Solar Impact Case Study. Trishia Swayne, P.E. Leidos

Size: px
Start display at page:

Download "Solar Impact Case Study. Trishia Swayne, P.E. Leidos"

Transcription

1 Solar Impact Case Study Trishia Swayne, P.E. Leidos

2 Introduction Clean Energy Outlook

3 Agenda Case study profile Load scenarios determined Base case model established Analysis and results Summary and

4 Case Study Profile 298 kw of proposed PV Two primary points of through transformers Four step down transformers within camp Two 23 kw inverters and nine 28 kw inverters total Primary voltage of 13.2 kv; only one circuit served from the transformer Site is 3.4 miles from the There is 5,135 feet of secondary overhead within the camp to interconnect the inverters The circuit has 8.1 kw of rooqop, solar

5 Case Study Profile PV Site Substa'on

6 Load Scenarios One year of hourly circuit data provided (MW, MVAR)- Filter to hours only PEAK MIN

7 Base Case Model Regulator and capacitor Pole # Phase Size Layout Hold Voltage Bandwidth Compensa'on (R) Compensa'on (X) Time Delay K45399 A 219 Pole K44869 A 50 Pole K44867 B 100 Pole K44868 C 100 Pole A 219 Pla\orm B 219 Pla\orm C 219 Pla\orm K45291 C 100 Pole Pole # KVAR Total Type Control Phase Can Size(s) Voltage Fixed K Fixed K Time Controlled A K Fixed

8 Base Case Model Add PV to model Pole Interconnected? Type kw Yes as of 12/11/2012 PV K45473 Yes as of 10/8/2014 PV 4

9 Analysis Reverse power flow problem Voltage and capacity review Voltage flicker analysis Short circuit analysis Risk of islanding assessment

10 Analysis - Reverse Power Flow Load dura@on curve at substa@on transformer (day@me hours only) MW

11 Analysis Voltage and Capacity Pre and post project load flows conducted Primary feeder voltage remains within planning criteria (126 V 118 V) Conductor capacity issues were not iden@fied High voltage was iden@fied on the secondary side of the project site, as high 146 V Bank of single- phase line regulators will experience reverse power flow

12 Analysis Voltage and Capacity

13 Analysis Voltage Flicker Analysis Criteria for this is IEEE 519; all PV in the model is studied in on/off format

14 Analysis Voltage Flicker Analysis Allowable Primary System Min Load Flicker (%) Max Load Flicker (%) Secondary System Min Load Flicker (%) Max Load Flicker (%) 2% 0.23% 1.03% 15.94% 16.46%

15 Analysis Short Circuit The primary transformers at the two points of are grounded wye on both windings The four new transformers within the camp are also grounded wye on both windings The inverters are able to the neutral of the step- transformers, a solidly grounded system

16 Analysis Short Circuit grounding indicate the system is grounded with the project online, based on IEEE < X0 < 3 X1 0 < < 1 R0 X1

17 Analysis Short Circuit Analysis was conducted to confirm if overvoltages on unfaulted phases at the point of would be of concern Use fault flow in WindMil to evaluate

18 Analysis Short Circuit Run fault current and determine if fault currents on the feeder exceed GEN Status Fault Loca'on LG LG LLL LLL Maximum % Fault (Amps) (MVA) (Amps) (MVA) Current Contribu'on OFF 13 kv Bus Substa@on 3, , ON 13 kv Bus Substa@on 3, , OFF 69 kv Bus Substa@on 4,346 5,193 4, ON 69 kv Bus Substa@on 4,347 5,195 4, % 0.04%

19 Analysis Risk of Islanding Four- step analysis was conducted based on the November 2012 Sandia Suggested Guidelines for Assessment of DG Islanding Risk report

20 Analysis Risk of Islanding Step 1: Determine whether the aggregate AC of all DG exceeds 2/3 of the minimum feeder loading. If Yes, proceed to Step 2. If No, there is minimal risk of islanding and analysis is complete. Step 2: Determine whether QPV + Qload is within 1% of the total aggregate capacitor ra@ng within the island, or alterna@vely, use real and reac@ve power flow measurements or simula@ons at the point at which the island can form to determine whether the feeder power factor is ever higher than 0.99 (lag or lead) at that point for an extended period If Yes to either evalua@on, a detailed islanding analysis should be considered. If No, proceed to Step 3. Step 3: Determine whether the poten@al island contains both rota@ng and inverter- based DG, and the sum of the AC ra@ngs of the rota@ng DG is more than 25% of the total AC ra@ng of all DG in the poten@al island. If Yes, a detailed islanding analysis should be considered. If No, proceed to Step 4. Step 4: Sort the inverters by manufacturer, sum up the total AC ra@ng of each manufacturer s product within the poten@al island, and determine each manufacturer s percentage of the total DG. If no single manufacturer s product makes up at least 2/3 of the total DG in the poten@al island, then further study may be prudent. If the situa@on is such that more than 2/3 of the total DG is from a single manufacturer, then the risk of uninten@onal islanding can be considered negligible.

