MADHYA PRADESH POWER TRANSMISSION COMPANY LIMITED STATE LOAD DESPATCH CENTRE, NAYAGAON, RAMPUR, JABALPUR

Similar documents
MADHYA PRADESH POWER TRANSMISSION COMPANY LIMITED STATE LOAD DESPATCH CENTRE, NAYAGAON, RAMPUR, JABALPUR

MADHYA PRADESH POWER TRANSMISSION COMPANY LIMITED STATE LOAD DESPATCH CENTRE, NAYAGAON, RAMPUR, JABALPUR

MADHYA PRADESH POWER TRANSMISSION COMPANY LIMITED STATE LOAD DESPATCH CENTRE, NAYAGAON, RAMPUR, JABALPUR

Corporate office: Madhya Pradesh Power Transmission Co. Ltd., Block No.2, Shakti Bhawan, Rampur, Jabalpur , CIN-U40109MP2001SGC01

No.07-05/SG-9B-II/4084 Jabalpur, dated:

MP POWER TRANSMISSION COMPANY LIMITED STATE LOAD DESPATCH CENTRE, NAYAGAON, JABALPUR

No.07-05/SG-9B-II/1594 Jabalpur, dated

MP POWER TRANSMISSION COMPANY LIMITED STATE LOAD DESPATCH CENTRE, NAYAGAON, JABALPUR

MADHYA PRADESH POWER TRANSMISSION COMPANY LIMITED STATE LOAD DESPATCH CENTRE, NAYAGAON, RAMPUR, JABALPUR

Corporate office: Madhya Pradesh Power Transmission Co. Ltd., Block No.2, Shakti Bhawan, Rampur, Jabalpur , CIN-U40109MP2001SGC01

MADHYA PRADESH POWER TRANSMISSION COMPANY LIMITED

In view of the above list of important grid element & exception list is as below:-

MINUTES OF THE 47 th SLCF MEETING HELD ON

No.07-05/SG-9B-II/ 1179 Jabalpur, dated been uploaded on the website of SLDC and can be downloaded.

KERALA STATE ELECTRICITY REGULATORY COMMISSION. NOTIFICATION Dated, Thiruvananthapuram 6 th August,2007

UP Electricity Regulatory Commission Vidyut Niyamak Bhawan, Vibhuti Khand, Gomti Nagar, Lucknow. Public Notice

Guidelines for Solar Grid Power Projects

STATE LOAD DISPATCH CENTRES (SLDC)

Renewable Regulatory Fund (RRF) Mechanism : -

Sub : In the matter of determination of Parallel Operation Charges. MPERC, Bhopal - Petitioner

Bihar Electricity Regulatory Commission Vidyut Bhawan, J.L.Nehru Marg, Patna

Annex_Tumkur In-principle(Phase-I) 1)Minutes of the meeting held on )In-principle Approval_Tumkur Phase-I

Case No. 163 of In the matter of

Case No. 109 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member. Maharashtra State Electricity Distribution Co. Ltd.

The Electric Power System

4,1 '~ ~ ~ 1I1f lc/)~ul I Central Electricity Authority

Agenda of 11 th System Studies Meeting in NER

EXTRA ORDINARY 16 AASHAADHA, 1937(S) BIHAR ELECTRICITY REGULATORY COMMISSION

Wheeling charges, Banking charges & Cross Subsidy Surcharge for Solar Power Generators

HARYANA POWER GENERATION CORPORATION LIMITED Regd. Office C-7, Urja Bhawan, Sector-6, Panchkula Corporate Identity Number: U45207HR1997SGC033517

Agenda for Connectivity and Long Term (Open) Access of IPP Generation Projects in Odisha of Eastern Region

(i) Establishment of 400kV Pooling Station at Fatehgarh (with a provision to upgrade at 765kV level)

Western Power s list of exemptions from compliance from Technical Rules granted after 1 July 2007.

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

Maharashtra Electricity Regulatory Commission (Renewable Purchase Obligation, Its. Regulations, 2016 STATEMENT OF REASONS

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Intra-State Availability Based Tariff (ABT)

Case Nos. 12 & 48 of 2009

IJRASET 2013: All Rights are Reserved

Georgia Transmission Corporation Georgia Systems Operations Corporation

Implementation procedure for certification and continued airworthiness of Beriev Be-200E and Be-200ES-E

APPLICATION FOR INSTALLATION OF SMALL SCALE EMBEDDED ELECTRICITY GENERATION

Proposed New ISO Rules Section Version 2.0 Generating Unit Technical Requirements ( New ISO Rules Section Version 2.

CASE No. 35 of In the matter of

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program.

Additional Agenda for 31 st Standing Committee Meeting of Power System Planning for Northern Region

Reactive Power Requirements and Financial Compensation. Addendum to Draft Final Proposal

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS.

Policy & Regulatory Issues : Solar & Wind. Shri Rajinder Kumar Kaura CMD, Bergen Group India 21 st August 2014

DETAILED NOTICE INVITING TENDER WEST BENGAL STATE ELECTRICITY TRANSMISSION COMPANY LIMITED. (A Govt of West Bengal Enterprise)

Need Assessment Document (NAD) DDUGJY

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation

Before the. Case No. 106 of 2009

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

Report. the feasibility of

Key DRAFT OPERATING CODE 2 LEGAL TEXT

Respondent 1) The Asst. Exe. Engineer, Electrical Sub Division, Pattanakkad

THE PUBLIC SERVICE COMMISSION OF WYOMING

TRANSMISSION CAPACITY ADDITION PROGRAMME DURING No. 1 Introduction 1

TRANSMISSION PLANNING CRITERIA

UTTARAKHAND POWER CORPORATION LIMITED

Umatilla Electric Cooperative Net Metering Rules

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) APPLICATION

TARIFF SCHEDULES FOR HIGH TENSION CONSUMERS. Table of Contents

Infrastructure Revitalization in India Power System Operation Corporation (POSOCO) New Delhi, India

Impact of Distributed Energy Resources on Transmission System Reliability

February 13, Docket No. ER ; ER Response to Request for Additional Information

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Role of Energy Storage Technologies in Providing Ancillary Services, Improving Power Quality and Reliability of the Indian Grid

Petition No. 1051, 1054 & 1055 of 2015 BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW Date of Order :

JAMMU AND KASHMIR STATE POWER DEVELOPMENT CORPORATION LIMITED PUBLIC NOTICE

Alberta Electric System Operator Saleski Transmission Project Needs Identification Document

ISLANDING SCHEME FOR STATION DURING GRID BLACK-OUT

POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 UNIT ON 9 FEBRUARY 2012

R.S.USHA CHIEF ENGINEER/ PLANNING & RC. Encl: Report and detailed estimate. To The Chief Engineer/D/Madurai Region

Minutes of the 19 th meeting of the Standing committee on transmission system of Northern Region held at Amritsar on 01/10/05.

