SPP Notification to Construct

Similar documents
SPP Notification to Construct

SPP Notification to Construct

1SPP Notification to Construct. RE: Notification to Construct Approved Reliability Network Upgrades

SPP Notification to Construct

SPP Notification to Construct with Conditions

SPP Notification to Construct with Conditions

SPP Notification to Construct

SPP Notification to Construct

SPP Notification to Construct

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

2013 ANNUAL PROGRESS REPORT

MILLIGAN SOLAR PROJECT

Sub Regional RTEP Committee Mid-Atlantic

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

Merger of the generator interconnection processes of Valley Electric and the ISO;

CUSTOMER/ TWIN ARROWS PROJECT

West Station-West Cañon 115 kv Transmission Project

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82

Kansas Legislature. Briefing for the. March 6, Paul Suskie & Mike Ross

March 7, Subject: Southern California Edison 2011 Annual Progress Report

Market Efficiency Update

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

Sub Regional RTEP Committee South

Appendix D Black Hills Project Summary

Q0044 interconnection at

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

February 8, Southwest Power Pool, Inc. Revisions to SPP Open Access Transmission Tariff to add Schedule 12 Docket No.

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04

Market Efficiency Update

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

FORTISBC INC. PRUDENCY REVIEW KETTLE VALLEY SUBSTATION EXHIBIT A2 5

is attached to and becomes a part of a agreement dated, 20

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1

REGIONAL TRANSMISSION ORGANIZATIONS / INDEPENDENT SYSTEM OPERATORS AND THE ENERGY IMBALANCE MARKET: AN OVERVIEW OF THE PICTURE IN THE WEST

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

State Regulatory Affairs and Local Relations Update. ATC Customer Meeting November 19, 2009

Decision on Merced Irrigation District Transition Agreement

is attached to and becomes a part of a agreement dated, 20,

PREPARED DIRECT TESTIMONY

May 11, Ms. Kavita Kale Executive Secretary Michigan Public Service Commission 7109 West Saginaw Highway Post Office Box Lansing, MI 48909

NORTHEAST NEBRASKA PUBLIC POWER DISTRICT RATE SCHEDULE LP-2 Large Power Service. Effective: For bills rendered on and after January 1, 2014.

Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions.

Re: California Independent System Operator Corporation

Sub Regional RTEP Committee Western Region ATSI

December 3, Southwest Power Pool, Inc., Docket No. ER13- Agreement and Network Operating Agreement

Generation Deactivation Notification Update

Minnesota Biennial Transmission. Zone Meeting 8

NORTHEAST NEBRASKA PUBLIC POWER DISTRICT RATE SCHEDULE LP-2 Large Power Service. Effective: For bills rendered on and after February 1, 2019.

TOT1A: Metering Point Relocation Comprehensive Progress Report (WECC Path 30)

HUB & SPOKE COST ALLOCATION BETWEEN LOAD AND GENERATION. Mike Proctor

STATE OF MINNESOTA BEFORE THE MINNESOTA PUBLIC UTILITIES COMMISSION DOCKET NO. ET6675/CN OAH DOCKET NO REBUTTAL TESTIMONY

ROLLOVER RIGHTS OF LONG TERM FIRM TRANSMISSION SERVICE

Market Efficiency Update

National Grid s 2017 Local Transmission Plan

Reliability Analysis Update

Project #94. Generation Interconnection System Impact Study Report Revision

Falcon-Midway 115 kv Line Uprate Project Report

Re: Comments on the 12/7/09 Dynamic Transfer Stakeholder Meeting

Sub Regional RTEP Committee South

Black Hills Project Summary

Updates and Modifications to Report

Terry Blackwell Page 1 of 5. Education North Carolina State University BS, Electrical Engineering Power Systems emphasis

We are filing these changes now to allow affected third parties sufficient lead time to prepare their systems for this change.

D.P.U A Appendix B 220 CMR: DEPARTMENT OF PUBLIC UTILITIES

WIRES University Overview of ISO/RTOs. Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool

SERTP rd Quarter Meeting

1) Introduction. a) Name of city/utility Utilities Commission, City of New Smyrna Beach

NOVA SCOTIA UTILITY AND REVIEW BOARD

Local Transmission Plan. October 11, 2013 Revised August 25, 2014

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

New Mexico Transmission Expansion Concepts For Wind Resources

2017 Indiana State Infrastructure Report (January 1, 2017 December 31, 2017)

ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT

SERTP rd Quarter Meeting

WestConnect Regional Planning Update

SYSTEM PROTECTION AND CONTROL WORKING GROUP

Southwest Power Pool Network Integration Transmission Service Application

Reliability Analysis Update

Public Service Company of Colorado Transmission Projects Status. CCPG May 5, 2016

