Increasing Backup Generation Capacity and System Reliability by Selling Electricity during Periods of Peak Demand

Size: px
Start display at page:

Download "Increasing Backup Generation Capacity and System Reliability by Selling Electricity during Periods of Peak Demand"

Transcription

1 Increasing Backup Generation Capacity and System Reliability by Selling Electricity during Periods of Peak Demand Elisabeth A. Gilmore a & Lester B. Lave a,b a: Department of Engineering and Public Policy, b: Tepper School of Business Mailing address: Department of Engineering and Public Policy Carnegie Mellon University Baker Hall 129, 5 Forbes Ave Pittsburgh, PA, USA, TEL (412) ; FAX (412) ; eagilmor@andrew.cmu.edu Abstract Meeting electricity demand during the 2 hours of greatest use each year is costly and challenging, especially in transmission constrained urban centers. Allowing installed backup and emergency generators to sell electricity for profit during peak demand and participate in the installed capacity (ICAP) market could lower the price of electricity and increase the reliability for all customers, not just the owners. The additional revenue could also provide an incentive for more customers to buy backup generators, adding still more reliability to the system. Here, we evaluate the economic potential of using backup generator for meeting peak electricity demand and ICAP requirements in the New York City Long Island (NYC-LONGLI) region in New York (NY) State. First, we calculate the implicit value of unserved electricity as revealed by the investment in backup generator. Second, we evaluate the profit that would be earned by a backup generator available during the 2 peak hours each year, using the NYC and LONGLI zonal prices in 25 and in 26 as a case study. The profits from real electricity are calculated as the zonal prices minus the marginal cost of the generator. The profits from the ICAP market are equal to the clearing price minus the opportunity cost of being ready to operate. We then subtract the available profits from the costs of ownership (fixed costs) to estimate the reduced implicit value of reliability, or the adjusted reservation price for purchasing a generator. We then estimate the increase in backup capacity. Finally, we address the effect of having all backup generators, rather than a single one, provide electricity to the market. We find that the implicit value of unserved electricity is much greater than the estimates in literature, since owners of backup generator reveal themselves to value electricity during lost service at approximately 26$/kWh or 85.9 $/kw year. A single backup generator selling during the top 2 hours in NYC or LONGLI and participating in the summer and winter ICAP markets could generate sufficient revenue to lower its costs by approximately 8% with most of the profits from the ICAP market. If additional backup generators could earn this revenue, we estimate that this would result in adding 4 MW of backup generator capacity in NYC and 115 MW in Long Island. However, as additional backup generators produce power during the peak hours, they reduce the market clearing price for electricity. They also reduce the price in ICAP markets. If all of backup generation were bid into the market, we estimate that the market clearing price would equal the generation cost of these backup units, generating no revenue beyond variable cost. Similarly, the price in the capacity market would fall to zero. While making all the backup generators available during peak hours would not generate much additional revenue for the owners of the generators, it would save electricity customers a great deal of money, especially in the capacity market, as well as increase system reliability. We estimate a savings of $66 million and $75 million in electricity payments in NYC and LONGLI, respectively, and $1 billion and $5 million in the ICAP market in NYC and LONGLI, respectively. 1. Introduction Matching supply to demand when demand for electricity is very high presents a major challenge for the US electricity sector. Unlike other commodities, electricity supply and demand must be met at all times or at least some customers will face curtailments (e.g. rolling brownouts). Under severe conditions, there will be a blackout. The problem of meeting peak electricity demand is becoming more acute. Load is projected to grow, while investment in new generation and transmission is lagging behind demand. In addition, there are substantial difficulties in siting new facilities, especially in highly populated urban areas where most of the growth in demand is anticipated. For example, in New York City (NYC) 1

