Compliance of Solar PV Installation with the New Renewables SA Grid Code Jimmy Goulding, Electrical Technologist, Aurecon, South Africa

Similar documents
Testing Renewable Power Plants on High-Voltage-Ride-Through Capability

White Paper. P13008 Net-metering concept for Small Scale Embedded Generation in South Africa. prepared for

Grid code Compliance and Renewable Energy Projects. Mick Barlow, Business Development Director, S&C Electric, United Kingdom

NRS 097-series / Grid Code Discussion:

Session 10 NERC Interconnection Requirements

GUIDELINES FOR EMBEDDED GENERATION. Application process to become an embedded generator in the City of Cape Town

Renewables induce a paradigm shift in power systems, is energy storage the holy grail?

Electrical grid stability with high wind energy penetration

Lösungen zur Spannungsregelung in Verteilernetzen

Maharashtra Electricity Regulatory Commission (Renewable Purchase Obligation, Its. Regulations, 2016 STATEMENT OF REASONS

SOUTH AFRICAN NATIONAL STANDARD

GUIDELINES FOR THE INSTALLATION OF EMBEDDED GENERATION

Grid Management Voltage Control Distribution Grid Voltage Regulation with DER. Michael Sheehan, P.E. IREC Pacific Northwest Solar Partnership

Generator Interconnection System Impact Study For

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

CHAPTER 5 FAULT AND HARMONIC ANALYSIS USING PV ARRAY BASED STATCOM

DRAFT. Guidelines on Power quality & safety issues in usage of roof-top solar pv system CENTRAL ELECTRICITY AUTHORITY

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

Appendix UA Ideal Power UL 1741 SA Advanced Inverter Features

Guidelines for connection of generators:

Targeted Application of STATCOM Technology in the Distribution Zone

Smart Inverter Technology for High PV Penetration

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems

Advanced controls of PV for microgrid applications

ANCILLARY SERVICES WITH VRE (VARIABLE RENEWABLE ENERGY): FOCUS PV

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS

Guideline for Using IEEE 1547 for Solar PV Interconnection Page 1

SOUTH AFRICAN NATIONAL STANDARD

Battery Energy Storage System addressing the Power Quality Issue in Grid Connected Wind Energy Conversion System 9/15/2017 1

Robust Control Technique for Grid-connected Power Conditioner

FAULT ANALYSIS OF AN ISLANDED MICRO-GRID WITH DOUBLY FED INDUCTION GENERATOR BASED WIND TURBINE

SYSTEM OPERATOR. Ancillary Services Technical Requirements for 2018/ /23 REFERENCE NO. :

AS/NZS :2016. Grid connection of energy systems via inverters AS/NZS :2016. Part 1: Installation requirements

Cabo Verde s new Renewable-Energy-Friendly Grid Code

Essential Reliability Services From PV Plants

Hardware Testing of Photovoltaic Inverter Loss of Mains Protection Performance

SA Power Networks Commissioning Witnessing Checklist

Experience on Technical Solutions for Grid Integration of Offshore Windfarms

C PER. Center for Advanced Power Engineering Research C PER

Distributed Energy Resources

PES Cook Islands KEMA Grid Study Final Report

Enhancing the Voltage Profile in Distribution System with 40GW of Solar PV rooftop in Indian grid by 2022: A review

Grid Stability Analysis for High Penetration Solar Photovoltaics

Impact of Islanding and Resynchroniza?on on Distribu?on Systems

Annex to technical regulation for thermal plants above 11 kw

Large Scale Solar Integration

PV inverters in a High PV Penetration scenario Challenges and opportunities for smart technologies

Integrated Plant Control and Q on Demand 24/7 SUNNY TRIPOWER

100 MW Wind Generation Project

Bihar Electricity Regulatory Commission Vidyut Bhawan, J.L.Nehru Marg, Patna

An Introduction to Completing a NERC PRC Study

EE 742 Chap. 7: Wind Power Generation. Y. Baghzouz Fall 2011

Enquiry Form (Non-Registered Generator With Capacity less than 5 MW)

Fuzzy based STATCOM Controller for Grid connected wind Farms with Fixed Speed Induction Generators

Modeling and Simulation of Battery Energy Storage Systems for Grid Frequency Regulation. X. XU, M. BISHOP, D. OIKARINEN S&C Electric Company USA

Field Verification and Data Analysis of High PV Penetration Impacts on Distribution Systems

Emerald Reactive Support Alternative Solution Expressions of interest

EXTRA ORDINARY 16 AASHAADHA, 1937(S) BIHAR ELECTRICITY REGULATORY COMMISSION

On and Off Grid Interactive Features AC Coupling

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Generation Interconnection Facilities Study For

2010 FIFA World Cup ~ South Africa Stadium electricity supplies. Presented on behalf of 2010 ESI Forum By TR Edmondson & Dr C Carter-Brown

Enquiry Form for Micro and Small Generators 5MW and Less

Requirements for Generators European Network Code

Integration of Large Wind Farms into Electric Grids

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Implementation of Distributed Generation

Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER

Testing procedure for the evaluation of grid compliance of power generating units according to the requirements of the Indian Grid Code

Energy Storage at Raglan Mine To Achieve High Penetration of Wind Power

Georgia Transmission Corporation Georgia Systems Operations Corporation

Inverter Advancements in UL1741 and UL 62109

Advanced Inverter Design

TABLE OF CONTENTS FOREWORD...3 INTRODUCTION SCOPE NORMATIVE REFERENCES DEFINITIONS AND ABBREVIATIONS REQUIREMENTS...