RFP Corrigendum No. 01

TECHNICAL SPECIFICATION FOR 11 KV AUTOMATIC CAPACITOR SWITCH

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

North Eastern Regional Power Committee

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016

In-House Paper on the implementation of Single Part Tariff in Power Distribution

Merger of the generator interconnection processes of Valley Electric and the ISO;

List of exemptions from compliance with the Technical Rules granted by Western Power after 1 July 2007

Interconnection System Impact Study Report Request # GI

PRAGATI ENGINEERING COLLEGE

Guideline for Parallel Grid Exit Point Connection 28/10/2010

7 The revised IS 8034:2002 and revised STI be implemented w.e.f. 1 Feb 2005.

EC Forum on Model Approaches to Distribution Pricing. June 2009

Southern California Edison Rule 21 Storage Charging Interconnection Load Process Guide. Version 1.1

Comparison of Indian Electricity Rules, 1956 Vs CEA (Measures relating to Safety and Electric Supply) Regulations, 2010

Terry Blackwell Page 1 of 5. Education North Carolina State University BS, Electrical Engineering Power Systems emphasis

GC108: EU Code: Emergency & Restoration: Black start testing requirement

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

Street Address. City-Village-Township

Modular Standardized Electrical and Control Solutions for Fast Track Projects

MMP Investigation of Arthur Kill 2 and 3

First Revision of Sheet No P.S.C.U. No. 50 Canceling Original Sheet No ROCKY MOUNTAIN POWER ELECTRIC SERVICE SCHEDULE NO.

Transcription:

MADHYA PRADESH POWER TRANSMISSION COMPANY LIMITED STATE LOAD DESPATCH CENTRE, NAYAGAON, RAMPUR, JABALPUR Telephone: (0761) 2970089 Fax: (0761) 2664343/2970119 e-mail sldcmpjbp@gmail.com Corporate office: Madhya Pradesh Power Transmission Co. Ltd., Block No.2, Shakti Bhawan, Rampur, Jabalpur 482008, CIN-U40109MP2001SGC014880, Email-mdtransco.nic.co.in No.07-05/SG-9B-II/3164 Jabalpur, dated:01.11.18 To As per distribution list Sub: Minutes of 65 th meeting of Operation and Coordination Committee of MP. The Minutes of 65 th meeting of the Operation and Coordination Committee of MP held on 14 th September 2018 at Conference Hall, SLDC, MPPTCL, Nayagaon, Jabalpur has been uploaded on the website of SLDC www.sldcmpindia.com and can be downloaded. (R.A. Sharma) Member Secretary, OCC SLDC, MPPTCL, Jabalpur

Distribution List 1. The Chief Engineer (Works), MP Power Transmission Co. Limited, Shakti Bhawan, Jabalpur, emailceehtmi@yahoo.com. 2. The Chief Engineer (T&C), MP Power Transmission Co. Limited, Jabalpur. Fax No- 0761-2665593, 2702710 Emailcetandc@gmail.com 3. The Chief Engineer (Transmission-East Zone), MP Power Transmission Co. Limited, Shakti Bhawan, Jabalpur. Emailsk.gaikwad@mptransco.nic.in. 4. The Chief Engineer (Transmission-West Zone), MP Power Transmission Co. Limited, Indore. 5. The Chief Engineer (Transmission-Central Zone), MP Power Transmission Co. Limited, Bijlee Nagar, Govindpura, Bhopal, email- setncbpl@gmail.com. 6. The Chief Engineer (Plg & Des), MP Power Transmission Co. Limited, Jabalpur, Fax No- 0761-2660908 Emailceps321@yahoo.com 7. The Chief Engineer (Procurement.), MP Power Transmission Co. Limited, Jabalpur,.Fax No- 0761-2660908 Email substation_vi@yahoo.com 8. The Chief Engineer(EHT:Const.), MP Power Transmission Co. Limited, Jabalpur. Fax-0761-2661618, E-mailce.ehtc@mptransco.nic.in. 9. The Chief Engineer(EHT:Maint&insp.), MP Power Transmission Co. Limited, Jabalpur. Fax-0761-2665593, E-mailce.mni@mptransco.nic.in. 10. The Executive Director (O & M:Gen), MP Power Generating Company Limited, Jabalpur. Fax No- 0761-2664749, Email- gcc.mppgcl@gmail.com, Email- edomg_mpeb@rediffmail.com 11. The Chief Engineer (O&M:Hydel), MP Power Generating Co. Ltd, Jabalpur, Fax No-0761-2664749. 12. The General Manager(PM), MPPMCL, Jabalpur Email gm_pm@mptradeco.com controlroom.tradeco@gmail.com 13. The Superintending Engineer (GCC), MPPGCL, Jabalpur Email segcc.mppgcl@gmail.com gcc.mppgcl@gmail.com. 14. The General Manger (DCC-EZ), DISCOM Control Centre, MP Poorva Kshetra Vidyut Vitaran Co.Limited, Jabalpur, Fax No- 0761-2668503, Email cmdez_ld@yahoo.co.in. 15. The Dy. General Manager (DCC CZ), DISCOM Control Centre, MP Madhya Kshetra Vidyut Vitaran Co. Limited, Bhopal, Fax No-0755-2580611,Email- plm.mpcz@gmail.com. 16. The Executive Engineer (DCC-WZ), DISCOM Control Centre, MP Paschim Kshetra Vidyut Vitaran Co. Limited, Near Polo Ground, Jail Road, Indore, Fax No- 0731-2421554, Email- dccindore@gmail.com. 17. The Executive Engineer, Sub Load Despatch Centre, MPPTCL, Indore, Fax No- 0731-2874515, Email eesubldcind@yahoo.com. 18. The Executive Engineer, Sub Load Despatch Centre, MPPTCL, Bhopal, Fax No- 0755-2885220, Email aldc_bpl@yahoo.co.in 19. The General Manger(RO), MPPMCL, In front of Bhojpur Club, E-4, Arera Colony,Bhopal, Fax No-0755-2423046, Email-Rajeev_keskar@rediffmail.com 20. The Chief Engineer (PM&C), Narmada Hydroelectric Development Corpn. Ltd, NHDC Parisar, Shamla Hills, Bhopal 462013., Fax No- 0755-4030130,Email om.co.nhdc@gmail.com 5vinodnhdc@rediffmail.com 21. The Chief Electrical Distribution Engineer, West Central Railway (WCR), General Manager s Office, Electrical Department, Jabalpur-482001 (MP), Fax: 0761-2627629, Email- cede@wcr.gov.in, dyceetrdwcr@gmail.com, M- 9752415312, Mr.Satyendra Kumar (Dy.CE), Mob.9752415301 (CEDE, WCR). 22. The General Manager, Indira Sagar Power Station, NHDC Office complex, PO : Narmada Nagar, Distt : Khandwa (MP) 450 119, Fax No- 07323-284080, Email nhdc-isp@rediffmail.com 23. The General Manager, Omkareshwar Power Station, Prashsnik Bhawan, Urja Vihar, Sidhwarkut, Distt : Khandwa (MP) 450 554, FaxNo-07280-271703, Email- pksaxena@nhdcl.com, saxena_pks123@rediffmail.com, omkareshwar.nhdc@gmail.com. 24. The Director (Projects), BLA Power Limited, At : Niwari, PO: Khorsipan, Tah : Gadarwara, Distt ; Narsinghpur 487 551, Fax No. 07791-243667 / 243669, Email manish@bla.co.in 25. The Sr. Vice President, Jaiprakash Power Ventures Ltd., Village Sirchopi Subpost Office-Agasod, Post Office-Bina- 470113 Distt- Sagar, Fax No. 07580-277200, Email jbtppbina400kvswitchyard@gmail.com jptpp.switchyard@jalindia.co.in, 26. The Chief Executive Officer, Kalpataru Satpura Transco Pvt. Ltd., Satpura Colony, Betul Road, Old Itarsi, Distt. Hoshangabad, Email cbhandari@kalpatarupower.com 27. M/s Ujaas Energy Ltd. 701, NRK Business park, Vijay Nagar Sqaure, Indore 452010, Email id :-solar@ujaas.com 28. M/s Suzlon Global Services Ltd., 1090, Scheme no. 114, Park-2, Ring Road, Universal Hospital Row, Email- deepesh.sankwa@suzlon.com, Indore 452010, Badree.hirve@suzlon.com