21 Analysis Risk of Islanding Y indicates risk Poten'al Island Step 1 (Y/N) Step 2 (Y/N) Step 3 (Y/N) Step 4 (Y/N) Circuit 3096 Y Y N N

22 Analysis Summary & Viola'on Reverse power flow at Excessive voltage flicker at site secondary Excessive steady state voltage at inverters Reverse power flow at bank of line regulators Risk of islanding Mi'ga'on Replace regulator controls Construct primary to site instead of ~1 mile of secondary Replace regulator controls Direct Transfer Trip (DTT)

23 Trishia Swayne, P.E. Leidos Director Studies Phone:

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems Ben Huckaba, P.E. President & Principal Engineer 317-273-9841 benh@alphaeng.us Indiana University Bloomington,

More information

TD-2306B-001, Interconnecting Large 2-20MW Generation Systems. Employees involved with generation interconnection on electric distribution circuits.

TD-2306B-001, Interconnecting Large 2-20MW Generation Systems. Employees involved with generation interconnection on electric distribution circuits. SUMMARY The protection requirements for connecting new Distributed Generation (DG) have been modified to reduce the need for Direct Transfer Trip (DTT) schemes which are costly to employ and difficult

More information

Targeted Application of STATCOM Technology in the Distribution Zone

Targeted Application of STATCOM Technology in the Distribution Zone Targeted Application of STATCOM Technology in the Distribution Zone Christopher J. Lee Senior Power Controls Design Engineer Electrical Distribution Division Mitsubishi Electric Power Products Electric

More information

Grid Management Voltage Control Distribution Grid Voltage Regulation with DER. Michael Sheehan, P.E. IREC Pacific Northwest Solar Partnership

Grid Management Voltage Control Distribution Grid Voltage Regulation with DER. Michael Sheehan, P.E. IREC Pacific Northwest Solar Partnership Grid Management Voltage Control Distribution Grid Voltage Regulation with DER Michael Sheehan, P.E. IREC Pacific Northwest Solar Partnership Overview of Grid Management Distribution Voltage Control Grid

More information

PV Grid Integration Research in the U.S.

PV Grid Integration Research in the U.S. PV Grid Integration Research in the U.S. Barry Mather Ph.D. NREL- Power Systems Engineering Center HEPIA IEA PVPS Task 14 Utility Workshop Geneva, Switzerland March 31 st, 2014 NREL is a national laboratory

More information

PV System Impact Guide

PV System Impact Guide PV System Impact Guide NRECA - PV System Impact Guide Foreword This Photovoltaic (PV) System Impact Guide is part of a series of National Rural Electric Cooperative Association (NRECA) guides including

More information

Guideline for Using IEEE 1547 for Solar PV Interconnection Page 1

Guideline for Using IEEE 1547 for Solar PV Interconnection Page 1 Guideline for Using IEEE 1547 for Solar PV Interconnection Page 1 A Guide for Iowa s Municipal Electric Utilities On the How the IEEE 1547 Distributed Generation Interconnection Standard Affects Solar

More information

The Role of Electricity Storage on the Grid each location requires different requirements

The Role of Electricity Storage on the Grid each location requires different requirements Functional Requirements for Energy on the Utility Grid EPRI Renewable Council Meeting Bill Steeley Senior Project Manager Dan Rastler Program Manager April 5-6, 2011 The Role of Electricity on the Grid

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description Final Draft Report Assessment Summary Hydro One Networks Inc. : Refurbish 115/44 kv, 25/33/42 MVA DESN Station CAA ID Number: 2007-EX360 1.0 General Description Hydro One is proposing to replace the existing

More information

Smart- Grid Ready PV Inverter

Smart- Grid Ready PV Inverter Smart- Grid Ready PV Inverter Tom Key, Technical Execu2ve EPRI tkey@epri.com IEEE PES Innova5ve Smart Grid Technologies Conference ISGT 2014, Washington, DC February 19, 2014 Smart Grid Ready Inverter:

More information

GRID CONNECTION ISSUES FOR DISTRIBUTED GENERATION REVIEW & STANDARDS

GRID CONNECTION ISSUES FOR DISTRIBUTED GENERATION REVIEW & STANDARDS GRID CONNECTION ISSUES FOR DISTRIBUTED GENERATION REVIEW & STANDARDS Prof. Suryanarayana Doolla Department of Energy Science and Engineering Indian Institute of Technology Bombay OUTLINE Intoduction Grid

More information

CUSTOMER / ACCOUNT INFORMATION Electric Utility Customer Information (As shown on utility bill)

