001.01 MOBILIZATION LS $34,716.18 007 3/17/2039 001.02 INCIDENTAL LS $23,929.43 019 3/17/2039 001.03 CONSTRUCTION STAKING LS $10,504.39 201 5/9/2013 001.04 REESTABLISH PROPERTY CORNERS EA $496.08 201 5/9/2013 001.06 RAILROAD INSURANCE EA $472.24 12/8/2011 A01.01 CLEARING & GRUBBING, TREES EA $630.43 010 11/27/2012 A03.01 CLEARING & GRUBBING LS $3,727.34 010 5/9/2013 B01.01 REMOVE SANITARY SEWER MAIN LF $6.23 013 5/9/2013 B01.02 REMOVE SEWER SERVICE LINE LF $8.31 013 5/9/2013 B01.03 REMOVE MANHOLE EA $643.68 013 5/9/2013 B01.05 REMOVE & RESET MANHOLE EA $1,435.23 013 9/14/2012 B02.01 REMOVE WATER MAIN LF $136.54 013 5/9/2013 B02.02 REMOVE & SALVAGE FIRE HYDRANT & AUX VALVE EA $449.90 013 2/26/2013 B02.03 REMOVE & SALVAGE FIRE HYDRANT, VALVE AND BOX EA $443.40 013 5/9/2013 B02.05 REMOVE CURB STOP AND BOX EA $112.96 013 5/9/2013 B03.01 REMOVE STORM SEWER MAIN LF $14.25 013 5/9/2013 B03.03 REMOVE & DISPOSE OF CMP EA $705.83 013 2/28/2012 B03.04 REMOVE END SECTION EA $135.13 013 12/8/2011 B03.05 REMOVE & SALVAGE END SECTION EA $314.25 013 8/14/2012 B03.06 REMOVE CONCRETE JUNCTION BOX EA $516.04 013 5/9/2013 B03.08 REMOVE TYPE "B" INLET EA $334.86 013 5/9/2013 B03.09 REMOVE TYPE "E" INLET EA $731.19 013 5/9/2013 B03.10 REMOVE AREA INLET EA $355.75 013 5/9/2013 B04.02 REMOVE CONTAMINATED SOIL CY $41.00 013 5/9/2013 B04.03 REMOVE CONTAMINATED WATER GAL $505.86 013 5/9/2013 B04.04 REMOVE RUBBLE CY $16.15 013 7/31/2012 B04.05 REMOVE SILT FENCE LF $1.24 013 5/9/2013 B05.01 REMOVE GRAVEL SURFACING SY $78.88 013 12/8/2011 B05.02 SAWING, ASPHALT PAVEMENT LF $8.26 013 3/17/2039 B05.03 SAWING, CONCRETE PAVEMENT / CURB & GUTTER LF $5.92 013 4/26/2011 B05.05 EDGE MILL & REMOVE AC PAVEMENT, 2" TO 0" SY $7.56 013 6/8/2012 B05.06 MILL & REMOVE AC PAVEMENT, 2" SY $3.86 013 8/28/2012 B05.07 MILL & REMOVE AC PAVEMENT, FULL DEPTH T $4.76 013 9/14/2012 B05.10 REMOVE AC PAVEMENT SY $7.10 013 5/9/2013 B05.11 REMOVE AC FROM PCC PAVEMENT SY $7.86 013 6/8/2012 B05.12 REMOVE PCC PAVEMENT WITH AC OVERLAY SY $11.29 013 5/9/2013 B05.13 REMOVE PCC PAVEMENT SY $13.16 013 9/25/2012 B05.14 REMOVE PCC APPROACH PAVEMENT SY $40.05 013 11/27/2012 B05.15 REMOVE PCC DRIVEWAY PAVEMENT SY $7.89 013 5/9/2013 B05.17 REMOVE PCC PANEL SY $10.53 013 5/9/2013 B05.18 REMOVE CONCRETE CURB & GUTTER LF $7.19 013 5/9/2013 B05.20 REMOVE CONCRETE DRAIN PAIN EA $40.97 013 11/27/2012 B05.21 REMOVE CONCRETE FILLET EA $12.32 013 8/11/2019 B05.22 REMOVE CONCRETE FILLET & PAN EA $164.90 013 12/8/2011 B05.24 REMOVE MEDIAN DRAIN EA $1.91 013 12/8/2011 B05.25 REMOVE PCC SIDEWALK SF $2.69 013 5/9/2013 B05.26 REMOVE PCC SIDEWALK SY $7.11 013 9/11/2012 B05.27 REMOVE RETAINING WALL LF $47.73 013 5/9/2013 B05.32 REMOVE & REPLACE CONCRETE CURB & GUTTER LF $34.51 013 12/8/2011 B05.35 REMOVE & REPLACE CONCRETE FILLET SY $71.14 013 4/26/2011 B05.37 REMOVE & REPLACE PCC SIDEWALK SF $6.53 013 4/26/2011 B06.01 REMOVE FENCE LF $6.52 013 8/14/2012 B06.02 REMOVE & SALVAGE FENCE LF $9.03 013 7/31/2012 B06.03 REMOVE & RESET FENCE LF $81.65 013 7/31/2012 B06.06 REMOVE & RESET MAILBOX EA $175.72 013 1/10/2012 B06.08 REMOVE TREE EA $791.36 2/26/2013 B07.02 REMOVE LIGHT POLE FOOTING EA $487.39 013 4/26/2011 B08.01 REMOVE PAVEMENT MARKING, STRIPES LF $1.10 013 1/10/2012 B08.04 REMOVE & RESET SIGN EA $108.95 013 11/27/2012 B08.05 REMOVE & SALVAGE SIGN EA $58.86 013 5/9/2013 4/20/2018, Page 1
