APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation

Similar documents
APPENDIX E: Project Need and Description

Pacific Gas and Electric Company s Revised 2015 Annual Progress

Pacific Gas and Electric Company s Revised 2016 Annual Progress

APPENDIX E: Project Need and Description

Feasibility Study Report

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation

2018 Annual Progress Report to WECC Pacific Gas and Electric Company

Supplemental Report on the NCTPC Collaborative Transmission Plan

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

The Application of Power Electronics to the Alberta Grid

Interconnection System Impact Study Report Request # GI

PACI RAS Updates. Vahid Madani Pacific Gas and Electric Co. August 2, 2017

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Georgia Transmission Corporation Georgia Systems Operations Corporation

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

ELG4125: Flexible AC Transmission Systems (FACTS)

APPENDIX F: 2012 Request Window Submittals

Interconnection Feasibility Study Report GIP-157-FEAS-R2

Q85 Generation Interconnection

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

System Impact Study Report

Feasibility Study Report

Status of PNM s Completed Transmission Construction Projects 11/30/2017

Project #148. Generation Interconnection System Impact Study Report

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Feasibility Study Report

100 MW Wind Generation Project

APPENDIX F: Project Need and Description

15 Nelson-Marlborough Regional Plan

2018 & 22 Final LCR Study Results Greater Bay Area

Electric Power Delivery To Big Cities

Experience on Technical Solutions for Grid Integration of Offshore Windfarms

Generation Interconnection Facilities Study For

Refurbishment and Life Extension of Existing Facilities in Vermont

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Overview of Flexible AC Transmission Systems

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA (U 39 E)

Dynamic Control of Grid Assets

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1

Project #94. Generation Interconnection System Impact Study Report Revision

Q0044 interconnection at

Targeted Application of STATCOM Technology in the Distribution Zone

Falcon-Midway 115 kv Line Uprate Project Report

Pacific Gas and Electric Company s 2013 Annual Progress Report

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

Request for Payment Instructions Wholesale Distribution Access Tariff (WDAT) Attachment I - GIP

WESTERN INTERCONNECTION TRANSMISSION TECHNOLGOY FORUM

Facilities Study for Alberta to US Available Transfer Capability

POWER SYSTEM OPERATION AND CONTROL USING FACTS DEVICES

March 2017 to June 2017 Preliminary Interconnection Cluster Window System Impact Study 49.9 MW IA-PNM May 2018

Power Quality Solutions STATCOM, 100kVAr to 30MVAr Dynamic reactive power compensation

15 Nelson-Marlborough Regional Plan

PG&E s 2017 Request Window Proposals CAISO 2017/2018 Transmission Planning Process

Sub Regional RTEP Committee Mid-Atlantic

Merchant Transmission Interconnection PJM Impact Study Report. PJM Merchant Transmission Request Queue Position X3-028.

Western Area Power Administration Sierra Nevada Region

Supplement to ISO Transmission Plan. Harry Allen-Eldorado Project Description and Functional Specifications

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Seabrook Substation Reliability Improvement Project

Q196 Generation Interconnection

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

New 115 kv Disconnect Switches at Bloomsburg MTS

Q87 Generation Interconnection

Interconnection System Impact Study Final Report February 19, 2018

Interconnection Feasibility Study Report GIP-369-FEAS-R1

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

APPENDIX G: Contingencies on the ISO System that may Impact Adjacent Systems

Western Area Power Administration Sierra Nevada Region

Pacific Gas and Electric Company TM

ABB FACTS Grid connection of Wind Farms

Large Scale Solar Integration

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Paper ID: EE19 SIMULATION OF REAL AND REACTIVE POWER FLOW ASSESSMENT WITH FACTS CONNECTED TO A SINGLE TRANSMISSION LINE

MILLIGAN SOLAR PROJECT

Generating Unit Model Validation Policy

2019 & 2023 Final LCR Study Results Greater Bay Area

DEMONSTRATION OF ESSENTIAL RELIABILITY SERVICES BY A 300-MW SOLAR PV POWER PLANT

Benefits of HVDC and FACTS Devices Applied in Power Systems

Voltage Sag Mitigation in IEEE 6 Bus System by using STATCOM and UPFC

Essential Reliability Services From PV Plants

Physical Design of a Volt/Var Implementation

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company

IEEE T&D FACTS Panel Session Part II (08TD0140) Wednesday, April 23, 2008

Improvement of Transmission Line Power Transfer Capability, Case Study

TRANSMISSION PLANNING CRITERIA

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Sub Regional RTEP Committee - Southern. August 19, 2011

Dynamic Control of Grid Assets

Cromby Units 1 and 2 and Eddystone Units 1 and 2. Deactivation Study

STATCOM Application to Address Grid Stability and Reliability: Part II. D.J. SHOUP, N.W. TENZA Mitsubishi Electric Power Products, Inc.