CUSTOMER / ACCOUNT INFORMATION Electric Utility Customer Information (As shown on utility bill) GENERATOR INTERCONNECTION APPLICATION Category 2 (Combined) For All Projects with Aggregate Generator Output of More Than 20 kw but Less Than or Equal to 150 kw Also Serves as Application for Category

More information

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY 2011-2020 P+ PowerPlus Engineering A Department of STAR Energy Services, LLC TEN YEAR PLANNING GUIDE 2011-2020 SHASTA LAKE ELECTRIC UTILITY CITY OF

More information

STOCHASTIC ESTIMATION OF FEEDER-SPECIFIC DISTRIBUTED GENERATION (DG) HOSTING CAPACITY

STOCHASTIC ESTIMATION OF FEEDER-SPECIFIC DISTRIBUTED GENERATION (DG) HOSTING CAPACITY STOCHASTIC ESTIMATION OF FEEDER-SPECIFIC DISTRIBUTED GENERATION (DG) HOSTING CAPACITY Estorque, L.K.L, REE, MSEE, Manila Electric Company (MERALCO), lklestorque@meralco.com.ph ABSTRACT The significant

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation Feasibility Study Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection J.E.D. Solid Waste Management Facility Holopaw Substation September 2013 1 of 12 Table of Contents GENERAL... 3 SHORT

More information

Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER

Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER 1 Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER Lisa Dangelmaier Hawaii Electric Light lisa.dangelmaier@hawaiielectriclight.com Hawai'i Electric Light System Overview

More information

Form G5-1 PACIFIC GAS AND ELECTRIC COMPANY GENERATION PRE-PARALLEL INSPECTION

Form G5-1 PACIFIC GAS AND ELECTRIC COMPANY GENERATION PRE-PARALLEL INSPECTION Form G5-1 Page 1 of 3 PACIFIC GAS AND ELECTRIC COMPANY PG&E LOG WO/GM D&C Name of Project: Location: Transmission Line No. Distance Circuit No. 1. Maintenance Data: Generation Customer s Maintenance Chief

More information

Legal Name of the Customer (or, if an individual, individual's name): Name: Contact Person: Mailing Address: Physical Address: City: State: Zip Code:

Legal Name of the Customer (or, if an individual, individual's name): Name: Contact Person: Mailing Address: Physical Address: City: State: Zip Code: Generating Facility Level 2 or 3 Interconnection Review (For Generating Facilities with Electric Nameplate Capacities no Larger than 20 MW) Instructions An Interconnection Customer who requests a Utah

More information

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Interconnection Feasibility Study Report GIP-222-FEAS-R3 Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.

More information

MILLIGAN SOLAR PROJECT

MILLIGAN SOLAR PROJECT February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission

More information

Generator Interconnection System Impact Study For

Generator Interconnection System Impact Study For Generator Interconnection System Impact Study For Prepared for: January 15, 2015 Prepared by: SCE&G Transmission Planning Table of Contents General Discussion... Page 3 I. Generator Interconnection Specifications...

More information

Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 25 kw to 10 MVA or less)

Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 25 kw to 10 MVA or less) Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 25 kw to 10 MVA or less) Interconnection Customer Contact Information Name Alternative Contact Information (if different

More information

Using Hosting Capacity Methodology to Develop Simplified Screens for New Solar PV Interconnections

Using Hosting Capacity Methodology to Develop Simplified Screens for New Solar PV Interconnections Using Hosting Capacity Methodology to Develop Simplified Screens for New Solar PV Interconnections Jeff Smith, Matt Rylander EPRI Robert Broderick Sandia National Laboratory Barry Mather NREL 6 th International

More information

Distributed Generation and Impacts to Distribution Systems. FMEA Energy Connections Conference 2017

Distributed Generation and Impacts to Distribution Systems. FMEA Energy Connections Conference 2017 Distributed Generation and Impacts to Distribution Systems FMEA Energy Connections Conference 2017 1 Biographies Matt Lundeen has a BSEE degree from the University of Florida and is currently pursuing

More information

Renewable Grid Integration Research in the U.S.

