Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04

Similar documents
Black Hills Project Summary

2013 ANNUAL PROGRESS REPORT

Falcon-Midway 115 kv Line Uprate Project Report

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

Interconnection System Impact Study Report Request # GI

Status of PNM s Completed Transmission Construction Projects 11/30/2017

March 7, Subject: Southern California Edison 2011 Annual Progress Report

Appendix D Black Hills Project Summary

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

TransWest Express Transmission AC and DC Project Interregional Transmission Project Submittal

Western Area Power Administration

MILLIGAN SOLAR PROJECT

New 115 kv Disconnect Switches at Bloomsburg MTS

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Sub-Regional RTEP Committee PJM South

Feasibility Study Report

TOT1A: Metering Point Relocation Comprehensive Progress Report (WECC Path 30)

South Dakota 890 Study

Western ND Meeting. February 19, 2014 Grant Levi, NDDOT Director

Merger of the generator interconnection processes of Valley Electric and the ISO;

New Mexico Transmission Expansion Concepts For Wind Resources

Sub Regional RTEP Committee Mid-Atlantic

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

System Impact Study Report

Sub Regional RTEP Committee Mid-Atlantic

Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions.

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

SPP Notification to Construct

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection

MEETING AGENDA. Western Area Power Administration Rocky Mountain Region. Transmission Planning Stakeholder Meeting

Sub Regional RTEP Committee South

Sub Regional RTEP Committee South

South Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget

100 MW Wind Generation Project

Project #94. Generation Interconnection System Impact Study Report Revision

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Public Service Company of Colorado Transmission Projects Status. CCPG May 5, 2016

Supplemental Report on the NCTPC Collaborative Transmission Plan

North Oregon Coast Area Study. Adam Lint

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G

SERTP rd Quarter Meeting

West Station-West Cañon 115 kv Transmission Project

Sub Regional RTEP Committee Western Region ATSI

Consulting Agreement Study. Completed for Transmission Customer

Arizona Transmission Challenges

SunZia Southwest Transmission Project

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

Local Transmission Plan. October 11, 2013 Revised August 25, 2014

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA

Pacific Gas and Electric Company s Revised 2015 Annual Progress

FINAL FACILITY STUDY. 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1. September 10, 2010

2018 Annual Progress Report to WECC Pacific Gas and Electric Company

SPP Notification to Construct

DFO STATEMENT OF NEED REPORT

Pacific Gas and Electric Company s Revised 2016 Annual Progress

BC Hydro System 2011 Annual Progress Report

Local Transmission Plan. Rev. 1: April 2018

PSE Attachment K Puget Sound Area Transmission Meeting

Q0044 interconnection at

welcome to the BC Hydro community open house

Project #148. Generation Interconnection System Impact Study Report

Sub Regional RTEP Committee Mid-Atlantic

Proposed New Construction for

Alternatives for meeting the need for transmission improvement described

SPP Notification to Construct

TRANSMISSION PLANNING CRITERIA

Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

Public Service Company of Colorado Transmission Projects Status. CCPG August 18, 2016

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014

Pacific Gas and Electric Company s 2013 Annual Progress Report

Q92 Asarco Interconnection

CUSTOMER/ TWIN ARROWS PROJECT

Feasibility Study Report

City of Palo Alto (ID # 6416) City Council Staff Report

Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives. Addendum. San Juan Major Project

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Interconnection System Impact Study Final Report February 19, 2018

Key to Status Fields in the Project List

Sub Regional RTEP Committee - Southern. August 19, 2011

The Capital Grid Project:

Appendix B. Summary of Changes to the Year Assessment

Reliability Analysis Update

Entergy Texas, Inc. Transmission Draft Construction Plan Update 1 Projects

15 Nelson-Marlborough Regional Plan

WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017

Gateway South Transmission Project

GENERAL DIRECTION SOUGHT AND SPECIFIC QUESTIONS TO BE ANSWERED

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Terry Blackwell Page 1 of 5. Education North Carolina State University BS, Electrical Engineering Power Systems emphasis

15 Nelson-Marlborough Regional Plan

ATTACHMENT B - Table 1: LIST OF MANAGEMENT-APPROVED PROJECTS UNDER $50M

System Impact Study Report Request # T MW Firm Point-to-Point Transmission Service Request from Wyoming to Colorado

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

Transcription:

Western Area Power Administration Rocky Mountain Region 2014 Annual Progress Report Projects Weld Substation Stage 04 Lovell Yellowtail 115-kV rebuild Curecanti 230/115-kV 150 MVA transformer Terry Ranch Road Substation

Weld Substation Stage 04 Project Description 1. Name: Weld Substation Stage 04 2. Participants: Western Area Power - Rocky Mountain Region Public Service Company of Colorado 3. Status: Completed 2nd QTR CY 2013 4. Description of Work: Install a new 150 MVA 230/115-kV transformer along with two (2) 230-kV power circuit breakers, and one (1) 115-kV power circuit breaker. 5. Contact: Linda Pope Electrical Engineering Technician 5555 E. Crossroads Blvd. Loveland, CO 80538 970-461-7348 jpope@wapa.gov

