NETSSWorks Software: An Extended AC Optimal Power Flow (AC XOPF) For Managing Available System Resources

Similar documents
Electric Power Research Institute, USA 2 ABB, USA

CHAPTER I INTRODUCTION

Guideline for Parallel Grid Exit Point Connection 28/10/2010

ABB POWER SYSTEMS CONSULTING

Feasibility Study Report

Introduction to PowerWorld Simulator: Interface and Common Tools

Voltage Control Strategies for Distributed Generation

Power Consump-on Management and Control for Peak Load Reduc-on in Smart Grids Using UPFC

Interconnection System Impact Study Report Request # GI

NRECA Cooperative Research Network. Modern Grid Initiative Southeast Summit August 10, 2006 Nashville, TN

TRANSMISSION LOSS MINIMIZATION USING ADVANCED UNIFIED POWER FLOW CONTROLLER (UPFC)

The Role of Electricity Storage on the Grid each location requires different requirements

Computation of Sensitive Node for IEEE- 14 Bus system Subjected to Load Variation

CHAPER 5 POWER FLOW STUDY IN THE INTEGRATED GRID NETWORK

Targeted Application of STATCOM Technology in the Distribution Zone

Power System Economics and Market Modeling

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Contingency Analysis

The Power Potential Project A guide to participating

Project #148. Generation Interconnection System Impact Study Report

DSA with wind security tool and automatic curtailment suggestion Siemens AG, EM SG PTI, 2015 All rights reserved

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Power System Economics and Market Modeling

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS

ECE 740. Optimal Power Flow

Benefits of Reducing Electric System Losses

EPRI HVDC Research. Gary Sibilant, EPRI. August 30, 2011

Emerald Reactive Support Alternative Solution Expressions of interest

IEEE SESSION COMPUTER AIDED SMART POWER GRID

Deploying Power Flow Control to Improve the Flexibility of Utilities Subject to Rate Freezes and Other Regulatory Restrictions

Power Potential Guide to Participating : A technical 0 guide to the services for synchronous and non-synchronous DER participants 04/10/2017

Feasibility Study Report

Generator Interconnection System Impact Study For

2015 Grid of the Future Symposium

DIgSILENT Pacific PowerFactory Technical Seminar

INSTALLATION OF CAPACITOR BANK IN 132/11 KV SUBSTATION FOR PARING DOWN OF LOAD CURRENT

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Dynamic Control of Grid Assets

: ANIMATION OF A POWER SYSTEM USING POWERWORLD SIMULATOR

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

Multifunctional transformers and innovative solutions for contingency planning

Initial Field Trials of Distributed Series Reactors and Implications for Future Applications

Ancillary Services & Essential Reliability Services

Interconnection Feasibility Study Report GIP-226-FEAS-R3

RESERVOIR SOLUTIONS. GE Power. Flexible, modular Energy Storage Solutions unlocking value across the electricity network

SIEMENS POWER SYSTEM SIMULATION FOR ENGINEERS (PSS/E) LAB1 INTRODUCTION TO SAVE CASE (*.sav) FILES

PMU-based Wide Area Protection System Concept and application in a large longitudinal system

Management of Congestion in the Deregulated Energy Market

Effects of Smart Grid Technology on the Bulk Power System

CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM

Gateway South Transmission Project

Grid Operations & Planning R&D Area Overview

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA

Utility Distribution Planning 101

Facilitated Discussion on the Future of the Power Grid

SPIDER Modeling Sub-Group DER Modeling, CAISO Experience

Building a 21 st Century Electric Grid. February 23, 2018

Essential Reliability Services From PV Plants

Transmission Planning using Production Cost Simulation & Power Flow Analysis

Dynamic Control of Grid Assets

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Microgrid solutions Delivering resilient power anywhere at any time

Optimal Power Flow (DC-OPF and AC-OPF)

Computer Aided Transient Stability Analysis

3 Reliability Issues and Solutions

BROCHURE. End-to-end microgrid solutions From consulting and advisory services to design and implementation

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC

Feasibility Study Report

New 115 kv Disconnect Switches at Bloomsburg MTS

WESTERN INTERCONNECTION TRANSMISSION TECHNOLGOY FORUM

Sub Regional RTEP Committee Western Region ATSI

IFC Workshop on Distributed Generation, 13 February 2013, Moscow, Russia

LEAP - Life Expectancy Analysis Program For Electrical Rotating Machines. Marcio Gennari ABB Brazil Automation Products Machines Service Osasco

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

Optimising battery energy storage systems operation

Reliability Analysis Update

Hamdy S. K. El-Goharey, Walid A. Omran, Adel T. M. Taha

POWERWORLD SIMULATOR. University of Texas at Austin By: Mohammad Majidi Feb 2014

Energy Systems Operational Optimisation. Emmanouil (Manolis) Loukarakis Pierluigi Mancarella

