BC Hydro System 2011 Annual Progress Report

Similar documents
BC Hydro System 2016 Annual Progress Report

BC Hydro System 2017 Annual Progress Report

March 7, Subject: Southern California Edison 2011 Annual Progress Report

2013 ANNUAL PROGRESS REPORT

Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions.

Pacific Gas and Electric Company s Revised 2015 Annual Progress

Facilities Study for Alberta to US Available Transfer Capability

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

Pacific Gas and Electric Company s Revised 2016 Annual Progress

Transmission Planning. WECC 2014 Progress Report. March 14, 2014

welcome to the BC Hydro community open house

2013 ANNUAL PROGRESS REPORT

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director

British Columbia Transmission Corporatlon ("BCTC") Transmission System Capital Plan F2006 to F2015 Amllcation

2018 Annual Progress Report to WECC Pacific Gas and Electric Company

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Appendix D Black Hills Project Summary

Pacific Gas and Electric Company s 2013 Annual Progress Report

TOT1A: Metering Point Relocation Comprehensive Progress Report (WECC Path 30)

Status of PNM s Completed Transmission Construction Projects 11/30/2017

Transmission Planning Attachment K Public Input Meeting

BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada. IEEE PES Meeting July 2014

Black Hills Project Summary

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04

BC HYDRO T&D SYSTEM OPERATIONS SYSTEM OPERATING ORDER 7T 30. NORTH COAST INTERCONNECTION Supersedes 7T-30 issued 07 June 2018

Process Timeline. Area Bubbles. Legend. Problem Area that have been resolved. Recurring Areas from previous System Assessment.

Falcon-Midway 115 kv Line Uprate Project Report

WECC Regional Planning Review. Canada/Pacific Northwest Northern California Transmission Line Project. Technical Analysis Committee Report

The Long-Range Transmission Plan

Public Service Company of Colorado Transmission Projects Status. CCPG May 5, 2016

NOVA Gas Transmission Ltd. Appendix 2: 2013 Facility Status Update (December)

Alternatives for meeting the need for transmission improvement described

HVDC Innovative Technology for Smart Grids and Super Grids. Wilfried Breuer CEO Power Transmission Solutions, Siemens Energy Sector

PSE Attachment K Puget Sound Area Transmission Meeting

Final System Impact Study for. Sierra Pacific Industries 31 MW Generation Project. Mount Vernon, WA. November 16, 2006

Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives. Addendum. San Juan Major Project

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks

South Dakota 890 Study

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation

Gateway South Transmission Project

XXXXX. Kokish River Hydroelectric Project. Interconnection Facilities Study and Project Plan

100 MW Wind Generation Project

Local Transmission Plan. October 11, 2013 Revised August 25, 2014

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

15 Nelson-Marlborough Regional Plan

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection

CITY OF PASADENA APPLICATION FOR PARTICIPATING TRANSMISSION OWNER STATUS

Connection Engineering Study Report for AUC Application: AESO Project # 1674

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Rocky Mountain Power Five Year Study Findings & Kick Off Meeting

ATTACHMENT B - Table 1: LIST OF MANAGEMENT-APPROVED PROJECTS UNDER $50M

Supplemental Report on the NCTPC Collaborative Transmission Plan

Transmission Planning Report

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

BC HYDRO REAL TIME OPERATIONS SYSTEM OPERATING ORDER 7T-35. PEACE 138/230 kv NETWORK OPERATION Supersedes 7T-35 issued 15 June 2017

New 115 kv Disconnect Switches at Bloomsburg MTS

Interconnection System Impact Study Report Request # GI

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

DFO STATEMENT OF NEED REPORT

SPP Notification to Construct

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

ATC Year Asessment Network Project List. Zone 2 switching initiative ASAP*** Operating flexibility Proposed -- --

A 500kV AIS Switchyard Rejuvenation in British Columbia using Hybrids

Updates and Modifications to Report

FINAL FACILITY STUDY. 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1. September 10, 2010

Market Efficiency RTEP Proposal Window

Interconnection Feasibility Study Report GIP-157-FEAS-R2

15 Nelson-Marlborough Regional Plan

Western Area Power Administration

Cromby Units 1 and 2 and Eddystone Units 1 and 2. Deactivation Study

NorthernLights HVDC Project

Pacific Northwest/Canada To Northern California Transmission Feasibility Study

Updates and Modifications to Report

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

Transmission Expansion Advisory Committee

TRANSPOWER PLANS, BUILDS, MAINTAINS AND OPERATES NEW ZEALAND S HIGH VOLTAGE ELECTRICITY TRANSMISSION NETWORK THE NATIONAL GRID.

