Appendix M-2 EMF from Underground and Overhead Transmission Lines on Block Island

Similar documents
JCP&L Verbatim Response to Middletown Township s Questions

APPENDIX E: ELECTRIC AND MAGNETIC FIELDS MANAGEMENT PLAN

ABB POWER SYSTEMS CONSULTING

STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS ENERGY FACILITY SITING BOARD

A. INTRODUCTION B. PRINCIPAL CONCLUSIONS AND IMPACTS C. BACKGROUND

METRO NORTH TRANSMISSION STUDY ELECTRIC AND MAGNETIC FIELD PROFILES (VILLAGE OF ANMORE)

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

A. INTRODUCTION B. PRINCIPAL CONCLUSIONS AND IMPACTS C. BACKGROUND

Electric and Magnetic Field (EMF) Analysis for the Mystic-to-Woburn x and y, 115-kV Transmission Lines

Mystic to Woburn Line Project. Town of Winchester Board of Selectmen Lincoln School Auditorium February 11, 2016

STATE OF NEW HAMPSHIRE Inter-Department Communication

The Narragansett Electric Company. d/b/a National Grid (Interstate Reliability Project) RIPUC Dkt. No Testimony of. David M. Campilii, P.E.

MUNICIPAL CONSULTATION FILING

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

March 31, 2014 VIA HAND DELIVERY & ELECTRONIC MAIL

STEEL CASING OVERHEATING ANALYSIS OF OPERATING POWER PIPE-TYPE CABLES

SECTION 1 DESCRIPTION OF THE PROPOSED PROJECT

OHL AC Cable DC Cable Submarine

TABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES:

PACIFICORP. Lassen Substation Electric and Magnetic Field Assessment. Revision B. October 16, 2015 PROJECT NUMBER:

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Analysis of Electric Field and Magnetic Field from Overhead Subtransmission Lines Affecting Occupational Health and Safety in MEA s Power System

ABB Group August 27, 2010 Slide 1

Stray Losses in Power Transformers

100 MW Wind Generation Project

Appendix D Black Hills Project Summary

STATE OF MINNESOTA ENVIRONMENTAL QUALITY BOARD MEQB DOCKET NO. MP-HVTL-EA-1-99

For Conduit Inspections

STATE OF MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS FOR THE PUBLIC UTILITIES COMMISSION PUC DOCKET NO. E002/TL OAH DOCKET NO.

Appendix G Aquilla Lake Pool Rise Recreational Resources

City of Palo Alto (ID # 6416) City Council Staff Report

Development of a High Efficiency Induction Motor and the Estimation of Energy Conservation Effect

EMF Readings in Tollgate Crossing community Robert L. Vaessen - 22 Dec 2016

Challenges With Underground High Voltage Transmission SCE Tehachapi Renewable Transmission Project First 500 kv Underground T/L in North America

Energy Technical Memorandum

Power System Analysis I TRANSMISSION LINE PARAMETERS

The Grid Link Project. Summary of the Report for the Independent Expert Panel

Magnetic Field Design for Low EMF and High Efficiency Wireless Power Transfer System in On-Line Electric Vehicles

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) )

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DE PUBLIC SERVICE COMPANY OF NEW HAMPSHIRE

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA

1 GENERAL Project Description Labrador Island Transmission Link (LIL) Language and Units Site Climate Data...

SPECIFICATIONS FOR RESIDENTIAL CONSTRUCTION

TrueGyde Microcoil. Author: Marcel Berard Co-Author: Philippe Berard

The Green Line Project

CHAPTER 6 INTRODUCTION TO MOTORS AND GENERATORS

TRANSPOWER PLANS, BUILDS, MAINTAINS AND OPERATES NEW ZEALAND S HIGH VOLTAGE ELECTRICITY TRANSMISSION NETWORK THE NATIONAL GRID.

welcome to the BC Hydro community open house

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design

TRANSIENT MAGNETIC FLUX DENSITY MEASUREMENT RESULTS ON A FUSELAGE-LIKE TEST SETUP AND INVESTIGATION OF THE EFFECTS OF APERTURES

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Offshore Wind China 2010 Bergen, 15th March Olivier Angoulevant Nexans Norway AS

Computer-Assisted Induction Aluminum

ABB Roger Rosenqvist: August 30, 2012

Kake - Petersburg Intertie Update

On June 11, 2012, the Park Board approved the installation of three electric vehicle charging stations along Beach Avenue.

Energize Eastside. Underground transmission lines and EMF webinar. Leann Kostek. Senior Project Manager, Puget Sound Energy

INTERCONNECTION FACILITIES STUDY REPORT

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

DFO STATEMENT OF NEED REPORT

Downtown Lee s Summit Parking Study

JDR PRODUCT APPLICATIONS. MCE Deepwater Development 2017

Submarine Power Cables

Christian Ohler, ABB Switzerland Corporate Research Physics of Electric Power Systems. ABB Group August 1, 2012 Slide 1

PHYS 1444 Section 004. Lecture #19. DC Generator Transformer. Generalized Faraday s Law Mutual Inductance Self Inductance. Wednesday, Apr.