C01.01 AASHTO T-180 SOIL TEST EA $207.53 011 5/9/2013 C02.01 EXCAVATION, UNCLASSIFIED CY $1,397.63 012 5/9/2013 C02.02 EXCAVATION, UNCLASSIFIED-DIGOUTS W/NATIVE MATERIAL CY $30.97 012 3/17/2039 C02.03 EXCAVATION, UNCLASSIFIED-DIGOUTS W/SUGAR ROCK T $44.13 012 6/18/2012 C02.04 EXCAVATION, UNCLASSIFIED-DIGOUTS W/TYPE 4 ROCK T $35.20 012 7/31/2012 C02.06 EXCAVATION, ROCK (GRADING) CY $48.97 012 5/9/2013 C02.09 EXCAVATION, UNDERCUT CY $10.31 012 5/9/2013 C02.10 EXCAVATION, EXPLORATORY HR $218.70 011 6/15/2011 C02.11 EXCAVATION, EXPLORATORY EA $1,043.78 011 7/31/2012 C03.01 IMPORTED BACKFILL MATERIAL (GRADING) CY $17.67 011 6/14/2011 C03.02 EMBANKMENT/COMPACTED FILL CY $18.00 014 2/28/2012 C03.03 CONTROLLED LOW STRENGTH BACKFILL MATERIAL (GRADING) CY $138.40 200 1/10/2012 C07.01 TOPSOIL, FURNISH & PLACE CY $33.78 017 5/9/2013 C07.02 TOPSOIL, PLACE CY $8.70 017 5/9/2013 C07.03 TOPSOIL, SALVAGE CY $3.48 016 5/9/2013 C07.05 SODDING SY $41.35 073 2/26/2013 C07.07 CO-COMPOST T $43.78 076 1/10/2012 C07.08 TOPSOIL & COMPOST MIXTURE, FURNISH & PLACE CY $35.03 076 2/28/2012 C08.02 SEEDING & FERTILIZING SY $110.79 071 4/26/2011 C08.03 SEEDING, FERTILIZING, & MULCHING SY $133.46 072 2/26/2013 C08.04 SEEDING, FERTILIZING, MULCHING, & IRRIGATION C4 SY $3.09 071 7/31/2012 C09.01 4" UNDERDRAIN LINE LF $8.82 064 5/9/2013 C10.01 4" UNDERDRAIN LINE CLEANOUT / VENT EA $310.81 064 5/9/2013 D01.01 EXCAVATION, ROCK (TRENCH) CY $73.70 011 7/13/2012 D01.02 EXCAVATION, CONTAMINATED (TRENCH) T $18.62 011 11/27/2012 D01.03 COMMON UTILITY TRENCH LF $9.61 011 12/8/2011 D03.01 CONTAMINATED WATER (TRENCH) MGAL $309.32 011 11/27/2012 D04.05 24" 14 G STEEL PIPE CASING LF $119.79 008 4/26/2011 D06.01 SEWER MAIN CONCRETE ENCASEMENT EA $553.74 009 11/27/2012 D06.02 WATER MAIN CONCRETE ENCASEMENT EA $557.51 008 5/9/2013 D07.01 SEWER AND WATER MAIN INSULATION SF $13.43 008 5/9/2013 D08.01 CONTROLLED LOW STRENGTH BACKFILL MATERIAL (TRENCH) CY $108.22 200 5/9/2013 D08.02 IMPORTED BACKFILL MATERIAL (TRENCH) CY $15.45 011 5/9/2013 D09.01 TYPE I BEDDING MATERIAL T $18.74 011 5/9/2013 D09.02 TYPE II BEDDING MATERIAL T $22.00 011 2/26/2013 D10.01 TYPE II FOUNDATION MATERIAL T $19.59 011 5/9/2013 D10.02 TYPE III FOUNDATION MATERIAL T $23.28 011 12/11/2012 D10.03 TYPE IV FOUNDATION MATERIAL T $22.35 011 7/31/2012 E02.01 8" PVC SEWER MAIN ( 0'- 6') LF $29.76 009 9/14/2012 E02.02 8" PVC SEWER MAIN ( 6'- 8') LF $36.15 009 11/27/2012 E02.03 8" PVC SEWER MAIN ( 8'-10') LF $38.38 009 2/26/2013 E02.04 8" PVC SEWER MAIN (10'-12') LF $41.26 009 5/9/2013 E02.05 8" PVC SEWER MAIN (12'-14') LF $48.25 009 9/14/2012 E02.06 8" PVC SEWER MAIN (14'-16') LF $54.12 009 9/14/2012 E02.07 8" PVC SEWER MAIN (16'-18') LF $71.74 009 9/14/2012 E03.03 10" PVC SEWER MAIN ( 8'-10') LF $48.89 009 11/27/2012 E03.04 10" PVC SEWER MAIN (10'-12') LF $48.48 009 5/9/2013 E04.01 12" PVC SEWER MAIN ( 0'- 6') LF $42.02 009 11/27/2012 E04.03 12" PVC SEWER MAIN ( 8'-10') LF $39.03 009 11/27/2012 E04.04 12" PVC SEWER MAIN (10'-12') LF $43.75 009 11/27/2012 E04.05 12" PVC SEWER MAIN (12'-14') LF $44.48 009 9/14/2012 E04.06 12" PVC SEWER MAIN (14'-16') LF $39.62 009 9/14/2012 E04.07 12" PVC SEWER MAIN (16'-18') LF $44.34 009 9/14/2012 E04.08 12" PVC SEWER MAIN (18'-20') LF $54.60 009 9/14/2012 E14.01 4" PVC SEWER SERVICE LINE LF $38.22 009 5/9/2013 E14.02 6" PVC SEWER SERVICE LINE LF $105.98 009 6/15/2011 E14.03 8" PVC SEWER SERVICE LINE LF $44.71 009 7/13/2012 E15.01 STANDARD MANHOLE, 48" EA $2,756.99 009 5/9/2013 E15.02 STANDARD MANHOLE, 60" EA $4,637.59 009 11/27/2012 E17.01 TERMINATION MANHOLE, 48" EA $2,518.18 009 2/26/2013 4/20/2018, Page 2
E18.01 DROP MANHOLE, 48" EA $3,924.55 009 9/14/2012 E18.02 DROP MANHOLE, 60" EA $4,177.58 009 6/15/2011 E19.01 EXTRA MANHOLE DEPTH, 48" VF $219.63 009 5/9/2013 E19.02 EXTRA MANHOLE DEPTH, 60" VF $366.53 009 11/27/2012 E21.01 4" PVC SEWER CLEANOUT EA $227.27 009 5/9/2013 E21.02 6" PVC SEWER CLEANOUT EA $241.14 009 6/15/2011 E23.03 ABANDON MANHOLE EA $702.26 009 11/27/2012 E24.02 CONNECT TO EXISTING SEWER MAIN EA $712.52 009 5/9/2013 E24.03 CONNECT NEW SEWER SERVICE EA $504.72 009 9/14/2012 E24.04 RECONNECT SEWER SERVICE EA $397.48 009 5/9/2013 E24.05 CONNECT TO EXISTING MANHOLE EA $927.34 009 1/10/2012 E27.01 ADJUST MANHOLE RING & COVER EA $762.92 009 3/17/2039 E27.03 RESHAPE MANHOLE INVERT EA $843.11 009 1/10/2012 E28.01 BYPASS PUMPING LS $11,378.66 009 5/9/2013 F01.01 6" PVC WATER MAIN C-900, CLASS 150 LF $38.53 008 5/9/2013 F01.05 8" PVC WATER MAIN C-900, CLASS 150 LF $33.94 008 5/9/2013 F01.07 8" PVC WATER MAIN C-900, CLASS 150, CERTA LOK LF $42.30 008 9/25/2012 F01.13 12" PVC WATER MAIN C-900, CLASS 150 LF $46.35 008 5/9/2013 F01.17 14" PVC WATER MAIN C-905, DR 25 LF $42.27 008 1/10/2012 F01.19 16" PVC WATER MAIN C-905, DR 25 LF $76.91 008 6/15/2011 F01.21 20" PVC WATER MAIN C-905, DR 25 (EXCEPTION REQUIRED) LF $93.48 008 6/15/2011 F06.03 4" 45 DEGREE BEND EA $261.47 008 5/9/2013 F06.07 6" 45 DEGREE BEND EA $338.60 008 5/9/2013 F06.08 6" 90 DEGREE BEND EA $348.03 008 5/9/2013 F06.09 8" 11.25 DEGREE BEND EA $371.75 008 9/25/2012 F06.10 8" 22.5 DEGREE BEND EA $371.90 008 9/25/2012 F06.11 8" 45 DEGREE BEND EA $414.61 008 5/9/2013 F06.12 8" 90 DEGREE BEND EA $447.63 008 5/9/2013 F06.17 12" 11.25 DEGREE BEND EA $765.08 008 5/9/2013 F06.18 12" 22.5 DEGREE BEND EA $755.91 008 5/9/2013 F06.19 12" 45 DEGREE BEND EA $692.83 008 5/9/2013 F06.25 16" 11.25 DEGREE BEND EA $1,199.96 008 7/31/2012 F06.26 