Power System Operating Incident Report Trip of Murray Lower Tumut No kv Transmission Line at Murray End Only on 18 November 2013

Similar documents
POWER SYSTEM OPERATING INCIDENT REPORT: TRIP OF 837 TARONG MT. ENGLAND 275 KV LINE AND MT. ENGLAND NO KV BUSBAR ON 30 OCTOBER 2011

POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF 220 KV C BUSBAR AT GORDON POWER STATION ON 26 NOVEMBER 2011

Power System Operating Incident Report Trip of Red Cliffs Horsham and Red Cliffs-Wemen Kerang 220 kv transmission lines on 15 January 2014

POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 UNIT ON 9 FEBRUARY 2012

POWER SYSTEM OPERATING INCIDENT REPORT TRIPS OF YALLOURN W POWER STATION UNITS W1 AND W3 ON 14 NOVEMBER 2012

POWER SYSTEM OPERATING INCIDENT REPORT LIGHTNING STRIKES IN TASMANIA AND PACIFIC ALUMINIUM POTLINE LOAD REDUCTIONS 21 MARCH 2013

POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF B 220 KV BUSBAR AT GEORGE TOWN ON 27 NOVEMBER 2012.

POWER SYSTEM OPERATING INCIDENT REPORT MULTIPLE CONTINGENCY EVENT IN NORTH WEST TASMANIA ON 6 APRIL 2012

POWER SYSTEM INCIDENT REPORT: TRIP OF NO 1 AND 2 NEW OSBORNE 66 KV BUSBARS ON 26 SEPTEMBER 2010

TRIP OF HORSHAM-REDCLIFFS 220 KV TRANSMISSION LINE AND MURRAYLINK INTERCONNECTOR ON 12 NOVEMBER 2015

MULTIPLE LINE OUTAGES IN THE MOUNT ENGLAND TARONG AREA IN QUEENSLAND, 13 FEBRUARY 2017

POWER SYSTEM INCIDENT REPORT NORTHERN POWER STATION STABILISER OUTAGE APRIL AND MAY 2010

POWER SYSTEM INCIDENT REPORT: OVERLOAD OF WAUBRA- HORSHAM 220 KV TRANSMISSION LINE AND INSECURE OPERATION OF THE SYSTEM ON 13 DECEMBER 2012

Utilities (Technical Regulation) (Electricity Transmission Supply Code) Approval 2016 (No 1)*

Jemena Electricity Networks (Vic) Ltd

SUBSTATION INTERLOCKING SCHEMES

18/10/2018. Mr Peter Adams General Manager, Wholesale Markets Australian Energy Regulator. By

South Australia Victoria (Heywood) Interconnector Upgrade. RIT-T: Project Specification Consultation Report

The Energy Queensland Group Notice of no non-network options

National Grid UK Electricity Transmission plc. NATIONAL SAFETY INSTRUCTION and Guidance

Final Capacity Auction Results 2018/2019 T-1 Capacity Auction. Date 26/01/2018 Version 1.0

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders

Final Capacity Auction Results 2019/2020 T-1 Capacity Auction. Date 01/02/2019 Document: FCAR1920T-1 Version 1.0

Installation Power Management Unit Battery Cables and Battery Harness

XXXXX. Kokish River Hydroelectric Project. Interconnection Facilities Study and Project Plan

Guideline for Parallel Grid Exit Point Connection 28/10/2010

Engineering Instruction

Header. Reasonableness Test RT 007/11 Balhannah & Uraidla 66 / 33 kv Substations. RT Balhannah and Uraidla - Final Draft Page 1 of 8

Managing Electrical Safety on Boats

Guidelines for connection of generators:

TRANSMISSION PLANNING CRITERIA

ELECTRICITY TRANSMISSION USE OF SYSTEM PRICES - 1 JULY 2014 TO 30 JUNE 2015

Eyre Peninsula electricity supply options investigation

Energy Regulation : Australian Experience. Engr.Khondkar Abdus Saleque

Installation Guide Smart-UPS On-Line External Battery Pack XBP48RM1U-LI

Feasibility Study for the Q MW Solar Project

Scania Used Vehicle Extended Driveline Warranty

Title Electrical Technical Maintenance Coding System. Reference Number PMP 01 (RIC Standard: EP SP)

Embedded Generation Guidelines

80V 300Ah Lithium-ion Battery Pack Data Sheet

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

Title High Voltage and 1500 System Earthing References and Definitions. Reference Number PDS 02 (RIC Standard: EP SP)

