Instructions for Installation

Similar documents
Replacement of 600-Ampere Bushing and 200-Ampere Bushing-Well Adapters

S&C Source-Transfer Vista Underground Distribution Switchgear

Installation and Operation

Installation, Operation, and Maintenance

S&C Vista Underground Distribution Switchgear

Installation and Operation

Instructions for Installation and Operation

Operation. S&C Vista Underground Distribution Switchgear UnderCover, Vault-Mounted, and Pad-Mounted Styles. Table of Contents

Installation. Loadbuster The S&C Loadbreak Tool Outdoor Distribution (14.4 kv through 34.5 kv) Table of Contents. Instruction Sheet

Installation. S&C Omni-Rupter Switches Outdoor Distribution 14.4 kv and 25 kv

S&C Circuit-Switchers Mark VI Installed on S&C Mounting Pedestals 84- through 102-inch Phase Spacing Outdoor Transmission (69 kv through 138 kv)

Cleaning Flooded Gear

Cleaning Flooded Gear

PAD-MOUNTED SWITCHGEAR INSPECTION & MAINTENANCE RECOMMENDATIONS TYPE PSI/II. 15kV 25kV. Qualified Persons

Instructions for Installation

Installation. S&C Manual PME Pad-Mounted Gear Outdoor Distribution (14.4 kv and 25 kv) Table of Contents

Instructions for Installation and Operation

Guide Specification. Three-Phase Solid Dielectric Trident-SR with SafeVu Integral Visible Break

TRINETICS CSD SERIES OIL SWITCH INSTALLATION INSTRUCTIONS

Inspection and Maintenance

Operation. S&C Source-Transfer Vista Underground Distribution Switchgear. Pad-Mounted, Dry-Vault-Mounted, Wet-Vault-Mounted, and UnderCover Styles

S&C Manual PME Pad-Mounted Gear

Installation and Operation

Installation and Operation

Effective March 2015 Supersedes S August 2012

Installation And Operation

GWI Rev. 1 October 2007 Supersedes Rev. 0 Dated February 2004

Type NR oil switch installation and operation instructions

Introduction CAUTION. S&C Power Operated Metal-Enclosed Switchgear Outdoor Distribution (4.16 kv, through 34.5 kv)

Installation. S&C Omni-Rupter Switches Outdoor Distribution 14.4 kv and 25 kv

SUBSTATION VACUUM CIRCUIT BREAKER (38KV)

SUBSTATION VACUUM CIRCUIT BREAKER (25.8 / 27KV)

15-kV Wall-Mount Switchgear Three-Phase Indoor/Outdoor 600 Amp S&C Mini-Rupter Switch

SUBSTATION VACUUM CIRCUIT BREAKER (15.5KV)

INSTRUCTIONS Ç CAUTION. S&C Manual PMH Pad-Mounted Gear Outdoor Distribution (14.4 kv and 25 kv) For Installation TABLE OF CONTENTS

GE Industrial Solutions. DEH Installation and Maintenance Manual AKD-20 AR / Entellisys AR Exhaust Plenum System

Introduction CAUTION CAUTION. S&C Power Operated Metal-Enclosed Switchgear Indoor and Outdoor Distribution (4.16 through 34.5 kv)

Solid Dielectric Load Break Switch SPECIFICATION. 25kV, 630A, 4 WAYS, 4 WAYS SWITCHED PADMOUNTED VACUUM LOAD INTERRUPTER

SecoVac * Ground & Test Device

Typical Specification

SERIES G100 / G110 SPECIFICATION 15KV & 25KV SUBMERSIBLE & VAULT MOUNTED SF 6 -INSULATED VACUUM LOAD INTERRUPTING SWITCHES

Medium Voltage Metal-Enclosed Switches

Medium Voltage Metal-Enclosed Switches

Specifications. S&C Alduti-Rupter Switches with Power Fuses Outdoor Distribution (14.4 kv through 46 kv)

IB PowlVac ITE-HK Remote Racking Device

Installation. S&C Circuit-Switchers Mark VI 69-kV 51-inch Phase Spacing Single Pedestal Design Outdoor Transmission.