16" 22.5 DEGREE BEND EA $1,233.26 008 7/31/2012 F06.27 16" 45 DEGREE BEND EA $1,409.00 008 7/31/2012 F06.28 16" 90 DEGREE BEND EA $1,789.03 008 7/31/2012 F07.04 8" X 8" CROSS EA $839.43 008 2/26/2013 F07.11 12" X 12" CROSS EA $1,748.69 008 5/9/2013 F07.20 16" X 12" CROSS EA $2,274.78 008 6/15/2011 F07.22 16" X 16" CROSS EA $2,848.70 008 7/31/2012 F07.28 20" X 16" CROSS EA $3,754.93 008 6/15/2011 F08.02 6" STANDARD COUPLING EA $320.78 008 4/26/2011 F08.05 12" STANDARD COUPLING EA $509.99 008 6/15/2011 F08.07 16" STANDARD COUPLING EA $1,146.85 008 6/15/2011 F08.09 20" STANDARD COUPLING EA $1,535.79 008 6/15/2011 F09.05 12" TRANSITIONAL COUPLING EA $782.12 008 7/31/2012 F10.02 6" HIGH DEFLECTION COUPLING EA $216.27 008 6/8/2012 F10.03 8" HIGH DEFLECTION COUPLING EA $227.89 008 2/26/2013 F10.05 12" HIGH DEFLECTION COUPLING EA $700.12 008 7/31/2012 F11.01 4" MJ PLUG EA $388.24 008 7/13/2012 F11.02 6" MJ PLUG EA $162.87 008 5/9/2013 F11.03 8" MJ PLUG EA $271.30 008 5/9/2013 F11.05 12" MJ PLUG EA $436.94 008 6/8/2012 F11.07 16" MJ PLUG EA $640.70 008 7/31/2012 F12.02 8" X 4" REDUCER EA $362.10 008 7/13/2012 F12.03 8" X 6" REDUCER EA $351.93 008 5/9/2013 F12.07 12" X 6" REDUCER EA $596.72 008 6/15/2011 F12.08 12" X 8" REDUCER EA $563.44 008 5/9/2013 F12.14 16" X 6" REDUCER EA $793.92 008 6/15/2011 F12.15 16" X 8" REDUCER EA $1,157.64 008 6/15/2011 F12.17 16" X 12" REDUCER EA $915.36 008 7/31/2012 4/20/2018, Page 3
F12.30 20" X 16" REDUCER EA $5,515.93 008 6/15/2011 F13.03 6" X 6" X 6" TEE EA $443.96 008 5/9/2013 F13.04 8" X 8" X 4" TEE EA $478.16 008 6/15/2011 F13.05 8" X 8" X 6" TEE EA $514.97 008 5/9/2013 F13.06 8" X 8" X 8" TEE EA $554.08 008 9/25/2012 F13.11 12" X 12" X 4" TEE EA $757.27 008 5/9/2013 F13.12 12" X 12" X 6" TEE EA $900.24 008 5/9/2013 F13.13 12" X 12" X 8" TEE EA $862.79 008 5/9/2013 F13.15 12" X 12" X 12" TEE EA $1,648.66 008 5/9/2013 F13.16 14" X 14" X 6" TEE EA $1,097.41 008 1/10/2012 F13.21 16" X 16" X 6" TEE EA $1,504.77 008 7/31/2012 F13.22 16" X 16" X 8" TEE EA $1,559.13 008 6/8/2012 F13.24 16" X 16" X 12" TEE EA $1,819.11 008 7/31/2012 F13.26 16" X 16" X 16" TEE EA $2,730.93 008 6/15/2011 F13.34 20" X 20" X 6" TEE EA $2,295.02 008 6/15/2011 F13.37 20" X 20" X 12" TEE EA $2,794.13 008 6/15/2011 F14.02 6" X 6" X 4" TAPPING TEE EA $2,317.64 008 12/8/2011 F14.03 6" X 6" X 6" TAPPING TEE EA $2,942.27 008 12/11/2012 F14.06 8" X 8" X 8" TAPPING TEE EA $3,590.00 008 9/25/2012 F14.30 18" X 18" X 12" TAPPING TEE EA $14,370.61 008 6/8/2012 F14.37 20" X 20" X 12" TAPPING TEE EA $8,455.00 008 5/9/2013 F15.01 4" GATE VALVE W/ BOX EA $939.93 008 5/9/2013 F15.02 6" GATE VALVE W/ BOX EA $1,065.55 008 5/9/2013 F15.03 8" GATE VALVE W/ BOX EA $1,498.15 008 5/9/2013 F15.05 12" GATE VALVE W/BOX EA $2,766.40 008 5/9/2013 F15.06 14" GATE VALVE W/BOX EA $6,017.21 008 1/10/2012 F15.07 16" GATE VALVE W/BOX EA $7,474.15 008 6/8/2012 F17.01 FIRE HYDRANT W/AUX VALVE, BOX & LEAD EA $4,881.38 