Reference Number PDS 18 - (RIC Standard: EP SP)

Summary of General Technical Requirements for the Interconnection of Distributed Generation (DG) to PG&E s Distribution System

Instruction Manual PC104/PC105 3-PHASE SOCKET TESTER. Check out what else you can get from Martindale:

Facilities Study for Alberta to US Available Transfer Capability

The Ultimate Smart Grid Solution INSTRUCTION MANUAL

Enquiry Form for Micro and Small Generators 5MW and Less

Maintenance of Signal Sighting and Signals

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks

Bald Hill on track to start lithium concentrate production this quarter

EROAD Inspect In-Vehicle User Guide

Grid Tied Limiter User Manual

N G 3 S p r i n g B r a k e s

Enquiry Form (Non-Registered Generator With Capacity less than 5 MW)

MINIMUM OIL BURN/AUTOMATIC FUEL SWAPPING CAPABILITY

THE ISSUE AND USE OF SECTION 10B PERMITS FOR ROAD PASSENGER TRANSPORT AND MINIBUS DRIVING IN NORTHERN IRELAND

650mA Phase Dimmable LED Driver

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

Construction Safety Amendment (Amusement Devices) Regulation 1998

Electricity Safety (Electrical Installations) Regulation 2005

II DISTRIBUTION & SUBSTATION TYPE C

The Management of Electrical Safety in Quarries, Associated Plant and Equipment

Craigieburn Employment Precinct North and English Street

PMD DRIVER RELOCATION KIT For Chevy 6.5L Diesel Trucks

Vertabelo Academy. Terms of Service PLEASE READ ALL OF THE FOLLOWING TERMS OF SERVICE BEFORE USING THIS WEBSITE A. General Terms

Broadband PowerShield. CP27U Models. User Manual

1000mA - 650mA Phase Dimmable LED Driver

NZQA Expiring unit standard 893 version 5 Page 1 of 5. Diagnose and rectify vehicle emission control system faults

Jemena Electricity Networks (Vic) Ltd

Higher Tier Wednesday 17 November 2010 Morning Time: 1 hour 30 minutes

www. ElectricalPartManuals. com Instructions for Field Testing of Ground Fault Systems Utilizing Cutler-Hammer Magnum DS Circuit Breakers

SOUTH AUSTRALIAN HISTORICAL MARKET INFORMATION REPORT SOUTH AUSTRALIAN ADVISORY FUNCTIONS

Conductor Strength Tests on ACCR 1622TW T13 Pecos Conductor

Utilization of Electric Power Laboratory 3 rd Year G2: Testing & Characteristic of MCCB Used in Commercial and Industrial Applications

UL/cUL FILE NUMBER E CE See last page of manual for CE Declaration of Conformity.

Thruster control assemblies ref iss.1

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

Matson Programmable Voltage Sensitive Relay MA98411

Power. On Your Terms.

Eyre Peninsula Electricity Supply Options

15 Nelson-Marlborough Regional Plan

Title Low Voltage Distribution and Installations Earthing References and Definitions. Reference Number PDS 03 (ARTC Standard: EP SP)

WELLINGTON, NEW ZEALAND. PURSUANT to section 152 of the Land Transport Act Land Transport Rule: Vehicle Standards Compliance 2002

Installation / Operation Instructions Sunnex ORION Series Exam Lights

Technical Standard - TS 129. Small Inverter Energy Systems (IES) - Capacity not exceeding 30kW. SA Power Networks. Published: November 2017

Installation and Operation Instructions Safety Director Arrow

100 MW Wind Generation Project

Discipline: Engineering (Track & Civil) Category: Code of Practice. Clearances. Section 7. Applicability. ARTC Network wide.

The Ultimate Smart Grid Solution INSTRUCTION MANUAL

OPERATION MANUAL Variable Speed Pump Controller Dated: 06/04/2013 Pump Down Application. Document No.: LMSII_V100_OM Page 1 of 8 Model-V100 LMS II

Granatelli Front & Rear Sway Bars FOR MUSTANG GT and V6 Part # GM-SB0507 INSTALLATION INSTRUCTIONS

1 This instrument must only be used by a competent and trained person and operated in strict accordance with the instructions.