Veridian s Perspectives of Distributed Energy Resources

C PER. Center for Advanced Power Engineering Research C PER

POWER FLOW SIMULATION AND ANALYSIS

Robust Battery Scheduling in a Micro-Grid with PV Generation Xing Wang, Ph.D. GE Grid Software 2016 March 30, 2016

IEEE-PES Chicago Chapter Presentation November 11, Smart Grid. Mike Born. Principal Engineer, Capacity Planning

Welcome to Breckenridge. T&D Research Stem Meeting Tuesday August 11, :00 5:00 pm

Proposed Solution to Mitigate Concerns Regarding AC Power Flow under Convergence Bidding. September 25, 2009

Galapagos San Cristobal Wind Project. VOLT/VAR Optimization Report. Prepared by the General Secretariat

APPENDIX E: Project Need and Description

Ancillary Services. Horace Horton Senior Market Trainer, Market Training, NYISO. New York Market Orientation Course (NYMOC)

ATTACHMENT Y STUDY REPORT

Generation Increase on Distribution Feeders using Electronic Voltage Regulators

Demand Optimization. Jason W Black Nov 2, 2010 University of Notre Dame. December 3, 2010

Sheffield-Highgate Export Interface SHEI. VSPC Quarterly Meeting October 18, 2017

Electrical Transmission System Analysis EE 456 project. Team Members Abdulaziz Almarzouqi Hamzah Abeer

A Case Study on Aggregate Load Modeling in Transient Stability Studies

Solar PV and Storage Overview

INTRODUCTION. In today s highly complex and interconnected power systems, mostly made up of thousands of buses and hundreds of generators,

100 MW Wind Generation Project

EEEE 524/624: Fall 2017 Advances in Power Systems

ELECTRIC POWER TRANSMISSION OPTIMIZATION

Transcription:

NETSSWorks Software: An Extended AC Optimal Power Flow (AC XOPF) For Managing Available System Resources Marija Ilic milic@netssinc.com and Jeffrey Lang jeffrey.lang@netssinc.com Principal NETSS Consultants EPRI AVC Workshop PJM, Norristown, PA May 19, 2011

The need for on-line system management Regularly adjust available resources (generation outputs, T&D equipment) as system conditions change (equipment status and/or demand) Instead of optimizing just real power dispatch, use all resources; we have shown this keeps the system more reliable and more efficient Corrective actions become routine Given the power systems complexity this requires software-enabled actions

AC Extended OPF (XOPF) Program An AC XOPF not specific to a single performance objective nor control choice could facilitate such system management (therefore, extended AC OPF). Must be computationally robust to support a variety of performance metrics and decision types. Should identify the key decision variables (controls) in the order of their importance for meeting system objectives. This overcomes the major implementation issue associated with AC OPF.

Features of NETSS AC XOPF One optimization engine with many cost functions Controls include: (1) real generator powers, (2) generator voltages, (3) transformer tap positions (ratio and phase angle), (4) switched-shunt susceptances, (5) DC line powers, and (6) adjustable loads. Each control may be adjusted or kept fixed. Provides sensitivities to identify critical controls. Can examine trade-offs between objective functions.

Optimizations: OPF/OQF/OSF/OLD/MXV Optimizations: Optimize real/reactive/apparent power flow (OPF/OQF/OSF) Optimize load distribution (OLD) Manage extreme voltages (MXV) Optimal branch flows (OBF) Constraints: Conserve real and reactive power at all buses Satisfy voltage limits at all buses Satisfy all real and reactive generation limits Satisfy all thermal limits for lines and transformers Satisfy all control limits (ratio and phase) for transformers Satisfy all control limits for switched shunts and adjustable loads Satisfy all control limits for DC lines Outputs: Optimal generation, bus voltages and other controls System-wide power flow Sensitivities for all constraints Marginal price of electricity at all buses (OPF only)

Typical AC XOPF Uses Improving system efficiency during operation: traditional economic dispatch and transmission loss minimization (OPF); determine minimum necessary reactive power reserve (OQF); optimize demand-side response (OLD); maximize power transfer through interfaces (OBF) Planning studies: import studies and determination of maximum power transfers (OLD); loadability studies for buses and zones (OLD); identify system weaknesses and locate new or improved equipment using sensitivities; assess the economic value of new equipment (All); evaluating the effectiveness of new equipment (All). Improving system reliability: make an infeasible system feasible (All); determine operating practices that meet all system constraints (All); maximizing voltage security by minimizing deviations from unity (MXV); look for voltage problems or minimize voltage outliers (MXV); determine realistic safety margins (All); load shedding to arrest evolving blackouts (OLD).