Bohn to Kettle River Transmission Project

Cost Benefit Analysis of Faster Transmission System Protection Systems

THORNTON SUBSTATION. Why is the substation needed? How were the three potential sites identified?

Special edition paper

Western NY Public Policy Transmission Planning Report

CUYAHOGA COUNTY DEPARTMENT OF PUBLIC WORKS TRAFFIC CONTROL STANDARDS

CUSTOMER/ TWIN ARROWS PROJECT

STATE OF MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS FOR THE PUBLIC UTILITIES COMMISSION PUC DOCKET NO. E002/TL OAH DOCKET NO.

SPECIFICATIONS FOR RESIDENTIAL CONSTRUCTION

Note: The October 2007 version of this report has been updated in this December 2008 report to present costs in year 2007 dollars.

PREPARED DIRECT TESTIMONY

CHAPTER 9: VEHICULAR ACCESS CONTROL Introduction and Goals Administration Standards

ENERGY STRATEGY FOR YUKON. Independent Power Production Policy

Hans Kvarme Nexans Norway AS. Offshore vindkraft Oslo, 14. desember 2010

Tehachapi Renewable Transmission Project 3.1 OVERVIEW OF PROPOSED PROJECT

Mecklenburg County Common Code Defects

INSTALL SERVICE- ENTRANCE SYSTEMS

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G

15 Nelson-Marlborough Regional Plan

Truck Traffic Impact Analysis

OVERVIEW OF UNDERGROUND POWER CABLES AT HIGH/EXTRA HIGH VOLTAGE LEVELS

RE: Traffic Impact Statement: Paper Mill Lake Subdivision

Virginia Offshore Wind Port Readiness Study

MINERVA PARK SITE TRAFFIC IMPACT STUDY M/I HOMES. September 2, 2015

Wisconsin Public Utility Institute. June 28, Minimum Distribution Charges. Larry Vogt. Director, Rates Mississippi Power

Chapter 6 Generator-Voltage System

Decision on Merced Irrigation District Transition Agreement

MREC Mark A. Cook General Manager, REPS PSCW. Farm Wiring Programs and Transmission Underbuild Issues

Supplement to ISO Transmission Plan. Harry Allen-Eldorado Project Description and Functional Specifications

A Practical Guide to Free Energy Devices

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82

CHAPTER 6 DESIGN AND DEVELOPMENT OF DOUBLE WINDING INDUCTION GENERATOR

Comparison of Indian Electricity Rules, 1956 Vs CEA (Measures relating to Safety and Electric Supply) Regulations, 2010

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

Transcription:

Appendix M-2 EMF from Underground and Overhead Transmission Lines on Block Island

Electrical Engineering and Computer Science Practice Deepwater Wind Block Island Wind Farm EMF from Underground Cables and Overhead Transmission Lines on Block Island

Deepwater Wind Block Island Wind Farm EMF from Underground Cables and Overhead Transmission Lines on Block Island Prepared for Normandeau Associates, Inc. 25 Nashua Rd. Bedford, NH 03110 Tetra Tech, Inc. 160 Federal Street, 3rd Floor Boston, MA 02110 Prepared by Exponent, Inc. 17000 Science Drive, Suite 200 Bowie, MD 20715 May 29, 2012 Exponent, Inc.

Contents Page List of Figures List of Tables Executive Summary iv v vi Introduction 1 Modeling Cases 6 Assessment Criteria 14 Methods 15 Results and Discussion 17 Conclusions 20 References 26 Limitations 27 iii

List of Figures Figure 1. Overview of proposed route for BIWF and BITS projects. 2 Page Figure 2. Configuration of an AC Export Cable showing 3-phase conductors and surrounding sheathing 5 Figure 3. Locations of study, Sections 1-4a, on Block Island. 6 Figure 4. Cross-sectional view of the buried Export and BITS submarine cables. 9 Figure 5. Duct bank configurations in Section 2. 10 Figure 6. Bridge crossing between Trims Pond and Harbor Pond. 11 Figure 7. Overhead configuration on BIPCO Property (Section 4). 12 Figure 8. Overhead configuration on BIPCO Property (Section 4a). 13 Figure 9. Calculated magnetic field at Sections 1 and 1a on Block Island. 21 Figure 10. Calculated magnetic field at Section 2 on Block Island. 21 Figure 11. Calculated magnetic field at Sections 3 and 3a on Block Island. 22 Figure 12. Calculated magnetic field at Section 4 on Block Island. 22 Figure 13. Calculated magnetic field at Section 4a on Block Island. 23 Figure 14. Calculated electric field at Section 4 on Block Island. 24 Figure 15. Calculated electric field at Section 4a on Block Island. 24 Figure 16. Electric and magnetic field levels in the environment. 25 iv