Renewable Grid Integration Research in the U.S. Renewable Grid Integration Research in the U.S. Barry Mather Ph.D. NREL- Distributed Energy Systems Integration Group UNSW IEA PVPS Task 14 Workshop Sydney, AU November 26 th, 2013 NREL is a national laboratory

More information

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008 PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral

More information

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management Southern Company Interconnection Process Dexter Lewis Research Engineer Research and Technology Management Southern Company Outline Southern Company GPC Solar Interconnection Process Application requirements

More information

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation CONNECTION ASSESSMENT & APPROVAL PROCESS ASSESSMENT SUMMARY Applicant: Project: Cardinal Substation Modification of 115kV Substation CAA ID: 2002 EX071 Long Term Forecasts & Assessments Department\ Consistent

More information

The North Carolina solar experience: high penetration of utility-scale DER on the distribution system

The North Carolina solar experience: high penetration of utility-scale DER on the distribution system 1 The North Carolina solar experience: high penetration of utility-scale DER on the distribution system John W. Gajda, P.E. Duke Energy IEEE PES Working Group on Distributed Resources Integration 2 High

More information

Accidental Islanding of Distribution Systems with Multiple Distributed Generation Units of Various Technologies

Accidental Islanding of Distribution Systems with Multiple Distributed Generation Units of Various Technologies CIGRÉ-EPRI Grid of the Future Symposium 21, rue d Artois, F-75008 PARIS Boston, MA, October 20-22, 2013 http : //www.cigre.org Accidental Islanding of Distribution Systems with Multiple Distributed Generation

More information

POW ER EN G IN EER S, L LC

POW ER EN G IN EER S, L LC POW ER EN G IN EER S, L LC Electrical Engineering, Power, Lighting, Technical Studies and Utility Consulting 37 Fox Den Road Kingston, MA 02364-2150 (508) 612-0382 Phone (781)936-8641 Fax Dave@PowerEngineersLLC.com

More information

TRANSMISSION PLANNING CRITERIA

TRANSMISSION PLANNING CRITERIA CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing

More information

Document Requirements for Engineering Review- PV Systems v1.1 12/6/2018

Document Requirements for Engineering Review- PV Systems v1.1 12/6/2018 Document Requirements for Engineering Review- PV Systems v1.1 12/6/2018 Outlined below are the engineering documents and their associated minimum detail requirements for a Distributed Energy Resource (DER)

More information

Document Requirements for Engineering Review PV Systems v1.0 6/9/2017

Document Requirements for Engineering Review PV Systems v1.0 6/9/2017 Document Requirements for Engineering Review PV Systems v1.0 6/9/2017 Outlined below are the documents and associated minimum details required for Engineering Review of Distributed Energy Resources Interconnection

More information

Draft Guideline for the connection of smallscale inverter based distributed generation. EEA Asset Management Forum 22 June 2016 Dr Richard Strahan

Draft Guideline for the connection of smallscale inverter based distributed generation. EEA Asset Management Forum 22 June 2016 Dr Richard Strahan Draft Guideline for the connection of smallscale inverter based distributed generation EEA Asset Management Forum 22 June 2016 Dr Richard Strahan Outline 1. Introduction and Issues to Address 2. Methodology

More information

Wind Interconnection and Net-Metering in MA. Tim Roughan - National Grid Joe Feraci - NStar

Wind Interconnection and Net-Metering in MA. Tim Roughan - National Grid Joe Feraci - NStar Wind Interconnection and Net-Metering in MA Tim Roughan - National Grid Joe Feraci - NStar Electric Transmission and Distribution System The Electric Power System (EPS) is designed to safely and reliably

More information

Small Generator Interconnection Program Interconnection Technical Requirements

Small Generator Interconnection Program Interconnection Technical Requirements General Program Information What is the purpose of the PGE Small Generator Interconnection Program? How do I initiate a distribution interconnection request for my project? The purpose of our Small Generator

More information

Net Metering Interconnection Requirements. Customer Generation Capacity Not Exceeding 100 kw. Date: Version: 1

Net Metering Interconnection Requirements. Customer Generation Capacity Not Exceeding 100 kw. Date: Version: 1 Net Metering Interconnection Requirements Customer Generation Capacity Not Exceeding 100 kw Date: 2017-07-01 Version: 1 Revision History Date Rev. Description July 01, 2017 1 Initial release Newfoundland

More information

PES Cook Islands KEMA Grid Study Final Report

PES Cook Islands KEMA Grid Study Final Report Integrating PV Solar and Wind generation with the TAU electric system Te Aponga Uira O Tumu-Te_Varovaro Contents 1. Executive summary... 2 2. Introduction... 5 2.1 Proposed wind turbine sites... 6 2.2

More information

CUSTOMER/ TWIN ARROWS PROJECT

CUSTOMER/ TWIN ARROWS PROJECT A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset

More information

Feasibility Study Report

Feasibility Study Report Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Chester County, SC Total Output Requested By Customer: 74.5 MW Commercial Operation Date Requested By Customer: 1/7/2019 Feasibility

More information

An Integrated Grid Path for Solar. Thomas Key, EPRI Senior Technical Executive. ISES Webinar. April 22, 2016

An Integrated Grid Path for Solar. Thomas Key, EPRI Senior Technical Executive. ISES Webinar. April 22, 2016 An Integrated Grid Path for Solar Thomas Key, EPRI Senior Technical Executive ISES Webinar April 22, 2016 Changing Landscape: An Integrated Grid is a Better Grid Combined Heat & Power Demand Response Energy

