CASE No. 35 of In the matter of

Similar documents
Case No. 109 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member. Maharashtra State Electricity Distribution Co. Ltd.

Maharashtra Electricity Regulatory Commission (Renewable Purchase Obligation, Its. Regulations, 2016 STATEMENT OF REASONS

Case No. 163 of In the matter of

Case Nos. 108 of In the matter of

CASE No. 139 of Coram. Shri. Azeez M. Khan, Member Shri. Deepak Lad, Member. Shri A. W. Mahajan (Rep) ORDER

Before the. Case No. 106 of 2009

Wheeling charges, Banking charges & Cross Subsidy Surcharge for Solar Power Generators

CASE No. 86 of In the matter of. Petition of the Brihanmumbai Electric Supply & Transport Undertaking for revision in Service Connection Charges

TRANSMISSION LICENCE NO. 1 OF 2011 LICENCE FOR TRANSMISSION OF ELECTRICITY IN THE STATE OF MAHARASHTRA

Case Nos. 12 & 48 of 2009

Reliance Infrastructure Limited Reg. Office: H Block, 1 st Floor, Dhirubhai Ambani Knowledge City, Navi Mumbai Website:

Petition No. 1051, 1054 & 1055 of 2015 BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW Date of Order :

Case No. 135 of Coram. Shri.Azeez M. Khan, Member Shri. Deepak Lad, Member. Maharashtra State Electricity Distribution Co. Ltd.

Indian Energy Exchange December For Public Use

UP Electricity Regulatory Commission Vidyut Niyamak Bhawan, Vibhuti Khand, Gomti Nagar, Lucknow. Public Notice

Case No. 88 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member. Maharashtra State Electricity Distribution Co. Ltd. Shri. A.V.

EXTRA ORDINARY 16 AASHAADHA, 1937(S) BIHAR ELECTRICITY REGULATORY COMMISSION

Bihar Electricity Regulatory Commission Vidyut Bhawan, J.L.Nehru Marg, Patna

Sub : In the matter of determination of Parallel Operation Charges. MPERC, Bhopal - Petitioner

KERALA STATE ELECTRICITY REGULATORY COMMISSION Thiruvananthapuram. Present : Sri. T. M. Manoharan, Chairman Sri. K. Vikraman Nair, Member OP 11/2016

Determination of Average Pooled Purchase Cost for FY

CASE No. 114 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member. Maharashtra State Electricity Distribution Co. Ltd.

RPO-REC Framework: Emerging Challenges and way forward. Background Presentation

Policy & Regulatory Issues : Solar & Wind. Shri Rajinder Kumar Kaura CMD, Bergen Group India 21 st August 2014

PUBLIC Law, Chapter 539 LD 1535, item 1, 124th Maine State Legislature An Act To Create a Smart Grid Policy in the State

POWER DEVELOPMENT DEPARTMENT OF JAMMU AND KASHMIR JANIPUR, JAMMU TEL: FAX: PUBLIC NOTICE

NEWFOUNDLAND AND LABRADOR BOARD OF COMMISSIONERS OF PUBLIC UTILITIES AN ORDER OF THE BOARD NO. P.U. 17(2017)

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) APPLICATION

Case No. 141 of Coram. Shri. Azeez M. Khan, Member Shri. Deepak Lad, Member. V/s Maharashtra State Electricity Distribution Co. Ltd.

City of Washington, Kansas Electric Department. Net Metering Policy & Procedure For Customer-Owned Renewable Energy Resources

BEFORE THE FLORIDA PUBLIC SERVICE COMMISSION. The following Commissioners participated in the disposition of this matter:

KERALA STATE ELECTRICITY REGULATORY COMMISSION. NOTIFICATION Dated, Thiruvananthapuram 6 th August,2007

Policy for Net-Metering based Renewable Energy Applications, Madhya Pradesh, DRAFT

Land Transport Rule Traction Engines [2008]

Examinations of Working Places in Metal and Nonmetal Mines. AGENCY: Mine Safety and Health Administration, Labor.

BEFORE THE CANTERBURY REGIONAL COUNCIL. Act 1991 AND. of Plan Change 3 to the Waitaki Catchment Water Allocation Regional Plan

Decision Blaze Energy Ltd. Application for an Exemption under Section 24 of the Hydro and Electric Energy Act.