Lovell Yellowtail 115-kV Rebuild A. Project Description 1. Name: Lovell Yellowtail 115-kV rebuild 2. Participants: Western Area Power- Rocky Mountain Region 3. Status: In-service date 4 th Qtr 2014 4. Description of Work: Rebuild with 795 ACSS 5. Contact: Linda Pope Electrical Engineering Technician 5555 E. Crossroads Blvd. Loveland, CO 80538 970-461-7348 jpope@wapa.gov

Curecanti 230/115-kV transformer replacement B. Project Description 1. Name: Curecanti 230/115-kV 150 MVA transformer replacement 2. Participants: Western Area Power- Rocky Mountain Region 3. Status: In-service date 4 th Qtr 2014 4. Description of Work: Replace Curecanti KZ1A 230/115-kV 75 MVA with a 150 MVA transformer 5. Contact: Linda Pope Electrical Engineering Technician 5555 E. Crossroads Blvd. Loveland, CO 80538 970-461-7348 jpope@wapa.gov

Terry Ranch Road Substation C. Project Description 1. Name: Terry Ranch Road Substation 2. Participants: Western Area Power- Rocky Mountain Region Black Hills Power 3. Status: In-service date 4 th Qtr 2014 4. Description of Work: Sectionalize Western s Ault-Cheyenne 230-kV and Archer-North Park 230-kV with a new substation known as Terry Ranch Road. Substation will be built in a 230-kV breaker and half configuration. 5. Contact: Linda Pope Electrical Engineering Technician 5555 E. Crossroads Blvd. Loveland, CO 80538 970-461-7348 jpope@wapa.gov

Western Area Power Administration Desert Southwest Region 2014 Annual Progress Report Projects: Davis 230 kv Substation ED5 Test Track 230 kv Transmission Line Project ED5 Substation Project Test Track Substation Expansion Project Longtin Substation Addition Project

Davis 230 kv Substation 1. Name: Davis 230 kv Substation Rebuild 2. Participants: Western Area Power Administration - Desert Southwest Region 3. Status: Completed 2013 4. Description of Work: Convert Davis 230 kv main and transfer substation to double bus double breaker arrangement. 5. Contact: Michael Baird Project Manager 615 South 43 rd Avenue Phoenix, Az. 85009 602-605-4428 baird@wapa.gov

ED5 Test Track 230 kv Transmission Line Project 1. Name: Transmission Infrastructure Program (TIP) Project 230-kV ED#5 230 kv Transmission Project 2. Participants: Western Area Power Administration - Desert Southwest Region 3. Status: In service date is 7/2014. Transmission line is in place. 4. Description of Work: Installed a second circuit, 22 miles long, on Western s 115-kV Casa Grande-Empire and Empire-ED5 transmission lines which were recently rebuilt as dual circuit steel monopoles, and 23 miles, on the SRP s Duke-Pinal Central 500-kV steel monopoles. 5. Contact: Todd Rhoades Project Manager 615 South 43 rd Avenue Phoenix, Az. 85009 602-605-2613 rhoades@wapa.gov ED5 Substation Project 1. Name: TIP Project ED#5 Substation Project 2. Participants: Western Area Power Administration - Desert Southwest Region 3. Status: In service date is 7/2014. 4. Description of Work: Construct a new 230 kv substation at ED#5 s existing 115 kv yard. Project includes a 225 MVA 230/115/12.47 kv transformer, two breaker 230 kv ring bus configuration, 3 breaker and a half bays built to 230 kv standards but operated at 115 kv. 5. Contact: Todd Rhoades Project Manager 615 South 43 rd Avenue Phoenix, Az. 85009 602-605-2613 rhoades@wapa.gov

Test Track Substation Expansion Project 1. Name: TIP Project Test Track Substation Expansion Project 2. Participants: Western Area Power Administration - Desert Southwest Region 3. Status: In service date is 7/2014. 4. Description of Work: Convert existing 4 breaker ring bus to 2 breaker and a half bays, add 2 new breaker and a half bays, and build tie line into SRP s Duke substation. 5. Contact: Todd Rhoades Project Manager 615 South 43 rd Avenue Phoenix, Az. 85009 602-605-2613 rhoades@wapa.gov

Longtin Substation Addition Project 1. Name: Longtin Substation Project 2. Participants: Western Area Power Administration - Desert Southwest Region 3. Status: In service date is 10/2014. 4. Description of Work: Add a new 230/69 kv substation, sectionalizing the Davis- Topock #1 transmission line. The 230 kv facilities will be a 3 breaker ring bus configuration. 5. Contact: Michael Baird Project Manager 615 South 43 rd Avenue Phoenix, Az. 85009 602-605-4428 baird@wapa.gov

Western Area Power Administration Sierra Nevada Region 2013 Annual Progress Report

No projects meeting WECC criteria

Western Area Power Administration Upper Great Plains Region 2013 Annual Progress Report