2 and Long Island (LONGLI), load is projected to grow by more than two percent per year. A recent study by the New York Independent System Operator (NYISO) concluded that by 211, without major investments in generation and transmission capacity, the region will be in violation of its reliability criteria (1). In a competitive electricity market, electricity prices should provide a sufficient signal to stimulate investment in the quantity, the location and type of generation needed to meet demand. The primary price signal is from selling real power. In its simplest form, a supply curve is constructed from bids from the available generators who in a perfectly competitive environment have the incentive to bid their marginal cost. This supply curve is intersected by the expected load. All generators that are dispatched to meet this demand are paid the marginal cost of the final generator dispatched. This price is referred to as the market clearing price (MCP). For generators with marginal costs less than the MCP, the difference between the MCP and the marginal cost is profit which is used to recover fixed capital and operating & maintenance (O&M) costs. However, if bids are restricted the marginal cost, a plant that is dispatched only at peak demand can never receive more than its marginal cost since it sets the MCP. In reality, generators can bid above their marginal costs when supply is constrained, especially if there are pivotal suppliers in the market. To prevent price spikes, many markets have established price caps (no greater than 1 $/MWh) to limit this type of bidding. While price caps are politically convenient, they reduce the ability of generators to recover their costs. A generator incurs certain costs to available to provide electricity. If it cannot recover these costs in the electricity market, the generator should shutdown. This, however, has implications for reliability. To provide sufficient profits to ensure adequate reserves and promote the construction of new generation, installed capacity (ICAP) markets have been developed (2). Several competitive electricity regions, including the PJM regional transmission operator (RTO), the independent system operator (ISO) New England (ISO-NE) and the New York ISO (NYISO) have instituted these markets. The ICAP markets are very much in flux. The NYISO market is a hybrid system where loads can acquire the stipulated reserves from bilateral trades and self provision with the balance purchased in a market. Similar to the market for electricity, the capacity market clears where supply meets demand, although in this case, the NYISO constructs the demand curve. These markets, however, are controversial and in the NYISO, the payments are expensive (3). At the same time as the markets are experiencing difficulty meeting demand, electricity consumers are demanding higher reliability. A range of consumers, for example financial services, hospitals and universities, with a high value load or high economic value for reliability have installed substantial amounts of backup or emergency generators (at least for their critical services). It is estimated that there is approximately 1,32 MW of backup capacity in New York City and 5 MW in Long Island (4). Presently operating only when the grid fails (approximately 2-3 hours/year in the United States) (5), these generators represent a substantial source of underutilized capacity. Since the capital costs of the backup generators can be ascribed to the reliability application, installed backup generators could operate at their marginal costs for peak electricity, increasing grid reliability and supporting electricity delivery (6). Further, allowing these generators to run for economic profit could also increase the total backup generator population, increasing overall reliability. Operating these generators could be very valuable in the New York City area as it experiences very high peak electricity prices, is severely transmission constrained and has not experienced sufficient investment and construction of new generation. There are also potential benefits in the capacity market, dramatically increasing the system reserves. There are, however, barriers to this strategy. First, there is the need for retrofits to the interconnections to allow the generator to operate in parallel with the grid. Second, most of these generators are diesel fuelled with limited environmental emission controls. Previous work on using these generators for meeting peak electricity demand showed that emission controls, specifically diesel particulate filters (DPF), are required to limit air quality and human health effects (7). While this is a suitable retrofit for some of the installed backup generators, newer diesel generators conform to the Environmental Protection Agency (EPA) emission standards for off road generators. Ideally, allowing these generators to operate for peak power and reliability would generate sufficient profit to encourage the purchase of new cleaner generators. Finally, the profits must be sufficient to justify the expense of dedicating resources to operate the backup generators during periods of peak electricity. Presently, backup generators are permitted into two NYISO programs: 1) the special case capacity reserves (SCR) and emergency demand response program (EDRP). In both programs, the backup generators operate when called upon by NYISO under conditions of system stress. These programs, however, do not capture the full value that these generators could bring to the market in terms of lowering electricity prices at peak electricity demand, reducing capacity payments and improving system reliability. In addition, the NYISO has expressed its intent to investigate protocols for bringing these generators into the regular markets, possibly by aggregating them to create megawatt (MW) size capacity blocks and decrease concerns about generators failing to comply. In this work, we quantify the potential of using backup generators for meeting peak electricity demand in the New York City (NYC) and Long Island (LONGLI). Specifically, our objectives are as follows: 2

3 1. To examine the available profits for backup generators selling during periods of peak electricity demand and participating in the capacity markets, and investigate how these profits influence the quantity of backup generators capacity; 2. To explore the system effects (simultaneity problem) of how profits will change with the additional backup generators; and, 3. To evaluate the system (social) benefits, specifically in reduced capacity market payments and improve reliability, and to what extent inducements are justified for this strategy. 2. Literature Review 2.1 Economics of reliability and backup generation The economic decision to install backup generation is a function of the value that a firm places on electricity. The value a consumer puts on an unsupplied MWh of energy is frequently defined as the value of lost load (VOLL). Since there is no market for unsupplied electricity, the VOLL is determined by indirect methods, and literature reveals numerous techniques (8). The most common method is the use of customer surveys. Industrial, commercial and residential sector customers are asked identify their costs from power interruptions. While this technique has been widely employed, there are concerns that individuals may overestimate their costs. To overcome this issue, economists also employ indirect methods. Telson (1975) popularized a macroeconomic approach, where VOLL is estimated as the gross economic output divided by electricity consumed (9). In 24, the US GDP was 11.7 trillion dollars and electricity consumption was 3.7 trillion kwh leading to an implied VOLL of 3.15 $/kwh. This value, however, does not account for the damages observed from an unplanned outage. This criticism prompted a second approach which evaluates the direct and indirect financial damages from an actual outage. For example, an evaluation of the New York City outage in 1977 yielded a VOLL of 13 $/kwh (in 27 dollars) (1). In Table 1, we present a range of literature values for VOLL in 27 dollars for the United States by consumer 1. Some researchers have noted a recent increase in VOLL (e.g. (11)), attributing it to the growth in importance of communication networks. Table 1: Mean values of lost load (with low and high values) (data from (8, 12)) Consumer Value in $/kwh Industrial 9.38 ( ) Commercial 1.4 ( ) Residential.8 ( ) United States Average 6.86 ( ) A different approach to estimating the VOLL is to assume that the cost of self-generating during an outage is equal to the marginal cost of an outage. Bental and Ravid (1982) argue that a rational consumer of electricity who would like insurance against all or some of the damages caused by a power outage will acquire backup generators. Since these generators are relatively expensive, the firm has to choose the optimal amount. For a profit maximizing, risk neutral firm, the optimal amount is found when the expected cost of generating the marginal kwh is equal to the expected gain from that kwh, which is also equal to the expected loss from the marginal kwh not supplied by the utility. They calculated a VOLL of 1.16 $/kwh (1982) or 3.5 $/kwh (27) for an expected outage of 1 hours per year (13). Presently, the US grid operates at an availability approaching 4 nines or approximately 99.96%. This corresponds to about 3.5 hours of outage per year. LaCommare and Eto (26) estimate that the average duration of an outage was 16 minutes with a standard deviation of 54 minutes and that outages occurred at a frequency of 1.2 events per year with a standard deviation of.5 events per year (5). Using these figures, we estimate 2.12 hours of outage per year. Even 2 hours, however, can have serious consequences for a wide range of electricity consumers, especially those that rely on communication networks such as banks, internet service providers, on-line trading and research centers. A wide range of 1 While these are point estimates, we note that in reality VOLL is also a function whether the outage is planned or unplanned, the time of day and the time of year and the duration of the outage. 3