MINUTES OF 65 th MEETING OF OPERATION & COORDINATION COMMITTEE OF MP HELD ON 14th SEPTEMBER 2018 AT 11:00 AM AT CONFERENCE HALL, SLDC, MPPTCL, NAYAGAON, JABALPUR. The 65th meeting of Operation & Coordination Committee of MP was held on 14th September 2018 at 11:00 AM at SLDC, MPPTCL, Nayagaon, Jabalpur. The list of participants is enclosed at Annexure -1.0. Shri K.K.Parbhakar C.E.(SLDC) & Chairman OCC welcomed all the guests & participants for 65th OCCM of MP. Chairman OCC requested all the guests &participants to ensure their presence in OCC meeting so that delay in starting the meeting is avoided & operational issues are discussed in detail and without lack of time. He stated that the upcoming months will be crucial from operational point of view due to increase demand of Rabi season. For meeting the increased demand in Rabi season support from NVDA & MPPGCL will be required. Further as MPPGCL has committed for availability of 3700MW generation during the month on Oct-18 & November-18, hence MPPGCL is requested to fulfill its commitment so that Rabi season demand of MP can be met successfully. He also stated that may be a situation of coal shortage with thermal generators, therefore MPPGCL may ensure remedial measures so that 3700MW generation as per their commitment could be fulfilled.. In response to this, representative from MPPGCL informed the committee that MPPGCL is trying to mitigate the coal shortage and will try to comply to 3700mw generation availability commitment. Chairman OCC also stated that one of the major issues with MPPGCL is of coordination of Hydel generators with NVDA &WRD, want of this proper planning/scheduling of hydel machines cannot be done. Considering requirement of NVDA/WRD, hydel m/c should be run in planned manner and taking the unit suddenly on BAR in an haphazard manner should be avoided, which disturbs the complete planning of generation availability in real time. He requested MPPGCL to coordinate properly with NVDA & WRDfor optimum use of hydel generation & mitigate the demand/grid requirement with hydel generation. Further Chairman OCC stated that as per provisions of MPEGC Regulation, SLDC is computing the DSM for intra wind & solar generators from the month of August- 18. He also mentioned that SLDC has planned to implement AGC-secondary response for Singha Ji TPS Ph-I & also requested MPPGCL to coordinate SLDC for implementation of AGC. He also informed the committee that as installation of 2 Units of MPPGCL is planned to be installed at Satpura TPS, therefore for commissioning of new thermal units at STPS, its complete 220 KV switchyard will be dismantled and the same was confirmed by MPPGCL representative in the meeting. Further he requested MPPTCL to submit the planning of transmission network considering proposed panning of dismantling of STPS 220 KV switchyard in coordination with MPPGCL so that the transmission network availability is ensured prior to dismantling of STPS 220 KV switchyard and commissioning of new thermal unit at STPS. He also stated that the Black Start Mock Drill at OSP HPS is still pending due to its outage of Bus Coupler Breaker and requested OSP to ensure availability of its Bus Coupler Breaker and propose a date for conducting the Black Start Mock Drill at OSP HPS. Thereafter he requested Member Secretary to take up the agenda points. Shri R.A.Sharma Member Secretary OCC & Addl. Chief Engineer, SLDC welcomed all the guests and participants for 65thOCCM. He stated that as apprised by Chairman OCC, that rightful communication may be done by MPPGCL with NVDA / WRD for proper planning of hydel generation in such a manner that hydel machines are run/scheduled as per the grid requirement instead of running one machine round the clock and during OFF peak hours and its drinking water requirement is also fulfilled. Thereafter the agenda points were taken up which is narrated here under in nutshell: ITEM NO. 1 : CONFIRMATION OF MINUTES : The committee was intimated that Minutes of 64 TH meeting of Operation & Coordination Committee of MP held on 09 th July 2018 at SLDC, MPPTCL, Jabalpur were forwarded to the committee members vide No. 07-05/SG-9B-II/2652 Jabalpur dated 31.08.2018. No comments have been received, hence committee confirms the minutes. Minutes Of 65th OCCM Of MP 1

ITEM NO. 2 : REVIEW OF SYSTEM OPERATION DURING THE MONTHS JUNE 2018 TO JULY 2018. 2.1. Frequency Particulars: The committee was apprised that during JUNE 2018 the system frequency was below 49.90 Hz for 11.48% of time against 10.25 % of time during JULY 2018. The system frequency was above 50.05 Hz for 11.19 % of time during JUNE 2018 against 11.27 % of time during JULY 2018. The system frequency was within the IEGC range of 49.90-50.05 Hz for 76.97 % of the time during JUNE 2018 against 78.48 % of time during JULY 2018. The average monthly frequency was 49.98 Hz during month of JUNE 2018 and 49.95 Hz during month of JULY 2018. The system frequency did not touch 49.98 Hz during the above period. The detailed frequency particulars for the month of JUNE 2018 and JULY 2018 are enclosed at Annexure-2.1. The brief detail of frequency profile is given here under: Month Average frequency Minimum Integrated frequency over an hour Maximum integrated frequency over an hour Instantaneous Minimum Frequency Instantaneous Maximum Frequency JUNE 2018 49.98 Hz 49.74 Hz 50.15 Hz 49.60 Hz 50.20 Hz JULY 2018 49.98 Hz 49.78 Hz 50.08 Hz 49.62 Hz 50.24 Hz 2.2 Operational Matters 2.2.1 Operational Discipline : The committee was apprised that system operated in terms of frequency profile for the months JUNE 2018 and JULY 2018 is as given below for discussion by the committee : Month JUNE 2018 JULY 2018 % of time Frequency Below 49.90 Hz % of time Frequency above 50. 05 Hz % of time frequency within the permissible range of 49.90-50.05 Hz. Average monthly frequency No. of times frequency dipped below 49.20 Hz 11.84% 11.19% 76.97% 49.98 Hz 0 10.25% 11.27% 78.48% 49.98 Hz 0 2.2.2 Voltage Profile: The committee was apprised that during the months JUNE 2018 and JULY 2018 the maximum and minimum voltage as recorded at following important 400 KV s/s in MP Grid:- JUNE 2018 JULY 2018 Max. Voltage Min. Voltage Max. Voltage Min. Voltage Name of Observed Observed Observed Observed Sr. 400 KV Volt Voltage No. Substation Voltage ag Voltage Date Date Date KV e KV KV KV Date 1 Indore 421 30.06.18 394 07.06.18 423 12.07.18 405 09.07.18 2 Itarsi 423 29.06.18 396 07.06.18 424 26.07.18 408 30.07.18 3 Bina 418 03.06.18 395 15.06.18 416 26.07.18 396 29.07.18 Minutes Of 65th OCCM Of MP 2