WSAA PRODUCT APPRAISAL CERTIFICATE

GUIDELINES FOR OPERATING, METERING AND PROTECTIVE RELAYING FOR. NET METERED SYSTEMS UP TO 50 kw AND BELOW 750 VOLTS

DALI Emergency LED Driver - 350/700/1000mA Constant Current

REAL WORLD DRIVING. Fuel Efficiency & Emissions Testing. Prepared for the Australian Automobile Association

Emerald Reactive Support Alternative Solution Expressions of interest

DALI 650mA LED Driver

4-20mA DC PROCESS CLAMP METER

Transcription:

Power System Operating Incident Report Trip of Murray Lower Tumut No.66 0 kv Transmission PREPARED BY: AEMO Systems Capability DATE: 1 December 201 FINAL

Version Release History VERSION DATE BY CHANGES CHECKED BY AUTHORISED BY 1 9 Dec 201 Peter McEniery Final Steven Darnell Peter Biddle Disclaimer Purpose This report has been prepared by the Australian Energy Market Operator Limited (AEMO) for the sole purpose of meeting obligations in accordance with clause 4.8.15 (c) of the National Electricity Rules (NER). No reliance or warranty This report contains data provided by third parties and might contain conclusions or forecasts and the like that rely on that data. This data might not be free from errors or omissions. While AEMO has used due care and skill, AEMO does not warrant or represent that the data, conclusions, forecasts or other information in this report are accurate, reliable, complete or current or that they are suitable for particular purposes. You should verify and check the accuracy, completeness, reliability and suitability of this report for any use to which you intend to put it, and seek independent expert advice before using it, or any information contained in it. Limitation of liability To the extent permitted by law, AEMO and its advisers, consultants and other contributors to this report (or their respective associated companies, businesses, partners, directors, officers or employees) shall not be liable for any errors, omissions, defects or misrepresentations in the information contained in this report, or for any loss or damage suffered by persons who use or rely on such information (including by reason of negligence, negligent misstatement or otherwise). If any law prohibits the exclusion of such liability, AEMO's liability is limited, at AEMO's option, to the re-supply of the information, provided that this limitation is permitted by law and is fair and reasonable. 201 Australian Energy Market Operator Ltd. All rights reserved 1 December 201 Page 2 of 7

Incident Classifications Time and date and of incident 1729 hrs Monday 18 November 201 Region of incident Affected regions Event type Primary cause Impact Associated reports NSW NSW OTH - Other OE & CON Operating Error and Non-conformance Nil - No Impact Nil Abbreviations and Symbols Abbreviation AEMO CB CVT EMMS EMS kv MSS NEM NER Term Australian Energy Market Operator Circuit Breaker Capacitor Voltage Transformer Electricity Market Management System Energy Management System Kilovolt Murray Switching Station National Electricity Market National Electricity Rules 1 December 201 Page of 7

1 Introduction This report reviews a power system operating incident that occurred on 18 November 201 in the New South Wales region at Murray Switching Station (MSS). AEMO is required to review this incident as it satisfies the requirements of a reviewable operating incident under the National Electricity Rules 1 (NER). The purpose of this incident review is to assess power system security over the course of the incident. The NER requires AEMO to assess the adequacy of the provision and response of facilities and services and the appropriateness of actions taken to restore or maintain power system security 2. This report is based upon information provided by TransGrid. Data from AEMO's Energy Management System (EMS) and Electricity Market Management System (EMMS) has also been used in analysing the incident. All references to time in this report are to National Electricity Market time (Australian Eastern Standard Time). 2 The Incident On Monday 18 November 201, at 1729 hrs, a 0 kv circuit breaker at MSS tripped. This trip offloaded the Murray Tumut No.66 0 kv transmission line. This was an unexpected event as there was no fault on the transmission system, and the Murray Tumut No.66 0 kv transmission line remained energised from Tumut Terminal Station (transmission lines usually trip at both ends). No load or generation was lost as a result of this incident, and the tripped circuit breaker (CB 662B) was returned to service within two minutes. TNSP Investigation On Monday 18 November 201 TransGrid were undertaking planned work at MSS. The planned work required 5A1 0 kv busbar to be removed from service. As part of this work the secondary links of the busbar capacitor voltage transformer (CVT) were to be isolated. Instead the secondary links of a CVT on the No. 66 0 kv Murray Tumut transmission line was inadvertently isolated. The CVT provides voltage measurements to protection controlling the 0 kv CB 662B at MSS. The apparent failure of the CVT initiated the trip of the 0 kv CB 662B at MSS. TransGrid immediately identified and rectified by the inadvertent CVT isolation. 4 Pre-Incident State The status of the power system prior to the incident is shown in Figure 1. For clarity only equipment relevant to this incident has been included in the diagram. The diagram shows No. 5A1 0 kv busbar at MSS out of service for planned work. 1 NER v59 Clause 4.8.15(a)(1)(i) and AEMC Reliability Panel Guidelines for Identifying Reviewable Operating Incidents. 2 NER v59 Clause 4.8.15 (b) 1 December 201 Page 4 of 7