List of Tables Page Table 1. ICNIRP and ICES guidelines for EMF exposure 14 Table 2. Cable/circuit data 15 Table 3. Calculated magnetic field values (mg) in Sections 1-4a 17 Table 4. Calculated electric field values (kv/m) in overhead sections 18 v

1 Executive Summary This report summarizes calculated levels of electric and magnetic fields (EMF) at representative transects of the Block Island Wind Farm (BIWF) project and the Block Island Transmission System (BITS) project on Block Island. Magnetic fields The calculated alternating current (AC) magnetic-field levels associated with the operation of the projects at an anticipated load of 32 mega-volt-amperes (MVA), calculated at a height of 3.28 feet (1 meter) above ground, are below limits for the general public recommended by the International Commission on Non-ionizing Radiation Protection (ICNIRP) and the International Commission on Electromagnetic Safety (ICES). The maximum calculated magnetic-field level for the underground portion of the route between the Block Island shore landing and the Block Island Substation is less than 25 milligauss (mg). At the bridge crossing between Trims Pond and Harbor Pond, where the cable is routed beneath the bridge, the highest calculated magnetic field at 3.28 feet (1 meter) above the bridge deck is less than 74 mg and the highest magnetic field under the bridge at 3.28 feet (1 meter) above the high tide level is less than 112 mg. On the portion of the route where the transmission lines run overhead on Block Island Power Company (BIPCO) Property, the highest calculated magnetic field is 146 mg. Electric Fields There are no project-related electric fields above ground over any underground portion of the BIWF and BITS projects as electric fields are effectively blocked by the ground. At the bridge crossing on Block Island no electric fields will be produced outside the cables, provided the cables are shielded and grounded. On BIPCO Property, where the 34.5- kilovolt(kv) Export Circuit and BITS Circuit are constructed on overhead wood poles, the highest calculated electric field is 0.4 kilovolts per meter (kv/m). Comparison to Standards The highest potential magnetic field due to the BITS and Export Circuits outside of BIPCO Property occurs at the 45-foot (14-meter) bridge crossing on Block Island. The calculated magnetic fields at this location are less than 1/15 th of those recommended by international health-based standards (ICES and ICNIRP) and are comparable to fields that may be found in homes next to major appliances. Where the Circuits are run overhead the electric field levels are less than 1/10 th of the recommended exposure limits and magnetic field vi

levels are about 1/15 th of the recommended exposure limits. For the underground portion of the route, the most intense magnetic fields generated by the project will be roughly comparable to those found beneath local distribution lines which run along most city streets and are less than 1/80 th of the exposure limits recommended by the ICES and ICNIRP. vii

2 Introduction This report summarizes the levels of electric and magnetic fields (EMF) calculated along representative transects perpendicular to electrical conductors of the Block Island Wind Farm (BIWF) project and the Block Island Transmission System (BITS) project on Block Island. The BIWF project will consist of five 6 megawatt (MW) wind turbine generators (WTG), a submarine cable interconnecting the WTGs (Inter-Array Cable), and a 34.5-kilovolt (kv) buried submarine and terrestrial cable connecting the northernmost WTG to an interconnection point on Block Island (Export Cable). As shown in Figure 1, the WTGs will be located approximately 3 miles (4.8 kilometers) southeast of Block Island, spaced approximately 0.5 miles (0.8 km) apart in radial configuration and connected by the Inter-Array Cable. At the northeast edge of the WTGs, the Export Cable will carry the current from all the WTGs for approximately 6.2 miles (10 kilometers) to its landing location at a manhole in the parking lot of Crescent Beach on Block Island. From this manhole, the Export Cable will be buried in an underground duct bank which will follow along existing public road rights-of-way to Block Island Power Company (BIPCO) Property. At the BIPCO Property, the Export Circuit will transition to overhead poles for a short distance and will terminate at a new switchyard within the existing Block Island Substation. In total, the Export Circuit will be approximately 7.25 miles (11.7 kilometers) from the northernmost WTG to the interconnection on the BIWF Switchyard (located within the newly proposed Block Island Substation on the BIPCO Property). The BITS project is a proposed 34.5-kV alternating current (AC) bi-directional transmission system including a 3-core submarine cable that will run approximately 21.8 miles (35.4 kilometers) from Block Island to a landing location at the Narragansett Town Beach (BITS Alternative 1) or approximately 25.9 miles (41.7 kilometers) to a landing location at the University of Rhode Island (URI) Bay Campus (BITS Alternative 2), both of which are on the Rhode Island mainland. The BITS Circuit will originate at the Block Island Switchyard located within the Block Island Substation and will follow the same route on Block Island as the Export Circuit, but with current flowing in the opposite direction. 1