4 Gwalior 418 06.06.18 388 24.06.18 417 22.07.18 390 08.07.18 5 Nagda 422 26.06.18 397 05.06.18 425 12.07.18 406 06.07.18 6 Satpura 424 03.06.18 408 04.06.18 427 26.07.18 415 30.07.18 7 Birsinghpur 425 07.06.18 407 23.06.18 423 25.07.18 412 29.07.18 8 ISP 428 23.06.18 402 06.06.18 426 12.07.18 405 09.07.18 9 Bhopal 416 29.06.18 393 07.06.18 419 26.07.18 402 09.07.18 10 Ashta 423 29.06.18 401 07.06.18 427 27.07.18 411 05.07.18 11 Pithampur 421 30.06.18 401 07.06.18 423 12.07.18 408 06.07.18 12 Singhaji 422 29.06.18 419 05.06.18 423 12.07.18 413 30.07.18 Member Secretary OCC stated that during upcoming rabi season low voltage problems will exist, hence all the generators were requested to provide desired MVAR support as per their capability curve to maintain Grid voltage well within limits especially at STPS & SSTPS. 2.2.3 Status of Capacitor Banks in sub-transmission system: The updated information of the status of capacitor banks in sub-transmission system as on 31 th JULY 2018 as submitted by DISCOMs, were discussed as detailed below: DISCOM Capacitor bank Capacitor installed in good Banks healthy condition (No) but not in service due to control ckt problem 600 1200 1500 KVAR KVAR KVAR Capacitor bank Require Requiremen Capacitor Balance installed but ment of t against banks already capacitor defective & are repair nonrepairable covered under banks to be repairable (No) against each capacitor ADB T-V covered in other unit (No) banks schemes 600 1200 1500 600 1200 1500 No of 100 600 1200 KVA R KVA R KVA KVAR KVAR KVAR R KVAR Units KVAR KVAR 600 1200 KVAR KVAR 600 1500 KVAR KVAR required EZ 411 136 40 28 10 05 08 11 0 25 - - - - - - CZ 5 685 788 - - - 1 0 0 3 0 0 0 0 0 0 WZ 633 549 703 5 7 4 16 09 18 148 5 10 - - - 3 Member Secretary OCC stated that all the Discoms shall ensure the availability of the capacitor bank during Rabi season so that the low voltage problems are avoided and the availability of capacitor banks which are healthy but not in service due to control ckt problem shall be ensured by Discoms. Representative from Central Discom informed the committee that all the capacitor banks in Gwalior region are healthy and in working condition and it is expected that it will provide MVAR support. Representative from MPPTCL informed the committee that in Shivpuri area it is observed that on 33 KV the MVAR loading is about 70% - 80% which is on higher side and Discom shall identify such feeders and plan for capacity addition of capacitor banks on such area. Minutes Of 65th OCCM Of MP 3

2.2.4 Status of Shunt Capacitor Banks installed at various EHV Transmission Substation: The updated information of the status of installed capacitor banks (in MVAR) in EHV transmission system as on 31.07.2018 as submitted by MPPTCL was informed to the committee: - Voltage Capacitor bank Capacity Added Capacitor banks TOTAL Capacitor Bank Class installed as on after Last OCC already covered CAPACITY AS Installed but 31.05.18(MVAR) Meeting (MVAR) under ADB T-V ON 31.07.18 defective & are not (MVAR) repairable (No & MVAR) 220 KV 100.00 0.00-100.00 All in Service 132 KV 1238.00 0.00-1238.00 5104.50 36.00-5140.50 Total 6442.50 36.00-6478.50 The members discussed the matter & noted. 2.2.5 Status of completion of ongoing Transmission Schemes being executed by MPPTCL: The committee was updated regarding the various ongoing Transmission Schemes completed during the financial year 2017-2018 (up to July 2018) and plan for completion of various ongoing Transmission Schemes for the Year 2017-2018 is enclosed as Annexure 2.2.5(i) and 2.2.5(ii) respectively. 2.2.6 U/F and df/dt Relay Operation (i) U/F and df/dt Relay Operation: Frequency did not touch 49.20 Hz during JUNE 2018 and JULY 2018. There was no df/dt operation during the same period. Member secretary OCC requested MPPTCL to ensure submission of consolidated report of healthiness of U/F & df/dt relay on monthly basis. (ii) Defective u/f, df/dt relays: MPPTCL has informed that all the df/dt and U/F relays are in operation, where the U/F relays are not available, the numerical relays programmed for under frequency operation. Defective df/dt relay at 220KV Sagar & 220KV S/S Chhatarpur have been replaced & at S/S Chapda the df/dt protection is provided through df/dt feature of DPR. All U/F stages are in good/ healthy & working condition. 2.3 Power Cuts / Load restrictions/differential Load Shedding by DISCOMS & group allocation to feeders: (i) Details of DISCOM wise Power supply given to various domestic categories during the period JUNE 2018 and JULY 2018 is enclosed at Annexure 2.3(i). [Committee may like to note] (ii) Group Allocation to Newly Commissioned existing EHV substations:- The region wise list of feeders emanating from various newly commissioned/existing EHV substations for which groups have not been allocated is given in Annexure 2.3 (ii). The DISCOM wise details of pending group allocation to feeders is given below, were apprised to the committee for discussion: - Minutes Of 65th OCCM Of MP 4

SN DISCOM Region No of feeders for which groups to be allocated 01 Jabalpur 02 02 Sagar 00 EAST 03 Rewa 01 04 Total 03 05 Indore 14 06 WEST Ujjain 03 07 Total 17 08 Bhopal 11 09 CENTRAL Gwalior 14 10 Total 25 TOTAL Grand Total 45 Representative from West Discom informed the committee that the group allocation of 17 no. feeders is under process and group will be allocated at the earliest. Representative from Central Discom informed the committee that out of 14 no. feeders, 8 no. feeders have been group allocated in Gwalior region and group allocation of remaining feeders shall be done at the earliest. The representative of Discom were requested that the order copy shall be submitted to P&D, MPPTCL under intimation to SLDC vide which group have been allocated. ITEM NO. 3 : OPERATIONAL PLANNNING: 3.1 Generating Units under planned outage and proposed maintenance programme: The annual maintenance /outages of thermal generating units of MPPGCL during SEPTEMBER 2018 to OCTOBER 18 as intimated by ED(O&M:Gen.), MPPGCL, Jabalpur is as follows:- S.NO UNIT FROM DATE TO DATE REASON 1. SGTPS # 1 26.08.2018 12.09.2018 A.O.H 2. STPS # 7 20.08.2018 13.09.2018 A.O.H The matter was discussed in the meeting. 3.2 Proposed shutdown programme of Transmission lines / Transformers: The proposed shutdown of transmission elements for the period 01.06.2018 to 31.07.2018 submitted by MPPTCL is enclosed as Annexure-3.2. The members have noted the points. 3.3 Long Outages of transmission elements and protections: The status submitted by MPPGCL /MPPTCL are given below, the members discussed the matter & noted.:- Sr. Line/Transformer/ etc Outage date Reason Response from Utility No under long Outage Minutes Of 65th OCCM Of MP 5