4 other consumers also rely on highly reliable electricity. Examples of sources of backup generators include hospitals, data centers, high-rise buildings, communication centers, water and wastewater treatment plants, military facilities, and airports (14). In addition, a facility is likely unable to resume full operations precisely when the power resumes, leading to a further loss of productivity. To protect against the disruptions caused by power failures, many firms have installed backup generators. The Federal Energy Regulatory Commission (FERC) estimates that there are about 12 million DG units installed across the country, with a total capacity of about 2 GW and that most of these are backup or emergency generators (15). In the Northeast states, it is estimated that the population of diesel internal combustion engines is well over 3, units with a combined capacity greater than 1 GW (4). Approximately 8% of the engines or 74% of the total capacity are estimated to be installed for emergency usage. Normally, a facility sizes the generators to meet the critical load of the facility. For some facilities such as hospitals this is a result of the legislation. For other facilities, Beenstock (1991) explains this behaviour has a reflection of either the high cost of self-generated power or the low assessment of the output loss relative to the equipment loss (16). In most jurisdictions, generators permitted for emergency usage are limited to operate only when the grid fails and for a maximum annual usage. For example, in New York State, the generators are limited to 5 hours per year and are exempt from emission standards or controls. 2.2 Backup generators and participation in electricity markets Regardless of the value of reliability of individual firms, once the generator is installed its operation is frequently limited to less than 2 hours per year for outages and approximately 2 hours per month for routine maintenance. Given the cumulative capacity in backup generators, their location near the load and their infrequent usage, several independent system operators (ISOs) have investigated or implemented programs that harness the backup generators during periods of peak electricity demand. In a recent survey conducted by the Federal Energy Regulatory Commission (FERC), it is estimated that there are 61 programs run by ISOs that make use of backup generators of which 27 are emergency demand response program, 16 are capacity market program, and 18 are demand bidding/buyback programs (17). These generators, however, do not participate in regular markets and are paid non-market prices for their participation. The NYISO operates three demand response programs which allow a load (either a firm or an aggregation) to profit from reducing its electricity demand either through efficiency or by shifting to a backup generator: 1) an Emergency Demand Response Program (EDRP); 2) a Day-Ahead Demand Response Program (DADRP); and, 3) an Installed Capacity Special Case Resources (ICAP-SCR) (18). The EDRP provides incentive payments to customers for load reductions during periods when reserve shortfalls arise. The ISO notifies the participants who have voluntarily enrolled to curtail their load serviced by the grid when called upon. They are, however, not required to actually curtail and face no penalties. In the NYISO, they are paid the higher of 5 /kwh or the wholesale electricity price in the generators area (known as the locational-based marginal price, LBMP). Since they are not required to curtail, they are not eligible to receive capacity payments from the ICAP-SCR. By contrast, the DADRP and ICAP-SCR have mandatory curtailment requirements, and the loads are subject to a penalty if they fail to meet their commitments. In addition, participants in DADRP are not permitted to use on site generation, while only 11% of the ICAP-SCR are from onsite generation in 24 (19). Participants in DADRP bid their load reductions on a day-ahead basis into the wholesale electricity market. These bids then compete with generators offers to meet demand. If accepted, the bidder is scheduled to reduce load during specified hours the following day. The bidder may specify a minimum payment, called a curtailment initiation cost with the participant receiving the higher of the curtailment cost or the hourly LBMP times the scheduled load. The ICAP-SCR program is designed primarily to provide an incentive for businesses and large power users to shutdown. In exchange, they are paid a capacity payment specified by the ISO upon program registration in advance for agreeing to cut power usage upon request. Payments ranged from 1.25 $/kwh on average in New York State to $/kwh in New York City. All these programs have met some success, and the NYISO s ERDP program is credited with providing an important resource during periods of reserve shortage during the August 23 blackout (17). There is, however, some controversy surrounding these programs as they require a system subsidy to ensure availability and are tightly controlled by the ISO rather than allowing the generators respond directly to market signals. In addition, in 23, the ERDP events were called only after the August 23 blackout, and there were no events in 24 (19). This situation leaves these backup generators available both to moderate high electricity prices and peak demand as well as to enhance system reserves. Presently, the NYISO has announced its intent to try to allow these generators to operate in their energy, ancillary and capacity markets. 4