Figure 1. Overview of proposed route for BIWF and BITS projects. 2

The Inter-Array, Export, and BITS Circuits will operate at 34.5 kv and are designed to carry up to 32 MVA of 3-phase AC power. In order to complete a conservative assessment of the potential EMF from the Project, the following configuration and type of cables used in different portions of the proposed project are detailed below. 1. The submarine portions of the Export and BITS Circuits will each consist of a single cable with three bundled 750 kcmil copper cores surrounded by layers of insulating material within conductive and non-conductive sheathing. Figure 2 illustrates a typical arrangement of an AC undersea cable and its composition, including the metallic sheaths. 2. On land, the Export and BITS Circuits will each consist of three single-core 2,000 kcmil aluminum conductors surrounded by layers of insulating material within conductive and non-conductive sheathing and buried in separate conduits within concrete duct banks. 3. At the bridge crossing, where copper will be used instead of aluminum for the cable conductors, both circuits will consist of three single-core 1000 kcmil, copper conductors surrounded by layers of insulating material within conductive and non-conductive sheathing which will be strapped together in a trefoil arrangement and routed beneath the bridge, each in a single conduit within separate bays. 4. On the overhead poles on BIPCO Property the Export and BITS Circuits will be 477 kcmil ACSR (Flicker) conductors, which (for short lengths of overhead conductor spans) will also join a local 4.16-kV distribution circuit using bundled 900 kcmil ACSR (Canary) conductors. Magnetic Fields The current flowing in the conductors of a cable or overhead transmission line generates a magnetic field near the conductors. The strength of project-related magnetic fields in this report is expressed as magnetic flux density in units of mg, where 1 Gauss (G) = 1,000 mg. In the case of AC transmission lines, these currents (and thus magnetic fields) vary in direction and magnitude with a 60-Hertz (Hz) cycle. Since load current expressed in units of amperes (A) generates magnetic fields around the conductors, measurements or calculations of the magnetic field present a snapshot for the load conditions at only one moment in time. 3

On a given day, throughout a week, or over the course of months and years, the magnetic-field level can change depending upon the patterns of power demand on the bulk transmission system. Electric Fields The voltage on the conductors of transmission lines generates an electric field in the space between the conductors and to ground. The buried Export and BITS Circuits are a negligible source of 60-Hz electric fields above ground, since electric fields are confined by the cables conductive sheath and armor, as well as by the surrounding soil and duct bank. Where the underground cables are run beneath the bridge on Block Island, the same conductive sheath and armor will eliminate electric fields outside the cable. In this report, electric-field levels are calculated beneath overhead portions of the Export and BITS Circuits. The strength of projectrelated electric fields is expressed in units of kilovolts per meter (kv/m), which is equal to 1,000 volts per meter (V/m). Many objects are conductive including fences, shrubbery, and buildings and thus block electric fields. The analysis in this report evaluates the EMF associated with the operation of the Export and BITS Circuits on Block Island. Analysis of the submarine portion of the BIWF and BITS projects is detailed in a separate report. Furthermore, analysis of the upland portion of the report including Alternative 1 at Narragansett and Alternative 2 near the URI Bay Campus is currently underway and will be detailed in a supplemental report. 4

Fiber optic cable Conductor Armor Wires Outer corrosion protection Insulation System Lead Sheath Figure 2. Configuration of an AC Export Cable showing 3-phase conductors and surrounding sheathing (Source: Nexans, 2010) 5

3 Modeling Cases The shore landing and terrestrial route of the Export and BITS Circuits on Block Island are modeled in seven separate cross sections (Sections 1-4a) including two cross sections each in Sections 1, 3, and 4. Section 1, 1a Single core buried cables Section 2 Underground Duct Bank Aluminum Core Cables Section 3, 3a Bridge Crossing Copper Core Cables in Trefoil Configuration Section 4, 4a Overhead Lines Figure 3. Locations of study, Sections 1-4a, on Block Island. 6

The Export and BITS Circuits will be brought ashore using either short- or long-distance horizontal directional drilling (HDD). The short-distance HDD will be approximately 300 feet (90 meters) and long-distance HDD will be between 900 and 1,900 feet (275-580 meters). The HDD will terminate at a manhole located within the Crescent Beach Parking lot, which will also serve as a transition point where the submarine cable will be anchored and spliced to the buried portion of the terrestrial cable. From the manhole to the edge of the BIPCO Property (0.8 miles, 1.3 kilometers) the Export Circuit will be buried in an underground duct bank which will follow along existing public road rights-of-way. Where the circuit crosses a bridge between Trims Pond and Harbor Pond (a distance of approximately 45 feet, [14 meters]) the circuit cables will be installed in a single conduit under the bridge in a bay below the sidewalk. At the BIPCO Property, the Export Circuit will transition to overhead poles for a distance of up to 0.2 miles (0.3 kilometers) where it terminates at the BIWF Switchyard located within the Block Island Substation. The BITS Circuit will originate at the Block Island Switchyard and will follow the same route on Block Island as the Export Circuit, but with current flowing in the opposite direction. For the overhead portion of the route (on BIPCO Property) the cables of the BITS Circuit will be collocated on overhead poles with the Export Circuit and will also be routed in the same underground duct bank as the Export Circuit. At the bridge crossing the BITS Circuit will be installed in a conduit under the bridge but in a bay separate from the Export Circuit. At the manhole, the terrestrial portion of the BITS Circuit will be spliced to a submarine cable and routed offshore using a separate HDD trench. A description of each of the seven modeled cross sections is detailed below. Section 1 and 1a model locations where the submarine BITS and Export Circuits are brought ashore in HDD bores from an off-shore coffer dam to a manhole in the parking lot of the Block Island Town Beach. Sections 1 and 1a differ in the distance from the cofferdam to the manhole. Section 1 models the long-distance HDD where the submarine cables are buried to a representative depth of 15 feet (4.6 meters) while Section 1a models the short-distance HDD where the submarine cables are buried to a representative depth of 8 feet (2.4 meters). In both cases the submarine cables are modeled with a representative separation distance of 10 feet 7