More information

Minnesota Dept. of Commerce, Division of Energy Resources. Distributed Generation Workshop Interconnection Standards

Minnesota Dept. of Commerce, Division of Energy Resources. Distributed Generation Workshop Interconnection Standards Minnesota Dept. of Commerce, Division of Energy Resources Distributed Generation Workshop Interconnection Standards Presented by Michael Sheehan, P.E. October 11, 2011 Germans Solar Projected Cost Reductions

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

GENERATOR INTERCONNECTION APPLICATION

GENERATOR INTERCONNECTION APPLICATION GENERATOR INTERCONNECTION APPLICATION FOR ALL PROJECTS WITH AGGREGATE GENERATOR OUTPUT OF MORE THAN 150 KW BUT LESS THAN OR EQUAL TO 550 KW Also Serves as Application for Category 3 Net Metering (Note:

More information

Energy Security Electrical Islanding Approach and Assessment Tools. Dr. Bill Kramer Senior Research Engineer Distributed Energy Systems Integration

Energy Security Electrical Islanding Approach and Assessment Tools. Dr. Bill Kramer Senior Research Engineer Distributed Energy Systems Integration Energy Security Electrical Islanding Approach and Assessment Tools Dr. Bill Kramer Senior Research Engineer Distributed Energy Systems Integration Dr. Bill Kramer - 2 Electricity, Resources, & Building

More information

Net Metering Interconnection Requirements

Net Metering Interconnection Requirements Net Metering Interconnection Requirements Customer Generation Capacity Not Exceeding 100 kw Date: 2017-07-01 Version: 1 Revision History Date Rev. Description July 1, 2017 1 Initial Release Newfoundland

More information

Appendix A2: Technical Requirements for Distributed Generators > 10 kw to be Connected to Kitchener-Wilmot Hydro Inc. s Distribution System

Appendix A2: Technical Requirements for Distributed Generators > 10 kw to be Connected to Kitchener-Wilmot Hydro Inc. s Distribution System Appendix A2: Technical Requirements for Distributed Generators > 10 kw to be Connected to Kitchener-Wilmot Hydro Inc. s Distribution System A. INTRODUCTION This document outlines the technical requirements

More information

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007 High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM-2006-02) Interconnection Facility Study Final Report November 2, 2007 Prepared by: Public Service Company of New Mexico Electric Services

More information

NW Energy XP Project

NW Energy XP Project NW Energy XP Project Grid Impacts of Embedded Energy Storage for Distributed PV Systems with Advanced Inverter Controls Student Team: John Hofman (WSU), Taylor Redding (OIT), Umid Mamadaminov (OIT), Andrew

More information

Distributed Generation

Distributed Generation Distributed Generation Presented by: Doug Fairchild & Chris Cooper 1 Agenda Hydro One Overview The state of DG in the Province of Ontario Technical Issues Operational Requirements Overview Control Room

More information

Interconnection Feasibility Study Report GIP-369-FEAS-R1

Interconnection Feasibility Study Report GIP-369-FEAS-R1 Interconnection Feasibility Study Report GIP-369-FEAS-R1 System Interconnection Request #369 50 MW Wind Generating Facility Cumberland County (L-6513) 2012-02-09 Control Centre Operations Nova Scotia Power

More information

Net Metering in the United States

Net Metering in the United States Net Metering in the United States Kevin T. Fox, KEYES & FOX LLP November 24, 2011 Sao Paulo, Brazil 1 PV Cost Reduc=ons 2 PV Module Cost Trends 3 Comparison to Retail Rates - Brazil Source: ANEEL 4 Comparison

More information

Copyright 2003 Advanced Power Technologies, Inc.

Copyright 2003 Advanced Power Technologies, Inc. Overview of the Standard for Interconnecting Distributed Resources with Electric Power Systems, IEEE 1547 and it s potential impact on operation of the Distributed Generation (DG) systems and on the design

More information

Generation Interconnection Facilities Study For

Generation Interconnection Facilities Study For Generation Interconnection Facilities Study For Prepared for: Prepared by: SCE&G Transmission Planning May 27, 2015 TABLE OF CONTENTS General Discussion... Page 3 Generator Interconnection Specifications...