5 3. Method and Data In this section, we describe the method we employed to evaluate the potential benefits of allowing the backup generators located in NYC and LONGLI into the regular NYISO markets. First, we calculate the implicit value of reliability from a backup generator. Second, we evaluate the profits available for a single generator in the electricity and installed capacity (ICAP) markets and calculate a reduced value of reliability. Third, we estimate the increase in the backup capacity in the NYC and LONGLI if the reservation price for purchasing backup is reduced. Fourth, we consider the effect on profits if all the previously installed capacity and the new capacity installed at the reduced reservation price enter into the electricity and ICAP markets. Even if there is little or no private incentive for the generators to operate, there is still the potential to reduce electricity prices, capacity payments and improve reliability by increasing system reserves. We calculate the system wide benefits from bringing these generators into the market. Finally, we contrast the value of this strategy in a regulated and deregulated market. For this analysis, we use market data from 25 and 26 from NYC and LONGLI as a case study. 3.1 The implicit value of reliability from a backup generator Following the approach of Bental and Ravid (1982), we calculate an implicit value of unserved electricity as the cost of the backup generator with no electricity or capacity market sales. A customer who installs a generator must believe that their cost of unserved load is at least this high. The implicit value is the total unit cost of a backup generator (TC) which consists of the levelized capital and fixed operation costs (FC) and the marginal or variable unit costs (MC) of operation: TC = FC + VC. Eqn 1 CC CRF FOM FC = + HY HY MC = VOM + FUEL Where CC is the overnight capital cost (in $/kw) CRF is the capital recovery factor which includes interest and depreciation (~ 1 %) FOM is the fixed operating and maintenance (O&M) ($/kw-yr) FUEL is the fuel cost ($/kwh) HY is the number of hours the plant generates electricity (hours/year) VOM is the variable O&M ($/kwh) We calculate the value of reliability based on the cost of installing and operating emergency backup for the three primary backup generator options: a diesel fueled internal combustion engine (ICE), a natural gas fueled ICE, and a natural gas microturbine. In Table 2, we present the data for four different backup configurations: the three generator options and a diesel ICE retrofitted with a diesel particulate filter (DPF). Since the actual costs are a function of the specifics of the generator installation, these costs are meant to be indicative. Table 2: Costs of Backup Generators with and without Emission Controls (2, 21) Generator Type Efficiency (%) Capital Cost ($/kw) Fixed O&M ($/kw-yr) Variable O&M ( /kwh) Diesel ICE 35% Diesel ICE w DPF 34% Natural gas ICE 29% Natural gas microturbine 25% In any given year, the price of fuel will determine the variable cost of operating the engine with the fuel cost is calculated as follows: FUEL = P HR. Eqn 2. fuel Where P fuel is the price of fuel (in $/mmbtu); and HR is the heat rate (in mmbtu/kwh). 5