Southern California Edison Rule 21 Storage Charging Interconnection Load Process Guide. Version 1.1

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)

Information Packet Kissimmee Utility Authority Customer-Owned Renewable Generation Interconnection And Net Metering Program

Supplemental Report on the NCTPC Collaborative Transmission Plan

STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS PUBLIC UTILITIES COMMISSION IN RE: NEW ENGLAND GAS COMPANY DOCKET NO ANNUAL GAS CHARGE FILING

Umatilla Electric Cooperative Net Metering Rules

SPP OVERVIEW. Mike Ross Senior Vice President, Government Affairs and Public Relations

Local Transmission Plan. Rev. 1: April 2018

DFO STATEMENT OF NEED REPORT

Status of PNM s Completed Transmission Construction Projects 11/30/2017

Proposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in Stakeholder Webconference February 28, 2013

TOTAL PROPOSED CONTRACT PRICE Ring Power Corporation $4,875,951

Chapter 7 - Appendix A

Frequently Asked Questions Trico Proposed Net Metering Tariff Modifications

PUD ELECTRIC SYSTEM INTERCONNECTION

2015 Grid of the Future Symposium

Transcription:

SPP Notification to Construct February 14, 2011 Mr. Alan Derichsweiler Western Farmers Electric Cooperative 701 NE 7th Street Anadarko, OK 73005 RE: Notification to Construct Approved Reliability Network Upgrades Dear Mr. Derichsweiler, Pursuant to Section 3.3 of the Southwest Power Pool, Inc. ( SPP ) Membership Agreement and Attachment O, Section VI, of the SPP Open Access Transmission Tariff ( OATT ), SPP provides this Notification to Construct ( NTC ) directing Western Farmers Electric Cooperative ( WFEC ), as the Designated Transmission Owner, to construct the Network Upgrade(s). On January 25, 2011, the Southwest Power Pool ( SPP ) Board of Directors approved the Network Upgrade(s) listed below to be constructed. New Network Upgrades Project ID: 659 Project Name: Line Reeding - Twin Lakes Switchyard conversion to 138 kv Need Date for Project: 6/1/2012 Estimated Cost for Project: $1,971,000 Network Upgrade ID: 10865 Network Upgrade Description: Convert 7-mile Reeding - Twin Lakes Switchyard 69 kv line to 138 kv. Network Upgrade Specification: Upgrade line to 179 MVA emergency rating. Network Upgrade Justification: To address low voltage at Reeding 69 kv and the Kingfisher area for the loss of the Dover 138/69 kv transformer. Need Date for Network Upgrade: 6/1/2012 1

Estimated Cost for Network Upgrade (current day dollars): $1,971,000 Estimated Cost Source: WFEC Project ID: 673 Project Name: Line Bradley - Lindsay 69 kv Ckt 1 reconductor Need Date for Project: 6/1/2015 Estimated Cost for Project: $3,712,500 Network Upgrade ID: 10879 Network Upgrade Description: Reconductor 11-mile Bradley - Lindsey 69 kv line from1/0 to 336.4 ACSR. Network Upgrade Specification: Upgrade line to 65 MVA emergency rating. Network Upgrade Justification: To address the overload of Bradley - Lindsay 69 kv for the loss of any segment of the Lindsay Switchyard - Paoli 69 kv line. Need Date for Network Upgrade: 6/1/2015 Estimated Cost for Network Upgrade (current day dollars): $3,712,500 Project ID: 846 Project Name: Multi Anadarko - Blanchard - OU SW 138 kv Ckt 1 Need Date for Project: 6/1/2012 Estimated Cost for Project: $15,862,500 Network Upgrade ID: 11116 Network Upgrade Description: Rebuild 2-mile Blanchard - OU Switchyard 69 kv line as 138 kv. Network Upgrade Specification: Upgrade line to 264 MVA emergency rating. Network Upgrade Justification: To address low voltages at Blanchard, OU, Cole and Criner 69 kv buses for loss of the OU SW 138/69 kv transformer. Need Date for Network Upgrade: 6/1/2012 Estimated Cost for Network Upgrade (current day dollars): $1,125,000 2