High-voltage primary bushings installation instructions

STANDARD SPECIFICATION FOR TYPE PLD LIVE-FRONT/DEAD-FRONT PAD-MOUNTED SWITCHGEAR 15kV 25kV A. General

Vacuum Circuit Breaker (Vehicle)

Publication No.: PSG

COOPER POWER SERIES. High-voltage primary bushings installation instructions. OEM Equipment MN800008EN

SM-1700 Secondary Shunt Trip Coil Assembly. Powered by Safety

35-kV Safefront SuperWell Mini-Switch Source Isolated Pad-Mounted Switchgear 50 Amp (Max) Clip-Mounted Current Limiting Fuses

SPECIFICATION BULLETIN

COOPER POWER SERIES. 600 A 15, 25, and 35 kv Class Cleer Loadbreak Bushing Insert Installation Instructions. Loadbreak/Deadbreak Connectors MN650016EN

Digitrip Retrofit System for ITE K-3000, K-3000 S, K-4000 and K-4000 S Breakers

APCO CRF-100A RUBBER FLAPPER SWING CHECK VALVES

Specifications. S&C Alduti-Rupter Switchesa Indoor Distribution (4.8 kv through 34.5 kv) Conditions of Sale SPECIAL TO THIS PRODUCT: How to Order

DeZURIK 2 20" BOS BUTTERFLY VALVES

SERIES 802 / 812 SPECIFICATION 15KV & 25KV PADMOUNTED LIQUID-INSULATED VACUUM LOAD INTERRUPTERS AND FUSE ASSEMBLIES

TYPE AST. Grounding Switch. ALL Ratings INSTALLATION & INSTRUCTION MANUAL

35-kV Apparatus Bushings B Series (bolt-in) for Elbow to Air-Insulated Service 200 Amp, 600 Amp, 900 Amp and 1250 Amp

COOPER POWER SERIES. S.T.A.R. type LVR faulted circuit indicator installation instructions. Fault Indicators MN320005EN

Vacuum Circuit Breakers (Vehicle)

15-kV Live Terminal 600 Amp Group Operated Pad-Mounted Metal-Enclosed Outdoor Switchgear 140 Amp (Max) Clip Mount Current-Limiting Fuses

25-kV Apparatus Bushings B Series (bolt-in) for Elbow to Air-Insulated Service 200 Amp, 600 Amp, 900 Amp and 1250 Amp

100 / 110 DRYWELL FUSE SPECIFICATION

35-kV 200-kV BIL Apparatus Bushings B Series (bolt-in) for Elbow to Air-Insulated Service 200 Amp, 600 Amp, 900 Amp and 1250 Amp

COOPER POWER SERIES. 200 A Fused Loadbreak Elbow Connector Replacement Fuse Installation Instructions. Fusing Equipment MN132021EN

35-kV Safefront Mini-Switch Source Isolated Pad-Mounted Switchgear 50 Amp (Max) Clip-Mounted Current-Limiting Fuses

25 kv Apparatus Bushings

Michigan State University Construction Standards SECONDARY UNIT SUBSTATIONS PAGE

15-kV Safefront Mini-Switch Source Isolated Pad-Mounted Switchgear 140 Amp (Max) Clip-Mounted Current-Limiting Fuses

Product Specifications for Phase Over Phase GOABS(r)

Vacuum Circuit Breakers (Vehicle) Type HKR 7.5kV to 15kV. Instructions Installation Operation Maintenance SGIM-9928C

COOPER POWER SERIES. HX-CB loadbreak fuse cutout installation instructions. Fusing Equipment MN132011EN

Specification Pad-Mounted Capacitor Bank with Dual Fusing Integral Load-Interrupter on Line-Side Fuse Mountings

Section SWITCHBOARDS. Introduction. Part 1 - General. Related Work

FIXED POWER FACTOR CORRECTION EQUIPMENT 5KV CLASS MEDIUM VOLTAGE SECTION Z

Specifications. S&C Power Fuses Types SM and SMLa. For use with SM Refill Units or SMU Fuse Units. Indoor Distribution (4.16 kv through 34.

COOPER POWER SERIES. 600 A 15/25 kv class T-OP II connector assembly installation instructions. Deadbreak Apparatus Connectors MN650048EN

CR193 Vacuum Limitamp* Contactors

Specifications. S&C Omni-Rupter Switches Outdoor Distribution (14.4 kv and 25 kv) Conditions of Sale

INSTRUCTIONS For Field Assembly and Installation

INSTRUCTION MANUAL Metal-Enclosed Switchgear Indoor and Outdoor Distribution 2400 volts through 34,500 volts

35-kV Safefront 200 Amp SuperWell Primary Metering Station Pad-Mounted Outdoor

SPECIFICATION FOR THREE-PHASE PAD MOUNT TRANSFORMERS. D. Dead Front, loop feed design shall be employed.