6 The heat rate equals 3,412 Btu/kWh or.3412 mmbtu/kwh (the conversion of energy (Btu) to electricity (kwh) at 1% efficiency) divided by the efficiency from Table 2. The price of natural gas and oil also influence the electricity prices, especially during peak hours where the marginal plant is fuelled by natural gas, residual distillate and oil distillate. The annual average natural gas price at the city gate was $/mmbtu on average in 25 and 26. For diesel, the price was approximately 14.9 $/mmbtu on average in 25 and 26, respectively (22). For the diesel ICE with a DPF, we add an incremental cost for utilizing low sulphur fuel (~ 1 /gallon). 3.2 The profits and increases in backup capacity Electricity markets Selling power into the electricity markets has the potential to be a profitable venture for the owner of a backup generator. We calculate the profits in $/kw year with equation 3: n Profits = ( MCP n MC backup ) Eqn 3. 1 Where MCP is the market clearing (in $/kwh); MC is the marginal cost of the backup generator (in $/kwh); and, n is the number of hours per year where MCP > MC. The NYISO has a two settlement process: a day-ahead market (DAM) and a real time market (RT). About 45% of the electricity is cleared through the DAM with any deviations from the projected demand met by the RT market. The amount of power traded on the real time market is less than 1 %. The remaining 5% is sold through bilateral contracts. In Appendix A, we show summary statistics for the DAM prices and RT prices. The average prices during the top 2 hours are two to three times the yearly average in both the NYC and LONGLI zones. The average peak prices in 25 and 26 are relatively consistent, but the average prices in 25 are higher than 26 due to higher natural gas prices. Similar other studies, we find that the RT market is more volatile than the DAM. This is due in part to the incentives for bidding into the DAM as well as the stronger market mitigation measures and price caps in the DAM compared to the RT market. Since this is an ex-post analysis, we assume that the owner of a generator has perfect information about the prices and duration of the spikes, and hence can maximize its profits. For simplicity, however, we assume that the generator chooses to participate in either the DAM or the RT market. We do not develop an optimal bidding strategy. All market data was extracted from the NYISO website (23). Generators also have the options of bidding to provide ancillary services, such as regulation and frequency response, 1 minute spinning reserves, 1 minute non-spinning reserves and 3 minute operating reserves. The engines would be ineligible for regulation and spinning reserve since they cannot respond for frequency response nor are they operating at all times. The generators, however, could potentially operate in the 1 minute non-spinning reserve and the 3 minute operating reserve market. While 1 minute non-spinning reserve would be an ideal application for backup generators, the most lucrative ancillary service market is for regulation. Previous work has shown that during the summer, real power MCPs are higher than 1 minute non-spinning and 3 minute operating reserves (24). This is generally the case with this data. As the number of new generators entering the market increases, however, the arbitrage opportunities will decrease and the backup generator may become the marginal plant. The NYISO estimates that there is approximately 1,36 MW of generation in the NYC zone and 5,32 MW of transmission capacity into city. Approximately, 4, MW arrives from upstate New York, 1, MW from New Jersey (PJM) and 3 MW from Long Island. During periods of peak loads, however, the transmission capacity is lower due to transmission constraints and local reliability rules (27). Generation capacity in Long Island is 5,767 MW with 1,731 MW of import capacity. This value does not include the new 66 MW PJM-Neptune Line which became operational in June July 27 (25). We take two complimentary approaches to evaluate whether the backup generators would become the marginal plant in the electricity market: 1) we construct theoretical zonal short run marginal cost curves (SRMC) using actual plant capacities and heat rates to estimate the room for arbitrage in the system, and 2) we compare the estimates from the system curves with estimates from real load-price relationships on peak days. To construct the SRMC, we use data on plant capacity and heat rates from the Emissions & Generation Resource Integrated Database (egrid) compiled by the Environmental Protection Agency (26). We also estimate that the 87.4% of the nameplate capacity is available 6

7 accounting for forced outages, maintenance schedules and reserve margins. We make the following assumptions for generators without heat rates in Table 3 and fuel costs in Table 4. The fuel costs are slightly lower for the electricity sector than the individual customers who own backup generators. We include imports equal to the transmission capacity and assume it is generated at 1 $/MWh. Since we do not know the actual transmission capacity at peak loads, we treat this as an adjustable parameter such we meet the peak loads with the marginal generators. Using the curve, we evaluate how many MW of capacity are dispatched with marginal costs above that of the backup generators. High prices, however, do not always correspond with high loads. This curve is a simplification of the actual dispatch. Frequently, on peak days, unexpected events such as outages or unexpected demand cause real time price to rise substantially even at lower loads. To provide a check on the modelled marginal cost curve, we isolate the load-price relationship for each day for days with the top 2 hourly loads. We fit each day to a curve and use this curve to estimate how much the price would reduced if all the available backup was available to be dispatched. Table 3: Marginal Costs for Generators (in $/MWh) Generation type Marginal Cost Hydro 1 Wind 1 Nuclear 2 Pumped Hydro 5 Biomass 5 Table 4: Fuel Costs (in $/mmbtu) Generation type Marginal Cost Coal 2.2 Natural Gas 7.5 Residual Fuel Oil (No. 6) 8.5 Distillate Fuel Oil (No. 2) Installed Capacity Markets Even if there is no profit in selling real power, there may, however, still be a profit for these generators in the installed capacity market (ICAP). For NYC and LONGLI, 8% and 99% of the regional peak load capacity must be procured from resources located in these regions, respectively. In Table 5, we show the monthly capacity payments in 25 and 26 for NYC and LI for summer (May October) and winter (Nov April). Table 5: Average seasonal ICAP clearing prices (in $/kw-month) (28) Season NYC LI NYC LI Winter Summer The NYISO ICAP market is a hybrid system combining a quantity based system and a demand curve system. In the quantity based system, load service entities (LSE) are required to procure a certain amount of generation capacity as calculated by the NYISO to meet their loads with a reserve margin. A part of this requirement is obtained through bilateral trades or self-supply (e.g. demand response and interruptible loads). This is combined with a market where the NYISO purchases capacity on behalf of the load based on a demand curve (2). In Figure 1, we present the demand curve for the ICAP market for 25 and 26. UCAP is known as unforced capacity which is equal to the installed capacity minus some allowance for reliability of the capacity. It is difficult to evaluate precisely how adding the backup generators would influence this market since the NYC market has been subject to gaming. We assume in our analysis, however, that this is a functioning market. 7