008 5/9/2013 F18.01 FIRE HYDRANT PROTECTION BOLLARDS EA $412.59 008 6/8/2012 F19.01 FIRE HYDRANT EXTENSION, 6" (EXCEPTION REQUIRED) EA $530.13 008 12/11/2012 F20.01 1" COPPER SERVICE LF $30.17 008 5/9/2013 F20.04 1.5" COPPER SERVICE LF $59.79 008 5/9/2013 F20.07 2" COPPER SERVICE LF $45.54 008 5/9/2013 F21.01 4" PVC WATER SERVICE LF $31.06 008 5/9/2013 F23.01 1" TAPPING SADDLE EA $252.23 008 5/9/2013 F23.02 1.5" TAPPING SADDLE & CORP STOP EA $492.59 008 5/9/2013 F23.03 2" TAPPING SADDLE & CORP STOP EA $422.73 008 5/9/2013 F24.01 1" CURB STOP & BOX EA $317.77 008 5/9/2013 F24.02 1.5" CURB STOP & BOX EA $702.96 008 5/9/2013 F24.03 2" CURB STOP & BOX EA $528.03 008 5/9/2013 F25.01 ABANDON WATER MAIN EA $28,139.34 008 5/10/2011 F25.03 ABANDON VALVE BOX EA $161.33 008 5/9/2013 F26.01 CONNECT TO EXISTING WATER MAIN EA $1,498.77 008 5/9/2013 F26.02 CONNECT NEW WATER SERVICE EA $371.91 008 6/8/2012 F26.03 RECONNECT WATER SERVICE EA $318.34 008 5/9/2013 F27.05 12" WATER MAIN LOWERING EA $14,683.33 008 2/28/2012 F28.03 ADJUST WATER VALVE EA $179.58 008 8/28/2012 F33.01 CATHODIC CONTROL TEST STATION EA $460.03 5/9/2013 F33.03 CATHODIC CONTROL ANODE, 18 LB - ZINC EA $2,656.97 5/9/2013 G01.01 12" RCP, CLASS II LF $42.44 054 12/8/2011 G01.02 12" RCP, CLASS III LF $54.19 054 5/9/2013 G01.05 18" RCP, CLASS II LF $45.15 054 12/8/2011 G01.06 18" RCP, CLASS III LF $46.49 054 5/9/2013 G01.08 24" RCP, CLASS II LF $66.53 054 12/8/2011 G01.09 24" RCP, CLASS III LF $58.62 054 5/9/2013 G01.10 30" RCP, CLASS II LF $71.97 054 4/26/2011 G01.12 36" RCP, CLASS II LF $102.47 054 12/8/2011 G01.16 48" RCP, CLASS II LF $163.79 054 4/26/2011 G02.06 18" RCP, CLASS III, O-RING GASKETED LF $50.39 054 5/9/2013 G02.08 24" RCP, CLASS III, O-RING GASKETED LF $49.30 054 5/9/2013 4/20/2018, Page 4
G06.01 12" RCP FLARED END EA $665.02 054 12/8/2011 G06.03 18" RCP FLARED END EA $792.94 054 2/28/2012 G06.04 24" RCP FLARED END EA $992.00 054 12/8/2011 G06.06 36" RCP FLARED END EA $1,368.79 054 12/8/2011 G12.27 36" RCP 45 DEGREE BEND EA $1,664.35 054 4/26/2011 G24.01 PRE CAST BOX CULVERT LF $681.15 058 2/28/2012 G24.04 CIP BOX CULVERT, END SECTION LF $4,960.00 058 2/28/2012 G26.01 BOX CULVERT UNDERCUT DRAINAGE FABRIC SY $3.57 053 4/26/2011 G26.02 BOX CULVERT UNDERCUT CY $44.87 052 4/26/2011 G27.01 4' X 4' RCP JUNCTION BOX EA $4,602.56 058 5/9/2013 G30.02 ADJUST STORM SEWER MANHOLE RING & COVER EA $636.67 063 8/28/2012 G31.01 TYPE "B" INLET EA $3,108.23 062 5/9/2013 G31.03 TYPE "E" INLET EA $5,051.03 062 4/26/2011 G31.05 AREA INLET EA $3,473.56 062 12/8/2011 G32.01 12" CMP LF $951.15 054 4/26/2011 G32.03 18" CMP LF $79.05 054 8/14/2012 G32.05 24" CMP LF $65.54 054 8/14/2012 G33.03 18" CMP SLOTTED DRAIN LF $181.51 054 4/26/2011 G34.03 18" CMP FLARED END EA $318.43 054 8/14/2012 G38.01 CONNECT TO EXISTING STORM SEWER EA $959.91 054 5/9/2013 G39.01 DRAINAGE FABRIC SY $5.10 202 5/9/2013 H01.01 EROSION AND WATER POLLUTION CONTROL LS $2,705.23 018 2/26/2013 H01.02 EROSION AND WATER POLLUTION CONTROL PLAN LS $2,250.16 018 5/9/2013 H01.03 WATER POLLUTION CONTROL LS $6,569.40 018 8/14/2012 H01.04 WATER FOR DUST CONTROL MGAL $20.72 190 5/10/2011 H02.01 CLASS 1 RIPRAP CY $70.85 065 2/28/2012 H02.03 CLASS 2 RIPRAP CY $67.85 065 7/31/2012 H02.06 CLASS 3 RIPRAP T $44.20 065 4/26/2011 H02.07 CLASS 4 RIPRAP CY $81.26 065 12/8/2011 H02.08 CLASS 4 RIPRAP T $49.46 065 4/26/2011 H03.01 GROUTED RIP-RAP APRON SY $80.71 065 2/28/2012 H05.02 BANK AND CHANNEL PROTECTION GABION CY $257.18 069 12/8/2011 H07.01 EROSION CONTROL BLANKET SY $3.61 146 9/14/2012 H08.01 BONDED FIBER MULCHING SY $1.67 146 4/26/2011 H09.03 GRAVEL FILLED FILTER BAG LF $6.49 066 5/9/2013 H10.01 TURF REINFORCEMENT MAT SY $9.26 146 12/8/2011 H10.02 TURF REINFORCEMENT MAT, SDDOT TYPE 1 SY $8.36 146 2/28/2012 H10.03 TURF REINFORCEMENT MAT, SDDOT TYPE 2 SY $7.29 146 4/26/2011 H12.01 SILT FENCE LF $5.54 146 2/26/2013 H12.03 SILT FENCE, HIGH FLOW LF $6.70 146 12/8/2011 H13.01 ROCK CONSTRUCTION ENTRANCE T $497.33 020 5/9/2013 H13.02 ROCK CONSTRUCTION ENTRANCE EA $311.69 020 2/26/2013 H15.01 9" WATTLES LF $9.74 018 2/26/2013 H15.02 12" WATTLES LF $6.03 018 8/14/2012 H15.03 SEDIMENT FILTER BAGS LF $6.15 018 2/26/2013 H16.01 EROSION CONTROL, INLET PROTECTION EA $155.02 018 3/17/2039 H16.03 EROSION CONTROL, PERIMETER CONTROL LF $471.97 018 5/9/2013 H17.01 CONCRETE WASHOUT AREA EA $844.88 018 2/28/2012 I01.01 AGGREGATE BASE COURSE, 3/4" T $22.90 020 8/28/2012 I01.02 AGGREGATE BASE COURSE, 1" T $26.32 020 2/26/2013 I01.03 AGGREGATE BASE COURSE, 3/4", OVER SOIL SUPPORT FABRIC T $22.92 020 6/8/2012 I01.06 AGGREGATE BASE COURSE T $34.64 020 3/17/2039 I02.01 GRAVEL CUSHION T $32.56 020 5/9/2013 I02.02 GRAVEL SURFACING, PERMANENT T $22.11 020 11/27/2012 I02.03 GRAVEL SURFACING, TEMPORARY T $22.51 020 5/9/2013 I03.01 COVER AGGREGATE T $75.35 037 5/10/2011 I03.04 WOVEN GEOTEXTILE SEPARATOR SY $3.25 202 5/9/2013 I04.01 AC, CLASS E, TYPE 1 PG64-28 T $137.64 032 5/9/2013 I04.03 AC, CLASS G, TYPE 1 PG64-28 T $113.68 033 2/26/2013 I04.04 AC, CLASS G, TYPE 2 PG64-28 T $151.70 033 4/26/2011 4/20/2018, Page 5
I07.03 AC OVERLAY, CLASS G, TYPE 1 PG64-28 T $92.30 033 6/8/2012 I08.03 AC PATCHING, CLASS G, TYPE 1 PG64-28 T $179.12 033 11/15/2011 I11.02 BITUMINOUS TACK COAT GAL $99.00 035 4/26/2011 I11.03 FLUSH SEAL SY $2.33 035 6/18/2012 I11.06 ASPHALT CRACK SEALING LF $1.93 031 4/26/2011 I12.01 ASPHALT COMPACTION TESTS EA $140.54 031 6/18/2012 I13.07 PCC PAVEMENT, 9" REINFORCED SY $107.36 040 11/27/2012 I14.01 PCC APPROACH PAVEMENT, 6" REINFORCED SY $125.72 040 2/26/2013 I14.02 PCC APPROACH PAVEMENT, 7" REINFORCED SY $65.25 040 5/9/2013 I16.01 PCC PAVEMENT, 6" NONREINFORCED SY $45.62 040 11/27/2012 I16.03 PCC PAVEMENT, 7" NONREINFORCED SY $44.80 040 5/9/2013 I16.05 PCC PAVEMENT, 8" NONREINFORCED SY $56.34 040 5/10/2011 I16.09 PCC PAVEMENT, 10" NONREINFORCED SY $71.24 040 1/10/2012 I17.01 PCC