Figure 1 - Status of the power system prior to the incident MURRAY SWITCHING STATION Bus removed from service 10 9 8 7 6 5 4 2 1 1000 900 800 5 4 700 600 500 400 2 00 200 1 100 1_2 68 67 66 65 5A2 5102 5A1 682A 672A M72 M12A M112A M12 5412 662A 652A 682B 672B M92 M12B M52B M112B M2 662B 652B 5B2 5112 5B1 5419 5429 7 6 1 2 1400 100 1200 1100 14 1 12 11 0 kv Busbar, line 12 kv Busbar, line 0/15/15 kv Transformer Closed CB Open CB 0/12 kv Transformer 15 kv Busbar, line CVT Out of service Busbar, line Closed Isolator Open Isolator Generator 5 Incident Event Log The sequence of events comprising the incident are itemised in Table 1. The incident spanned approximately two minutes from the trip of the 0 kv CB 662B at MSS. Table 1 Event Log Date and Time Event 1729 hrs 18 November 201 Secondary links of the CVT on the Murray Tumut No.66 0 kv transmission line inadvertently isolated. 1729 hrs 18 November 201 The 0 kv CB 662B at MSS trips out of service. 171 hrs 18 November 201 Remedial action taken by TransGrid. 0 kv CB 662B at MSS manually reclosed by TransGrid. 1 December 201 Page 5 of 7

6 Post-Incident State The status of the power system immediately after the incident is shown in Figure 2. The diagram shows the 0 kv CB 662B at MSS open and the Murray Tumut No. 66 0 kv transmission line energised from the Tumut end. Figure 2 - Status of the power system immediately after the incident MURRAY SWITCHING STATION 10 9 8 7 6 5 1000 900 800 700 600 500 5 4 400 4 2 00 200 Line energised from Tumut 2 1 CVT links isolated out of service 1 100 1_2 68 67 66 65 5A2 5102 5A1 682A 672A M72 M12A M112A M12 5412 662A 652A 682B 672B M92 M12B M52B M112B M2 662B 652B 5B2 5112 5B1 5419 5429 1400 7 100 1200 6 CVT remains in 1 2 service (intended to be isolated) 1100 CB tripped out of service 14 1 12 11 0 kv Busbar, line 12 kv Busbar, line Out of service Busbar, line 0/15/15 kv Transformer Closed CB Open CB 0/12 kv Transformer 15 kv Busbar, line CVT Closed Isolator Open Isolator Generator 7 Immediate Actions The cause of the trip was immediately identified by TransGrid, and the links to the CVT were restored. At 171 hrs the 0 kv CB 662B at MSS was reclosed manually by TransGrid. This prompt response obviated the need for AEMO to invoke constraints to manage power system security. TransGrid then advised AEMO that the cause of the event had been identified, resolved and was unlikely to reoccur. AEMO should then have issued a market notice to inform the market that a non-credible contingency had occurred. AEMO has since clarified and reinforced with its staff that the trip of a transmission line at one end is a non-credible contingency event and thereby requires a market notice to be issued. 8 Follow-up Actions No further actions were required by TransGrid or AEMO. Section 11., SO_OP715 AEMO Power System Security Guidelines 1 December 201 Page 6 of 7

9 Power System Security Following a non-credible contingency event AEMO is required to assess whether or not to reclassify the event as a credible contingency 4 and to report how re-classification criteria were applied 5. AEMO has to determine if the condition that caused the non-credible contingency event has been resolved. For this event AEMO did not reclassify the event as a credible contingency because TransGrid had promptly advised AEMO that the cause of the event had been identified, resolved and was unlikely to reoccur. 10 Conclusions The trip of the 0 kv CB 662B at MSS was initiated by the inadvertent removal of CVT links during planned work. Over the course of the incident, the response of AEMO and TransGrid was appropriate to maintain power system security. AEMO should have issued a Market Notice declaring the incident to be a non-credible contingency and that a reclassification of the incident was not required. 11 Recommendations There are no recommendations arising from this incident. 4 NER v59 Clause 4.2.A (c) 5 NER v59 Clause 4.8.15 (ca) 1 December 201 Page 7 of 7