(3 meters). The cores of both cables are contained in a single submarine cable with different phases modeled in a trefoil arrangement as shown in Figure 4. Since the relative phasing of the Export and BITS Circuits cannot precisely be controlled in these directional bores, the magnetic fields in this section are modeled assuming minimum mutual cancellation of fields between the two cables. In Section 2 both the Export and BITS Circuits are split into three individual single-core cables and are routed approximately 0.8 miles (1.3 kilometers) in the ducts of an underground duct bank as shown in Figure 5. The three cables of each circuit have 2000-kcmil aluminum cores, and are modeled with phasing as shown in Figure 5. The phasing in this section has been chosen to optimize mutual cancellation of fields at a distance of 10 feet (3 meters) from the center of the underground duct bank. Sections 3 and 3a are located at the bridge between Trims Pond and Harbor Pond. At the bridge, the three cables from each of the two Circuits are spliced to 1000 kcmil shielded copper conductors and are strapped together in a trefoil arrangement so that each circuit can be run beneath the bridge in a single conduit. The two circuits are routed beneath the bridge for a distance of 45 feet (14 meters) in non-metallic conduits as shown in Figure 6. 1 Section 3 models the magnetic fields above the bridge sidewalk (the sidewalk is located 16 inches [0.4 meters] above the conduit and magnetic fields are modeled at 3.28 feet [1 meter] above the sidewalk). Section 3a models magnetic fields at a height of 3.28 feet (1 meter) above the meanhigh-water height (6 feet-6 inches [2 meters] below the conduits). The Export and BITS circuits are assumed to be separated by a minimum distance of 20 inches (0.5 meters). In these sections, the magnetic fields are modeled assuming minimum mutual cancellation of fields because the relative phasing of the individual cables comprising Export and BITS Circuits might not be precisely controlled. In Section 4, the Export and BITS Circuits exit the duct bank and run overhead on BIPCO Property for approximately 0.2 miles (0.3 kilometers) on the upper and lower cross-arms of self-supporting laminated wood structures ( 11 Note that the cross section shown in Figure 6 is looking east while the cross sections in the map of a 8

Figure 7). Both overhead lines are modeled with 477 kcmil ACSR (Flicker) conductors. The fields are modeled assuming a minimum conductor height at midspan of 25 feet (7.6 meters). The optimal phasing of the conductors in this section is A-B-C for the BITS Circuit (on the top crossarm) and A-B-C for the Export Circuit (on the bottom crossarm). Section 4a, occurs on a subset of the spans within Section 4, all within the boundary of the BIPCO Property, where the Export and BITS Circuits are joined by a local distribution cable operating at 4.16 kv. The distribution cable is carried on the bottom crossarm of the selfsupporting laminated wood structures as shown in Figure 8 and is modeled with bundled 900 kcmil ACSR (Canary) conductors. The midspan height of the lowest conductor in this section is assumed to be 20 feet (6 meters). The phasing of the conductors in this section is A-B-C for the BITS Circuit (on the top crossarm), A-B-C for the Export Circuit (on the middle crossarm), and A-B-C for the distribution circuit (on the bottom crossarm) in the plane of Section 4a. The phasing of the distribution circuit is assumed to be in phase with the Export and BITS Circuits. Balanced loading has also been assumed for the distribution circuit. Figure 4. Cross-sectional view of the buried Export and BITS submarine cables. 9

4 Export A A B C B C BITS Figure 5. Duct bank configurations in Section 2. In Section 2, cables of the Export Circuit are located in three separate ducts on the left-half of the duct bank and the BITS Circuit cables are located in the righthalf of the duct bank. Optimal phasing is indicated. 10

SIDEWALK Modeling Cross Section Center Export BITS Figure 6. Bridge crossing between Trims Pond and Harbor Pond.The Export and BITS Circuits are contained in non-metallic conduits as indicated. Note that the cross section above is shown looking east. 11

Figure 7. Overhead configuration on BIPCO Property (Section 4). In Section 4, conductors of the BITS Circuit are modeled on the upper crossarm, with A, B, and C phases arranged left to right in the depicted section plane. Conductors of the Export Circuit are modeled on the lower crossarm, with A, B, and C phases arranged left to right. 12