APPROACH PAVEMENT, 6" NONREINFORCED SY $65.29 040 2/26/2013 I18.01 PCC DRIVEWAY PAVEMENT 4", NONREINFORCED SY $50.87 040 5/9/2013 I18.02 PCC DRIVEWAY PAVEMENT, 5" NONREINFORCED SY $64.16 040 5/10/2011 I18.03 PCC DRIVEWAY PAVEMENT 6", NONREINFORCED SY $53.37 040 2/26/2013 I19.01 CONCRETE CURB & GUTTER, TYPE B6-6 LF $25.79 061 12/11/2012 I19.03 CONCRETE CURB & GUTTER, TYPE B6-7 LF $22.70 061 5/9/2013 I19.05 CONCRETE CURB & GUTTER, TYPE B6-8 LF $21.42 061 5/10/2011 I19.09 CONCRETE CURB & GUTTER, TYPE B6-10 LF $21.73 061 1/10/2012 I20.01 CONCRETE CURB & GUTTER, TYPE BL6-6 LF $20.60 061 6/8/2012 I20.03 CONCRETE CURB & GUTTER, TYPE BL6-7 LF $18.75 061 5/9/2013 I21.01 CONCRETE "P6" GUTTER LF $18.72 061 11/27/2012 I21.03 CONCRETE "P7" GUTTER LF $16.93 061 5/9/2013 I21.09 CONCRETE "P10" GUTTER LF $25.51 061 4/26/2011 I23.01 CONCRETE DRAIN PAN, 4" REINFORCED SY $17.23 061 12/8/2011 I23.02 CONCRETE DRAIN PAN, 6" REINFORCED SY $61.22 061 9/25/2012 I23.03 CONCRETE DRAIN PAN, 6.5" REINFORCED SY $5,209.40 061 9/14/2012 I24.01 CONCRETE FILLET & PAN, 6" REINFORCED SY $66.24 061 2/26/2013 I24.03 CONCRETE FILLET & PAN, 7" REINFORCED SY $85.63 061 5/9/2013 I24.05 CONCRETE FILLET & PAN, 8" REINFORCED SY $86.37 061 5/10/2011 I24.09 CONCRETE FILLET & PAN, 10" REINFORCED SY $103.51 061 4/26/2011 I25.03 PCC PAVEMENT, JOINT SEAL, HOT TAR LF $3.65 114 1/10/2012 I25.04 PCC PAVEMENT, JOINT SEAL, BACKER ROD / SILICONE LF $3.38 114 5/10/2011 I27.02 PCC PAVEMENT, TYPE A SPALL REPAIR SF $80.20 040 9/11/2012 I27.03 PCC PAVEMENT PANEL REPLACEMENT, 8" SY $74.18 040 12/14/2011 I29.01 DOWEL BAR ASSEMBLY LF $12.25 123 5/9/2013 I29.02 DOWEL BAR EA $11.15 123 5/10/2011 I30.02 INSTALL #10 STEEL BAR IN CONCRETE EA $19.61 123 5/9/2013 I30.03 INSTALL #5 STEEL BAR IN CONCRETE EA $15.14 123 5/9/2013 I31.02 INSTALL #10 SMOOTH STEEL BAR IN CONCRETE EA $3.60 123 1/10/2012 I32.01 CONCRETE SIDEWALK, 4" REINFORCED SF $6.71 061 6/8/2012 I32.03 CONCRETE SIDEWALK, 6" REINFORCED SF $7.77 061 11/27/2012 I33.01 CONCRETE SIDEWALK, 4" NONREINFORCED SF $6.94 061 2/26/2013 I33.03 CONCRETE SIDEWALK, 6" NONREINFORCED SF $7.19 061 8/28/2012 I34.05 CONCRETE SIDEWALK, 5", COLORED SF $7.98 061 12/8/2011 I38.01 DETECTABLE WARNING PANEL LF $80.37 061 5/9/2013 I39.01 CONCRETE TYPE C RETAINING WALL (0-2') LF $60.73 061 2/26/2013 I39.02 CONCRETE TYPE C RETAINING WALL (2-4') LF $102.07 061 5/9/2013 J02.01 LANDSCAPE FABRIC SY $3.26 9/25/2012 J03.01 LANDSCAPE ROCK, 1"-2" CLEAN RIVER ROCK T $65.88 9/25/2012 J04.04 6' CHAIN LINK FENCE LF $16.84 6/18/2012 J05.06 10' CHAIN LINK GATE EA $390.00 6/18/2012 J07.01 TYPE 2 ROW FENCE LF $2.83 8/14/2012 J07.02 TEMPORARY FENCE LF $6.52 12/8/2011 J13.01 METAL BENCHES, POWDER COATED EA $1,204.48 5/9/2013 J14.01 TRASH RECEPTACLES, POWDER COATED EA $1,163.96 5/9/2013 J15.01 BICYCLE RACKS, POWDER COATED EA $770.73 5/9/2013 J17.01 TREE GRATE EA $2,498.60 5/9/2013 4/20/2018, Page 6