Experience with Large Scale Systems System Buses Generator Buses AC Lines Xformers DC Lines Switched Shunts I 303 53 359 85 0 0 II 1447 348 2352 507 0 0 III 5249 531 4301 1943 2 320 IV-EMS 2003 371 1921 877 0 31 IV-OPS 7678 761 6505 3221 0 472 The system characteristics are measured after the reduction of breakers. Only variable switched shunts are listed. Typical starting solved power flow case always has voltages outside the acceptable limits. This is not physically implementable, but it is a direct result of power flow runs which do not observe voltage limits. Also, sometimes the real power generation is outside the acceptable limits, as power flow does not check for this.

Voltage Security Method Employ an optimization that quadratically penalizes voltages outside the range of 0.95-1.05 puv. Consider normal operating conditions. First, examine what can be accomplished through real power dispatch alone. Next, examine what can be accomplished by varying all available controls: generator voltages and real power, and transformer settings. Finally, examine what can be accomplished with additional equipment such as controllable shunts. This is a planning exercise, but could ultimately be used for operations.

Voltage Security System II Voltage security under normal conditions. Controls include generator voltages and real power, and transformer settings. Run # Solution Controls Outliers Worst-Case Outliers (Min, Max) [puv] - Original Original. 318 0.891, 1.152 A NETSS Fixed except for real power generation. 65 0.907, 1.096 B NETSS Variable. 38 0.917, 1.069 C NETSS Same as Run B with 240 and 15 MVAR capacitive shunts at buses 282 and 600. 30 0.950, 1.058 Note: System I had no voltage security issues. All voltages as given were within the limits of 0.95-1.05 puv.

Voltage Security System II

Voltage Security System III Voltage security under normal conditions. Controls include generator voltages and real power, transformer settings and DC lines. Run # Solution Controls Outliers Worst-Case Outliers (Min, Max) [puv] - Original Original. 600 0.806, 1.113 D NETSS Fixed except for real power generation. 273 0.810, 1.108 E NETSS Variable. 73 0.810, 1.106 Note that Runs D and E exhibit many bus voltages just outside the desired range of 0.95-1.05 puv. They could be brought within the desired range by using a tighter optimization penalty.

Voltage Security System III

Voltage Security System IV- EMS Voltage security under normal conditions. Controls include generator voltages and real power, and transformer settings in System IV alone. Run # Solution Controls Outliers Worst-Case Outliers (Min, Max) [puv] - Original Original. 17 None, 1.250 20 NETSS Fixed except for real power generation. 5 None, 1.244 21 NETSS Same as Run 20 except for control voltage adjustment at Bus 92. 2 None, 1.244 22 NETSS Variable. 2 None, 1.170 23 NETSS Same as Run 22 with 100 MVAR inductive shunts at buses 434 and 435. 0 None, None Three generators were originally scheduled to control the voltage at Bus 92 to 1.054 puv. These voltage controls were released for Run 21.

Voltage Security System IV- EMS

Loadability Method Employ an optimization that maximizes load within security limits. Use a single load scale factor, as opposed to priorities. (Priorities could be used given local knowledge.) Consider normal operating conditions. First, examine what can be accomplished through real power dispatch alone. Next, examine what can be accomplished by varying all available controls: generator voltages and real power, and transformer settings. Next, identify critical controls. Finally, examine what can be accomplished with new equipment such as controllable shunts. This is a planning exercise.

Loadability System I Loadability under normal conditions. Controls include generator voltages and real power, and transformer settings. Run # Solution Controls Load Increase 26 NETSS Fixed except for real-power generation. 3.4 % 27 NETSS Same as Run 26 except for voltage adjustment at Bus 3917, and a tap adjustment for the transformer at Buses 6310-6313. 6.5 % 28 NETSS Same as Run 27 except for voltage adjustment at Bus 254. 8.2 % 29 NETSS Variable. 15.2 %

Loadability System I

Loadability System I

Loadability System I

Loadability System II Loadability under normal conditions. Controls include generator voltages and real power, and transformer settings. Run # Solution Controls Load Increase F NETSS Fixed except for real-power generation. 0 % G NETSS Variable. 1.1 % H NETSS Same as Run G with the placement of a 75 MVAR capacitive shunt at Bus 113. I NETSS Same as Run G with the placement of a 110 MVAR capacitive shunt at Bus 113 and a 330 MVAR capacitive shunt at Bus 282. 8.4 % 10.9 % J NETSS Same as Run G with the placement of a 150 MVAR capacitive shunt at Bus 113, a 390 MVAR capacitive shunt at Bus 282, and a 70 MVAR capacitive shunt at Bus 341. 24.5 %

