Black Hills Energy Contractor Covered Task List Last updated 10/10/2018

Similar documents
Southern Star Central Gas Pipeline Contractor Covered Task List Last updated 8/15/2018

Dominion Energy Questar Pipeline LLC Contractor Covered Task List Last updated 10/3/2017

Northern Natural Gas Contractor Covered Task List Last updated 4/26/2018

EnLink Midstream Contractor Covered Task List Last updated 11/8/2017

Epic Consolidated Operations LLC Contractor Covered Task List Last updated 9/6/2018

Columbia Pipeline Group Contractor Covered Task List Last updated 1/8/2018

DCP Midstream Contractor Covered Task List Last updated 7/11/2018

Saddle Butte Rockies Midstream LLC Contractor Covered Task List Last updated 12/6/2017

Boardwalk Pipeline Partners, LP Contractor Covered Task List Last updated 9/17/2018

Howard Midstream Energy Partners LLC Contractor Covered Task List Last updated 10/11/2013

TransCanada US Contractor Covered Task List Last updated 9/27/2018

Energy Transfer Partners LP Contractor Covered Task List Last updated 3/2/2018

Williams Contractor Covered Task List Last updated 11/7/2017

Noble Energy Contractor Covered Task List Last updated 2/20/2019

Energy Transfer Partners LP Contractor Covered Task List Last updated 12/10/2018

Enbridge Gas Transmission and Midstream and Enbridge Liquid Pipelines (Express-Platte) Contractor Covered Task List Last updated 8/30/2018

Appendix A Kinder Morgan Operator Qualification Program List of Covered Tasks - Natural Gas - Part 192 Revised 12/13/2017

ASMECourseCatalog.

Appendix B Kinder Morgan Operator Qualification Program List of Covered Tasks Hazardous Liquid Pipelines Part 195 revised 8/24/2018

Appendix B Kinder Morgan Operator Qualification Program List of Covered Tasks Hazardous Liquid Pipelines Part 195 revised 12/12/2017

Florida City Gas Contractor Covered Task List

Operator Qualification (OQ) Report

COVERED TASK Conduct Cathodic Protection Surveys 1 DESCRIPTION ELEMENTS OF TASK 4 PART QUESTION NOTES ABNORMAL OPERATING CONDITIONS

PIGGING PRODUCTS. Capex supply. PIG LAUNCHER and RECEIVER

HDPE FUSIBLE VALVES EXPECT INNOVATION

INSTALLATION, OPERATION, & MAINTENANCE MANUAL Models # MM-30, MM-30HT, MM-50, MM-50HT, & MM-50 EXL with Special HP Tool and Special HP EXL Tool

GF Piping Systems. SurTap System Operation with VersaTap Fittings Manual

Monthly Checklist For Depot

PIPELINE CORROSION CONTROL

PROCEDURE EXTRUDED HOT TAP & LINE STOP TEES DESIGN & MANUFACTURING VALIDATION

New UST Installation Inspection Checklist

INSTALLATION, OPERATION, AND MAINTENANCE MANUAL WELKER AUTOMATIC INSERTION PROBE

Pipe Support The Fast, Economical Solution for Low Pressure Pipeline Repair

INSTALLATION INSTRUCTIONS

ANNUAL UST SYSTEM INSPECTION CHECKLIST

OPERATION AND SAFETY MANUAL

EXPECT SUPREME PE BALL VALVES

PTFE Lined Pipe and Fittings

Rolls -Royce M250--C47M OPERATION AND MAINTENANCE

FISC Puget Sound Manchester Fuel Department. Maintenance, Leak Detection in Large Underground Storage Tanks. Glenn E. Schmitt, P.E.

This publication is copyrighted and intended for the sole use of General Industries - 07/07/2016

This article discusses a tank

FINAL REPORT CATHODIC PROTECTION EVALUATION. 42-Inch Water Transmission Pipeline Contract 1 Station 0+00 to South Texas Water Authority

The Use of Conduction Tracers Vs Bare Tracers Metric Version

GAS DISTRIBUTION PRODUCTS METER RISERS

PHMSA Office of Pipeline Safety Dave Mulligan Western Region

MUELLER GAS. Shur StopTM Unit 812 PE Line Stopping. System 8" 12" SDR Reliable Connections. General Information 2

Highway Crossings - Cased or Uncased

The Gradient Control Mat (GCM)

CASE STUDY ON PIPELINE UNDER-PROTECTION ALONG WITH MITIGATION METHODS. Vipul Vilas Sawant. Mahanagar Gas Ltd, Mumbai, India

KENNEDY VALVE Plant and Industrial Group 1021 East Water Street Elmira, New York Telephone (607) Fax (607)

Installation, Operation, and Maintenance Manual

The Implementation of a Storage Facility Inspection Program. Presented By: John R. Rueckel PCA Engineering, Inc.

