MTEP14 South SPM #2 MISO Texas Project Information April 7, 2014
MISO Southern Region EAST TEXAS ELECTRIC COOPERATIVE 2
East Texas Electric Cooperative (ETEC) No projects submitted for moving to Appendix A or Appendix B in MTEP14 for ETEC 3 3
MISO Southern Region ENTERGY TEXAS 4
Entergy-Texas Entergy-Texas has a total of 16 project proposals in the MTEP14 database Of those 16 projects: 6 project proposals have a target appendix of Appendix A. Of those 6, 3 projects have a cost >$5M, 1 project has a cost between $1M and $5M, and 2 projects have a cost <$1M. 10 project proposals are targeted for Appendix B. These are reliability driven projects. Of those 6 projects designated to move to Appendix A All are Baseline Reliability Projects 4 Projects driven by a new load addition 2 Projects are relay modifications 5
MISO MTEP14 APPENDIX A PROJECTS 6
Projects Driven by Protection System Modification Target Appendix Prj. ID Project Name Project Description 4801 ETI SPOF Projects: Modify ETI SPOF Projects: Modify relaying at relaying at Sabine 230/138 kv Sabine 230/138 kv Expected ISD Estimated Cost 6/1/2015 A in MTEP14 4802 ETI SPOF Projects: Modify relaying at VFW Park 230 kv ETI SPOF Projects: Modify relaying at VFW Park 230 kv 6/1/2015 $1,994,400 7
Projects Driven by New Load Addition Target Appendix Prj. ID Project Name Project Description 4800 Parkway: Construct new Construct new Parkway 138 kv substation substation near Hickory Ridge Expected ISD Estimated Cost 12/1/2014 $8,475,000 4803 Nederland 230 kv Substation: Construct new substation Construct new Nederland 230 kv substation 10/1/2014 $11,700,000 A in MTEP14 4804 Petry Woods 138 kv Substation: Construct new substation Construct new Petry Woods 138 kv substation 6/30/2014 $7,650,000 4805 Ranchland 69 kv Substation: Construct new substation Construct new Ranchland 69 kv substation 12/1/2014 $3,402,000 8
MISO MTEP14 APPENDIX B PROJECTS 9
Projects Driven by New Load Addition Target Appendix Prj. ID Project Name Project Description 4798 Forest: Add distribution Install Distribution transformers and transformers at new substation facilities at the Forest 138 kv substation Expected ISD Estimated Cost 6/1/2016 $2,480,000 B in MTEP14 4799 Dishman: Construct new substation Construct new 230kV substation on the Amelia to Helbig 230kV line 6/1/2017 $10,500,000 10
Projects driven by contingent events for Entergy Texas 11
New China to Stowell 138 kv Line P4618 (11-ETI-037) 20 Mi New 138 kv line: Expected In Service Date: 6/1/2018 Estimated Cost: $31,500,000 Target Appendix: B in MTEP14 Project Type: Baseline Reliability TPL Category: P1.2 (Fault Transmission Circuit) 12 MISO, using Ventyx Velocity Suite 2014
Kolbs 230kV Substation Add Capacitor Bank P4620 (12-ETI-006) Add a 72 Mvar 230kV Capacitor Bank: Expected In Service Date: 6/1/2018 Estimated Cost: $1,350,000 Target Appendix: B in MTEP14 Project Type: Baseline Reliability TPL Category: P3.2 (Generator + Line) 13 MISO, using Ventyx Velocity Suite 2014
Gulfway 230 kv Substation Upgrade Equipment P4621 (12-ETI-017) Upgrade Terminal on VFW Park Line bay: Expected In Service Date: 6/1/2018 Estimated Cost: $100,000 Target Appendix: B in MTEP14 Project Type: Baseline Reliability TPL Category: P2.3 (Breaker Fault) 14 MISO, using Ventyx Velocity Suite 2014
Raywood Area Improvements P4619 (14-ETI-001-01) Add 2nd 138-69 kv Autotransformer at Raywood: Expected In Service Date: 6/1/2018 Estimated Cost: $3,600,000 Target Appendix: B in MTEP14 Project Type: Baseline Reliability TPL Category: P1.3 (Fault Transformer) 15 MISO, using Ventyx Velocity Suite 2014
Raywood Area Improvements P4624 (14-ETI-001-02) 2.2 MI Add 2nd 69kV line: Expected In Service Date: 6/1/2018 Estimated Cost: $5,400,000 Target Appendix: B in MTEP14 Project Type: Baseline Reliability TPL Category: P1.2 (Fault Transmission Circuit) 16 MISO, using Ventyx Velocity Suite 2014
Egypt to Panorama 138 kv Line: Reconductor Line P4617 (13-ETI-013) Reconductor the 138 kv Line Expected In Service Date: 6/1/2017 Estimated Cost: $1,500,000 Target Appendix: B in MTEP14 Project Type: Baseline Reliability TPL Category: P3.2 (Generator + Line) 17 MISO, using Ventyx Velocity Suite 2014
Panorama to Longmire 138 kv Line: Reconductor Line P4623 (13-ETI-014) Reconductor the 138 kv Line Expected In Service Date: 6/1/2019 Estimated Cost: $3,200,000 Target Appendix: B in MTEP14 Project Type: Baseline Reliability TPL Category: P3.2( Generator + Line) 18 MISO, using Ventyx Velocity Suite 2014
Upgrade Splendora to Apollo 138 kv line P4622 (11-ETI-026) Upgrade 138 kv line: Expected In Service Date: 6/1/2019 Estimated Cost: $3,000,000 Target Appendix: B in MTEP14 Project Type: Baseline Reliability TPL Category: P3.2 (Generator + Line) 19 MISO, using Ventyx Velocity Suite 2014
Contact Information Edin Habibovic Manager Expansion Planning, Southern Region ehabibovic@misoenergy.org William Kenney Expansion Planning Engineer, Southern Region WKenney@misoenergy.org 20