DETAIL A DETAIL B DETAIL C Figure 8. Overhead configuration on BIPCO Property (Section 4a). Conductors of the BITS Circuit are modeled on the upper crossarm, with A, B, and C phases arranged left to right in the depicted section plane. Conductors of the Export Circuit are modeled on the middle crossarm, with A, B, and C phases arranged left to right. The 4.16 kv distribution circuit is modeled on the bottom crossarm with A, B, and C phases arranged from left to right. 13

5 Assessment Criteria Neither the federal government nor Rhode Island has enacted standards for magnetic fields or electric fields from power lines or other sources at power frequencies. Several other states have statutes or guidelines that apply to fields produced by new transmission lines, but these guidelines are not health based. For example, New York and Florida have limits on EMF that were designed to limit fields from new transmission lines to levels determined from a survey of the fields from existing transmission lines. More relevant EMF assessment criteria include the exposure limits recommended by scientific organizations. These exposure guidelines were developed to protect health and safety and are based upon reviews and evaluations of relevant health research. These guidelines include exposure limits for the general public recommended by the ICES and ICNIRP to address health and safety issues (ICES, 2002; ICNIRP, 2010). In a June 2007 Factsheet, the World Health Organization included recommendations that policy makers should adopt international exposure limit guidelines, such as those from ICNIRP or ICES (Table 1), for occupational and public exposure to EMF. Table 1. ICNIRP and ICES guidelines for EMF exposure Exposure (60 Hz) Electric Field Magnetic Field ICNIRP Occupational 8.3 kv/m 10 G (10,000 mg) General Public 4.2 kv/m 2 G (2,000 mg) ICES Occupational 20 kv/m 27.1 G (27,100 mg) General Public 5 kv/m* 9.040 G (9,040 mg) *Within power line rights of way, the guideline is 10 kv/m under normal load conditions. 14

6 Methods The EMF levels were calculated at 3.28 feet (1 meter) above ground, in accordance with IEEE Std. C95.3.1-2010, and are reported as the root-mean-square (rms) value of the field ellipse at each location along a transect perpendicular to the transmission centerline. At the bridge crossing section these fields are calculated at 3.28 feet (1 meter) above the sidewalk on the bridge (16 inches [0.4 meters] above the circuit cables), and at 3.28 feet (1 meter) above mean high water height (6 feet-6 inches [2 meters] below the circuit cables). EMF levels based upon proposed construction were calculated using computer algorithms developed by the Bonneville Power Administration, an agency of the U.S. Department of Energy (BPA, 1991). These algorithms have been shown to accurately predict EMF levels measured near power lines. The electric fields and magnetic fields were calculated as the resultant of x, y, and z field vectors. The inputs to the program are data regarding voltage, current flow, and phasing of voltages and currents, and conductor configurations as provided by AECOM and Mott MacDonald. These line loadings are summarized below in Table 2 assuming a 2 MVA load for Block Island. Table 2. Cable/circuit data Cable/Circuit From To Voltage (kv) MVA Current (A) Export BIWF BIPCO Switchyard 34.5-32 -536 BITS Local Distribution BIPCO Switchyard BIPCO Property Rhode Island Mainland BIPCO Property 34.5 30 502 4.16 7.5 1040 At locations where the submarine cables are proposed and at the bridge crossing, the circuit phasing was modeled to minimize cancellation of the calculated magnetic field because the orientation of the Export and BITS Cables relative to one another cannot precisely be controlled. For the remaining portions of the route, including the underground portion within duct banks and on the overhead sections entering the Block Island Switchyard, phasing was chosen to provide optimal field cancellation thus minimizing the magnetic fields at a distance of 10 feet (3 meters) or more from the conductors. Deepwater Wind will strive to follow the provided 15

optimal phasing, though this phasing is subject to construction limitations and may need to be changed to accommodate other design or impact considerations. At the bridge crossing on Block Island, the EMF have been modeled in isolation from surrounding structures and it should be noted that improper grounding of the cables, especially along this portion of the route, will lead to additional issues in the operation of the proposed circuits and changes in the levels of produced EMF. Additionally, the electric field from the circuits is assumed to be confined by a metallic shielding sheath which acts to limit the electric field to a region between the central conductor and the metallic sheath. As a conservative modeling assumption, the effects of cable armoring and sheaths were not modeled in the magnetic-field profiles depicted in Figure 9. The conductive sheathing of the AC cables is totally effective in blocking the electric field if the cable is perfectly grounded, but it is only partially effective in reducing the magnetic field outside the cables. A reduction in the magnetic-field level outside the cable is produced by the shunting of the magnetic field by the cable armoring. The effectiveness of the armoring in attenuating the magnetic field is a function of the magnetic permeability of the armoring, i.e., higher permeability will attenuate the magnetic field by shunting. Furthermore, induced eddy currents in conductive sheathing materials will create an opposing magnetic field that partially cancels the magnetic field from the cores. As shown by calculations for a 138-kV AC undersea cable, flux shunting accounted for an almost 2-fold reduction in the magnetic field, with a much smaller reduction attributable to eddy currents (Silva et al., 2006). The results discussed here are therefore upper bounds on the magnetic-field levels expected to be produced by the Project. 16

