Status of PNM s Completed Transmission Construction Projects 11/30/2017

Similar documents
Verde Transmission, LLC. Verde Project. System Impact Study Report

New Mexico Transmission System Overview TRANSMISSION SYSTEM OVERVIEW NETWORK OPERATING COMMITTEE

New Mexico Transmission Expansion Concepts For Wind Resources

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM)

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1

Appendix D Black Hills Project Summary

March 2017 to June 2017 Preliminary Interconnection Cluster Window System Impact Study 49.9 MW IA-PNM May 2018

Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

Pacific Gas and Electric Company s Revised 2015 Annual Progress

2018 Annual Progress Report to WECC Pacific Gas and Electric Company

Pacific Gas and Electric Company s Revised 2016 Annual Progress

March 7, Subject: Southern California Edison 2011 Annual Progress Report

Black Hills Project Summary

Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives. Addendum. San Juan Major Project

Updates and Modifications to Report

Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions.

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04

ABB Inc. Public Service Company of New Mexico Broadview Full Buildout Affected PSLF Study

Falcon-Midway 115 kv Line Uprate Project Report

Pacific Gas and Electric Company s 2013 Annual Progress Report

ATTACHMENT B - Table 1: LIST OF MANAGEMENT-APPROVED PROJECTS UNDER $50M

Updates and Modifications to Report

2013 ANNUAL PROGRESS REPORT

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT

100 MW Wind Generation Project

XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS

Greater Albuquerque Area Monthly Housing Trends vs. 2016

Greater Albuquerque Area Monthly Housing Trends vs. 2017

BC Hydro System 2016 Annual Progress Report

APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS

Local Transmission Plan. October 11, 2013 Revised August 25, 2014

Greater Albuquerque Area Monthly Housing Trends vs. 2011

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION

EL PASO ELECTRIC COMPANY SHORT CIRCUIT ANALYSIS FOR XXX S PROPOSED GENERATION INTERCONNECTION

Greater Albuquerque Area Monthly Housing Trends vs. 2014

Cargill Power Markets LLC Transmission Service Study (OASIS # TSR and )

Designated Entity Pre-Qualification Materials. Exelon Corporation

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV

West Station-West Cañon 115 kv Transmission Project

South Dakota 890 Study

December Individual Quality Review Calendar FY 18 FY 19. Mon Tues Wed Thu Fri Sat. Sun METRO1 SAMPLE TO REGION

Tri-State December 2013 Board Meeting

FINAL FACILITY STUDY. 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1. September 10, 2010

Western Area Power Administration

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

BC Hydro System 2017 Annual Progress Report

XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study

Clean Line Energy Partners, LLC. Western Spirit Clean Line 345 kv. System Impact Study

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

EXCEPTIONS TO RELIABILITY RULES Revision 10 August 11, 2017

Inventory Levels - All Prices. Inventory Levels - By Price Range

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY

Inventory Levels - All Prices. Inventory Levels - By Price Range

Illinois State Report

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014

EXCEPTIONS TO RELIABILITY RULES REVISION 4 MAY 8, 2015

North Oregon Coast Area Study. Adam Lint

EXCEPTIONS TO RELIABILITY RULES Revision 11 February 9, 2018

BEFORE THE NEW JERSEY BOARD OF PUBLIC UTILITIES

APPENDIX F: Project Need and Description

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Inventory Levels - All Prices. Inventory Levels - By Price Range

Gateway South Transmission Project

Sub Regional RTEP Committee - Southern. August 19, 2011

SPS Planning Criteria and Study Methodology

BC Hydro System 2011 Annual Progress Report

Supplemental Report on the NCTPC Collaborative Transmission Plan

CITY OF PASADENA APPLICATION FOR PARTICIPATING TRANSMISSION OWNER STATUS

Key to Status Fields in the Project List

APPENDIX E: Project Need and Description

South Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget

MTEP13 SPM #2- Central Region. March 25, 2013

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Proposed New Construction for

Interconnection Feasibility Study Report GIP-157-FEAS-R2

EXCEPTIONS TO NYSRC RELIABILITY RULES

APPENDIX F: 2012 Request Window Submittals

Four Corners Queue Transmission Interconnection Study

National Grid s 2017 Local Transmission Plan

APPENDIX E: Project Need and Description

Sub-Regional RTEP Committee PJM South

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Alberta Electric System Operator Saleski Transmission Project Needs Identification Document