Case No. 77 of In the matter of

City of, Kansas Electric Department. Net Metering Policy & Procedures for Customer-Owned Renewable Energy Resources

Case No. 164 of Coram. Shri. Anand B. Kulkarni, Chairperson

PRESS NOTE. Distribution Tariff for Maharashtra State Electricity Distribution Company Limited (MSEDCL) applicable with effect from 1 June, 2015

STAFF REPORT ACTION REQUIRED

Department of Market Quality and Renewable Integration November 2016

Toyota Motor North America, Inc. Grant of Petition for Temporary Exemption from an Electrical Safety Requirement of FMVSS No. 305

CMP294: National Grid Legal Separation changes to CUSC Section 14. CUSC Modification Proposal Form

THE CONNECTICUT LIGHT AND POWER COMPANY dba EVERSOURCE ENERGY AND THE UNITED ILLUMINATING COMPANY

Case No.33/2010 AND. DUET India Infrastructure Pvt. Ltd., having its registered office at 815, ITT, Nehru Place, New Delhi

BOOT/OPEX/Pay As You Use Model for Rooftop Solar Projects Workshop on Getting Started on Energy Management & Solar

Docket No EI Date: May 22, 2014

Respondent 1) The Asst. Exe. Engineer, Electrical Sub Division, Pattanakkad

March 17, To: Nelson Hydro Customers

February 10, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

LANCASTER CHOICE ENERGY S BIENNIAL ENERGY STORAGE PROCUREMENT COMPLIANCE REPORT

BEFORE THE GUAM PUBLIC UTILITIES COMMISSION ) ) ) ) ) ) ) ) ORDER INTRODUCTION

Policy for Net-Metering based Renewable Energy Applications, Madhya Pradesh, DRAFT

IN THE HIGH COURT OF NEW ZEALAND CHRISTCHURCH REGISTRY CRI [2015] NZHC 775 ANDREW NIKORA NEW ZEALAND POLICE. N A Pointer for Crown

Regulatory update on implementation of the 0.50% sulphur limit for international shipping

City Title. . Is System Owner interested in being contacted about energy efficiency opportunities at this site? Title. City. Site Contact.

THE ROYAL SOCIETY FOR THE PREVENTION OF ACCIDENTS RoSPA RESPONSE TO THE DRIVING STANDARDS AGENCY CONSULTATION PAPER

August 15, Please contact the undersigned directly with any questions or concerns regarding the foregoing.

Vermont Public Power Supply Authority 2018 Tier 3 Annual Plan

IN THE SUPREME COURT OF INDIA CIVIL ORIGINAL JURISDICTION

Docket No. ER June 2018 Informational Report Energy Imbalance Market Transition Period Report Idaho Power Company

PRESS RELEASE ON 19March, 2018

Starting a franchise business ESTABLISHMENT GUIDE

GC108: EU Code: Emergency & Restoration: Black start testing requirement

STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DE LIBERTY UTILITIES (GRANITE STATE ELECTRIC) CORP. d/b/a LIBERTY UTILITIES

Addressing ambiguity in how electricity industry legislation applies to secondary networks

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

(Text with EEA relevance)

BMW of North America, LLC, Grant of Petition for Decision of. AGENCY: National Highway Traffic Safety Administration (NHTSA),

JAMMU AND KASHMIR STATE POWER DEVELOPMENT CORPORATION LIMITED PUBLIC NOTICE

CITY COUNCIL OF THE CITY OF NOVATO ORDINANCE NO. 1620

WELLINGTON, NEW ZEALAND. PURSUANT to sections 152, 155(a) and (e) and 158(a)(i) of the Land Transport Act 1998

Implementation procedure for certification and continued airworthiness of Beriev Be-200E and Be-200ES-E

Illinois Official Reports

ANNEX MOTOR VEHICLES AND MOTOR VEHICLES' PARTS. Article 1. General Provisions

Case No. 160 of In the matter of

Direct Energy Regulated Services

For personal use only

U.S. Light-Duty Vehicle GHG and CAFE Standards

Guidelines for Solar Grid Power Projects

PUBLIC UTILITIES COMMISSION

Alberta Electric System Operator Saleski Transmission Project Needs Identification Document

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS.