Twin Cities Minnesota Zone Meeting Xcel Energy. May 11, 2005 Bloomington, MN

Q0044 interconnection at

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82

2017 Interim Area Transmission Review of the New York State Bulk Power Transmission System

ATC Year Assessment Network Project List. MTEP Cost Reason for Change since Previous System Addition

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC

South Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget

Dunvegan Hydroelectric Project. For Glacier Power Limited. Preliminary Interconnection Study

Reliability Analysis Update

FORTISBC INC. PRUDENCY REVIEW KETTLE VALLEY SUBSTATION EXHIBIT A2 5

April 10, Dear Customer:

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)

National Committee Kosovo. SEERC October 2017 Istanbul

TRANSMISSION PLANNING CRITERIA

Ten-year Plan. Figure 1 and Table 1. Each of the facilities shown in the plan is described in greater depth in the last appendix of this report.

Interconnection Feasibility Study

Interconnection System Impact Study

Public Service Company of Colorado Transmission Projects Status. CCPG August 18, 2016

Transcription:

March 1, 2011 Mr. Kyle R. Kohne, Chairman WECC Technical Studies Subcommittee Bonneville Power Administration P.O. Box 491 MS, TPP-OPP-3 Vancouver, WA 98666 Mr. Kent Bolton WECC Technical Staff 155 North 400 West, Suite 200 Salt Lake City, UT 84103-1114 U.S.A. 2011 ANNUAL PROGRESS REPORT In accordance with reporting guidelines by the WECC Planning Coordinating Committee (PCC), please find attached BC Hydro s 2011 Annual Progress Report on significant additions and changes to our system. Please call me at (604) 699-7367 if you have any questions. Sincerely, British Columbia Hydro By Guihua Wang Manager Performance Planning, T&D AIM Phone: (604) 699-7367 Fax: (604) 699-7538 E-mail: Guihua.wang@bchydro.com BC Hydro System 2011 Annual Progress Report Major transmission and generation facilities planned and operated by British Columbia Hydro (BCH) over the next 10-year period from 2011 to 2021 are outlined below. A. Previously Reported Projects: 1. BC-Washington 500 kv Tie- Line Upgrade Scheduled in Service Date: October 2010 1 March 1 2011

A project has been raised to increase the thermal capabilities of the two 500 kv circuits between Ingledow substation in BC and Custer substation in Washington to 3000 A each. A WECC Path Rating process has been initiated for this upgrade. This project was completed. 2. Selkirk Transformer Addition Scheduled in Service Date: September 2011 A new 1,200 MVA 500/230 kv transformer (T4) is being added at the Selkirk 500 kv substation in the South Interior of the province. SEL T4 was energized in December 2010. 3. Ashton Creek Substation Shunt Capacitor Banks Scheduled in Service Date: October 2010 This project, adding two 500 kv 250 MVAr switched shunt capacitor banks in Ashton Creek Substation, is under construction. This project was completed. 4. Series compensation on 500 kv lines from The definition phase for series compensation on the two 500 kv lines between Mica and Nicola has been initiated. The scheduled in-service date is delayed to October 2014. The definition phase for series compensation on two 500 kv lines, one is from Ashton Creek to Selkirk and another one is from Ashton Creek tovassuax in South Interior, has started. The scheduled in-service date is defered to October 2014. 5. New ILM 500 kv Line Scheduled in Service Date: October 2014 The new line is planned to provide incremental transmission transfer capability from the Interior of British Columbia to the load centers in the Lower Mainland. This new 500 kv transmission circuit, 5L83, will be approximately 250 km long and will run between the Nicola and Meridian substations. 5L83 will be 50% series compensated at or near American Creek Capacitor Station. Technical planning studies have been completed and the project is currently undergoing definition phase. 6. Selkirk Substation Shunt Reactor Scheduled in Service Date: September 2010 2 March 1 2011

A 500 kv 123 MVar shunt reactor is being planned for Selkirk 500 kv substation. This project was energized in Feb 2011. 7. Major Generation Addition(> 200 MW) Plant Capacity In Service Date Status Revelstoke G5 500 MW Dec. 2010 (In completed Service) Waneta Expansion 435 MW Mar 2013 In progress East Toba and Montrose Creek Hydroelectric 236 MW Jul 2010 (In service) completed 8. Nicola station reconfiguration Scheduled in Service Date: Oct 2014 A project is planned to reconfigure Nicola station, a critical station that collects power flows from the South Interior before transmitting the power to Lower Mainland, to prevent total lost of the station and increase the reliability of the transfer of power to the Lower Mainland. 9. Cranbrook station to Invermere station Second 230 kv line. Scheduled in Service Date: Defered, in service date is unkown This new transmission line project in the East Kootenay area is planned to reinforce the radial transmission system to serve load in the area reliably. This project is deferred indefinitely, please remove it from this report in the future. 10. Saltery Bay Substation. Scheduled in Service Date: June 1, 2010 This new substation project in Saltery Bay, BC is currently under construction to facilitate interconnection of East Toba/Montrose Creek project. It contains two 150 MVA 230/138 kv transformers, with one new and the other one moving from Malaspina substation. Saltery Bay is located 26 km from Malaspina substation. Also, as part of the project, the line section of 1L48 from Malaspina to Saltery Bay (26 km) will be operated at 230 kv. Presently, the line is operated at 138 kv level, although it was designed for 230 kv. The project was completed. 11. Harewood West Substation. 3 March 1 2011