7 Results and Discussion Calculated magnetic-field profiles on Block Island (Sections 1-4a) are depicted in Figures 9-12 and the calculated electric-field profile where applicable (Sections 3a, 4, 5a) are depicted in Figures 13-15. Table 3 summarizes the maximum calculated magnetic-field level in the vicinity of the cables, as well as the magnetic-field level at distances of 10 feet (3 meters) and 40 feet (12 meters) from the respective centerline of the various sections. Table 4 summarizes the calculated electric field at the same locations and shows that, for each route segment, the electric and magnetic fields produced by the Project are significantly below the ICNIRP and ICES guidelines for EMF exposure detailed in Table 1 above. Table 3. Calculated magnetic field values (mg) in Sections 1-4a Location Route Section -40 ft from center -10 ft from center Max on ROW 10 ft from center 40 ft from center Beach Landing 1 0.8 3.7 4.6 3.7 0.8 1a 0.9 7.7 10.1 7.5 0.9 Duct Bank 2 1.2 12.0 24.8 11.3 1.2 Bridge Crossing Overhead Lines on BIPCO Property 3 0.9 15.1 111.6 14.8 0.9 3a 0.9 14.0 73.5 13.7 0.9 4 6.1 27.9 33.4 27.2 6.1 4a 23.8 113.8 147.9 111.5 23.4 17

Table 4. Calculated electric field values (kv/m) in overhead sections Route Overhead Lines on BIPCO Property Section -40 ft from center -10 ft from center Location Max on ROW 10 ft from center 40 ft from center 4 0.2 0.4 0.4 0.3 0.1 4a 0.2 0.4 0.4 0.3 0.1 On Block Island the magnetic fields are lowest at the shore landings (where the cables are buried deeper and contained in the 3-core cable), and are somewhat higher when buried in the underground duct banks. The maximum calculated magnetic field in Sections 1-2 is 24.8 mg, falling off to 12 mg or less at 10 feet (3 meters) from the centerline and below 1.2 mg at distances of 40 feet (12 meters) or more from the centerline. In Sections 3 and 3a where the circuits cross beneath the bridge on Block Island, the magneticfield levels are higher but are still well below limits recommended by ICNIRP and ICES. Above the bridge, the maximum magnetic field is 73.5 mg which falls to 14 mg or less at a distance of 10 feet (3 meters) from the centerline and below 0.9 mg at distances of 40 feet (12 meters) or more. Below the bridge, the maximum magnetic field is 111.6 mg which falls to 15.1 mg or less at a distance of 10 feet (3 meters) from the centerline and falls below 0.9 mg at distances of 40 feet (12 meters) or more from the centerline. Where the circuits are run overhead entering BIPCO Property, the magnetic-field levels are somewhat higher than in the buried portions of the route. In Section 4, the proposed overhead transmission lines entering BIPCO Property are calculated to produce a maximum magnetic field of 33.4 mg which falls to 27.9 mg or lower at a distance of 10 feet (3 meters) from the centerline and to 6.1 mg or less at distances of 40 feet (12 meters) or more. Inside BIPCO Property, where the two circuits are joined by the local distribution circuit the maximum calculated magnetic field is 147.9 mg. At a distance 10 feet (3 meters) from the centerline, the magnetic fields fall to 113.8 mg or less and at 40 feet (12 meters) from the centerline, the magnetic fields fall to 23.8 mg or less. The electric field in these two sections is calculated to have a maximum value of 0.4 kv/m which falls to 0.2 kv/m or less at 40 feet (12 meters) from the centerline. 18

The intensity of both electric fields and magnetic fields diminishes with increasing distance from the source; for example, higher EMF levels are measured close to the conductors of distribution and transmission lines and generally decrease with distance from the conductors in proportion to the square of the distance, as illustrated by the calculated field levels in Table 3 and Table 4. The analysis in this report evaluates EMF associated with the operation of the Export and BITS Circuits on Block Island. Analysis of the submarine portion of the BIWF and BITS projects is detailed in a separate report. The upland portion of the report, including Alternative 1 at Narragansett and Alternative 2 near the URI Bay Campus, is currently underway and will be detailed in a supplemental report. At each of these locations, the operational voltage and loading of the BITS Circuit will be modeled as 34.5 kv and 30 MVA, as was done in support of the BIWF Export Cable and BITS on Block Island in this report. As such, the expected magnetic-field level for the transition from the submarine to terrestrial portion of the route will be comparable to or lower than those presented in this report. For underground routing of the BITS Circuit in both alternatives, it is expected that the produced magnetic fields will be somewhat higher than those presented in this report (but still well below those found at the bridge crossing) because only the BITS circuit will be present and will not have the benefit of mutual cancellation of fields from the Export Circuit. Where the BITS Circuit may transition to overhead structures, the resultant EMF will be strongly affected by surrounding circuits (as shown in Section 4a) and it may be desired to choose the BITS circuit phasing to minimize the fields.. 19