Decision on Merced Irrigation District Transition Agreement

Case No. 112 of In the matter of Application of Tata Power Company Limited for grant of Transmission Licence

Before the FEDERAL COMMUNICATIONS COMMISSION Washington, D.C ) ) ) ) ) ) ) ) ) ) REPLY COMMENTS OF CTIA THE WIRELESS ASSOCIATION

12042/16 MGT/NC/ra DGE 2

Sumitomo Rubber Industries, Ltd., Receipt of Petition for. AGENCY: National Highway Traffic Safety Administration (NHTSA),

SURREBUTTAL TESTIMONY & ATTACHMENTS

2. Background and History of New Jersey s Renewable Portfolio Standards

ENVIRONMENT C RSIA CARBON OFFSETTING AND REDUCTION SCHEME FOR INTERNATIONAL AVIATION IMPLEMENTATION PLAN

POLLUTION PREVENTION AND RESPONSE. Application of more than one engine operational profile ("multi-map") under the NOx Technical Code 2008

Official Journal of the European Union

#14. Evaluation of Regulation 1071/2009 and 1072/ General survey COMPLETE 1 / 6. PAGE 1: Background

BIENNIAL REPORT REGARDING FUEL AND FUEL-RELATED CHARGE ADJUSTMENT PROCEEDINGS FOR ELECTRIC UTILITIES. REQUIRED PURSUANT TO G.S

RECOMMENDATION: It is recommended that the City Council, following a public hearing, adopt the attached resolution which:

GOVERNMENT OF NCT OF DELHI

Implementation Status & Results Bosnia and Herzegovina ROAD INFRASTRUCTURE AND SAFETY PROJECT (P100792)

Transcription:

Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website: www.mercindia.org.in / www. merc.gov.in CASE No. 35 of 2017 In the matter of Petition of Reliance Infrastructure Ltd. (Distribution) to allow cumulative fulfilment of its Renewable Purchase Obligation targets for FY 2016-17 and FY 2017-18 Coram Shri. Azeez M. Khan, Member Shri. Deepak Lad, Member Reliance Infrastructure Ltd. (Distribution) Maharashtra Energy Development Agency Petitioner Impleaded Party Appearance For Petitioner For Impleaded Party For Authorized Consumer Representative : Shri Ghansham Thakkar (Rep.) : None : Dr. Ashok Pendse (Rep), TBIA ORDER Date: 14 July, 2017 1. M/s Reliance Infrastructure Ltd. (Distribution) (RInfra-D), H Block, 1 st Floor, Dhirubhai Ambani Knowledge City, Navi Mumbai, has filed a Petition on 3 March, 2017 citing Regulations 7 and 16 of the MERC (Renewable Purchase Obligation (RPO), its Compliance and Implementation of REC Framework) Regulations, 2016 ( RPO Regulations for allowing the cumulative fulfilment of its RPO for FY 2016-17 and FY 2017-18. 2. RInfra-D s prayers are as follows: a. Allow cumulative fulfillment of Renewable Purchase Obligation target for FY2016-17 and FY2017-18 under Regulation 16 (Power to Relax) of MERC (Renewable Purchase Obligations, its Compliance and Implementation of REC Framework) Regulations 2016... Order in Case No 35 of 2017 Page 1

3. The Petition states as follows: a) Regulation 7.1 of the RPO Regulations specifies the quantum of purchase (in %) by Obligated Entities from Renewable Energy (RE) sources for and non- energy aggregating to a particular percentage for FY 2016-17 onwards upto FY 2019-20: 7 Renewable Purchase Obligation target 7.1 Every Obligated Entity shall procure electricity generated from eligible renewable energy sources at the percentages as per the following schedule: Year Quantum of purchase (in %) from renewable energy sources (in terms of energy equivalent in kwh) Non- (other RE) Total 2016-17 1.00% 10.00% 11.00% 2017-18 2.00% 10.50% 12.50% 2018-19 2.75% 11.00% 13.75% 2019-20 3.50% 11.50% 15.00% b) To fulfill the RPO targets specified for FY 2016-17, RInfra-D has purchased RE ( and non-) from its long term contracts and also purchased non- Renewable Energy Certificates (RECs) to meet its RPO. Based on the estimated Input Energy, the energy available from RE sources for FY 2016-17 and REC purchase till date, there is still a shortfall of 24 MUs and 228 MUs for meeting the and non- RPO, respectively. It had proposed to meet this shortfall by way of purchase of and non- RECs from the Power Exchanges in March, 2017. The summary of the RPO requirement for FY2016-17 is as given below: Non- (Including Mini- Micro Hydro) Estimated Input Energy (MUs) 9020 9020 RPO (%) 1 10 RPO Target (MUs) 90.2 902 Estimated RE Availability (MUs) 67 234 Balance Requirement (MUs) 24 668 REC Purchased as on Feb. 2017 (in equivalent MUs) 0 440 Shortfall as on Feb 17 (MUs) 24 228 c) If the present shortfall is met by purchase of RECs in March, 2017, it would entail a cost of approximately Rs. 42 crore, based on prevailing REC floor price on the Power Exchanges: Order in Case No 35 of 2017 Page 2