Model NTX7 Series Automatic Battery Charger User s Manual Rev. 1.0 October 17, 2006

25-kV Apparatus Bushings A Series (clamp-in) for Elbow to Air-Insulated Service 200 Amp and 600 Amp

INSTRUCTION MANUAL. Type SWF. Sine Wave Filters 480 Volts, 60Hz. Page 1 of 14. April 15, 2010: updated capacitor UL File number)

GE CONSUMER & INDUSTRIAL

Specifications. S&C Type XS Fuse Cutouts. Outdoor Distribution (4.16 kv through 25 kv)

COOPER POWER SERIES. UltraSIL polymer-insulated D-73P disconnect switches installation instructions. Switches MN008004EN

S Fault Indicators. S.T.A.R. Type TPR Faulted Circuit Indicator Installation Instructions. Contents INSTALLATION PROCEDURES

CENTER BREAK GROUP OPERATED AIR BREAK SWITCHES RATED 15.5kV THROUGH 170kV EFFECTIVE DATE: 10/25/16 REV B

Operator's Manual. Storage System. Ultrasound Probe Cabinet. Manufactured by:

Product Specification Guide. Title: Southern States 72 kv RLSwitcher Vertical Interrupter Style Reactor Switcher

15-kV Safefront 200 Amp Primary Capacitor Station Pad-Mounted Outdoor

Vacuum Circuit Breakers (Vehicle)

Galaxy Receiving and Unpacking 09/

Transcription:

S&C Vista Underground Distribution Switchgear Wind Turbine Style Instructions for Installation Table of Contents Section Page Section Page Introduction Qualified Persons... 2 Read this Instruction Sheet.... 2 Retain this Instruction Sheet.... 2 Proper Application............................. 2 Warranty... 2 Safety Information Understanding Safety-Alert Messages... 3 Following Safety Instructions..................... 3 Replacement Instructions and Labels.... 3 Location of Safety Labels... 4 Safety Precautions............................ 5 Inspection and Handling Packing... 6 Inspection... 6 Storage... 6 Removal of Elbow Cover Assembly................ 7 Handling..................................... 8 Installation Switchgear Placement.......................... 9 Cables.... 9 Grounding... 9 Replacement of Elbow Cover Assembly.... 10 Completing the Installation... 10 Cable Connections........................... 11 Dielectric Testing Routine Switchgear Testing..................... 12 Fault-Interrupter Testing... 12 Cable Testing and Fault Locating... 12 Ratings Wind Turbine Style Vista Switchgear Ratings....... 14 Fault Interrupter Rating.... 14 Load-Interrupter Switch Ratings... 14 Specifications Optional Features... 15 Accessories................................. 15 Touch-Up Kit Components... 15 June 15, 2009 S&C Electric Company Instruction Sheet 681-506

Introduction Qualified Persons Read this Instruction Sheet Retain this Instruction Sheet Proper Application Warranty Ç WARNING The equipment covered by this publication must be installed, operated, and maintained by qualified persons who are knowledgeable in the installation, operation, and maintenance of underground electric power distribution equipment along with the associated hazards. A qualified person is one who is trained and competent in: The skills and techniques necessary to distinguish exposed live parts from nonlive parts of electrical equipment. The skills and techniques necessary to determine the proper approach distances corresponding to the voltages to which the qualified person will be exposed. The proper use of the special precautionary techniques, personal protective equipment, insulating and shielding materials, and insulated tools for working on or near exposed energized parts of electrical equipment. These instructions are intended only for such qualified persons. They are not intended to be a substitute for adequate training and experience in safety procedures for this type of equipment. Thoroughly and carefully read this instruction sheet before installing or operating your Wind Turbine Style Vista Switchgear. Familiarize yourself with SAFETY INFORMATION on pages 3 and 4. The latest version is available online in PDF format at www.sandc.com. This instruction sheet is a permanent part of your Wind Turbine Style Vista Switchgear. Designate a location where you can easily retrieve and refer to this publication. Ç CAUTION The equipment in this publication must be selected for a specific application. The application must be within the ratings of the equipment. Ratings for this gear are listed on a ratings label on the top of the switchgear. The warranty and/or obligations described in S&C s standard conditions of sale, as set forth in Price Sheet 150, plus any special warranty provisions, as set forth in the applicable product-line specification bulletin, are exclusive. The remedies provided in the former for breach of these warranties shall constitute immediate purchaser s or end user s exclusive remedy and a fulfillment of all seller s liability. In no event shall seller s liability to immediate purchaser or end user exceed the price of the specific product which gives rise to immediate purchaser s or end user s claim. All other warranties whether express or implied or arising by operation of law, course of dealing, usage of trade or otherwise, are excluded. The only warranties are those stated in Price Sheet 150, and THERE ARE NO EXPRESS OR IMPLIED WARRANTIES OF MERCHANTABILITY OR FITNESS FOR A PARTICULAR PURPOSE. ANY EXPRESS WARRANTY OR OTHER OBLIGATION PROVIDED IN PRICE SHEET 150 IS GRANTED ONLY TO THE IMMEDIATE PURCHASER AND END USER, AS DEFINED THEREIN. OTHER THAN AN END USER, NO REMOTE PURCHASER MAY RELY ON ANY AFFIRMATION OF FACT OR PROMISE THAT RELATES TO THE GOODS DESCRIBED HEREIN, ANY DESCRIPTION THAT RELATES TO THE GOODS, OR ANY REMEDIAL PROMISE INCLUDED IN PRICE SHEET 150. 2 S&C Instruction Sheet 681-506