1. 40 MVA, 132/ CGL make X mer, Sr. No. T- 8362-3 at 220kv s/s Ujjain. 2. 16MVA BBL make X mer at S/S Berasiya 3. 40MVA NGEF make at S/S Ghatabillod 4 315MVA, 400/220 X mer-ii at 400kv S/s Bina. 5 20MVA EMCO X mer at S/S Chicholi. 6. 160MVA, 220/ BHEL Make X mer at 400 KV S/s Ashta. 7. 40MVA ECE make X mer at 220KV S/S Badod 8. 63MVA BHEL make X mer at S/S Dabra 22.06.2017 10.06.2018 02.06.2018 Tripped on differential indication. X mer tripped on Differential & Buchholz Trip Indications X mer tripped on Differential & Buchholz trip indications. 14.02.2018 Differential, Buchholz. 27.06.2018 23.07.2018 24.07.2018 04.08.2018 Tripped on Buchholz trip indications. X mer tripped on Differential & Buchholz trip indications. X mer tripped on Differential & Buchholz trip indications. X mer tripped on OSR and Differentail trip indications due to failure of OLTC. Transformer has been declared failed and has been replaced by 20 MVA X mer on 21.07.2018. MPPTCL informed that X mer is under investigation & testing and is expected to be taken in service by October 2018. MPPTCL informed the committee that the X mer will be replaced by 20 MVA X mer from 132 KV S/s Nowgaon. MPPTCL informed that after investigation & Testing X mer declared failed and transformer will be replaced by new 50 MVA X mer by Oct-2018. Representative from MPPTCL informed the committee that the X mer has reached the S/s and is expected to be taken in service by 1 st week of October. MPPTCL informed that another transformer will be commissioned by Oct-2018 end. Representative from MPPTCL informed the committee that the testing of X mer is under process & is expected to be taken in service within 2-3 days. MPPTCL informed that the X mer is under inspection & testing and is expected to be taken in service by October 2018. Representative from MPPTCL informed the committee that the X mer will be replaced by another 20 MVA X mer & is expected to be taken in service by end of OCT-18. MPPTCL informed that after investigation & Testing X mer declared failed and transformer will be replaced by another 160MVA X mer. Representative from MPPTCL informed the committee that the X mer has reached the site and its erection is under process and is expected to be charged in OCT- 18. Representative from MPPTCL informed the committee that 40 MVA X mer will be replaced by 20 MVA X mer from 132 KV S/s Ingoria and is expected to be taken in service by end of September-18. Transformer is under GP and referred to OEM for replacement of defective diverter switch. Representative from MPPTCL informed the committee that the transformer will be taken in service by end of Sept-18. Minutes Of 65th OCCM Of MP 6

9. Station X mer STPS#11, PH-IV Sarni. 30.07.2018 10. UAT-7B, STPS, Sarni 30.06.2018 11. 500 MVA, 400/220 KV X mer at STPS. 12. 400 KV Transfer Bus Coupler at SGTPS 13. 50 MVAR (Make GE) Line Reactor at 400KV Sarni- Asta Ckt-I. 19.04.2018 Under shutdown for filtration of transformer oil, as the water content in transformer oil is on higher side. Differential relay & bucholz relay operated. X mer tripped at 21:55 Hrs. due to LA Burst. Emergency shutdown taken for 15 days from 21.04.18 to 05.05.18 for CPRI oil filtering and RLA testing work.thereafter ICTis kept off. 02.09.2018 SF6 Gas Leakage 31.03.2018 Under outage since 31.03.18 due to concentration of Acetylene gas. DGA test of transformer oil of reactor was carried out by M/s CPRI, Bhopal. Station Transformer has been charged on 24.08.2018 and taken load on 01.09.2018. MPPGCL informed that tendering work is under progress for all winding replacement. NIT has been uploaded on 31.08.2018. Due date is 09.10.2018. Representative from MPPGCL informed the committee that price bid will be opened on 09.10.18. MPPGCL informed that Owing to adverse report of RLA conducted on ICT during shutdown, proposal for permanent discontinuation of ICT from service has been submitted. The MPPTCL representative was requested to make alternate arrangement. It has been informed by site that maintenance will be carried out after monsoon. Representative from MPPGCL informed the committee that the breaker will be available by 1 st week of OCT-18. To carry out the internal inspection of reactor, NIT will be opened on 4th September 2018. Due date has been extended for 10 days. Latest status may also be intimated by MPPGCL in the meeting. Representative from MPPGCL informed the committee that the tender opening date has been extended. The representative of all utilities was also requested that itransmission element/ EHV element under outage, should invariably be intimated to SLDC. All entities are requested to ensure the same. ITEM NO. 4 : OPERATIONAL STATISTICS FOR THE MONTH OF JUNE 2018 AND JULY 2018: The details of actual generation, Schedule from Central Sector, demand etc. were tabled for discussion as annexed below:- Annex. 4.1 Unit wise actual Generation of MPPGCL thermal Units and station wise Generation of Annex. 4.2 Annex. 4.3 Annex. 4.4 MPPGCL & NHDC Hydel Units. Power Supply Position. Hourly Average of Availability and Demand. Hourly average schedule Vs Drawal of DISCOMs. Minutes Of 65th OCCM Of MP 7

ITEM NO. 5 : SYSTEM DISTURBANCE IN MP DURING OF JUNE 2018 AND JULY 2018: The Grid Disturbances and Grid Incidents in MP during these months as indicated in Annexure 5 were apprised to the committee and was discussed. ITEM NO. 6.0 : IMPORTANT OPERATIONAL ISSUES:- 6.1 STATUS OF COMPLETION OF ONGOING SCHEMES FOR COMMISSIONING OF REACTORS / TRANSMISSION ELEMENTS:- The present status regarding schedule and commissioning of reactors / transmission elements is as below:- S.No. 400 KV S/s Size MVAR Implementing Agency Expected Date of Commissioning as intimated in last OCC 1. Bus Reactor : ISP 2. Line Reactor on 400 kv Sapura ISP line at STPS 3. Bus Reactor at SSTPS 125 MVAR NHDC 50 MVAR MPPGCL 125 MVAR MPPGCL In 63 rd from ISP informed the committee that the reactor has been installed and the inspection by the engineer from CEA has been done, the report of which is still awaited. Representative from ISP informed the committee that CEA clearance is received & reactor is expected to be taken in service by end of Sept-18. MPPGCL informed that the price bid has to be opened and the reactor will be commissioned by December 2018. Representative from MPPGCL informed the committee that the order has been placed in June-18 and reactor is expected to be commissioned by March-19. 6.2 Generation target / LGBR preparation for the year 2018-19:- LGBR preparation for the year 2019-20:- - It was apprised to the committee that as per the regulation 5.7.4 of Central Electricity Regulatory Commission (Indian Electricity Grid Code) ) First Amendment) Regulations 2011, WRPC shall prepared Loan Generation Balance Report for the year 2019-20 in respect of Western Region. In this context all respective utilities were requested to provide desired information upto 15 th September 2018, so that same may be communicated to WRPC for necessary action. It was mentioned that a meeting has been proposed to be held on 4 th week of September 2018 at WRPC wherein constituents will discuss the matter. The desired data still awaited from all respective utilities. Accordingly, it was again requested to all concern that following data may be provided to SLDC on priority basis: - 1. Generation Units proposed annual Maintenance programme in respect of your system ( also under your control area) for the year April 2019- March 2020. 2. Annual Maintenance programme in respect of transmission elements in your system for the year April 2019- March 2020. 3. Month-wise restricted and unrestricted requirement of power (MW) and energy (GWH) for the year April 2019 March 2020. Minutes Of 65th OCCM Of MP 8

