US 67 WIDENING PROJECT From Belt Line Rd. to I-20
History & Background The US 67 improvements from Belt Line Rd to I-20 were originally part of TxDOT s Southern Gateway project, studied as part of the Environmental Assessment that received a Finding of No Significant Impact (FONSI) in 2006. Through public input from the cities of Duncanville and Cedar Hill the project scope was revised in 2015 and was determined to be best built as a separate project. Original project scope included a reversible managed toll lane, current project scope does not include reversible managed toll lanes. 2
Purpose and Need The goal of the US 67 Project is to: Increase Capacity Manage Traffic Congestion Improve Operations and Local Access 3
Project Location US 67 from Belt Line Rd. to I-20 4
Project Overview Project let in May 2017 for a bid amount of $59,011,998. Increase mainlanes from 4 to 6, constructed by widening to the outside of the existing pavement. Reconstructing and relocating additional ramps to facilitate increased operations and local access. Cities of Duncanville and Cedar Hill requested local intersection improvements. The project plans include the following: U-turn bridges at Belt Line Rd. and FM 1382 intersection Various warranted turn lanes and lane re-assignments at intersections Proposed warranted traffic signal at Wintergreen Rd. Construction began September 25, 2017 Anticipated Construction Completion: Fall 2019 Project includes 9 Milestones 5
Typical Sections 6
Proposed Ramp Improvements Belt Line Rd to FM 1382 SB FR widen to accommodate auxiliary lane NB exit to FM 1382 and NB entrance from Belt Line Rd. rebuilt NB FR widen to accommodate auxiliary lane Milestone 1: NB US67 Entrance Ramp from Belt Line 30 Day Max Scheduled to being February 2018 Milestone 1 7
Proposed Ramp Improvements FM 1382 to Pleasant Run Rd NB entrance and exit ramps locations reversed NB FR widen to accommodate auxiliary lane Milestone 2: NB US67 Exit to Pleasant Run 45 Day Max Scheduled to being May 2018 Milestone 2 8
Proposed Ramp Improvements Pleasant Run Rd. to Joe Wilson Rd. Proposed NB entrance from Pleasant Run Rd. Proposed SB exit to Pleasant Run Rd. 9
Proposed Ramp Improvements Joe Wilson Rd. to Wintergreen Rd. NB and SB entrance and exit ramp locations reversed NB FR and SB FR widen to accommodate auxiliary lane Milestone 4: NB US67 Exit to Wintergreen Rd 30 Day Max Scheduled to being September 2018 Milestone 9: SB US67 Exit to Joe Wilson 45 Day Max Scheduled to being October 2018 Milestone 9 Milestone 4 10
Proposed Ramp Improvements Wintergreen Rd. to S. Main Street Proposed NB exit to S. Main Street 11
Proposed Ramp Improvements S. Main St to Danieldale Rd. NB and SB entrance and exit ramp locations reversed NB FR and SB FR widen to accommodate auxiliary lane Milestone 7: SB US67 Exit to Main St. 45 Day Max Scheduled to being March 2018 Milestone 5: NB US67 Exit to Danieldale Rd. 30 Day Max Scheduled to being November 2018 Milestone 7 Milestone 5 12
Proposed Ramp Improvements Danieldale Rd. to Cockrell Hill Rd. NB and SB entrance and exit ramp locations reversed NB FR and SB FR widen to accommodate auxiliary lane Milestone 8: SB US67 Exit to Danieldale Rd 45 Day Max Scheduled to being October 2018 Milestone 6: NB US67 Entrance from Danieldale Rd 30 Day Max Scheduled to being February 2019 Milestone 8 Milestone 6 13
Proposed Ramp Improvements Cockrell Hill Rd. to Wheatland Rd. NB entrance ramp from Cockrell Hill Rd. rebuilt SB exit ramp to Cockrell Hill Rd. rebuilt Milestone 3: NB US67 Exit to Wheatland Rd 75 Day Max Scheduled to being August 2018 Temporary NB Entrance from Cockrell Hill Milestone 3 14
Proposed U-Turn Bridges U-Turn Bridges are proposed at the US 67 intersections with Belt Line Rd. and FM 1382. This should improve operations at the intersections. Will allow free movement of the NB-SB and SB-NB direction at these intersections along the frontage roads. US 67 at Belt Line Rd US 67 at FM1382 15
Proposed Intersection Improvements Right Turn Lane, US 67 SB FR at Belt Line Rd Right Turn Lane, FM 1382 at US 67 NBFR 16
Proposed Intersection Improvements Left Turn Lane, US 67 SB FR at Joe Wilson Rd. 17
Completed Construction Work Phase 1, Stage 1 Installing advance warning signs Installing Barrier and CCA on Mainlanes Completing Work Zone Striping Placing asphalt for traffic detours 18
Construction Look Ahead Current Construction Work: Installing Low Profile Barrier on the frontage roads Installing Drainage Items Widening US67 Main Lanes Excavation work around Belt Line and FM 1382 19
Construction Look Ahead Future Construction Work: Continued excavation work throughout project limits Detour and Pavement for Phase 1 NB Off Ramps: FM1382 & Joe Wilson NB On Ramps: Joe Wilson, Wintergreen Main St Widening Main Lanes of US67 Bridge & Retaining Wall Work Drill Shaft schedule for SB Wheatland, Mauk Branch and Ten Mile Creek Demo & Widening at Wheatland, Mauk Branch and Ten Mile Creek Retaining Wall Work NB & SB Pleasant Run Locations Temporary Shoring MSE Panels Drainage Work 20