Safety Information Understanding Safety- Alert Messages There are several types of safety-alert messages which may appear throughout this instruction sheet as well as on labels attached to the Wind Turbine Style Vista Switchgear. Familiarize yourself with these types of messages and the importance of the various signal words, as explained below. Ç DANGER DANGER identifies the most serious and immediate hazards which will likely result in serious personal injury or death if instructions, including recommended precautions, are not followed. Ç WARNING WARNING identifies hazards or unsafe practices which can result in serious personal injury or death if instructions, including recommended precautions, are not followed. Ç CAUTION CAUTION identifies hazards or unsafe practices which can result in minor personal injury or product or property damage if instructions, including recommended precautions, are not followed. NOTICE NOTICE identifies important procedures or requirements that, if not followed, can result in product or property damage if instructions are not followed. Following Safety Instructions If you do not understand any portion of this instruction sheet and need assistance, contact your nearest S&C Sales Office or S&C Authorized Distributor. Their telephone numbers are listed on S&C s website www.sandc.com. Or call S&C Headquarters at (773) 338-1000; in Canada, call S&C Electric Canada Ltd. at (416) 249-9171. NOTICE Thoroughly and carefully read this instruction sheet before installing your Wind Turbine Style Vista Switchgear. Replacement Instructions and Labels If you need additional copies of this instruction sheet, contact your nearest S&C Sales Office, S&C Authorized Distributor, S&C Headquarters, or S&C Electric Canada Ltd. Instruction sheets can also be viewed on S&C s website: www.sandc.com. It is important that any missing, damaged, or faded labels on the equipment be replaced immediately. Replacement labels are available by contacting your nearest S&C Sales Office, S&C Authorized Distributor, S&C Headquarters, or S&C Electric Canada Ltd. S&C Instruction Sheet 681-506 3

Safety Information Location of Safety Labels A B a C Top of Switchgear a E D Reorder Information for Safety Labels Location Safety-Alert Message Description Number A Ç DANGER Hazardous Voltage Always Consider Circuits and Components Live... G-6700 B Ç DANGER Never Drill Into Tank Hazardous Voltage, Contains Pressurized SF 6 Gas G-6682 C Ç DANGER Keep Away Hazardous Voltage ( Mr. Ouch )a G-6699 D Ç WARNING Check Gas Pressure Before Operating Switchgear G-6686 E Ç WARNING Always Visually Confirm Blade Positiona G-6693 a This label is located on the side of the gear and is not visible in this photo. 4 S&C Instruction Sheet 681-506