Inspector's Initials: Tank Owner or Agent Signature: Title: Date:

A. This Section includes piping and related specialties for general-service compressed-air systems operating at 150 psig or less.

Broetje-Automation Company Standard Structural component specification for welded parts

PIPELINE INTEGRITY CONFERENCE BHR GROUP 5th-7th NOVEMBER 2008 SCHIPOL, THE NETHERLANDS PIPPELINE IN INDIA

Bid Summary Still Creek Wastewater Improvements Phase III City Job No. 411-D November 21, 2013

PIPELINE INSPECTION SURVEY QUESTIONNAIRE

Double-jacketed gaskets for heat exchangers sealabilty behavior in flanges with and without nubbin

TRADE EXPERIENCE LOG BOOK CANADIAN PETROLEUM CONTRACTORS ASSOCIATION. Petroleum Mechanic Training & Certification

VALVES, FIRE HYDRANTS, AND APPURTENANCES

7. Protection System Testing

Underground Storage Tank Guidance for Commercial Building Inspectors

Type B (Extruded Branch) Sizes 4 through 30

Processing Plant Enters. the Pipeline World. A Case Study of a Chemically Welded Anomaly Repair. By Randy Vaughn. R&F Pipecon Resources

ESTABLISHMENT OF ULTRASONIC TESTING IN UNIQUE DESIGNED PARTIAL PENETRATION END PLUG OF HEADER IN BOILERS.

MSC Manifolds - DIN for Steam Distribution and Condensate Collection Installation and Maintenance Instructions

AIR CLEANER GENERAL REMOVAL. 1CAUTION Do not run engine without filter element in place. Debris could be drawn into the engine causing damage.

Septic Tanks. Effluent Screen Cleaning. Effluent Screens. Surveying Abbreviations. Installation Keys. Septic Tanks, Holding Tanks & Pump Tanks

CONTENTS. Foreword...iii. 1. Introduction...1

An Introduction to Constructing and Maintaining Cathodic Protection Systems

Installation, Operation, and Maintenance Manual. Welker Automatic Insertion Corrosion Coupon Device Model AID-1CC

GAS DISTRIBUTION PRODUCTS CON-STAB ID SEAL FITTINGS

DONKIN ASSET PROTECTION SYSTEM WARRANTY UP TO 20 YEARS* DONKIN ASSET PROTECTION SYSTEM

SY-SERIES S04DA75 THRU S06DA180 & S04SR75 THRU S06SR180 DOUBLE ACTING & SPRING RETURN SCOTCH YOKE ACTUATORS

LINE STOPPING. Extending and modifying your existing pressurized system while it s under full operating conditions.

Mercy Hospital of Buffalo Catholic Health System 2 nd Floor Patient Holding Center 3 rd Floor Locker Rooms Shaflucas Architects, PC Project No.

Mass Tank Inspection Services, LLC 29 Abbey Lane Middleboro, MA masstankinspection.com

Atmos Energy DOT Report-Distribution Leaks Cause of Leak WTX LA MS CO KS KY M-TX TN VA Total

Hand Expansion Valves Built Stronger to Last Longer Sizes: 6mm (¼ ) to 305mm (4 )

Cable-Tight Wire Management System

Generator Fire Safety: Generator assemblies should be located outside the building.