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

SPP Notification to Construct

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)

Market Efficiency RTEP Proposal Window

Sub Regional RTEP Committee Mid-Atlantic

TransWest Express Project

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA PACIFICORP. Direct Testimony of Richard A. Vail

National Grid s 2018 Local Transmission Plan

2020 & 2024 Draft LCR Study Results SDG&E Non-Bulk System. Frank Chen - Regional Transmission Engineer Lead Stakeholder Meeting March 14, 2019

Transcription:

Status of s Completed Transmission Construction Projects Second Tah Ta Hey 115/345 kv Transformer Yah Ta Hey Switching Station On January 9, 2015, filed with the NMPRC under NMPRC Rule 440 information on a project to expand and rebuild the Yah Ta Hey Switching Station and the addition of a breaker in the McKinley 345 kv station. The purpose of this project is to strengthen and expand the transmission system in northwest and New Mexico and ensure reliable service and will mitigate the overloads and low volatege conditions by providing additional transformer capacity consistent with NERC Reliability Standards. This substation was completed in September of 2017. Richmond Switching Station City of Albuquerque On February 13, 2015, filed with the NMPRC under NMPRC Rule 440 information on a project to construct a new 115kV Switching Station north of Menaul Blvd and the Richmond Drive intersection. The purpose of this project is to strengthen and expand the transmission system in northeast and southeast Albuquerque to ensure reliable service and will mitigate the overloads under a single contingency consistent with NERC Reliability Standards. This substation was completed in August of 2017. New 345kV Clines Corners Switching Station Southeast Santa Fe County On April 22, 2016, filed with the NMPRC under NMPRC Rule 440 information on a project to build a new 345kV three (3) Breaker Ring Bus Switching Station. The purpose of this project is to complete required transmission system upgrades in association with the interconnection of a wind farm to the Eastern Interconnect Project ( EIP ) transmission line. This substation was completed in April of 2017 and the wind farm project interconnection was completed in June 2017. Alamogordo Replacement Capacitor Installation Alamogordo Switching Station On November 12, 2014, filed with the NMPRC under NMPRC Rule 440 information on a project to expand the Alamogordo 115 kv bus and to install a replacement 115 kv shunt capacitor bank after the failure and damage of an existing capacitor bank. The replacement capacitor banks are required to maintain compliance with NERC Reliability Standards for the Alamogordo Station. This project was completed in March 2017. Installation of Shunt Reactors 1

Status of s Completed Transmission Construction Projects San Juan 345 kv Switching Station will install one (1) shunt reactor circuit breaker and one (1) specialty shunt reactor switching device at the San Juan 345 kv Switching Station to permit full switching capability of the shunt reactors directly connected to the San Juan-BA 345 kv and to the San Juan-Ojo 345 kv line. The shunt reactor breaker installation on the San Juan-Ojo 345 kv line was completed August 2011. This project was completed in June 2014. Installation of Shunt Capacitors Alamogordo Switching Station, NM On December 21, 2011, filed with the NMPRC under NMPRC Rule 440 information on a project to install two switched 16 Mvar shunt capacitor banks in the existing Alamogordo Switching Station in Otero County, NM to address low voltage conditions under outages of a 115 kv source in to the Alamogordo Switching Station or the Amrad 345/115 kv transformer. The purpose of the project is to improve contingency voltage performance and low voltage conditions under outage conditions. Ojo Transformer Replacement Ojo 345 kv Switching Station On February 29, 2012, filed with the NMPRC under NMPRC Rule 440 information on a project to replace the existing Ojo 345/115 kv transformer located at the Ojo 345 kv Switching Station near Espanola, NM with a new 300 MVA transformer. The transformer will be installed by expanding the existing Ojo 345 kv switching station so that the existing transformer may remain in service throughout the construction process. This project was put into service as of late June 2014. YP Line Clearance Improvements Yah-Ta-Hey Switching Station On August 15, 2014, filed with the NMPRC under NMPRC Rule 440 information on a project for increasing clearance on the Yah-Ta-Hey Pittsburg-Midway 115 kv (YP) transmission line. The project increases the current carrying capability by increasing the structure height to create additional clearance between the line conductor and the ground. The YP line serves load northwest of Gallup. This project was completed in October 2014. Yah-Ta-Hey Switching Station YN Line Clearance Improvements On August 15, 2014, filed with the NMPRC under NMPRC Rule 440 information on a project for increasing clearance on the Yah-Ta-Hey - Coalmine 115 kv (YN) transmission line. The project increases the current carrying capability by increasing the structure height to create additional clearance between the line conductor and the ground. The YN line serves load in the area of Gallup. 2