Safety Precautions Ç DANGER Switchgear contains high voltage. Failure to observe the precautions below will result in serious injury or death. Some of these precautions may differ from company operating procedures and rules. Where a discrepancy exists, users should follow their company s operating procedures and rules. 1. QUALIFIED PERSONS. Access to switchgear must be restricted only to qualified persons. See Qualified Persons on page 2. 2. SAFETY PROCEDURES. Always follow safe operating procedures and rules. 3. PERSONAL PROTECTIVE EQUIPMENT. Always use suitable protective equipment such as rubber gloves, rubber mats, hard hats, safety glasses, and flash clothing in accordance with safe operating procedures and rules. 4. SAFETY LABELS. Do not remove or obscure any of the CAUTION, WARNING, or DANGER labels. 5. ENERGIZED BUSHINGS. Always assume that the bushings are energized unless proved otherwise by test, by visual evidence of an open-circuit condition at the fault interrupter, or by observing that the fault interrupter is grounded. 6. BACKFEED. Bushings, cables, and fault interrupter may be energized by backfeed. 7. DE-ENERGIZING, TESTING, AND GROUNDING. Before touching any bushings or components inside the switchgear tank that are to be inspected, replaced, serviced, or repaired, always disconnect the fault interrupter from all power sources (including backfeed), test for voltage, and properly ground. 8. TESTING. Test the bushings for voltage using the voltage-indication feature (if furnished) or other proper high-voltage test equipment before touching any bushings or components that are to be inspected, replaced, serviced, or repaired. 9. GROUNDING. v Make sure that the switchgear tank is properly grounded to the station or facility ground. v After the switchgear has been completely disconnected from all sources of power and tested for voltage, properly ground the fault interrupter before touching any bushings or components that are to be inspected, replaced, serviced, or repaired. 10. FAULT-INTERRUPTER POSITION. v Always confirm the open/close/grounded position of the fault interrupter by visually observing the position of the blades. v Fault interrupter may be energized by backfeed. v Fault interrupter may be energized in any position. 11. MAINTAINING PROPER CLEARANCE. Always maintain proper clearance from energized bushings. S&C Instruction Sheet 681-506 5

Inspection and Handling Packing Inspection Storage Wind Turbine Style Vista Switchgear is shipped in a wooden crate. At the first opportunity, remove all packing materials (cardboard, paper, foam padding, etc.) from the outside of the switchgear. This will prevent the finish on the elbow cover assembly from being damaged by rainwater absorbed by the packing materials and will also prevent wind-induced abrasion from loose cardboard. Examine the shipment for external evidence of damage as soon after receipt as possible, preferably before removal from the carrier s conveyance. Check the bill of lading to make sure that all shipping skids, crates, and containers listed thereon are present. If there is visible loss and/or damage: 1. Notify the delivering carrier immediately. 2. Ask for a carrier inspection. 3. Note condition of shipment on all copies of the delivery receipt. 4. File a claim with the carrier. If concealed damaged is discovered: 1. Notify the delivering carrier within 15 days of receipt of shipment. 2. Ask for a carrier inspection. 3. File a claim with the carrier. Also notify S&C Electric Company in all instances of loss and/or damage. If the Wind Turbine Style Vista Switchgear cannot be immediately installed, ensure that it is stored in a clean, warm, dry environment. If this is not possible, shelter the switchgear in a tent-like covering which will allow adequate ventilation, but prevent entry of rain, snow, and contaminants through any openings. 6 S&C Instruction Sheet 681-506

Inspection and Handling Removal of Elbow Cover Assembly 1. Loosen the seven thumbscrews on the front cover. 2. Remove the front cover. 3. Remove the four hex-head cap screws on the top cover. 4. Remove the four hex nuts on the underside of the top cover. 5. Remove the top cover. 6. Loosen the six hex nuts on the right side cover. See Figure 1. 7. Remove the right side cover by pulling it forward. See Figure 2. 8. Repeat Steps 6 and 7 for the left side cover. Elbow cover assembly Base spacer Figure 1. Loosen the six hex nuts on the right side cover. Figure 2. Remove the right side cover by pulling it forward. S&C Instruction Sheet 681-506 7

Inspection and Handling Handling Ç WARNING When handling Wind Turbine Style Vista Switchgear with an overhead hoist, observe standard lifting practices as well as the general instructions below. Failure to follow these precautions can result in serious personal injury or equipment damage. 1. Use 6-foot or longer hoist slings of equal length to prevent damaging the switchgear during lifting. 2. Arrange the hoist slings so as to distribute the lifting forces equally between the lifting tabs. See Figure 3. 3. Avoid sudden starts and stops. Figure 3. Hoist slings. 8 S&C Instruction Sheet 681-506