More information

ELECTRIC SERVICE RULES DISTRIBUTED GENERATION Issued Jan 2016

ELECTRIC SERVICE RULES DISTRIBUTED GENERATION Issued Jan 2016 DISTRIBUTED GENERATION CHAPTER 5 500. SCOPE This chapter includes distributed or customer-owned generation connected in parallel and operating with Alliant Energy s electric distribution system. For all

More information

Distributed Energy Resources

Distributed Energy Resources Distributed Energy Resources WECC Data Subcommittee Rich Hydzik, Avista (ERSWG/DER Subgroup Lead) June 29, 2018 Why Are We Concerned About DER? Concern about changing generation fleet Large coal fired

More information

Reactive Power Compensation for Solar Power Plants. Andy Leon IEEE PES Chicago Chapter December 12 th, 2018

Reactive Power Compensation for Solar Power Plants. Andy Leon IEEE PES Chicago Chapter December 12 th, 2018 1 Reactive Power Compensation for Solar Power Plants Andy Leon IEEE PES Chicago Chapter December 12 th, 2018 2 Objectives Refresh the basics of reactive power from a generator s perspective Regulatory

More information

Maryland Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kw to 10 MW or less)

Maryland Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kw to 10 MW or less) Maryland Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kw to 10 MW or less) Interconnection Customer Contact Information Name: Address: City: Telephone (aytime):

More information

TECHNICAL SPECIFICATION FOR INDEPENDENT POWER PRODUCERS. NB Power Customer Service and Distribution. June 2008

TECHNICAL SPECIFICATION FOR INDEPENDENT POWER PRODUCERS. NB Power Customer Service and Distribution. June 2008 NB Power Customer Service and Distribution June 2008 Prepared by: Steven Wilcox Revised by: Steven Wilcox TABLE OF CONTENTS 1.0 Introduction 4 2.0 NB Power Policy on Independent Power Production 4 3.0

More information

SPIDER Modeling Sub-Group DER Modeling, CAISO Experience

SPIDER Modeling Sub-Group DER Modeling, CAISO Experience SPIDER Modeling Sub-Group DER Modeling, CAISO Experience Irina Green, Modeling Sub-Group Chair Regional Transmission Senior Advisor, California ISO NERC SPIDER Work Group Meeting, January 2019 Presentation

More information

Renewable Energy & Storage Best Practice at TPL and Issues Faced. Murray Sheerin Power Generation Manager, Tonga Power Limited.

Renewable Energy & Storage Best Practice at TPL and Issues Faced. Murray Sheerin Power Generation Manager, Tonga Power Limited. Renewable Energy & Storage Best Practice at TPL and Issues Faced. Murray Sheerin Power Generation Manager, Tonga Power Limited. Tonga Power Limited Tonga Power Limited (TPL) is a 100% state owned enterprise

More information

MIPSYCON 2014 Can a Grid be Smart without Communications? A Look at an Integrated Volt Var Control (IVVC) Implementation

MIPSYCON 2014 Can a Grid be Smart without Communications? A Look at an Integrated Volt Var Control (IVVC) Implementation MIPSYCON 2014 Can a Grid be Smart without Communications? A Look at an Integrated Volt Var Control (IVVC) Implementation David Aldrich Beckwith Electric Company Goals Flatten voltage profile across entire

More information

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655)

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655) - (SMUD FORM 2655) A. Applicability: This Generating Facility Interconnection Application (Application) shall be used to request the interconnection of a Generating Facility to Sacramento Municipal Utility

More information

Southern California Edison (SCE) PRP Solar Si?ng Survey Overview

Southern California Edison (SCE) PRP Solar Si?ng Survey Overview Southern California Edison (SCE) PRP Solar Si?ng Survey Overview These documents and the analysis and conclusions contained in them are exclusively the work of Clean Coali?on, who bears sole responsibility

More information

El Paso Electric Company

El Paso Electric Company Feasibility Study XXXXXX Solar Generation Prepared for El Paso Electric Company Prepared by TRC Engineers, LLC 249 Eastern Avenues Augusta, ME 04330 (207) 621-7000 Project Number: 202327 May 2013 FOREWORD

More information

New 115 kv Disconnect Switches at Bloomsburg MTS

New 115 kv Disconnect Switches at Bloomsburg MTS 115 kv Line tap from C9 to Bloomsburg MTS & New Bus Tie Switch CAA ID Number: 2007-EX353 Final Draft ASSESSMENT SUMMARY 1. GENERAL DESCRIPTION Norfolk TS and Bloomsburg MTS are supplied by a single 115

More information

Solar Farms: design & construction

Solar Farms: design & construction Solar Farms: design & construction Impacts to utility distribution systems John W. Gajda, P.E. Duke Energy Manager, DER Operations Support Agenda North Carolina s unique situation, which is coming to a

More information

PSNH INTERCONNECTION REQUEST

PSNH INTERCONNECTION REQUEST PSNH INTERCONNECTION REQUEST Send the completed Interconnection Request and required attachments to: Public Service of New Hampshire Attn: Michael Motta, Senior Engineer Supplemental Energy Sources P.