8 25 2 Figure 1: Demand curve for ICAP for summer of 25 and 26 NYC 25 NYC 26 LI 25 LI 26 Price (in $/kw-month) Unforced Capacity (in MW) 4. Results and Discussion 4.1 Economics of backup generators for reliability The economic argument for using backup generators for meeting peak electricity demand is that the capital cost is already attributed to the reliability application. The average outage lasts 1.77 hours and occurs 1.2 times per year for 2.12 hours per year of outage (8). However, the number of hours of outage per year is only an indication of how much operation time the firm would loss if it did not have backup; it takes time to restart equipment. Previous work has suggested that it takes from 1 hour to 4 hours to restart after an outage (29, 3). Therefore, an average firm would buy a generator to protect against 3.3 to 6.9 hours per year. In Table 6, we show the implicit value of reliability for the three backup generator options in $/kwh and $/kw year assuming the minimum 3.3 hours per year of outage. These values are at the very high end of the VOLL literature values for commercial customers and are more than double the average VOLL. These figures suggest that either the owners of these generators are acting irrationally or that the literature VOLLs are far too low at least for these owners. It is, however, hard to believe that all 1.3 GW of backup generators were installed by irrational owners. In Figure 2, we show the sensitivity of the implicit reliability value for a diesel ICE to the number of hours of outage per year. As expected, as the number of hours of outage increase, the value of reliability is reduced. Table 6: Implicit value of reliability for backup generators Backup generator $/kwh ($/MWh) $/kw year ($/MW year) Diesel ICE 25.9 (25,9) 85.3 (85,3) Natural gas ICE 27.4 (27,4) 9.3 (9,3) Natural gas microturbine (28,95) 95.4 (95,4) The slightly lower implicit value of reliability helps explain why diesel fuelled generators are the most popular form of emergency backup. Presently, most of the installed generators are diesel fuelled. The diesel generators also have characteristics that make them highly suited for the backup application: a very short start up time, high reliability and efficiency, and have low maintenance costs. By contrast, natural gas engines have lower efficiencies and have longer start up times. Additionally, depending on the reason for the outage, the natural gas fuel system may be shut off. Fuel cells are an alternative to combustion based systems, but are very expensive. Other options like photovoltaic cells and wind turbines cannot be dispatched on demand, and therefore, are not suitable for backup. Also, we do not consider 8

9 uninterruptible power systems (UPS) such as batteries in this analysis. Many backup systems include UPS to protect against voltage fluctuations and to avoid interruption as the engines ramp up to full load. These systems, however, are designed to last no more than an hour and do not provide long term reliability. Figure 2: Implicit Reliability Cost for a Diesel ICE as a Function of Hours of Outage (in $/kwh) 35 3 Implicit Cost of Reliability ($/kwh) Hours of Outage 4.2 Economics of using backup generators for peak electricity demand and for installed capacity In Figure 3, we show the marginal and average (levelized) cost of operating the different backup configurations from Table 2. The levelized cost represents a technology s average costs per kwh over its life span. We assume 2 hours a year of peak power operation (31) and a discount rate of 1%. We show the average cost in two cases: 1) assuming that the capital cost of the diesel ICE is covered by the reliability application, and only the incremental cost above the diesel ICE is not covered for the natural gas options; and 2) assuming that the entire capital cost is covered in the levelized cost. A well maintained diesel generator has a lifetime on the order of thousands of hours. Adding 2 hours per year of operation will not shorten its useful life. In addition, these units are discarded long before the units is worn out (i.e., the life span of the unit is determined by age not by the hours of operation). Finally, using the engine for peak power could improve the probability that the engine will turn on in the case of an outage. There are two other costs that we show in the levelized cost that are not captured in the marginal costs of operation. First, most emergency generators will require a retrofit on the electrical interconnections to operate in parallel with the grid. An average cost estimate for these interconnections is approximately $2/kW, although the actual cost depends on the size of the engine, the configuration of the electrical network and the utility requirements (32). Secondly, we show a diesel retrofitted with a diesel particulate filter (DPF) to prevent severely harming human health. Over the past decade, the Environmental Protection Agency (EPA) and state environmental agencies have promulgated increasingly stringent emission standards for off-road diesel generators, known as Tier I through IV standards. Generally, emergency and standby generators are not subject to these standards, generating only when the grid fails. In New York, an emergency generator is permitted to operate up to 5 hours per year with emission controls. If these generators were to operate concurrently with the grid, the regulations would most likely be enforced. In the ICAP market, a generator has the incentive to bid the cost per kw of keeping the plant on standby rather than shutting down when the LBMPs do not cover their marginal and fixed costs of being available. Since a backup generator must always be ready to operate, the opportunity cost of being available is zero. 9