4. Month-wise minimum requirement of power (MW) for the year April 2019- March 2020. 5. Projected month-wise, unit-wise generation of power (MW) corresponding energy (GWH) as furnished in Generation Target for the above period. 6. Commissioning dates of new generation units during the year April 2018- March 2019. 7. Expected dates of commissioning of new generating units likely to be commissioned during the April 2019-March 2020. 8. Month wise detail of proposed / tied-up bilateral agreements/ Short term open access sought for availing assistance from other agencies during the above period. 9. Expected RES energy (MUs) & corresponding demand (MW) for the year 2019-March 2020. Representative from MPPGCL informed the committee that the desired information is being prepared and will be submitted at the earliest. 6.3 Multiple trippings of EHV elements at Birsinghpur on 28.08.2018: - It was apprised to the committee that at around 18:02 hrs on dtd. 28.08.2018 bus bar protection operated at 220 KV substation Birsinghpur (Pali) resulted tripping of all outgoing feeders radiating from Pali substation. Subsequently at around 18:04 hrs, 220 KV Birsinghpur-Rewa line tripped along with bus coupler at SGTPS Power House, this caused tripping s of unit No.-II & IV at SGTPS due to lack of load evacuation path. The aforesaid trappings required to be analyzed on following points: - 1. Why 220 KV bus I & II bus bar protection operated simultaneously and reasons/ remedial actions thereof. 2. The tripping of bus coupler at SGTPS, the relay setting provided for the same, load carrying capacity permitted therein, as tripping of these elements resulted generation loss of approx. 370 MW in unit No. II & IV at SGTPS. The MPPTCL/ MPPGCL were requested to provide detailed report of tripping. The matter was discussed in the meeting. 6.4 Review of Load Dropping Scheme installed at 220 KV substation, Rewa:- - It was apprised to the committee that Load Dropping Scheme have been installed at 220 KV S/s, Rewa to handle over loading condition under various contingencies considering limited source of availability of 220 KV supply at Rewa as during Rabi season, 220 KV Rewa-Tons and Rewa-Sirmour-Tons circuits were kept open earlier to mitigate loading condition at Satna substation. The following feeders are being tripped due to operation of Load Dropping Scheme to safeguard over loading of 220/132 KV ICT at Rewa / 220 KV Rewa-Sidhi line / 220 Rewa- Birsinghpur line for which different settings have been provided: Minutes Of 65th OCCM Of MP 9

i. 132 KV Mangawan- Ckt. I ii. 132 KV Pahadiya iii. 132 KV Jinna iv. 132 KV Rampur-Nakin The configuration of Load Dropping Scheme was discussed and pointed out that due to tripping of 132 KV Mangawan Ckt. I and Pahadiya Ckt. Due to operation of above scheme load dropped due to disconnection of 132 KV feeders i.e. 132 kv Majgawa and Pahadia, ultimately load redirect on 220 KV Rewa-Sidhi feeder. Thus, these two feeders do not give any significant relief. Therefore, it was sujested that Load Dropping Scheme provided on 220 KV Rewa-Sidhi line may be discontinued. Now-a-days at 220 KV Substation, Rewa multiple 220 KV supplies are available as 220 KV Rewa-Tons and 220 KV Rewa-Sirmour-Tons links are always kept closed after LILO arrangement at Kotar substation. The additional transformer capacities have been integrated at Satna-PG substation and 220 KV Interconnector III/IV Satna-Satna has also been integrated. The 220 KV network at Satna, Rewa area is comparatively stronger than previous arrangement. In view of above, it was indicated that Load Dropping Scheme may be reviewed and this scheme may be restricted up to over loading of transformer at Rewa. Further it was suggested, multiple 220 KV supply are available at Rewa, therefore the 220 KV Rewa-Sidhi and 220 KV Rewa-Birsinghpur line may be considered for disconnection from Load Dropping Scheme because tripping of these lines unnecessarily resulted tripping of 132 KV network which may lead to weaken the reliability and also caused interruption to some area. Representative from MPPTCL informed the committee that the matter is under discussion with SE(T&C), Satna and will be intimated thereafter. The matter was discussed in the meeting. 6.5 Compliance to IEGC Regulation 5.2(f) to 5.2 (i) reg. :- - It was apprised to the committee that a Special Meeting of SLDC along with intra-state generating stations mandated to provide primary frequency response as per IEGC 5.2 (f), (g), (h) & (i) was held on 26.07.2018 at WRLDC, Mumbai. Representative from SLDC, MPPGCL, Jaypee Bina, ISP & OSP of NHDC from MP were attended the interactive session on primary frequency response. Various matters related to compliance to IEGC Regulation 5.2 (f) to 5.2 (i) along with the recent events mentioned in the reference letter WRLDC, Mumbai letter No. WRLDC/SO-I/2018/36 dtd 11.07.2018 for significant change in MW / frequency were discussed in the meeting at WRLDC, Mumbai. As per IEGC 5th amendment, all coal/ lignite based thermal generating units of 200 MW and above, Open Cycle Gas Turbine/ Combined Cycle generating stations having gas turbines of capacity more than 50 MW each and all hydro units of 25 MW and above are mandated to provide adequate primary frequency response. The installed capacity on Bar in a station is considered while computing the ideal response. The actual response is compared with ideal response. The committee was apprised that there is a penalty for non compliance: CERC (terms and conditions of tariff) Regulations, 2014: Clause 2(iv & v) of Regulation 24 (Return on Equity) as mentioned below: the rate of return of anew project shall be reduced by 1% for such period as may be decided by the Commission, if the generating station or transmission system is found to be declared under commercial operation without commissioning of any of the Restricted Governor Mode Operation (RGMO)/ Free Governor Minutes Of 65th OCCM Of MP 10

Mode Operation (FGMO), data telemetry, communication system up to load dispatch centre of protection system as and when any of the above requirements are found lacking in a generating station based on the report submitted by the respective RLDC, RoE shall be reduced by 1% for the period for which the deficiency continues. Vide this office letter No. 07-05/RPC-27/2108 dtd 13.07.2018 & No. 2219 dtd. 19.07.2018 the generators were requested for ensuring the compliance on the matter. In view of above, the utilities were requested to ensure compliance of IEGC regulation 5.2 (f) to 5.2(i). The matter was discussed in the meeting. 6.6 Status of pending protection audit observations of phase I plan and action plan and status of second phase protection audit of existing substations: -- It was apprised to the committee that the SE Protection WRPC vide letter No. WRPC/Protection/PAR/2018/916 dtd 11/07/2018 has enquired regarding status of pending audit observation- compliance thereof and action plan and status of second phase of protection audit of existing substation is enclosed herewith for kind perusal. In the above committee members were intimated that as decided in PCM of WRPC the protection audit of new substations are required to be carried out within year of commissioning and for other substations the periodicity of protection audit is five years. As first phase of protection audit was targeted to be completed by stack holder s up to 2017. However, it is observed that compliance of many protection audit observations are still pending. It is therefore requested that pending protection audit observation be completed earliest and compliance report may kindly be provided so that the same may be made available to WRPC. The details of protection audit observations completed so far and details of pending protection audit cases are annexed. In the above context all utilities were requested to intimate regarding the action plan and status of second phase of protection audit of existing substations may kindly be checked out and provided to this office for finalizing second phase protection audit activities. Kindly treat this as urgent. Representative from MPPGCL informed the committee that the compliance of protection audit observations is pending in which procurement is required and is under process. Representative from MPPTCL also informed that compliance of protection audit observation are pending for the observation in which procurement is required and is under process which will be complied at the earliest. 6.7 Provision of synchronization facility at EHV sub-stations of MPPTCL and at all power house: - - It was apprised to the committee that as per Grid Code, the synchronization facility should be available at all the Power Stations, 400 KV Sub-stations and 220 KV Sub-stations and 132 KV sub-stations in the path of black start. In 60 TH OCC meeting MPPTCL representative informed the committee that order for 69 no. synchronization trolleys has been placed and 1 no. synchronization trolley has been delivered for checking and testing purpose at 220KV S/S Barwaha. In subsequent meetings this issue has been discussed. However, no any fruitful progress has been observed so far. In the above context it is indicated that at Manikheda HPS Minutes Of 65th OCCM Of MP 11