8 Conclusions Since electricity is such an integral part of our infrastructure (e.g., transportation systems, homes, and businesses), people living in modern communities are surrounded by sources of EMF. Figure 16 depicts typical magnetic-field levels measured in residential and occupational environments, compared to levels measured on or at the edge of transmission line rights-of-way. While magnetic levels decrease with distance from the source, any home, school, or office tends to have a background magnetic level as a result of the combined effect of the numerous EMF sources. In general, the background magnetic-field level as estimated from the average of measurements throughout a house away from appliances is often between 1-2 mg, while levels can be hundreds of mg in close proximity to appliances. Comparing Figure 16 to Table 3, the calculated magnetic-field levels in the vicinity of terrestrial portions of the project are comparable in magnitude to the magnetic-field levels encountered in the vicinity of distribution lines and in workplaces. The highest potential magnetic field due to the BITS and Export Circuits outside the BIPCO property occurs at the 45-foot (14-meter) bridge crossing on Block Island. The calculated magnetic fields at this location is less than 1/15 th of those recommended by international healthbased standards (ICES and ICNIRP) and are comparable to fields that may be found in homes next to major appliances. Where the Circuits are run overhead outside the BIPCO Property the electric field levels are less than 1/10 th of recommended exposure limits and magnetic field levels are about 1/15 th of the recommended exposure limits.. For the underground portion of the route, the most intense magnetic fields generated by the project will be roughly comparable to those found beneath local distribution lines which run along most city streets and are less than 1/80 th of the exposure limits recommended by the ICES and ICNIRP. 20

Figure 9. Calculated magnetic field at Sections 1 and 1a on Block Island. Figure 10. Calculated magnetic field at Section 2 on Block Island. 21

Figure 11. Calculated magnetic field at Sections 3 and 3a on Block Island. Figure 12. Calculated magnetic field at Section 4 on Block Island. 22

Figure 13. Calculated magnetic field at Section 4a on Block Island. 23

Figure 14. Calculated electric field at Section 4 on Block Island. Figure 15. Calculated electric field at Section 4a on Block Island. 24

Figure 16. Electric and magnetic field levels in the environment. 25

9 References International Commission on Non-ionizing Radiation Protection (ICNIRP). ICNIRP Statement Guidelines for limiting exposure to time-varying electric and magnetic fields (1 Hz to 100 KHz). Health Phys 99:819-816, 2010. International Committee on Electromagnetic Safety (ICES). IEEE Standard for Safety Levels with Respect to Human Exposure to Electromagnetic Fields 0 to 3 khz C95. 6-2002. Piscataway, NJ: IEEE, 2002. Nexans Norway AS (Nexans). State of the art and latest technology developments in HVAC transmission. In presentation: Offshore Wind Farms China 2010, presented at Bergen, Norway, 15th March 2010, p 12 of 30. Accessed December 9, 2011 at http://www.norway.cn/pagefiles/391359/nexans%20-%20olivier%20angoulevant.pdf Silva JM. EMF Study: Long Island Power Authority (LIPA), Offshore Wind Project, 2006. World Health Organization (WHO). Environmental Health Criteria 238: Extremely Low Frequency (ELF) Fields. Geneva, Switzerland: World Health Organization, 2007. 26

Limitations At the request of Normandeau Associates, Inc. and Tetra Tech, Inc., Exponent conducted specific modeling of components of the electrical environment of the Deepwater Wind Block Island Wind, LLC Block Island Wind Farm (BIWF) and the Deepwater Wind Block Island Transmission, LLC Block Island Transmission System (BITS) projects. Both of the corporate entities associated with the development of the BIWF and BITS projects are wholly owned indirect subsidiaries of Deepwater Wind Holdings, LLC, and for the purposes of this report are collectively referred to as Deepwater Wind. This report summarizes work performed to date and presents the findings resulting from that work. In the analysis, we have relied on geometry, material data, usage conditions, specifications, regulatory status, and various other types of information provided by the client. We have not verified the correctness of this input data as it was not part of the scope of work and rely on the client for the accuracy of the data Although Exponent has exercised usual and customary care in the conduct of this analysis, the responsibility for the design and operation of the project remains fully with the client. The findings presented herein are made to a reasonable degree of engineering and scientific certainty. Exponent reserves the right to supplement this report and to expand or modify opinions based on review of additional material as it becomes available, through any additional work, or review of additional work performed by others. The scope of services performed during this investigation may not adequately address the needs of other users of this report, and any re-use of this report or its findings, conclusions, or recommendations presented herein are at the sole risk of the user. The opinions and comments formulated during this assessment are based on observations and information available at the time of the investigation. No guarantee or warranty as to future life or performance of any reviewed condition is expressed or implied. 27