15 Nelson-Marlborough Regional Plan

Net +Plus Connection Code

Renewable Energy & Storage Best Practice at TPL and Issues Faced. Murray Sheerin Power Generation Manager, Tonga Power Limited.

Essential Reliability Services Engineering the Changing Grid

Ukujima Photovoltaic Park 400 MW Stable Integration of a 400MW Photovoltaic Farm into the Japanese Power System Challenges and Chances

Technical Standard - TS 129. Small Inverter Energy Systems (IES) - Capacity not exceeding 30kW. SA Power Networks. Published: November 2017

GRID CONNECTION ISSUES FOR DISTRIBUTED GENERATION REVIEW & STANDARDS

G83/2 Engineering Recommendation

Relative Power Factor Correction costs

NERSA CONSULTATION PAPER PROCESS. Moefi Moroeng Specialist: Wholesale Electricity Trading

Basic tariff guiding principles

Exemptions currently in force

PV Penetration on Island Mini-Grid or Grid!- Niue. King Island Connect 2015

(by authors Jouko Niiranen, Slavomir Seman, Jari-Pekka Matsinen, Reijo Virtanen, and Antti Vilhunen)

ABB POWER SYSTEMS CONSULTING

Micro Embedded Generating Units (0-30 kva)

Integrating Embedded Generation into distribution networks. Mobolaji Bello and Dr Clinton Carter-Brown Eskom Holdings Limited South Africa

DYNAMIC BEHAVIOUR OF SINGLE-PHASE INDUCTION GENERATORS DURING DISCONNECTION AND RECONNECTION TO THE GRID

500 / 630 / 720 / 760 / 800 / 850 / 900

Full-Scale Medium-Voltage Converters for Wind Power Generators up to 7 MVA

Journal of American Science 2015;11(11) Integration of wind Power Plant on Electrical grid based on PSS/E

Renewable sources of electricity a brief overview

Workshop on Grid Integration of Variable Renewable Energy: Part 1

Streamlined Application Decision Perimeter Seating Bus Additional Vehicles

PROPOSAL FOR STORAGE CONNECTION REQUIREMENTS

APPENDIX E: Project Need and Description

Transcription:

Compliance of Solar PV Installation with the New Renewables SA Grid Code Jimmy Goulding, Electrical Technologist, Aurecon, South Africa

Content Introduction Overview of Categories for Grid Connection of Renewable Power Generation Technical Considerations Current Legal Requirement and Exemption Process Conclusions

Introduction The primary objective of the recently released Grid Connection Code for Renewable Power Plants (RPP s) grid connection code is: To specify minimum technical and design grid connection requirements for Renewable Power Plants (RPPs) connected to or seeking connection to the South African electricity transmission system (TS) or distribution system (DS).

Introduction A summary of the those technical requirements as stipulated in the this code is relevant to all forms of renewable power If any specific requirements are relevant to PV only this is identified The technical requirements identified need to be noted by the developers and manufacturers for design purposes There is a process for application for exemption from requirements which needs to be followed

Introduction This presentation simply identifies selected technical requirements in the RPP code that are considered to be the most challenging and hence need careful consideration This latest version of the RPP Connection Code is a document that the System Operator will gladly discuss and debate specific queries

Categories for Grid Connection of RPP Generation There are three Categories which are derived from the voltage connection level and proposed installed capacity: Category A: Small or Micro Turbines connected to LV levels having a size of less than 1MVA. (LV voltages up to and including 1kV)

Categories for Grid Connection of RPP Generation Category A is further split into three sub categories: Category A1: 0-13,8kVA Category A2: 13,8-100kVA Category A3: 100 1MVA Category B: 1MVA-20MVA and generators less than 1MVA connected to the MV System. (MV - 1kV up to and including 33kV) Category C: 20MVA or higher

Looking at those technical requirements that need to be noted by the developers: Section 5.1 - Tolerance of Frequency and Voltage Deviations Normal Operating Conditions Voltage Ranges - ensure compliance as specified, however this is not in line with NRS 048-2 and the SA Transmission Network Code Amendment to the voltage ranges has been requested

Frequency Ranges - ensure compliance as specified These frequency operating ranges are in line with International practice Section 5.2 - Tolerance of Frequency and Voltage Deviations Abnormal Operating Conditions Clause 1 Phase jump ride through at the point of connection (POC)