and Rajghat HPS synchronization facility is not available. It is felt that every Hydel Power station should be equipped with synchronization facilities invariably for system reliability and Crises Management. Thus, MPPGCL is requested to provide synchronization facility at Manikheda HPS and Rajghat HPS. It is therefore requested, the MPPGCL may kindly provide status of making synchronization facility in aforesaid HPS The MPPTCL may kindly provide the status of installation and commissioning of synchronization trolleys at different substations. Further, is also requested to indicate, whether synchronization facility could be provided at Karera substation on priority basis. The matter was discussed in the meeting. 6.9 Compliance report on 2nd meeting of State Level Relay Settings Group for review and coordination of relay setting held on 20.05.2018: - It was apprised to the committee that the relay setting at OSP and adjoining substations were discussed on 10.05.2018 and the State Level Relay Settings Committee has provided recommendations. On recommendation of the Committee a joint testing was carried out by the members comprising of MPPTCL and OSP Testing Engineers. The recommendations of Relay Settings Group, incorporating outcome of joint testing were conveyed to OSP for compliance. The OSP is requested to provide compliance report on aforesaid issue so that same may be appraised to the member of OCCM. Representative from OSP informed the committee that the relays at OSP has to be replaced by new numerical relays with latest features for implementation of recommendations of the committee as these features are not available in existing relays at OSP. Hence these relays are being planned to be purchased in the upcoming new financial years and will be complied thereafter and the present status will be submitted. 6.10 Procedure for availing outage on ISTS EHV elements and OCC approval thereof:- It was apprised to the committee that as per standard procedure of WRPC, all EHV elements which have been listed under the list of important grid elements of Western Region, the outages for such elements required OCCM approval. All such proposed outages of interstate and 400 KV transmission elements of next months should be got approved in the OCCM of WRPC in the current month. All the constituents of WR shall inform to the WRPC for readiness for availing outage of transmission elements on D-3 basis. Further, as decided non- OCCM outages should be discouraged. Only under exceptional cases, the request for transmission outage after issue of OCCM minutes must be posted through email for concurrence of WRPC Member at least three days in advance. It has been seen that OCCM outage proposal which are being submitted and got approved, however the same are not being availed in real time. It was also pointed out that the occm proposal are being submitted very casual manner without accentuating actual requirement, moreover the proposal of a few lines is being submitted regularly in repeated pattern but the outage on the same are not being availed. Where as it is always tried to get approval of non occm outage, which unnecessarily creates disputes with WRLDC/WRPC. It is therefore required that actual requirement of shutdown on EHV Elements may be planned and accordingly outage proposal be submitted to SLDC for approval of OCCM. The work related with construction activities / shifting work, new addition etc. invariably incorporated in OCCM proposal. In the above context EHT Construction was requested to arrange to send their OCCM outage proposal through CE (T &C ) within Minutes Of 65th OCCM Of MP 12

stipulated time as from EHT Construction, OCCM proposal never being received in accordance with laid down procedure they generally insisted upon non OCCM outage approval just before targeted date. The Members were informed that WRPC is reluctant to permit Non OCCM outage for construction activities. Therefore for such cases OCCM approval are invariably required. Member Secretary OCC requested all the entities to intimate SLDC about the approved/proposed shut down which have not been availed as it needs to be further intimated to WRLDC/WRPC. The matter was discussed in the meeting. 6.11 Delay In Submission of Documents For First Time Charging of Elements:- It was apprised to the committee that procedure for interconnection of new transmission elements is briefly narrated hereunder:- Intimation by Transmission Licensee to RLDC / SLDC(Annexure A1-A5): 10 days prior to anticipated date of first time charging. Acknowledgement and comments of RLDC/ SLDC to Tr. Licensee ( Format-II): Within 3 days. Submission of request for first time charging by Tr. Licensee to RLDC//SLDC (Annexure B1-B5): 3 days prior to anticipated date of first time charging. RLDC shall issue Provisional Charging Approval for first time charging to licensee and in case of interregional element RLDC to issue consent/ request to NLDC for IR lines. In case of intrastate line charging approval shall be conveyed by SLDC: (within 2 days). Licensee to submit dummy SEM reading to RLDC to ensure that the Meter processing Software is able to read the SEM data from the new meters. Licensee to take Operational Code from RLDC /SLDC Control Room for switching operations. The code shall be issued keeping view of grid reliability. Transmission Licensee submit Post Charging documents (Annexure C1 to C4). RLDC/ N LDC shall verify the post charging documents and issue certificate for interstate / Interregional lines / ISTS lines. The respective testing department shall furnish regarding measures taken to take care new element interconnection for protection co-ordination for adjacent s/s and accordingly undertaking shall be provided. The licensee / utilities swere requested to adhere with time schedule for documentation of first time charging of new transmission elements of all interstate line and all EHV elements 400kv and above. It was also requested to ensure, FTC formalities should have completed before availing outage for integration of element. The authority submitted FTC document should ensure compliance of protection/ metering/telemetry issue in coordination with T&C official. It is also desired that all necessary data should have made available to all adjacent s/s for relay coordination well before targeted date. The authority submitted FTC document should ensure all formalities have been completed otherwise it would be difficult to obtain clearance from WRLDC.In general non-attachment of requisite papers/ SLD/ document of standing committee approval /approval of Electrical inspector /noncompliance of relay coordination of adjacent s/s / providing information incorrectly caused delay in obtaining FTC approval. Minutes Of 65th OCCM Of MP 13