Project ID: 847 Project Name: Line Wakita - Nash 69 kv Ckt 1 Need Date for Project: 6/1/2011 Estimated Cost for Project: $6,705,000 Network Upgrade ID: 11117 Network Upgrade Description: Upgrade 15-mile Wakita -Nash 69 kv line from 1/0 to 336.4 ACSR. Network Upgrade Specification: Upgrade line to 65 MVA emergency rating. Network Upgrade Justification: To address low voltages at Nash 69 kv and Ringwood 69 kv Substations for the loss of Cleo Corner - Cleo Jct. 69 kv or Cleo Jct. - Ringwood 69 kv. Need Date for Network Upgrade: 6/1/2011 Estimated Cost for Network Upgrade (current day dollars): $6,705,000 Project ID: 1084 Project Name: Line Alva - Freedom 69 kv Ckt 1 Need Date for Project: 6/1/2011 Estimated Cost for Project: $6,243,750 Network Upgrade ID: 11424 Network Upgrade Description: Rebuild 18.5-mile Alva - Freedom 69 kv line from 3/0 to 556.5 ACSR. Network Upgrade Specification: Upgrade line to 89 MVA emergency rating. Network Upgrade Justification: To address low voltages at Buffalo 69 kv and West 69 kv Substations for the loss of Buffalo Bear - Buffalo 69 kv. Need Date for Network Upgrade: 6/1/2011 Estimated Cost for Network Upgrade (current day dollars): $6,243,750 3

Project ID: 1085 Project Name: Line - Criner - Lindsay 69 kv Ckt 1 Need Date for Project: 6/1/2011 Estimated Cost for Project: $50,000 Network Upgrade ID: 11429 Network Upgrade Description: Upgrade relaying at OU Switchyard and Lindsay Switchyard. Close the normally open Criner - Lindsay 69 kv line. Network Upgrade Specification: Upgrade facilities to 89 MVA emergency rating. Network Upgrade Justification: To address low voltages in the Cole area for the loss of the OU 138/69 kv transformer. Need Date for Network Upgrade: 6/1/2011 Estimated Cost for Network Upgrade (current day dollars): $50,000 Estimated Cost Source: WFEC Upgrades with Modifications Previous NTC number: 20085 Previous NTC Issue Date: 2/8/2010 Project ID: 846 Project Name: Multi Anadarko - Blanchard - OU SW 138 kv Ckt 1 Need Date for Project: 6/1/2012 Estimated Cost for Project: $15,862,500 Network Upgrade ID: 11115 Network Upgrade Description: Rebuild 25.2-mile Anadarko - Blanchard 69 kv line as 138 kv. Reason For Change: Modify timing. 2010 STEP identified new RTO Determined Need Date. The previous RTO Determined Need Date was 6/1/2013. Network Upgrade Specification: Upgrade line to 264 MVA emergency rating. Upgrade Justification: To address low voltages at Blanchard, OU, Cole and Criner 69 kv buses for loss of the OU SW 138/69 kv transformer. Need Date for Network Upgrade: 6/1/2012 4

Estimated Cost for Network Upgrade (current day dollars): $14,737,500 Commitment to Construct Please provide to SPP a written commitment to construct the Network Upgrade(s) within 90 days of the date of this NTC, pursuant to Attachment O, Section VI.6 of the SPP OATT, in addition to providing a construction schedule for the Network Upgrade(s). Failure to provide a sufficient written commitment to construct as required by Attachment O could result in the Network Upgrade(s) being assigned to another entity. Mitigation Plan The Need Date represents the timing required for the Network Upgrade(s) to address the identified need. Your prompt attention is required in the formulation and approval of any necessary mitigation plans for the Network Upgrade(s) included in the Network Upgrade(s) if the Need Date is not feasible. Additionally, if it is anticipated that the completion of any Network Upgrade will be delayed past the Need Date, SPP requires a mitigation plan be filed within 60 days of the determination of expected delays. Notification of Commercial Operation Please submit a notification of commercial operation for each listed Network Upgrade to SPP as soon as the Network Upgrade is complete and in-service. Please provide SPP with the actual costs of these Network Upgrades as soon as possible after completion of construction. This will facilitate the timely billing by SPP based on actual costs. Notification of Progress On an ongoing basis, please keep SPP advised of any inability onwfec s part to complete the approved Network Upgrade(s). For project tracking purposes, SPP requires WFEC to submit updates on the status of the Network Upgrade(s) on a quarterly basis in conjunction with the SPP Board of Directors meetings. However, WFEC shall also advise SPP of any inability to comply with the Project Schedule as soon as the inability becomes apparent. All terms and conditions of the SPP OATT and the SPP Membership Agreement shall apply to this Project, and nothing in this NTC shall vary such terms and conditions. 5

Don't hesitate to contact me if you have questions or comments regarding these instructions. Thank you for the important role that you play in maintaining the reliability of our electric grid. Sincerely, Lanny Nickell Vice President, Engineering Phone (501) 614-3232 Fax: (501) 821-3198 lnickell@spp.org cc: Carl Monroe, Katherine Prewitt, Mitchell Williams, Ron Cunningham 6