Installation Switchgear Placement 1. Remove the switchgear from its crate and lift the gear into place, observing the precautions given under Handling on page 8. 2. Secure the switchgear to the pad using the anchor brackets provided. 3. Refer to the catalog dimensional drawing furnished with the switchgear and verify that the base spacer is positioned correctly and that the base spacer is properly aligned with respect to the anchor bolts. 4. Secure the base spacer to the pad using the anchor brackets provided. See Figure 4. Four.6250 dia. anchor bolts by user 1.50 min. Anchor bracket by S&C Base spacer Gasket Concrete pad Cables Figure 4. Anchor bracket. Refer to CABLE CONNECTIONS on page 11. Grounding 1. Connect the cable concentric-neutral ground wires to the grounding system as appropriate. 2. Connect the ground pad of the switchgear to the system ground facility in accordance with the user s standard grounding practice. See Figure 5. 3. Use the equivalent of 4/0 copper (or cable sized in accordance with the user s standard practice) in either a single or multiple connection to realize the maximum momentary rating of the switchgear. For a multiple connection, cables smaller than 1/0 copper or equivalent should not be used. Switchgear ground pad Figure 5. Switchgear ground pad. Ground in accordance with user s standard grounding practice (grounding not shown) S&C Instruction Sheet 681-506 9

Installation Replacement of Elbow Cover Assembly 1. Slide the right side cover over the six studs. See Figure 6. 2. Tighten the six hex nuts that were retained on the studs. See Figure 7. 3. Repeat Steps 1 and 2 for the left side cover. 4. Lift top cover into place. 5. Replace and tighten the four hex-head cap screws on the top cover. 6. Replace and tighten the four hex nuts on the underside of the top cover. 7. Lift front cover into place. 8. Tighten the seven thumb screws that were retained on the front cover. Figure 6. Slide the right side cover over the six studs. Figure 7. Tighten the six hex nuts that were retained on the studs. Completing the Installation 1. A resilient closed-cell gasket on the bottom flange of the switchgear protects the finish from being scratched during installation and isolates it from the alkalinity of a concrete foundation. This gasket also helps to seal the enclosure to the foundation to guard against entry of rodents, insects, or weeds, and to discourage tampering. 2. Wipe down the exterior of the elbow cover assembly with a clean, damp cloth. Refinish any scratches or abrasions with S&C touch-up finish and red-oxide primer which are available in aerosol spray cans. See page 15 for ordering information. No other finish or primer is approved. The area to be touched up should be cleaned to remove all oil and grease. Sand the area, removing any traces of rust that may be present, and make sure that all edges are feathered before applying primer. 10 S&C Instruction Sheet 681-506

Cable Connections Ç DANGER Before energizing the switchgear, replace the shipping caps on all bushings and bushing wells with elbows or insulated protective covers or plugs. Failure to replace the shipping caps with elbows or insulated protective covers or plugs can result in a flashover and serious personal injury or death. 1. Remove the shipping covers from the bushings and bushing wells. See Figure 9. Wind-turbine generator side bushings Shipping covers Collection system bushings Figure 9. Shipping covers. Ç CAUTION ALWAYS follow proper cable installation practices. When installing cable to be attached to the switchgear, provide a strainrelief segment to minimize the load on the bushings. Cables must be allowed to expand and flex without putting a significant load on the bushings. Failure to follow these precautions can result in damage to the bushings and bushing wells and subsequent leakage of the SF 6 insulating gas. 2. Assemble the elbow connectors to the cables following the elbow connector manufacturer s instructions. See Figure 10. Bushing and bushing well interfaces conform to ANSI/IEEE Standard 386 to accept standard elbow connectors and components Elbow connectors and components supplied by user Figure 10. Elbow connectors. S&C Instruction Sheet 681-506 11