Non- (Including Mini- Micro Hydro) RE Shortfall as on Feb 17 (MUs) 24 228 REC Floor Price (Rs/Unit) 3.5 1.5 REC Cost (Rs Crore) 8 34 d) The Central Electricity Regulatory Commission (CERC), by its draft Order dated 28 February, 2017, has proposed a reduction in the Forbearance and Floor prices of and non- RECs to be applicable from 1 April, 2017 and invited comments by 20 March, 2017. The existing and proposed REC prices are as given below: Non- Existing Proposed Existing Proposed Forbearance Price (Rs/REC) 5800 2500 3300 2900 Floor Price (Rs/REC) 3500 1000 1500 1000 e) RInfra-D is yet to purchase 252 MUs ( and non-) equivalent of RECs to meet its RPO target for FY2016-17, which it was proposing to buy in March, 2017. It has complied with its RPO target as specified by the Commission for the prior period upto FY 2015-16. f) If this balance REC requirement is allowed to be purchased in FY2017-18, when REC prices are revised by CERC, it will result in REC purchase cost of Rs 25 Crore as against Rs 42 crore based on the existing REC prices, thereby resulting in a benefit of approximately Rs 17 crore to consumers of RInfra-D: Non- (Including Mini-Micro Hydro) RE Shortfall as on Feb 17 (MUs) 24 228 REC Floor Price-Existing (Rs/Unit) 3.5 1.5 REC Cost at existing price(rs Crore) 8 34 REC Floor Price-proposed (Rs/Unit) 1 1 REC Cost at proposed price(rs Crore) 2 23 Savings (Rs Crore) 6 11 g) The draft Order of CERC is likely to come into effect from 1 April, 2017 and will certainly result in reducing the REC purchase cost and benefit the consumers. h) RInfra-D has already made substantial purchase of RE power and RECs to meet its RPO for FY 2016-17. The Commission may allow it to defer the purchase of the balance requirement of approximately 252 MUs to FY 2017-18 and allow cumulative fulfilment of RPO for FY 2016-17 and FY2017-18 in exercise of its power under Regulation 16 (power to relax) of the RPO Regulations. Order in Case No 35 of 2017 Page 3

4. Vide letter dated 4 March, 2017 requested the Commission for an early hearing since the last REC trading session for FY 2016-17 was scheduled on 29 March, 2017, which was the last opportunity for it to purchase the required to full its RPO target for 2016-17 and avoid Regulatory Charges for non-compliance if its prayer is eventually not granted by the Commission. 5. The proceedings at the hearing held on 16 March, 2017 are summarized as follows: 5.1 RInfra-D reiterated the submissions in its Petition, stating that: (i) In order to fulfill its RPO target for FY 2016-17, RInfra-D has purchased RE under long term contracts and non- RECs. Based on the estimated Input Energy (9020 MUs), considering the RE being procured and REC purchase till date for FY 2016-17, there is still a shortfall at present of 24 MUs and 228 MUs (total 252 MUs) for meeting its and non- RPO, respectively. (ii) The CERC, in its draft Order dated 28 February, 2017, has proposed a downward revision of the Forbearance and Floor prices of and non- RECs from 1 April, 2017. The proposed Floor price is Rs. 1000/ REC. (iii) RInfra-D has complied with its RPO targets upto FY 2015-16. It is yet to purchase the balance 252 MUs ( and non-) equivalent of RECs to meet the RPO target for FY 2016-17, which it was proposing to buy in March, 2017. However, if this balance REC requirement is allowed to be purchased in FY 2017-18 instead of in March, 2017, the REC purchase cost will be much lower, at Rs. 25 crore considering the lower price expected to be finalized by CERC, as against Rs. 42 crore at present REC rates. This would result in a benefit of Rs. 17 crore to consumers of RInfra-D. (iv) In view of the above and in exercise of its power under Regulation 16 to relax the RPO Regulations, the Commission may allow RInfra-D to defer the purchase of the balance requirement of RECs to the extent of approximately 252 MUs to FY 2017-18, and to allow cumulative fulfillment of its RPO for FY 2016-17 and FY 2017-18. (v) The Commission may intimate its decision before 29 March, 2017, which will be the last occasion for purchase of RECs in FY 2016-17, so that RInfra-D can decide by that date the appropriate course of action for RPO compliance. 5.2 Dr. Ashok Pendse, on behalf of Thane-Belapur Industries Association (TBIA), an Authorized Consumer Representative, stated that purchasing RECs at the lower Floor Price expected to be finalized by CERC would be of substantial benefit to the consumers. Hence, the proposal of RInfra-D may be agreed to, and a similar dispensation provided to other Distribution Licensees also. Order in Case No 35 of 2017 Page 4