More information

Request for Payment Instructions Wholesale Distribution Access Tariff (WDAT) Attachment I - GIP

Request for Payment Instructions Wholesale Distribution Access Tariff (WDAT) Attachment I - GIP Grid Interconnection & Contract Development Request for Payment Instructions Wholesale Distribution Access Tariff (WDAT) Attachment I - GIP Submittal Instructions Prior to submitting your application and

More information

Exelon Energy Delivery Interconnection Guidelines for Generators 2 MVA or less

Exelon Energy Delivery Interconnection Guidelines for Generators 2 MVA or less Exelon Energy Delivery Interconnection Guidelines for Generators 2 MVA or less Original: October 31, 2006 Table of Contents: INTRODUCTION and SCOPE... 3 DEFINITIONS... 3 QUALIFICATIONS FOR AN EXPEDITED

More information

SERTP - 1 st Quarter Meeting

SERTP - 1 st Quarter Meeting 2019 SERTP SERTP - 1 st Quarter Meeting First RPSG Meeting & Session March 20 th, 2019 Charlotte, NC 1 2019 SERTP Process Information The SERTP process is a transmission planning process. Please contact

More information

APPLICATION Net Energy Metering Interconnection For Solar And/Or Wind Electric Generating Facilities Of 30 Kilowatts Or Less

APPLICATION Net Energy Metering Interconnection For Solar And/Or Wind Electric Generating Facilities Of 30 Kilowatts Or Less IMPORTANT NOTES: Customers may not operate their Generating Facility while interconnected to the PG&E system until they receive written permission from PG&E. For a non-exporting Generating Facility, RES-BCT

More information

Maryland Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kw to 10 MW or less)

Maryland Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kw to 10 MW or less) Maryland Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kw to 10 MW or less) Interconnection Customer Contact Information Name: Address: Alternative Contact Information

More information

State Policies - Distributed Energy Resources

State Policies - Distributed Energy Resources State Policies - Distributed Energy Resources Ken Nichols Presented to: NCSL 2015 August 2, 2015 ken@eqlenergy.com 503-438-8223 Distribution Utility of the Future Distribution utilities will no longer

More information

NORTH CAROLINA INTERCONNECTION REQUEST APPLICATION FORM. Utility: Duke Energy Progress

NORTH CAROLINA INTERCONNECTION REQUEST APPLICATION FORM. Utility: Duke Energy Progress NORTH CAROLINA INTERCONNECTION REQUEST APPLICATION FORM ATTACHMENT 2 Utility: Duke Energy Progress Designated Utility Contact: Attention: Customer Owned Generation Mail Code ST13A E-Mail Address: Customerownedgeneration@duke-energy.com

More information

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting BHE Wyoming Q4 Stakeholder Meeting November 17, 2016 @ 1:00PM MT Black Hills Energy Service Center 409 Deadwood Avenue, Rapid

More information

Power Protection Discrete Automation & Motion South Africa

Power Protection Discrete Automation & Motion South Africa Carel Oberholzer, ABB South Africa, May 2013 PCS100 Power Protection Discrete Automation & Motion South Africa May 13, 2013 Slide 1 Power Protection Agenda 1. Introduction of power protection 2. Overview

More information

Review paper on Fault analysis and its Limiting Techniques.

Review paper on Fault analysis and its Limiting Techniques. Review paper on Fault analysis and its Limiting Techniques. Milap Akbari 1, Hemal Chavda 2, Jay Chitroda 3, Neha Kothadiya 4 Guided by: - Mr.Gaurang Patel 5 ( 1234 Parul Institute of Engineering &Technology,

More information

DYNAMIC LOAD FLOW STUDIES OF DISTRIBUTION FEEDS IN THE SAN JOAQUIN VALLEY REGION

DYNAMIC LOAD FLOW STUDIES OF DISTRIBUTION FEEDS IN THE SAN JOAQUIN VALLEY REGION DYNAMIC LOAD FLOW STUDIES OF DISTRIBUTION FEEDS IN THE SAN JOAQUIN VALLEY REGION INTERIM REPORT AS OF JULY 21, 2016 PRESENTED JULY 21, 2016 1 TABLE OF CONTENTS Section Introduction Advanced Inverter Approach

More information

PV GRID Forum, Stockholm, April Experiences from Denmark. Presentation

PV GRID Forum, Stockholm, April Experiences from Denmark. Presentation PV GRID Forum, Stockholm, April 26. 2013 Experiences from Denmark Kenn H. B. Frederiksen Presentation About EnergiMidt General status PV and grid interconnection Some of the R&D projects. 1 About EnergiMidt

More information

Enquiry Form (Non-Registered Generator With Capacity less than 5 MW)

Enquiry Form (Non-Registered Generator With Capacity less than 5 MW) Connection Applicant (Embedded Generating Unit Owner/Proponent) Business name: ABN: Contact name: Address: Telephone number: E-mail address: Connection Applicant acting and working on behalf of the above