Dielectric Testing Routine Switchgear Testing For the convenience of users who normally perform electrical tests on system components such as switchgear, appropriate withstand test values for Wind Turbine Style Vista Switchgear are given in the table below. These test values are significantly greater than the normal operating voltage of the switchgear and are near the flashover voltage of the gear. They should be applied only when the switchgear is completely de-energized and disconnected from all power sources. Ç WARNING When performing electrical withstand tests on Wind Turbine Style Vista Switchgear, always observe the following precautions. Failure to observe these precautions can result in a flashover, injury, and equipment damage. 1. Completely de-energize the switchgear and disconnect it from all power sources. 2. Install insulated caps or other appropriate separable connector components capable of withstanding the test voltage. 3. Verify that the SF 6 pressure gauge is in the green zone. MAXIMUM INSULATION TEST VOLTAGES Vista Switchgear Rating, kv 50 Hz 60 Hz Impulse (BIL) Withstand Test Voltage, kv Power Frequency1 Dc23 12 15.5 95 27 42 24 27 125 40 62 36 38 150 50 82 1 The power-frequency withstand test voltages listed in the table are approximately 80% of the design values for new equipment. 2 The dc withstand test voltages listed in the table are approximately 80% of the design values for new equipment. 3 Dc withstand test voltages are given for reference only for those users performing dc withstand tests. The presence of these values does not imply a dc withstand rating or performance requirements for the switchgear. A dc withstand design test is specified for new equipment because the switchgear may be subjected to dc test voltage when connected to the cable. The dc withstand test values listed in the table are approximately equal to the ac peak test voltage. Fault-Interrupter Testing Cable Testing and Fault Locating When performing dielectrical tests on Wind Turbine Style Vista Switchgear, the vacuum fault interrupter will not be subject to voltage across the open gap because the disconnect switch will isolate the vacuum interrupter from the test voltage. Since the vacuum interrupter will not be energized across the open gap, there is no exposure to X-rays that are normally associated with high-voltage testing of vacuum devices. Routine testing of the vacuum fault interrupter is not recommended. For those users who desire to test the vacuum interrupter, contact the nearest S&C Sales Office for specific instructions. Dc testing of installed cables is performed to determine the condition of the cables and to locate faults. Industry standards, like IEEE 400, IEEE Guide for Making High-Direct- Voltage Tests on Power Cable Systems in the Field, describe such testing and should be referenced for selection of the test procedures. Dc testing also includes cable thumping, i.e., the sudden application of dc voltage from a large capacitor for the purposes of fault locating, which causes transients and voltage doubling at the end of the open cable. When the cables are attached to the switchgear, the gear will also be subjected to the dc test voltages. 12 S&C Instruction Sheet 681-506

Dielectric Testing Ç WARNING The dc withstand capability of the switchgear may be reduced due to aging, damage, gas leakage, or electrical or mechanical wear. Therefore, the dc test voltage must be selected such that it does not exceed the withstand limits of the switchgear. Application of the dc test voltages greater than the withstand capability of the switchgear can result in a flashover, injury, and equipment damage. In addition, always verify that the SF 6 -gas pressure gauge is in the green zone before proceeding with any test. Ç DANGER Do not exceed the test voltages given in the table on page 13. Exceeding the test voltages can cause a flashover of the isolating gap or phase-to-phase insulation of the switchgear. This can lead to a power-frequency fault in the gear or of the dc test source and result in severe personal injury or death. Cables connected to Wind Turbine Style Vista Switchgear may be dc tested as follows: With the switchgear energized and the switch blade in the open position. The maximum test voltage should not exceed the Dc Cable Thumping Voltage indicated in the table below. Cables must be de-energized before connecting them to the dc fault-locating equipment. With the switch blade in the grounded position, grounding the cables connecting the wind turbine generator to the switchgear. The maximum test voltage should not exceed the Dc Cable Test Voltage indicated in the table below. Cables must be de-energized before connecting them to the dc test equipment. After testing, the dc fault-locating or test equipment should be used to discharge any stored charge on the cables before regrounding the cables. Ç WARNING When testing cables connected to energized switchgear, proper isolation of the pwer-frequency source and dc test source must be maintained. Follow the recommendations of the dc fault-locating or test equipment. The user s operating and safety procedures should be followed for grounding a cable, connecting the dc test source, isolating the dc test source (in case of flashover), ungrounding the cable, applying the dc test source, discharging the cable, and regrounding the cable. MAXIMUM CABLE TEST AND CABLE THUMPING VOLTAGES Vista Switchgear Rating, kv 50 Hz 60 Hz Impulse (BIL) Dc Cable Test Voltage, kv Dc Cable Thumping Voltage, kv1 12 15.5 95 30 15 24 27 125 40 20 36 38 150 40 20 1 The dc cable thumping voltage is 50% of the dc cable test voltage because of voltage doubling that will occur at the open end of the cable which is assumed to be a unit of Wind Turbine Style Vista Switchgear. If the open end of the cable is grounded, the dc cable thumping voltage applied to the cable and switchgear can be increased to the dc cable test voltage. S&C Instruction Sheet 681-506 13

