Expo Line Community Meeting Quarterly Phase 2 Construction Update Los Angeles February 2015
Meeting Agenda Phase 2 Construction Update Meeting Meeting Purpose and Format Construction Update Expo Bikeway Update Next Steps Open House Session
Meeting Purpose and Format Meeting Purpose and Format The purpose of tonight s meeting is to: Provide an update on construction activity in the City of Los Angeles Share information on the Expo Bikeway Receive input and feedback from the community The format will include a short presentation followed by an interactive Open House session to facilitate dialogue and community input. Please be sure to visit all the stations and: Collect information Ask questions Share your ideas
Expo Line Project Description Phase 2 Expo Line from Culver City to Santa Monica: 6.6 mile corridor 7 new Stations 64,000 Daily Riders by 2030 Estimated Travel Time (Downtown LA to Santa Monica): 46 minutes Estimated Cost: $1.5 billion Final design in now complete Project is 85% complete Major construction started in 2012
Construction Progress Expo Phase 2 Construction Progress at a Glance 2015 Construction Highlights: Station construction is 75% complete All 7 bridges have been completed All 7 stations are under construction Track installation to be completed Spring 2015 Roadway widening work and final paving to be completed Spring
Palms Station Street view from Exposition Boulevard looking west
Westwood/Rancho Park Station Street view from Exposition Boulevard looking east
Expo/Sepulveda Station Street view from Exposition Boulevard looking west
Expo/Bundy Station Street view from Exposition Boulevard looking east
Expo Right of Way (ROW) Construction Progress Construction Update Venice Blvd Sidewalk Installation OCS Wire Regulation near Westwood Blvd Paving at Pico Blvd Curb Installation near Barrington Ave
Construction Activities thru May 2015 Venice Boulevard to Motor Avenue Sidewalk, street light and landscape installation Train control and communications testing Complete street improvements near Bagley Avenue Complete roadway improvements near National/Palms Motor Avenue to Military Avenue Complete roadway improvements at Military Avenue Traffic signal, street light and landscape installation Train control and communications testing Construction Progress Military Avenue to Centinela Avenue Complete roadway improvements at Sepulveda Boulevard and Sawtelle Boulevard Sidewalk, street light and landscape installation Train control and communications testing Bagley Avenue Traffic Signals
Construction Progress Station Progress thru May 2015 Palms Westwood/ Rancho Park Expo/ Sepulveda Canopy, archway and paver installation completed Elevator installation nearing completion On-going electrical and train control systems installation On-going plaza construction Art panel installation Installation of station signage Expo/ Bundy Palms Station Platform Paver Installation
Construction Progress Station Progress thru May 2015 Palms Westwood/ Rancho Park Pavers, archway, canopy and guardrail installation completed Electrical and train control systems installation on-going Kiss-and-Ride and Transit Plaza construction Expo/ Sepulveda Expo/ Bundy Westwood Rancho Park Station Progress
Construction Progress Station Progress thru May 2015 Palms Westwood/ Rancho Park Expo/ Sepulveda Elevator installation nearing completion Electrical and train control systems installation ongoing Canopy, archway and stair installation on-going Utility room construction completed On-going plaza construction Expo/ Bundy Sepulveda Station Plaza Progress
Construction Progress Station Progress thru May 2015 Palms Westwood/ Rancho Park Expo/ Sepulveda Platform foundation work completed Track installation completed Elevator installation nearing completion Electrical and train control systems installation ongoing Canopy and archway installation on-going Utility Room construction Expo/ Bundy Bundy Station Elevator Installation Progress
Bikeway Expo Bikeway Design/Construction Final design is complete Soil grading and excavation Irrigation, drainage systems, and curb and gutter Electrical and lighting conduits Typical Los Angeles Bike Path Design
Construction Timeline Construction Progress and Timeline Construction Timeline 2011 Pre-Construction Activities 2012 Bridge Construction, Utility Relocation and Guideway Excavation, and Soundwalls 2013 2014 2015 Bridge and Station Construction, Utility Relocation, Soundwalls, Track Installation and Street/Roadway Improvements Continue Street/Roadway Improvements, Track Installation, Utility Relocation Station Finishes, Electrical System, and Train Control Continue Street/Roadway Improvements, Landscaping Installation, Systems Testing and Pre-Revenue Operations
Next Steps Next Steps Provide regular updates to stakeholder groups throughout construction Next Quarterly Update Meeting: Summer 2015 September 2014 Los Angeles Quarterly Meeting
Format for Open House Session The room is divided into informational tables where you can: View final renderings of the Phase 2 stations Open House Session Meet with project staff that can address your questions/concerns on issues such as station design, noise impacts, traffic and circulation, and safety Provide your feedback Table #1 Table #2 Table #3 General Project Information and Expo Bikeway Construction Design
Contacts How to Reach Us Project Website: www.buildexpo.org Sign-up on our homepage to be added to the project database and receive notices via email. Project Hotline: 213-922-EXPO (3976) Email: info@buildexpo.org Community Relations Contacts: Torri Hill SRJV Community Relations Manager 310-500-1485 or torri.hill@skanska.com Heather Rozman SRJV Community Relations Coordinator 310-500-1487 or heather.rozman@skanska.com Social Media: www.facebook.com/expoline www.twitter.com/expoline