10 75 Figure 3: The Marginal and Average Cost of Generators (in /kwh) Diesel ICE Diesel ICE w DPF Natural Gas ICE Natural Gas MT Price (in cents/kwh) 5 25 Marginal Costs Average Cost w Reliability Total Average Costs 4.3 Profits from using backup generators to sell peak power Since 8% of the installed capacity is diesel generators, we will restrict the remainder of our analysis to diesel generators. In order to make a profit in the electricity market, the market clearing price (MCP) must be higher than marginal cost of using the generator (i.e., MC of an uncontrolled diesel = $/MWh or MC for a controlled diesel = $/MWh). In Tables 7 1, we present the number of hours of profitable operation for the controlled and uncontrolled diesel generator in the DAM and RT markets as well as the profits for the top 2 hours and for up to the top 5 hours. Table 7: Profits for an uncontrolled diesel in New York City (in $/kw year) DAM 25 RT 25 DAM 26 RT 26 # of h above MC All Profits 16,48 62,68 7,95 34,56 Profits (5 h) 16,4 59,73 7,95 34,56 Profits (2 h) 12,36 46,59 7,95 34,25 Table 8: Profits for a controlled diesel in New York City (in $/kw year) DAM 25 RT 25 DAM 26 RT 26 # of h above MC All Profits 7,55 47,54 5,93 29,52 Profits (5 h) 7,55 47,54 5,93 29,52 Profits (2 h) 7,48 41,71 5,93 29,52 Table 9: Profits for an uncontrolled diesel in Long Island (in $/kw year) DAM 25 RT 25 DAM 26 RT 26 # of h above MC All Profits 2,65 98,5 3,12 78,4 Profits (5 h) 19,2 88,28 3,12 78,4 Profits (2 h) 12,9 62,75 27,72 66,15 1

11 Table 1: Profits for a controlled diesel in Long Island (in $/kw year) DAM 25 RT 25 DAM 26 RT 26 # of h above MC All Profits 8,23 78,49 23,21 67,53 Profits (5 h) 8,23 76,8 23,21 67,53 Profits (2 h) 8,2 57,87 22,84 61,27 In Tables 11 and 12, we examine the profits for a generator in the ICAP market. For both an uncontrolled and controlled diesel engine, the opportunity cost of being prepared to turn on is $/MWh since the backup generator must be ready operate all times. An uncontrolled generator, however, cannot operate all year long in its present configuration and is limited to 5 hours of operation a year. To maximize profits, this generator would operate in the summer only. A diesel generator retrofitted with emission controls could potentially bid into the capacity market all year long. Finally, we assume that the engines will be downrated by 95% of their nameplate capacity to generate an unforced capacity (UCAP). Table 11: ICAP profits in New York City (in $/kw year) Uncontrolled diesel Controlled diesel Table 12: ICAP profits in Long Island (in $/kw year) Uncontrolled diesel Controlled diesel To generate peak power and act as installed capacity, the generator must be retrofit with the interconnections to operate in parallel with the grid at 2 $/kw year. In addition, it is possible, however, that a generator without emission controls would not be allowed to operate at all in the capacity market. The DPF retrofit costs 4 $/kw or 4 $/kw year at a 1 % discount rate. In Tables 13 and 14, we present the total profits available in the New York City and Long Island minus the retrofits and calculate the change in the implicit value of reliability. We show the profits as the average of the DAM and RT markets. On average, an uncontrolled diesel generator can make sufficient profit to reduce the implied cost of reliability from more than two times the average to below the average VOLL for commercial and industrial facilities. The VOLL for the uncontrolled generator, however, is still double the VOLL for residential customers. However, a diesel generator which has been retrofitted with a DPF can operate for more than 5 hours per year. The extra profits from the capacity market reduce the implied VOLL to $/kwh in New York City and 1.67 $/kwh in Long Island. Table 13: Average profits and reduced implicit reservation price in New York City Generator Peak Electricity ($/kw yr) ICAP ($/kw- yr) Total ($/kw-yr) Profits w Retrofits ($/kw yr) % of Cost of Reliability Reservation Price ($/kwh) Diesel ICE % 3.19 Diesel ICE w DPF % < Generator Table 14: Average profits and reduced implicit reservation price in Long Island Peak ICAP Total Profits w % of Cost of Electricity ($/kw- yr) ($/kw-yr) Retrofits Reliability ($/kw yr) ($/kw yr) Reservation Price ($/kwh) Diesel ICE % 5.9 Diesel ICE w DPF % Reductions in Price and Increases in Backup Power Capacity As the cost of reliability decreases, we should observe an increase in backup capacity. At the reservations prices that we calculate, we estimate that many more customers would be willing to pay to protect themselves from an outage. Determining the increase in capacity that would result from this decrease requires estimating the demand for reliability as 11