WAUW Annual Progress Report Western Area Power Administration (Western) Upper Great Plains Region (UGPR) WAUW Control Area March 12, 2014 Listed below is Western s UGPR Annual Progress Report, which is provided on a BA, TO and/or TOP basis. None of WAUW s planned transmission system additions/upgrades have any regional impacts to the WECC Interconnected System and none are above the 200 kv or 200 MW reporting thresholds. However, they are significant to the local area and some do include future provisions for energization at 230 kv. 1. Final Progress Report Shelby 2 Substation Reactor Replacement Project (Start Summer 2010, Completed April 2013) Western owns, operates and maintains the Shelby 2 230/115/12.47kV Substation. The existing 6.5 MVA oil filled reactor reached its reliable life cycle and was schedule to be replaced. System studies were conducted to size a new unit based on current system operating conditions and topology. A replacement 12 MVA air core unit has been delivered and available for installation. This project was scheduled for 2010 but was postponed due to higher priority projects. The reactor has been physically installed and the project is awaiting final steel for an associated disconnect switch that was determined to be non-reliable. Completion is expected by April, 2013. No interruption of customer service during construction is anticipated. 2. Updated Progress Report Havre Substation Upgrade Project (Start Fall 2010, Expected Completion Fall 2014) Western currently owns, operates and maintains the Havre 161/115/12.47kV Substation. Upgrades are a result of needed relaying replacements and a new 115 kv interconnect for network load. The existing 115 kv single breaker and bypass switch will be replaced with a ring bus configuration serving the existing Shelby circuit and new network service interconnect. In addition, a new dedicated circuit interrupter will be installed for protection of the transformer. Construction design is complete. The control building was completed 2012 and currently is receiving protective relaying upgrades. Completion of the 115 kv yard work is expected by fall of 2014. The 115 kv bus will be out of service for extended periods during the 2014 construction season. However, no interruption of customer service during construction is anticipated. Minor outages are expected for Hill County Electric Coop during sequenced re-energization. Herron Park is currently served via a temporary tap off the Havre-Shelby 115 KV line.

3. Updated Progress Report Havre to Rainbow 161kV Transmission Rebuild / Upgrade Project (Started Fall 2007, On-Hold 2012-2017, Target Completion 2022) This project is on-hold status due to high priority oil load growth. Western s 103 mile Havre Verona Rainbow 161kV transmission line was constructed and energized in 1935. It electrically parallels NorthWestern Energy s (NWE s) Havre Rainbow 161kV circuit. These two circuits maintain separate rights-of-ways with two crossings. Western intends to rebuild its circuit in segments, at 230kV specification. Each segment is anticipated to be complete and re-energized in approximately one month. The existing right-of-way is inadequate and will be expanded in most areas and re-routed in others. An Environmental Assessment (EA) is complete for this project and has been issued for final publication. The first 30 mile segment between Havre and Verona is complete, along with 1 mile at the Rainbow / Great Falls end for re-termination into NorthWestern Energy s (NWE's) Great Falls Substation in conjunction with Project 2) described below. In 2011, 14 miles of reroute and reconstruction began in the Loma, MT area and was approximately one-third complete when crews were re-dispatched due to storm damage in Eastern Montana / Western North Dakota (East Grid WAUE BA). Due to both storm damage and dramatic oil exploration load growth in the Eastern Montana / Western North Dakota area, this project has been placed onhold for approximately 5 years, with approximately 5 years of construction remaining prior to completion. Therefore, target completion is estimated to be 2022. Once the project resumes, construction will again continue during nonpeak loading periods only. Upon completion of each segment, the line will continue to be energized at 161kV until such time that conversion to 230kV is required. Additional system impact study analyses will be required with stakeholder approval prior to the 230kV voltage conversion. No interruption of customer service during construction is anticipated with this project. The project will receive a single 1 mile reroute this summer, near Carter, to raise the highway crossing for accommodation of extra large/tall shipments of pre-fabricated tanks North of Great Falls, MT. 4. Updated Progress Report New 161/115kV Substation between Richardson Coulee and Malta Substations (On-Hold Status, Earliest Start Fall 2014, Target Completion 2016) This project is on-hold status waiting for regulatory approval. Western currently owns, operates and maintains the 180 mile Fort Peck-Richardson Coulee-Malta- Harlem-Havre 161kV circuit, which is constructed for future 230kV conversion. A new substation is anticipated to be installed approximately 18 miles East of Malta in the 49 mile section between the Richardson Coulee and Malta Substations. This new substation will provide a 161kV ring bus constructed at 230kV specification, 161/115kV transformation and a 115kV tap for a new 115kV line that will extend approximately 48 miles to serve an ultimate 21 MW of new oil

development network load. VAR support will include a 15 MVAR shunt capacitance at the new 161kV substation and a 15 MVAR shunt capacitance at the load. Due to regulatory delays, construction is not anticipated to begin before fall of 2014. No interruption of customer service during construction is anticipated.