Status of s Completed Transmission Construction Projects Project was placed into service in December 2014. Rio Puerco-Progress 115 kv Line Northern Rio Rancho On April 23, 2014, filed with the NMPRC under NMPRC Rule 440 information on a project to construct an 8 mile 115 kv line connecting the existing Rio Puerco Switching Station to the Progress 115 kv Substation ( Project ). The purpose of the Project is to insure reliable service to existing customers and to service new customers in northern Rio Rancho. Project was placed into service in December 2014. Amrad-Artesia 345 kv Line Rebuild Chavez, NM On August 15, 2014, filed with the NMPRC under NMPRC Rule 440 information on a project to rebuild a 17 mile section of the existing Amrad to Artesia 345 kv line ( Line ) due to damage as a result of two (2) severe back-to-back ice storms. The Line is operated by El Paso Electric Company ( EPE ) and jointly owned by EPE and. The rebuild of the Line will return the southern NM transmission system to its normal configuration. This Project was completed in April 2015. Installation of Shunt Reactors San Juan 345 kv Switching Station will install one (1) shunt reactor circuit breaker and one (1) specialty shunt reactor switching device at the San Juan 345 kv Switching Station to permit full switching capability of the shunt reactors directly connected to the San Juan-BA 345 kv and to the San Juan-Ojo 345 kv line. The shunt reactor breaker installation on the San Juan-Ojo 345 kv line was completed August 2011. This project has a projected completion date, for the shunt reactor switching device on the San Juan- BA 345 kv line, of the 4 th quarter of 2015. This Project completed in January 2016. 3

Status of s Completed Transmission Construction Projects La Morada Substation NW Albuquerque On November 12, 2014, filed with the NMPRC under NMPRC Rule 440 information on a project to construct a new 115 kv substation in northwest Albuquerque. The substation will serve customers south of Ouray to I-40 and west of Alamogordo Drive, supporting the existing load and expected new growth. The substation will also provide back-up support under contingency situation for St. Joseph, Unser and Volcano Substations. This Project completed in December 2015. Rio Puerco Switching Station Expansion Rio Puerco Switching Station On April 23, 2014 filed with the NMPRC under NMPRC Rule 440 information on a project to expand the existing Rio Puerco 345 kv station to loop-in the Four Corners-West Mesa 345 kv ( FW ) and San Juan-BA 345 kv ( WW ) lines and protection modifications for the existing Rio Puerco series capacitor banks. The expansion will be configured to accommodate the planned addition of Static VAR Compensation (SVC) at Rio Puerco. This project was energized in April 2016 Rio Puerco SVC Rio Puerco Switching Station On April 25, 2014 filed with the NMPRC under NMPRC Rule 440 information on a project to install a Static Var Compensator ( SVC ) within s existing Rio Puerco 345 kv Switching Station boundaries. The SVC project will maximize the import capabilities over s Northern New Mexico transmission Path 48. The purpose of the SVC project is to ensure that s bulk power system will continue to provide reliable service to customers. This project was energized in June 2016. College Substation SE Valencia County On November 12, 2014, filed with the NMPRC under NMPRC Rule 440 information on a project to construct a new 115 kv substation in southeast Valencia County. The substation will serve customers south of Highway 263, support the existing demand and load growth along the Highway 47 corridor and the Manzano Expressway. The Substation will also provide back-up support during contingency situations for the Tome, Manzano and El Cerro Substations which currently provide the distribution delivery for this area. This project was energized in July 2016. Blackwater 345 kv Switching Station Expansion 4

Status of s Completed Transmission Construction Projects Blackwater 345 kv Switching Station On December 18, 2015, filed with the NMPRC under NMPRC Rule 440 information on a project to expand the Blackwater 345 kv switching station. The purpose of this Project is to allow interconnection of a 345kV transmission line for Western Interconnect, LLC. This project was completed on February 2, 2017. 5