Improved Efficiency System IV Run # Solution Controls Generation [MW] Losses [MW] Losses [%] - Original Original 70298 1986 100 5 NETSS Fixed except for real-power generation 70264 1952 98 6 NETSS Variable 70181 1107 56

Minimized Q Needs System IV Run # Solution Controls RSS Reactive Generation [MVAR] Real Generation [MW] - Original Original 1492 30567 13 NETSS Fixed except for real power generation 1418 30500 14 NETSS Same as Run 13 except for voltage adjustments at four buses 15 NETSS Same as Run 14 except for additional voltage adjustments at two buses 1368 30502 1342 30502 16 NETSS Variable 1152 30492

System Contingencies System I III IV- EMS IV- OPS Contingency Description All individual 161-kV lines, and all double 400-kV line combinations Loss of 5 critical lines and shunts 1026 contingencies defined by breaker settings 875 contingencies involving line, transformer and machine outages

Managing Non-time Critical Contingencies systematic voltage adjustment of controllable T&D and generation equipment could be used to ensure that the majority of non-time critical contingencies can be managed on-line correctively rather than preventively. Results - Major opportunities found on all tested systems for making non-feasible contingencies feasible by adjusting voltage controllable equipment - The implication of these demonstrations is that very significant savings in stand-by reserves could be made if this procedure were implemented.

Corrective Actions System I Contingency NETSS Results 161-kV single-line outages (308 cases) All contingencies are feasible except: (1) 24 cases in which radial buses become disconnected, requiring 100% load shedding; and (2) 4 cases which require partial load shedding. 400-kV double-line outages (496 cases) All contingencies are feasible.

Minimum Corrective Actions for Feasibility System I System I System III System IV

Run # Contingency System III Comments» Corrective Actions System III NETSS Results # Outliers - None Base case 600 M #1 Low voltages and insufficient voltage stability Secure voltages (0.95-1.05) excepting original outliers after optimization. N #2 Unstable system Secure voltages (0.95-1.05) excepting original outliers after optimization. O #3 Low voltages and insufficient voltage stability P #4 Low voltages and insufficient voltage stability Q #5 Voltages too low at XXX-500 Secure voltages (0.95-1.05) excepting original outliers after optimization. Secure voltages (0.95-1.05) excepting original outliers after optimization. Secure voltages (0.95-1.05) excepting original outliers after optimization. Voltage at XXX-500 is 1.05. Results are based on variable equipment, 0.95-1.05 pu voltages, and Rate A thermal limits, and using voltage penalty limits of 0.951-1.049 puv. 52 54 52 50 50

Results of Corrective Actions System III

Summary on Large System Studies Representative examples of different optimizations supported by the NETSS AC XOPF have been shown. The effectiveness of optimization sensitivities for identifying key controls has been illustrated. The software converged for all examples, applying minimized load shedding for infeasible systems. The software is fast, typically taking between 30 seconds and several minutes to complete an optimization. GUI supported use of software for selecting performance metrics, decisions, etc.

Summary Demonstrated the ability of NETSS Extended AC OPF (AC XOPF) for deferring new investments-planning TOOL -- Automated computing of the best investment locations by optimizing, instead of based on exhaustive power flow analysis of candidate investments. -- Automated selection of the best hardware type (OLTCs, versus CBs, vs. PARs) Demonstrated the potential of NETSS AC OPF for adjusting key decision variables in the system-- (both real power and voltage, on generators and T&D system) OPERATIONS TOOL Enhanced reliability during normal conditions Enhanced reliability during non-time critical contingencies Enhanced efficiency during normal operations Enabling the grid to adjust to initially non-feasible conditions (partial load shedding, line flow settings in controllable components such as PARs and OLTCs)--LOW HANGING FRUIT RELATED TO SMART GRIDS

Recommendations It is becoming necessary to enable system operators and market makers with system management software capable of exploring many options to manage complex power systems An AC XOPF program which is a carefully designed software not specific to single performance objective or control choice could serve as such enabler In particular, AC XOPF can be used to determine when load shedding is and is not required to maintain system-wide security Voltage dispatch greatly reduces the need for load shedding When load shedding is required, the AC XOPF program can determine the minimum load shedding required to maintain system-wide security

New Problems Solved with AC XOPF Economic and environmental implications of not using AC XOPF -cost of wind and PV integration with and without voltage optimization -managing the system as dirty plants are retired How to align the market and operations objectives Work with industry on using AC XOPF for more frequent adjustments of interface limits; this would have major impact on market efficiency Voltage/reactive power support pricing methods