDCI Outage 11/15/15 Exchange of power with Sylmar via one pole is possible **A local Northern Terminal End Back to Back connection will allow the BPA 525 kv HVac Feeders to energize the new converters No. 1 & 2 on the ac side of the new Poles. The HVdc Poles No. 1 & 2 will then be cross connected on the HVdc side providing a local loop at a North Terminal local station to allow a of test the new poles at Celilo, at full voltage and nearly full power levels, with minimal impact to the WECC Network. Only energy losses during the BtB operation will need to be purchased by BPA.

Back to Back Testing Configuration 24

Thank you for your time 25