Welker Adjustable Probe with Check Valve and Welker Automatic Insertion Probe with Check Valve

INSTALLATION, OPERATION, AND MAINTENANCE MANUAL WELKER SAMPLE / INJECTION PUMP

Adjustable Differential Relay A1

Series 85 Donkin Certus Range

SECTION FACILITY FUEL - NATURAL GAS PIPING AND SYSTEMS

User Guide IM/TORBAR-EN Rev. D. Averaging pitot tubes

Wide-Range Coupling Solutions

THD-SERIES S11DA280 THRU S27DA1020 & S11SR280 THRU S27SR1020 DOUBLE ACTING & SPRING RETURN SCOTCH YOKE ACTUATORS

Application for Permit to Install Underground Storage Tanks (Petroleum or Hazardous Substances) 1. Owner Information 2. Installation Site Information

LIBERTY SALES & DISTRIBUTION

Assembly instructions

UAHT BRAKE CYLINDERS. operation & maintenance instruction , S.12 NOVEMBER, Supersedes issue dated November, 1986

Client Success Story Sheri Baucom Senior Advisor II

GUIDELINE FOR GLOVEBOXES THIRD EDITION AGS-G001 February 2007

C40008 & C40009 EXHAUST BRAKES

EQUIPMENT PERFORMANCE SPILL PREVENTION AND PIPING KEVIN HENDERSON

Operating Procedures for 4 to 24 Double Block and Bleed Test and Isolation Plugs

Transcription:

007 Operate Valves 103 Non-destructive Testing (Other than testing of welds) -- Mag Particle 201 Abnormal Operating Conditions Related to Welding on Pipelines 195.452(h) 192.225 192.227 192.715 192.717 192.713 192.245 202 Monitoring of Welding Process 192.241(a) 192.241(c) 192.231 192.235 192.245 203 Visual Inspection of Welds not Non-Destructively Tested 192.241(b) 192.241(c) 204 Non-Destructive Testing (Dye Penetrant) 192.243 205 Non-Destructive Testing (Mag Particle) 192.243 207 Non-Destructive Testing (X-Ray) 192.243 208 Plastic Pipe Joining: Butt Fusion 192.281 209 Plastic Pipe Joining: Mechanical Joining 192.281 210 Plastic Pipe Joining: Electrofusion Joining 192.281 195.222 195.214 195.230 195.224 195.226 195.204 195.224 195.228 195.234 Oral Oral 195.204 Oral 211 Perform Plastic Fusion Inspection Oral 214 Joining of Metal Pipe and Components by means other than Welding - Threaded Connections 215 Joining of Metal Pipe and Components by means other than Welding- Flanged Connections 192.271 192.271 216 Joining of Metal Pipe - Compression Couplings 192.271 195.126 Page 1 Copyright 2018. Veriforce, LLC. All rights reserved. Rev. 44

218 Plastic Pipe Joining: Solvent Cement 192.281(d) (b) (c) 219 Plastic Pipe Joining: Stab Fittings 192.281 301 Install Tracer (electrically conductive) Wire (e) NA 302 Installation of Customer Meters and Service Regulators (Residential and Small Commercial) 192.353 192.355 192.357 NA 325 Installation of Above Ground Pipe 195.254 330 Installation of Plastic Pipe in a Ditch 192.319 192.325 192.327 192.328(a) 331 Installation of Plastic Pipe in a Bore 192.307 332 Installation of Plastic Pipe By Plowing (Pull-in/Planting) 192.307 401 of Buried Pipelines When Exposed 192.459 411 Inspect/Test to Assure Electrical Isolation is Adequate 192.467(d) 192.620(d)(6) 195.569 Oral 195.575 412 Install CP Leads on Pipeline Using Exothermic Weld 192.471 195.567 414 Inspect for Internal Corrosion Whenever Pipe is Removed 192.475(b)(1) 415 Monitoring for Internal Corrosion with Probes and Coupons 192.477 192.620(d)(5) 416 Monitoring for Internal Corrosion with Gas Samples 192.477 195.579(c) 195.579(b) 417 Atmospheric Corrosion Monitoring 192.481 418 General and Localized Corrosion Measurement (Remedial Measures) 192.485(a)(b) 419 Cathodic Protection Potential Measurement 192.465(a) 192.620(d)(8) 195.585(b) 195.587 195.573(a) Page 2 Copyright 2018. Veriforce, LLC. All rights reserved. Rev. 44