Network faults, specifically short circuit type) can cause phase jumps larger than the 40 phase jump specified in the RPP code Does this mean disconnection of the generators if above 40 phase shift even within the Low Voltage Ride Through limits? This question has been raised and consideration is being given to limit this requirement between the normal operating voltage range only as specified in the RPP code

Section 5.2.1 - Tolerance to Sudden Voltage Drops and Peaks Abnormal Operating Conditions The Low Voltage and High Voltage Ride Through (LVRT and HVRT) requirements are illustrated in the RPP code for all categories at the point of connection (POC) Category A1 and A2, LVRT only at present is questionable - present proposed penetration levels of RPP into the South African Grid are extremely low

Due to these generators connection at LV levels impact of localised voltage dips due to faults on the network would generally not lead to disconnection of these small plants Even in the case that they do disconnect the impact to the security of SA Grid would not be compromised This requirement for the Category A1 and A2 has been queried either to drop it or postpone until higher penetration levels RPP are reached in South Africa

LVRT and HVRT requirements for categories A3, B and C are defined at the point of connection (POC) Besides staying connected in these defined voltage limits there is a requirement for these RPP s to deliver reactive current in the case that the voltage is outside the normal operating band WRT A3 and B LVRT is technically feasible for inverterdriven generators although demanding

HVRT requirement is of concern for many inverters due to well defined maximum voltage limits Due to the same reasons as mentioned in Category A1 and A2, the low penetration levels of RPP, these voltage increases of short duration would not be expected over the whole system Hence, query raised to consider postponement of this requirement until penetration levels are higher

WRT reactive current support for A3 and C generators benefit is questionable what is the advantage since this is typically to support voltage dips in a system with a large penetration of inverter-driven generators? Low voltage support at MV and LV levels where the electrical protection generally non directional and the fault levels low- tripping selectivity is difficult and incorrect tripping can result Hence system stability can be compromised

The RPP code at present does not allow for disabling of reactive current injection by the System Operator Query raised to consider that A3 inverterdriven generators be exempt from providing reactive current support and allow selectivity of reactive current injection for inverterdriven generators of Category B WRT Category C LVRT and HVRT is technically feasible for inverter-driven generators - demanding

WRT reactive current support for these generators the requirement is supported, however, this support requires fast control The RPP Code defines that this support should be at the point of common coupling (PCC) within specific time intervals would require fast control this may be challenging when considering a large amount of central inverters and communication to and from these

Query raised that this control requirement be at the individual inverters on the LV Terminals instead of at the PCC, with a slightly relaxed settling times Query raised that incremental reactive current limits be used instead of limiting total current and if the reactive current definition at the POC was to remain it would require that the absolute value of voltage should be replaced by a voltage change - both these as shown on the characteristic the RPP code.

Section 6 Frequency Response WRT Category A Requirement is for power curtailment for over frequency conditions - in line with international standards and most PV inverter manufacturers should be able to adjust their equipment to meet the SA requirements WRT Category B and C Requirements are for primary frequency control for over and underfrequency conditions as shown in the RPP code

WRT Category B and C Requirements are for primary frequency control for over and underfrequency conditions as shown in the RPP code This functionality is only required if a specific agreement is made with the System Operator for this capability Internationally this requirement is generally not required from RPP s

This frequency support functionality is assumed to be required during emergency conditions Hence, a query was made again addressing the case that the RPP s initial penetration into the grid is of such a low amount, how much influence would these utilities have under these conditions?

A query also made that perhaps category B and C generators should have the same requirements high frequency response as Category A as a mandatory requirement A query also made that Category B and C generators need only consider the other frequency requirements if a specific agreement with the System Operator was desired

Section 7 Reactive Power Capability Generally speaking, these requirements are in line with international standards Suggestions made that Category A1 and A2 generators should operate at unity power factor with a tolerance band specified and A3 generators operating in the range of 0.95 leading/lagging power factor

Section 8 Reactive Power and Voltage Control These requirements are clear and concise Dynamic control requirements not specific Suggestion made that a clear statement on the dynamic controller requirements for the use and application of Mechanically Switched Capacitors and Reactors (MSC s and MSR s) to comply with the reactive power requirements needs to be made

Conclusions Development of this RPP code in a short time so as to accommodate the intended RPP s connection into the SA Grid - therefore there will be amendments to bring requirements not in line with international requirements into line without compromising the security of the existing system Static and Dynamic Studies by developers and manufacturers are essential to ensure correct design and engineering There are other requirements not mentioned here, however these covered are the ones providing the most concern at present.

Current Legal Requirement and Exemption Process The question was posed to the System Operator and NERSA with regards to the requirements until the revised version is published The existing version 2.6 is the current legal document Hence, if there is a compliance issue of a temporary nature manufacturers / developers will need to apply for temporary exemptions The same applies for permanent non compliance application for this will need to be made

Contact Details For any additional information, please do not hesitate to contact Jimmy Goulding: Email:.jimmy.goulding@aurecongroup.com Phone: +27 21 526 6996 Aurecon SA (Pty) Ltd Thank you