Ratings WIND TURBINE STYLE VISTA SWITCHGEAR RATINGS12 Voltage, kv Current, Amperes (RMS) System Class Max BIL Main Bus Cont. Current Short-Circuit, Sym. 15.5 (12) 27 (24) 38 (36) 15.5 (15.5) 29 (29) 38 (38) 95 (95) 125 (125) 150 (150 af af af () () () Fault-Interrupter ratings (If applicable)12 Voltage, kv System Class 15.5 (12) 27 (24) 38 (36) Cont., Load Dropping, and Load Splitting3 200 (200)d 200 (200)d 200 (200)d Current, Amperes, RMS Ten-Time Duty-Cycle Fault-Closing, Sym. Into Closed Position () () () Into Grounded Position () h () h () h Ten-Time Duty-Cycle Fault-Interrupting, Sym. () () () LOAD-INTERRUPTER SWITCH RATINGS12 (If applicable) Voltage, kv System Class 15.5 (12) 27 (24) 38 (36) Cont., Load Dropping, and Load Splitting3 a a a 1 ANSI ratings have been assigned in accordance with the applicable portions of IEEE C37.71, C37.72, and C37.73. IEC Ratings have been assigned in accordance with the applicable portions of IEC 265-1 for a Class A switch. 2 Refer to the nearest S&C Sales Office for other possible ratings. 3 Parallel or loop switching. Fault interrupters and load-interrupter switches can switch the magnetizing current of transformers associated with the load-dropping rating. Unloaded cable switching rating: 10 amperes at 15.5 kv, 20 amperes at 29 kv and 38 kv. 4 Applicable to fault closing into closed or grounded position. Current, Amperes, RMS Ten-Time Duty-Cycle Fault-Closing, Sym.4 () h 16 000 (16 000) h 16 000 (16 000) Mom. and One-Second, Sym. () () () h a 200 (200) amperes when switchgear is furnished with optional 200- ampere bushing wells at load-interrupter switch terminals, Catalog Number Suffix -M4. f 200 (200) amperes when optional -ampere bushings at fault interrupter terminals, Catalog Number Suffix ( -M2 or -M3 ) is not specified. d amperes when switchgear is furnished with optional - ampere bushings at fault interrupter terminals, Catalog Number Suffix -M2 or -M3. h amperes symmetrical three-time duty-cycle faultclosing rating; 16 000 (16 000) amperes symmetrical ten-time duty-cycle fault-closing rating. 14 S&C Instruction Sheet 681-506

Specifications OPTIONAL FEATURES Potential Indication with Test Feature. Includes liquid-crystal display which indicates presence of voltage on each phase, and solar panel to supply power for testing of complete voltage-indication circuit and phasing circuit (if furnished) Remote Low-Pressure Alarm1 includes internal contact for remote low-pressure indication, with wiring to outside of tank External Trip Provisions, allows three-pole tripping of fault interrupter via a trip signal from a remote location or an external relay. Requires 120-Vac control power23 Item Key Interlock on Fault Interrupter4 1 This option must be specified if future remote supervisory features, including remote low-pressure indication, are planned. 2 Refer to the nearest S&C Sales Office if compatibility with control power other than 120 Vac is required. Suffix Added to Switchgear Catalog Number Without provisions for low-voltage phasing -L1 With provisions for low-voltage phasing -L2 With wires routed on tank for future customer connections -R11 With wires terminated in an enclosure furnished with a terminal block for customer connections In addition to standard overcurrent control -R31 In lieu of standard overcurrent control and current transformers -R2 -R41 3 The user-supplied trip-initiating signal must be a momentary contact. Refer to the nearest S&C Sales Office if an application requires the use of a latching contact. 4 Motor operator cannot be fitted on fault interrupter with key interlock. -X1 ACCESSORIES Shotgun Clamp Sticks for use with separable connectors Item Catalog Number 69 5Z\x0 length 9933-150 89 5Z\x0 length 9933-151 Storage Bag for Shotgun Clamp Stick, heavy canvas Overcurrent-Control Adapter Cable required for programming overcurrent control Portable Motor Operator for operation of fault interrupter from a remote location. Includes carrying case, 50 foot cable with remote controls, and power supplied by 69 60 length 9933-152 89 60 length 9933-153 For connecting control to user-furnished personal computer in the field, having a 9-pin (DB9) serial communication port and a PS/2 (mouse) port For connecting control (removed from is enclosure) to user-furnished personal computer in the shop, having a 9-pin (DB9) serial communication port and a PS/2 (mouse) port For connecting control to user-furnished personal computer having a USB port. Kit includes USB cable, adapter cable, driver CD-ROM, and installation instructions User-furnished 24-volt battery and battery charger S&C-furnished 24-volt battery and battery charger S&C-furnished AC input power supply TA-2367 TA-2368 TA-3153 38320R1 38322R1 38323R1 Touch-Up Kit Components Aerosol Coatings1 Item Catalog Number S&C Light Gray Outdoor Finish 9999-080 S&C Red-Oxide Primer 9999-061 1 In 12-ounce cans. S&C Instruction Sheet 681-506 15

Printed in U.S.A.