INTERCONNECTION FACILITIES STUDY REPORT

ATTACHMENT B - Table 1: LIST OF MANAGEMENT-APPROVED PROJECTS UNDER $50M

List of exemptions from compliance with the Technical Rules granted by Western Power after 1 July 2007

COMPARISON OF STATCOM AND TCSC ON VOLTAGE STABILITY USING MLP INDEX

Black Hills Project Summary

A Review on Reactive Power Compensation Technologies

Transcription:

APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation

Intentionally left blank

F1 Description and Functional Specifications of Proposed Reliability- Driven Round Mountain 500 kv Dynamic Reactive Support F1.1 Description In the 2018-2019 Transmission Plan, the ISO has identified a reliability-driven need for a +/- 500 MVAR dynamic reactive power support connecting in vicinity of the Round Mountain 500 kv substation as depicted below. Figure F1-1: Location of Round Mountain Substation and 500 kv Network Malin Captain Jack Round Mountain Table Mountain Olinda Maxwell Vaca Dixon Tracy Tesla Metcalf Los Banos Moss Landing Gates Diablo Midway Whirlwind Vincent Further review of the engineering detail for the termination of the Round Mountain 500 kv Reactive Project is required due to siting issues at Round Mountain for the project. Board of Governor approval is recommended, and the additional detail will be posted as an addendum to the transmission plan. The functional specification for the project and the competitive procurement process for the project will commence after that has taken place.

F1.2 Functional Specifications Dynamic Reactive Power Support Functional Specification Point of Interconnection: TBD 1 Rated Real Power Output: 0 MW Rated MVAR: +500/-500 MVAR. The entire inductive (absorption) range should be continuously available when the voltage is in the 500 kv 550 kv range and the entire capacitive (injection) range should be available when the voltage is in the 473 kv 540 kv range. Response time: The time required for the output to go from 10% of the final value to 90% of the final value should be less than 100 ms. Nominal Terminal Voltage: 500 kv (typically the bus voltage is at 530 kv) Latest in Service Date: June 1, 2024 Inverter Ride Through Capability: NERC PRC-024 requirements and NERC industry recommendation on momentary cessation 2 Availability and Reliability requirements: Proposed dynamic reactive power support solutions shall be designed for high availability. All proposals shall provide a calculation identifying the designed annual availability of the dynamic reactive support system proposed 1 Further review of the engineering detail for the termination of the Round Mountain 500 kv Reactive Project is required due to siting issues at Round Mountain for the project. Board of Governor approval is recommended, and the additional detail will be posted as an addendum to the transmission plan. The competitive procurement process for the project will commence after that has taken place. 2 https://www.nerc.com/pa/rrm/bpsa/alerts%20dl/nerc_alert_loss_of_solar_resources_during_transmission_disturbance-ii_2018.pdf

F2 Description and Functional Specifications of Proposed Reliability- Driven Gates 500 kv Dynamic Reactive Support F2.1 Description In the 2018-2019 Transmission Plan, the ISO has identified a reliability-driven need for a +/-800 MVAR dynamic reactive power support connecting to the Gates 500 kv bus as depicted below. The reactive device is to be installed in a minimum of two equally-sized blocks independently connected to the 500 kv bus to accommodate maintenance and contingencies of the reactive device. These blocks are to be completely independent of each other and have their own dedicated connections to the bus. There will be no single point of failure between them. The blocks will not share a 500kV breaker and the associated step up transformers will be separated by a blast wall. However, both tie lines can be on the same tower. Figure F2-1: Location of Gates Substation and 500 kv Network

The reactive power support is required to provide continuous dynamic reactive power output over the complete range of the capability (unless the facility experienced a planned or forced outage). It can be one of the following types of devices: SVC (Static VAR Compensator) with Thyristor Switched Capacitors (TSC), STATCOM (Static Synchronous Compensator), or Synchronous Condenser. An appropriately sized and configured inverter associated with a battery storage project could also provide the reactive support. Voltage support requirements would take precedence over any other operation of the battery storage facility. Subsynchronous Resonance (SSR) studies are required to be completed and any identified mitigation shall be implemented as part of this project. The ISO estimates that the proposed reactive power support will approximately cost $210 to $250 million. The project is to be in-service by June of 2024. Figure F2-2 provides a schematic diagram of the current bus configuration in the Gates 500 kv switchyard with the previously approved transmission project and projects identified in the generation interconnection process to facilitate the interconnection of generator interconnection requests in the ISO queue. The project interconnections can enter the Gates substation from either the north or the south side. Figure F2-2: Gates 500 kv switchyard layout GIP ADNU Upgrades Los Banos #3 STA Bank #13 Los Banos #1 STA Bank #12 TPP Project Gates Substation 500 kv 500 kv BUS #2 762 752 742 622 662 652 642 522 612 562 552 542 512 500 kv BUS #1 Q1479 Project Diablo Midway STA Bank #11

F2.2 Functional Specifications Dynamic Reactive Power Support Functional Specification Point of Interconnection: Gates 500 kv bus Rated Real Power Output: 0 MW Rated MVAR: +800/-800 MVAR at the Gates 500 kv bus. The entire inductive (absorption) range should be continuously available when the voltage is in the 500 kv 550 kv range and the entire capacitive (injection) range should be available when the voltage is in the 473 kv 540 kv range. Nominal Terminal Voltage: 500 kv (typically the bus voltage is at 530 kv) Latest in Service Date: June 1, 2024 Inverter Ride Through Capability: NERC PRC-024 requirements and NERC industry recommendation on momentary cessation 3 Availability and Reliability requirements: Proposed dynamic reactive power support solutions shall be designed for high availability. All proposals shall provide a calculation identifying the designed annual availability of the dynamic reactive support system proposed 3 https://www.nerc.com/pa/rrm/bpsa/alerts%20dl/nerc_alert_loss_of_solar_resources_during_transmission_disturbance-ii_2018.pdf