5.3 As recorded in its Daily Order, the Commission noted that, by its Order dated 28 February, 2017, CERC has sought stake-holder comments on its proposal to fix, from 1 April, 2017, the Floor price at Rs. 1,000/MWh for both and non- REC (as against Rs. 3,500 and Rs. 1,500/MWh, respectively, at present); and the Forbearance prices at Rs. 2,500 for and Rs. 2,900/MWh for non- RECs (as against the existing Rs. 5,800 and Rs. 3,300/MWh, respectively). Thus, CERC has envisaged substantially lower REC prices in FY 2017-18. While these have yet to be finalized, considering the likelihood that they will be significantly lower in FY 2017-18 and the fact that it is already the fag end of FY 2016-17, purchase of RECs now in March, 2017 to meet any remaining RPO shortfall may be considerably more costly for the Distribution Licensees and consequently their consumers (and for other Obligated Entities) than if they could buy RECs for the purpose in FY 2017-18, which commences a few days from now. 5.4 In these circumstances, the Commission considered it appropriate, in exercise of its power under Regulation 16, to relax the provisions of the RPO Regulations while keeping in view the basic purpose of the Regulations, and allowed RInfra-D and the other Distribution Licensees and Obligated Entities to purchase RECs in FY 2017-18 to the extent of any shortfall in RPO compliance as on date, and to consider such purchase towards compliance of their RPO targets upto FY 2016-17. This was recorded in the Commission s Daily Order. Commission s Analysis and Ruling 6. Considering the submissions of RInfra-D and of the Consumer Representative TBIA during these proceedings, the Commission has already allowed RInfra-D and other Obligated Entities, vide its Daily Order dated 16 March, 2017, to purchase RECs in FY 2017-18 to the extent of any shortfall in FY 2016-17 RPO compliance as on that date, and to consider such purchase towards compliance of their RPO targets upto FY 2016-17. This dispensation was provided at the fag end of FY 2016-17 considering the substantial cost benefit likely to accrue to consumers from the expected reduction in REC prices by CERC. 7. The Commission notes that the RPO Regulations, 2016 allow a variation of +/- 5% in the fulfillment of RPO targets in any particular year in exceptional circumstances subject to scrutiny. In the specific case of RInfra-D, considering its estimated Input Energy (MUs) for FY 2016-17 of 9020 MUs (subject to finalization in the forthcoming RPO compliance verification proceedings for that year), the total RPO target is 992.20 MUs, and the stated shortfall of 252 MUs by February, 2017 is well within this band. 8. The Commission provided the dispensation in its Daily Order in relaxation of the RPO Regulations. The Appellate Tribunal for Electricity (ATE) has, in its Judgment dated 20 April, 2015 in O.P. No. 1 of 2013 and others holding that the carry forward of RPO should be restricted when RECs are available and allowed Order in Case No 35 of 2017 Page 5

against RPO, had also observed in that context that the power to relax and the power to remove difficulties under the Regulations should be exercised judiciously and should not be used routinely:...vi) The provisions in Regulations like power to relax and power to remove difficulty should be exercised judiciously under the exceptional circumstances, as per law and should not be used routinely to defeat the object and purpose of the Regulations. The Commission is of the view that the dispensation provided in its Daily Order dated 16 March, 2017 meets these requirements considering the circumstances set out, and would also subserve the interest of consumers without vitiating the object of the Regulations. 9. As had been envisaged, subsequent to the Commission s Daily Order, the CERC substantially reduced the REC prices for FY 2017-18 on 30 March, 2017. However, the Supreme Court stayed the CERC Order on 8 May, 2017 in Civil Appeal No. 6083/2017. While it is true that no time limit for purchase of RECs in FY 2017-18 was stipulated in the Commission s Daily Order, RInfra-D and others would have been expected to exercise due diligence by doing so in the first trading session of FY 2017-18, i.e. in April, 2017, before the Supreme Court stay of 8 May, 2017. For those who did not to do so before that date, the Commission will consider on merits, in the RPO compliance verification of FY 2016-17, the subsequent purchase of RECs against the RPO shortfall as in March, 2017 depending on the outcome of the Supreme Court matter, the REC rates finally decided and other relevant circumstances. The Petition of M/s Reliance Infrastructure Ltd. (Distribution) in Case No.35 of 2017 stands disposed of accordingly. Sd/- (Deepak Lad) Member Sd/- (Azeez M. Khan) Member Order in Case No 35 of 2017 Page 6