420 Soil Resistivity 421 Measurement of Depth of Pitting with Pit Gage 192.485 195.569 195.585 423 Perform Direct Current Voltage Gradient (DCVG) Survey 192.490 424 Perform AC Current Attenuation (ACCA) Survey 192.490 192.328(e) 425 Perform Alternating Current Voltage Gradient (ACVG) Survey 192.112(h)(3) 426 Inspect Pipe Coating with Holiday Detector 192.455(a) 192.457(a) 192.461 192.479 195.588 195.588 195.588 195.561 195.569 427 Inspection of Above or Below Ground Coatings Oral 428 Pin Brazing to Install CP Leads on Pipeline 192.471 195.567 434 Visual Inspection of Installed Pipe and Components for Mechanical Damage 435 Measure and Identify Mechanical Damage on Installed Pipe and Components 192.307 192.309 192.711 192.713 192.933 436 Perform Close Survey 192.328(e) 192.465(e) 192.620(d)(6) & (7) 195.401 195.422 195.573(a) 480 Apply Approved Coating by Hand Application 192.461(a) 195.557 482 Apply Approved Coatings by Mechanical Spray and Hand Application Methods 192.461(a) 195.557 484 Apply Approved Coatings by Wrap Application 192.461(a) 195.557 501 Conduct a Pressure Test 192.505 192.507 192.513 192.328(d) 502 Conduct Pressure Test on Pipe that is to be Operated at a Pressure <100 psig 601 Start-up/Shut-down of Pipeline to Assure Operation Within MAOP / MOP 192.509 192.511 192.513(b) 192.605(b)(5) 195.304 195.305 195.306 195.402 195.406 Oral Page 3 Copyright 2018. Veriforce, LLC. All rights reserved. Rev. 44

605 Locate Line/Install Temporary Marking of Buried Pipeline 192.614(c)(5) 195.442(c)(5) 607 Damage Prevention: Observation of Excavating and Backfilling 192.614(c)(6) 192.319(b) 611 Hot Tap (Steel Pipe) 192.627 612 Hot Tap (Plastic Pipe) 192.627 613 Purge Pipeline Facilities With Gas 192.629(a) 614 Purge Pipeline Facilities With Air or Inert Gas 192.629(b) 619 Damage Prevention during Vacuum Excavation and Backfilling Activities 661 Launching and/or Receiving Internal Devices (Pigs) 192.937(c) 192.476 192.620(d)(5)(iv ) 192.620(d)(9) 195.252 195.442(c)(6) 195.422 195.402(c)(10) Oral 192.614(c)(6) 195.442(c)(6) Oral 195.426 702 Leakage Survey with Leak Detection Device 192.706 703 Placing/Maintaining Line Markers 192.707 195.410(a) 195.410(c) 704 Permanent Field Repair by Grinding 192.713 195.226 195.230 707 Permanent Field Repair Using Bolt-On Clamp/Sleeve 192.717 195.422(a) 195.585(a)(2) 716 Inspect, Maintain, and Operate Valves 192.745 192.747 195.420(a) 195.420(b) Oral 725 Aerial Leakage Survey: Transmission 192.706 728 Aerial Leakage Survey: Transmission (UV/IR) 192.706 740 Above Ground Supports and Anchors: Inspection, Preventive and Corrective Maintenance 741 Installation and Maintenance of Casing Spacers, Vents and Seals 742 Temporary Isolation of Service Lines and Service Discontinuance 192.323 192.379 192.727(d) 762 Line Stopping Utilizing a Hot Tap Fitting 763 Squeeze Off Plastic Pipe 192.703(b) Page 4 Copyright 2018. Veriforce, LLC. All rights reserved. Rev. 44

902 Field Bending of Pipe 192.313 904 Inspection of Material 192. 328(a)(1) Oral 905 Lowering/Installation of Steel Pipe into Ditch 192.328(a) 192.319 908 Installation of Cathodic Protection 192.453 192.620(c)(6) BHE 220 Plastic Pipe Joining: Sidewall Heat Fusion 192.281 BHE 321 Installation of Steel Pipe in a Ditch 192.319 192.325 192.327 192.328(a) BHE 322 Installation of Steel Pipe in a Bore 192.307 195.246 195.246 195.248 195.250 BHE 325 Installation of Above Ground Pipe 195.254 BHE 740 Above Ground Supports and Anchors: Inspection, Prevention, and Corrective Maintenance 192.161 192.203 Page 5 Copyright 2018. Veriforce, LLC. All rights reserved. Rev. 44