Scheduled in Service Date: March 31, 2011 This new substation is part of Central Vancouver Island (CVI) re-inforcement project, currently under construction. It taps into the existing 2L123 and 2L128 at Harewood West, with two 300 MVA 230x138 transformers. This project was currently partially completed and has been in service with one transformer since Oct 2010. 12. Invermere to Goldon 230 kv line. Scheduled in Service Date: October 2012 This new 230 kv transmission line project in the upper Columbia Valley area is planned to reinforce the radial transmission system to serve load in the area reliably. The new 230kV line is to be built from INV to Kicking horse substation, with the total length of 120 km. B. Additional Projects (Not Reported Previously): 13. Northwest Transmission Line (NTL) Project. Scheduled in Service Date: December 2013 The proposed approximately 340 km Northwest Transmission Line (NTL) is a 287 kilovolt (kv) transmission line running from Skeena Substation near Terrace to a new substation that would be built near Bob Quinn Lake. This project would provide a reliable supply of clean power to potential industrial developments, as well as remote northwest communities who currently obtain their power from diesel generators. 14. Dawson Creek / Chetwynd Area Transmission (DCAT) Project. Scheduled in Service Date: October 2013 The Dawson Creek / Chetwynd Area Transmission Project (DCAT) consists a two 60 km 230kV lines running from a new 230 / 138 kv substation named Sundance Substation (SLS) to Bear Mountain Terminal (BMT) and a new 138 kv line from BMT to Dawson Creek Substation (DAW). This project would provide additional transmission capacity into the Dawson Creek area to support new unconventional gas production loads. 15. Site C Major Generation Addition. Scheduled in Service Date: Dec 31 2020 The Site C project involves building the third dam on the Peace River in northeast B. There will be six 150 MW generators, with the total capacity of 900 MW. Site C is now in the 4 March 1 2011

regulatory review phase, this phase is expected to take about two years, and it is anticipated that Site C will be available for domestic electricity need by 2020. 16. Transmission Lines from Site C to Peace Canyon. Scheduled in Service Date: Dec. 31 2020 Build two 500 KV lines from Site C to Peace Canyon. 17. Mica G5 and G6 Addition. Scheduled in Service Date: G5 in Oct. 2014, G6 in Oct. 2015 The plan is to build two 500 MW units at the current Mica generation plant. 18. Other Transmission Projects (Urban system upgrade in Vancouver area): Vancouver City Central Transmission Project (230 kv) Scheduled in Service Date: April 2012 Construction of a new substation and new transmission lines. New station: Mount Pleasant Substation New lines: 2L20 (3.4 KM) Cathedral Square to Mount Pleasant 2L44 (4.8 KM) Mount Pleasant to Sperling Fraser valley West Area Reinforcement (230 kv) Scheduled in Service Date: October 2014 Construction of a new substation and new transmission lines. New station: Fleetwood Substation Splitting 2L75 Ingledow to McLellan to 2 lines. New lines: 2L75 (8 KM) Ingledow to Fleetwood 2L81 (8 KM) Fleetwood to McLellan West End Substation (230 kv) Scheduled in Service Date: October 2019 Construction of a new substation and new transmission lines. New station: West End substation Splitting 2L32 Horne Payne to Cathedral Square to 2 lines. 2L32 (7.5 KM) Horne Payne to Murrin 2L30 (1.2 KM) Murrin x Cathedral Square Reterminate 2L31 from Murrin x Cathedral Square to Murrin x West End (3.9 KM) Add new line 2L25 (1.7 KM) Cathedral Square x West End. Metro North Area Reinforcement (230 kv) Scheduled in Service Date: October 2018 5 March 1 2011

1) Reterminate 2L49 from Meridian x Horne Payne to Meridian x Murrin (34 KM) 2) Reterminate 2L50 from Burrard x Murrin to Burrard x Horne Payne (19.5 KM) 3) Add 2 new lines: 2L26 (7.45 KM) Horne Payne x Murrin 2L23 (19.3 KM) Como Lake x Horne Payne 6 March 1 2011