J18.01 TREE TRIMMING LS $535.00 5/9/2013 J19.01 TRANSPLANT TREE W/44" SPADE EA $428.48 075 12/8/2011 J20.01 DECIDUOUS TREE (1-2" CAL) EA $191.86 074 12/8/2011 J20.02 DECIDUOUS TREE (2-3" CAL) EA $531.57 074 5/9/2013 J21.01 EVERGREEN TREE (4') EA $370.53 074 12/8/2011 J22.01 BUSHES (1-2 GAL) EA $56.70 074 9/14/2012 J23.01 IRRIGATION SYSTEM LS $14,124.45 12/8/2011 J24.01 IRRIGATION LINE, 3/4" PVC LF $1.68 12/8/2011 J24.04 IRRIGATION LINE, 1 1/2" PVC LF $1.95 12/8/2011 J24.07 IRRIGATION LINE, 3" PVC LF $4.91 12/8/2011 J26.02 2" BACKFLOW PREVENTER & 2" METER EA $3,200.00 5/9/2013 J31.01 8 STA IRRIGATION CONTROLLER EA $2,302.78 5/9/2013 K01.01 2" RIGID CONDUIT, SCHEDULE 40 LF $4.58 092 5/9/2013 K01.03 4" RIGID CONDUIT, SCHEDULE 40 LF $6.11 092 12/8/2011 K01.05 2" RIGID CONDUIT, SCHEDULE 80 LF $9.01 092 5/9/2013 K01.06 3" RIGID CONDUIT, SCHEDULE 80 LF $6.53 092 8/14/2012 K02.02 1/C #2 AWG COPPER WIRE LF $2.51 092 5/9/2013 K02.07 1/C #6 AWG COPPER WIRE LF $1.06 092 5/9/2013 K02.08 1/C #8 AWG COPPER WIRE LF $1.07 092 12/8/2011 K02.09 1/C #10 AWG COPPER WIRE LF $0.57 092 5/9/2013 K04.01 2/C #10 COPPER POLE AND BRACKET CABLE LF $9.99 092 5/9/2013 K04.02 #16 AWG COPPER TWIST SHIELDED PAIR LF $0.83 092 5/9/2013 K05.02 13" X 24" NON-METALLIC JUNCTION BOX EA $482.23 092 5/9/2013 K11.01 2' DIAMETER FOOTING LF $142.64 092 5/9/2013 K13.01 ELECTRICAL SERVICE EQUIPMENT EA $8,105.25 092 5/9/2013 K17.04 PEDESTRIAN PUSH BUTTON POLE EA $986.24 092 5/9/2013 K18.01 PREFORMED DETECTOR LOOP EA $701.69 092 5/9/2013 K19.01 RELOCATE SIGNAL EQUIPMENT LS $569.02 092 5/9/2013 K19.03 RELOCATE LIGHT POLE EA $1,185.78 092 4/26/2011 L01.01 PAVEMENT MARKING PAINT, 4" WHITE LF $1.20 093 5/9/2013 L01.02 PAVEMETN MARKING PAINT, 8" WHITE LF $1.33 093 8/14/2012 L01.03 PAVEMENT MARKING PAINT, 12" WHITE LF $2.92 093 8/28/2012 L01.05 PAVEMENT MARKING PAINT, 24" WHITE LF $3.67 093 8/28/2012 L01.06 PAVEMENT MARKING PAINT, ARROW, WHITE EA $101.97 093 8/28/2012 L01.07 PAVEMETN MARKING PAINT, MESSAGE, WHITE WORD $81.49 093 12/8/2011 L02.01 PAVEMENT MARKING PAINT, 4" YELLOW LF $0.73 093 9/11/2012 L03.01 COLD APPLIED PLASTIC PAVEMENT MARKING, 4" LF $292.66 093 5/9/2013 L03.03 COLD APPLIED PLASTIC PAVEMENT MARKING, 12" LF $82.64 093 5/9/2013 L03.05 COLD APPLIED PLASTIC PAVEMENT MARKING, 24" LF $19.06 093 2/26/2013 L03.06 COLD APPLIED PLASTIC PAVEMENT MARKING, ARROW EA $245.36 093 5/9/2013 L04.01 GROOVE FOR COLD APPLIED PLASTIC MARKING, 4" LF $0.76 093 5/9/2013 L04.03 GROOVE FOR COLD APPLIED PLASTIC MARKING, 12" LF $3.46 093 5/9/2013 L04.05 GROOVE FOR COLD APPLIED PLASTIC MARKING, 24" LF $5.76 093 9/11/2012 L04.06 GROOVE FOR COLD APPLIED PLASTIC MARKING, ARROW EA $109.10 093 5/9/2013 L05.01 ROAD SIGN SF $78.72 093 5/9/2013 L05.02 SIGN POST LF $131.64 093 5/9/2013 L05.03 TYPE B ADV WARNING ARROW PANEL EA $442.46 091 9/11/2012 L06.01 TRAFFIC CONTROL LS $7,971.75 090 5/9/2013 L06.02 TRAFFIC CONTROL PLAN LS $994.21 090 11/27/2012 L06.03 FLAGGING HR $24.29 090 6/8/2012 4/20/2018, Page 7