More information

Galapagos San Cristobal Wind Project. VOLT/VAR Optimization Report. Prepared by the General Secretariat

Galapagos San Cristobal Wind Project. VOLT/VAR Optimization Report. Prepared by the General Secretariat Galapagos San Cristobal Wind Project VOLT/VAR Optimization Report Prepared by the General Secretariat May 2015 Foreword The GSEP 2.4 MW Wind Park and its Hybrid control system was commissioned in October

More information

Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kva to 10 MVA or less)

Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kva to 10 MVA or less) Section 466.APPENIX C Levels 2 to 4 Application Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kva to 10 MVA or less) Interconnection Customer Contact Information

More information

Comments on the Solar Alliance Proposal for Changes to New Jersey Interconnection Rules

Comments on the Solar Alliance Proposal for Changes to New Jersey Interconnection Rules Comments on the Solar Alliance Proposal for Changes to New Jersey Interconnection Rules Submitted to New Jersey Board of Public Utilities By Qado Energy Power Engineering Team August 12, 2011 1 Table of

More information

Oncor Application for Interconnection of Distributed Generation

Oncor Application for Interconnection of Distributed Generation Oncor Application for Interconnection of Distributed Generation Certified Systems (12/7/2017) What is a certified system? A certified system is one that meets the requirements of UL-1741 Utility Interactive

More information

Grid connected battery energy storage

Grid connected battery energy storage Grid connected battery energy storage Asset Management Energex Limited March 2016 A presentation to 2016 API Summer School Energex driving energy innova9on Contents Energex ba+ery trials Grid connected

More information

Small Electrical Systems (Microgrids)

Small Electrical Systems (Microgrids) ELG4126: Microgrids Small Electrical Systems (Microgrids) A microgrid is a localized, scalable, and sustainable power grid consisting of an aggregation of electrical and thermal loads and corresponding

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

Grid Stability Analysis for High Penetration Solar Photovoltaics

Grid Stability Analysis for High Penetration Solar Photovoltaics Grid Stability Analysis for High Penetration Solar Photovoltaics Ajit Kumar K Asst. Manager Solar Business Unit Larsen & Toubro Construction, Chennai Co Authors Dr. M. P. Selvan Asst. Professor Department

More information

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation 1. Description In the 2013-2014 Transmission Planning Cycle, the ISO approved the construction

More information

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission

More information

Diane Lindsey CenterPoint Energy SWEDE 2010

Diane Lindsey CenterPoint Energy SWEDE 2010 Diane Lindsey CenterPoint Energy SWEDE 2010 Agenda Background Pre Hurricane Ike Dredge Evaluation Aftermath of Hurricane Ike in 2008 Temporary West Galveston Mobile Substation Post Hurricane Ike Dredge

More information

DC Microgrids and Distribution Systems for Residences

DC Microgrids and Distribution Systems for Residences Microgrids and Distribution Systems for Residences Toshifumi ISE, Hiroaki KAKIGANO (Osaka University, JAPAN) Outline of the Presentation 1. Introduction 2. System Configuration and Control Scheme 3. System

More information

C PER. Center for Advanced Power Engineering Research C PER

C PER. Center for Advanced Power Engineering Research C PER Center for Advanced Power Engineering Research C PER 2017 Summer Research Planning Workshop Energy Storage Technologies and Application Roadmap Presented By: Johan Enslin Zucker Family Graduate Education

More information

CATEGORY 2 GENERATOR INTERCONNECTION APPLICATION

CATEGORY 2 GENERATOR INTERCONNECTION APPLICATION CATEGORY 2 GENERATOR INTERCONNECTION APPLICATION FOR ALL PROJECTS WITH AGGREGATE GENERATOR OUTPUT OF MORE THAN 20 KW BUT LESS THAN OR EQUAL TO 150 KW Also Serves as Application for Category 2 Net Metering

More information

The Effect Of Distributed Generation On Voltage Profile and Electrical Power Losses Muhammad Waqas 1, Zmarrak Wali Khan 2

The Effect Of Distributed Generation On Voltage Profile and Electrical Power Losses Muhammad Waqas 1, Zmarrak Wali Khan 2 International Journal of Engineering Works Kambohwell Publisher Enterprises Vol., Issue 1, PP. 99-103, Dec. 015 www.kwpublisher.com The Effect Of Distributed Generation On Voltage Profile and Electrical

More information

Electric Utility Contact Information Indiana Michigan Power

Electric Utility Contact Information Indiana Michigan Power CATEGORY 2 GENERATOR INTERCONNECTION APPLICATION FOR ALL PROJECTS WITH AGGREGATE GENERATOR OUTPUT OF MORE THAN 20 KW BUT LESS THAN OR EQUAL TO 150 KW Also Serves as Application for Category 2 Net Metering

More information