Therefore it is desired that FTC document completed in all respect may be provided in stipulated time schedule so that FTC formalities could be completed within targeted date of charging. The matter was discussed in the meeting. 6.12 CONTROLLING HIGH VOLTAGE DURING OFF-PEAK HOURS:- - It was apprised to the committee that Switchable Shunt Reactors are being taken in service during high voltage conditions. However in view of inadequate shunt reactive compensation, the generating units are advised to contribute in voltage regulation by operating their units in under-excited mode (absorb Reactive Power) within the capability curve. The MW, MVAR and Voltage of generating units was analyzed for the month of Feb 2017 with the help of SCADA data available at WRLDC. This matter has been discussed in 64 th OCCM and accordingly, it has been again requested that AVR setting and the GT taps may be reviewed / adjusted so as to enable the unit to contribute in voltage regulation within the capability curve. The directives in this regard may please be adhered to control the high voltage during off peak hours. The matter was discussed by the committee. 6.13 Reporting Of Flash Report, DR and EL of Transmission Elements & Detailed Tripping Report:- It was apprised to the committee that as per the provisions of Regulation 5.2 (r) of CERC (Indian Electricity Grid Code) Regulations 2010 and Regulation of 5(9) of CERC (Indian Electricity Grid Code) (First Amendment) Regulations, 2012 all the Regional Entities of the Region shall furnish the tripping details including DR & SEL output to RLDC with in 24 hrs of the event for analysis and identify the real time measures required in future to ensure secured grid operation. The flash report is also required to be furnished to SLDC within an hour of tripping. It is observed that FLASH REPORT, DR & EL of station is not made available after tripping of transmission grid element by the State Grid Entities and the flash report is also not being sent after repeated pursuation. It was also to informed that as per CEA Protection Standards, in case of tripping of Inter Regional Lines of voltage class 220 KV & above, the DR/EL files shall be invariably submitted to RLDC under intimation to this office. It has been observed that the DR/EL files has not been submitted to WRLDC of Inter Regional trippings as mentioned below: - S.NO. NAME OF LINE DATE TIME 1. 220 KV Malanpur Auraiya Ckt 07.06.2018 06:21 Hrs. 2 220 KV Malanpur Auraiya Ckt 09.06.2018 20:56 Hrs. All intra-state entities should submit the flash report, DR & EL of station during tripping of transmission grid elements. The matter was discussed in the meeting. Minutes Of 65th OCCM Of MP 14

6.14 Ten Daily Reservoir operation table of MPPGCL HPS:- It was apprised to the committee that in the meeting held in Regional Office of MPPMCL at Bhopal on 24.09.2016 to discuss availability from Sardar Sarovar Project, ISP & OPS and State Hydel Plants for Rabi season, MPPGCL had agreed to obtain ten daily reservoir operation table from WRD and NVDA for their operation of their hydro generators. In last 54 th, 55 th & 56 th OCCM, request has been made to MPPGCL for furnishing the same to SLDC within a week, In last meeting MPPGCL has submitted the Ten Daily Reservoir Table of Bargi and Bansagar Hydel Power Stations. It is requested that MPPGCL shall submit the Ten Daily Reservoir Table of remaining hydel power stations in coordination with NVDA and WRD for optimum utilization of available water in the reservoirs during the summer season. The matter was discussed in the meeting. 6.15 MONITORING OF SCHEMES FUNDED FROM PSDF :- It was apprised to the committee that it was decided in the 6th meeting of NPC held on 19th December 2016 at Bengaluru, that all the RPCs in the monthly OCC meetings may follow up with the utilities to expedite the completion of schemes by giving due priority. The implementation of most of the schemes are based on the recommendation of the enquiry committee on grid disturbance of July 2012 headed by Chairperson, CEA. Therefore timely implementation of these schemes would enhance the grid security and reliability. Accordingly the details of grant sanctioned from PSDF for the schemes of MP is enclosed at Annexure- 6.15A. The status of implementation of above schemes (physical as well as financial progress) may please be reviewed and the entities are requested to expedite implementation of the schemes. The utilities were advised to furnish the information in the format enclosed at Annexure 6.15B by first week of every month on regular basis to Member Convener, PSDF project monitoring group (AGM, NLDC, POSOCO) with a copy to NPC, WRPC division and SLDC. The status of the same is being monitored by WRPC in OCC meeting of WRPC every month. In view of above it is desired that PSDF scheme may kindly be expedite and be completed within targeted dates.the matter was discussed in the meeting. 6.16 ABNORMAL VOLTAGE VARIATION OBSERVED IN PMU AT 400 KV S/s BINA:- It was apprised to the committee that the abnormal voltage variations is being observed in PMU s at 400 KV S/s Bina (plots enclosed as Annexure-6.16 (3 pages) since May 2018. SLDC has taken up the matter with T&C, MPPTCL and M/s GE. M/s GE engineer visit was arranged to 400 KV S/s Bina to investigate the problem in PMUs & it has been informed by GE site engineer that the voltage spikes are also observed in the input values of PMU from Bus PT s & line CVT secondary, hence it can be gathered that these PMU s are showing correct values and there is no issue in PMU. Further it is also to intimate that the abnormal voltage spikes are still being observed in the PMU of 400 KV Main Bus I & II and 400 KV Bina(M.P) JP BinaCkt installed at 400 KV S/s Bina and the magnitude &frequency of spikes is continuously increasing with time.in addition to above, it is to also intimate that the voltage spikes are observed in 400 KV Bina-JP BinaCkt even when the line is hand-tripped from both ends. Minutes Of 65th OCCM Of MP 15

The matter was discussed in 64 th OCCM and MPPTCL was requested to arrange for testing of Bus PT s, line CVT & related equipments installed at 400 KV S/s Bina for investigation of root cause of these voltage spikes observed, for its rectification and ensure healthiness of equipments at site. MPPTCL may kindly update the status. Representative from MPPTCL informed the committee that the matter is under investigation and it is being planned to replace the CVT. ITEM NO. 7: BLACK-START MOCK DRILL OF HYDEL POWER STATIONS : Black Start mock drill of Hydel stations of MPPGCL:- It was apprised to the committee that during 2018-2019 the black start mock drill successfully carried out at Hydel power station as mentioned below:- S.NO. NAME OF HPS DATE OF MOCK DRILL 1 Pench & Bargi HPS Joint Mock Drill 11.04.2018 2. Gandhi Sagar HPS 06.07.2018 3. Rajghat HPS 29.08.2018 MPPGCL may apprise the same in the meeting. It is also to intimate that the Black Start Mock Drill of Manikheda HPS was proposed on 28.08.2018. Accordingly, the procedure for afore said exercise has been conveyed vide SLDC Letter no. No.07-05/RPC- 38/2578 dtd-21.08.2018, after due consultation with GCC/Manikheda HPS officials. Thereafter Superintending Engineer(O&M),MHPS vide letter MHPS e-mail/letter no. 597-1500/blackstart/535 dtd-21.08.2018, informed that permission to release water from WRD is awaited and looking to the scarcity of water, requested to postpone the Black Start Mock Drill of Manikheda HPS for one month. In view of the above MPPGCL may kindly inform the latest status of regarding permission to release water from WRD and propose an appropriate date for conducting Black Start Mock Drill Exercise at Manikheda HPS. The black start mock drill exercise of OSP was to be held in April 2018 but due to non-availability of Bus Coupler Breaker at OSP the Mock Drill date cannot be finalized. In 63rd OCC OSP informed the committee that the purchase of Bus Coupler Breaker is under process and the tender is being awarded. In view of the above OSP HPS may kindly inform the latest status of Bus Coupler Breaker so that at the earliest Mock Drill exercise may be organized. Representative from MPPGCL informed the committee that Black Start Mock Drill at Manikheda can be conducted on 30 th October. Representative from OSP informed the committee that the finalized date for conducting Black Start Mock Drill at OSP will be intimated to SLDC at the earliest. ITEM NO. 08: AVAILABILITY BASED TARIFF (ABT) RELATED ISSUES: 8.1 Testing & Callibration of meters and non-receipt of timely JMR data: 1. SLDC representative requested CE(T&C) office to apprise the status of testing / calibration of interface meters as per Regulations 10 and 18 of Central Electricity Authority (Installation and operation of meter) Regulation 2010 to the committee. CE(T&C) office representative informed Minutes Of 65th OCCM Of MP 16