12 a function of price (e.g. an elasticity of demand for reliability). We know of no estimate of this demand, but there have been many studies of the demand for electricity as a function price. While the two concepts are different, the latter can give some insights into the former. Literature values for the elasticity of demand is generally between.1 and.4 (33). This implies that a 1% increase in price would results in a 1 4% reduction in electricity usage. Using these values as a rough guide of the demand for reliability, the 77% to greater than 1% decrease in the implicit cost of reliability should increase backup capacity by 8% in LONGLI for uncontrolled diesel generators to almost 5% for controlled diesel engines in NYC. With an installed backup capacity of 5 MW in LONGLI, we estimate an increase of 39 MW 154 MW of uncontrolled capacity or 46.8 MW to 187 MW of controlled capacity. For NYC, we estimate MW of uncontrolled capacity and MW of controlled capacity. On average, we assume 115 MW of new capacity in LONGLI and 4 MW of new capacity in NYC. We will use only controlled capacity since we assume that controls will be required to operate in the markets. Bring these additional generators into the market will increase the reliability in the system as more customers will be protected in the case of blackout. At the same time, since these individuals would be selling into the market during periods where there are presently reserve shortages, there would also be an increase in system level reliability. 4.5 The Simultaneity Problem Presently, the high prices observed in the NYC and LONGLI markets arise when old peaking units with high heat rates are brought on line to meet high demand. As the existing and additional backup capacity is introduced into the market, the backup generators may become the marginal unit. In this limiting situation, there would be no economic profits available for these generators. Hence, there would be no motivation for the backup generators to enter into the electricity market or to invest in new backup capacity Electricity Markets To evaluate this simultaneity problem in the electricity market, we construct marginal cost curves for the NYC and LONGLI zones. In competitive markets like the NYISO, units are run in merit order economic dispatch. This means that the marginal costs of the generation units are sorted from lowest to highest. The lowest cost units are dispatched until the demand is met. In some parts of the grid, the least expensive plant cannot be dispatched to the location of demand due to insufficient transmission capacity. A more expensive generator closer to the load must be used. This is referred to as transmission constrained economic dispatch and leads to locational based marginal prices (LBMPs). Based on the theoretical SRMC curves for New York City, there appears to be little room for arbitrage at the peak loads. In NYC, the curve is especially steep with only 143 MW of generation operating with a marginal cost higher than a diesel generator with a DPF. We do not expect the profits to remain for NYC and no new generation would enter the market. In Long Island, there is 64 MW of capacity with a high marginal cost, specifically distillate oil fuelled turbines. As a result, there is the potential that all 615 MW of new capacity could be dispatched and not become the marginal plant. We recognize, however, that the SRMCs do not capture all the system dynamics, and specifically, cannot capture the features of peak load days. In Appendix B, we show the relationship between load and price for the two zones in 25 and 26. There is significant scatter in the price-load relationship, especially for real-time prices. While we have not yet reached this point in the analysis, we plan to verify the above results by isolating the days with peak load and investigate how many MW of generation could be added before the marginal cost is that of diesel with a DPF. Preliminary results suggest that the addition of the existing population of backup generators into NYC reduces the arbitrage opportunities to zero. In Long Island, we find some evidence that adding 615 MW might still leave opportunities for arbitrage. This analysis, however, did not include the new 66 MW Neptune PJM Line. With this additional capacity, we expect the arbitrage opportunities to decrease significantly. Adding the backup generators to the NYC market, however, would save customers a lot of money by reducing the peak electricity prices. As a first estimate of the benefits, we assume that if the day ahead market (DAM) price is higher than the marginal price of the diesel, the marginal cost is now the marginal cost of a diesel with a DPF (e.g $/MWh). Customers in NYC would save $67 million in 25 and $65 million in 26. Similarly, if we assume that the backup generators are the marginal unit in LONGLI, customers would save $36 million in 25 and $12 million in

13 1 75 Figure 4: Marginal Cost Curve for NYC with and without backup generation 1.7 GW 1.3 GW BASE Price (in $/MWh) Figure 5: Marginal Cost Curve for LONGLI with and without backup generation MW 5 MW BASE Price (in $/MWh) Capacity Market A major source of profit for the generators is the capacity market. To evaluate whether the generator will swamp the market, we combine the capacity market clearing price with the scheduled demand curve presented in Figure 1. In NYC, we find that there is room for 1,24 MW in the summer of 25 and 1,31 MW in the summer of 26 before the clearing price would drop to zero. This value is approximately the same as allowing all the already installed backup generator capacity into the market. In the Long Island market, we estimate that 512 MW could enter in 25 and 451 MW could enter in 26 before there is no opportunity for arbitrage. Again, this is approximately the same as the 13

14 installed backup capacity in Long Island. Although the individual owners cannot make money by bidding into the capacity market and no new backup capacity would be added by reducing the implicit cost of reliability, there is a social benefit to adding these generators to the capacity market. Reducing the clearing price to zero would save, approximately $1 billion dollars in New York City and approximately $5 million in Long Island. One issue that may limit the ability of backup generators to participate in ICAP markets is that it must be capable of providing 4 hours or more of capacity. Depending on the size of the generator, the New York City fire code may limit operation. Presently, no more than 275 gallons of fuel can be kept in a day tank per floor. For example, a 5 kw generator requires approximately US gallons per hour. For four hours of operation, gallons of diesel fuel needs to be available which falls within the regulations. While this is within the fire code, the fuel required for a 1 MW generator would exceed the fuel limit. To allow these generators to operate for extended periods of times for reliability, a more complicated arrangement is required. Properly constructed tanks are stored underground, and the fuel is pumped to the day tanks. There is no limit on how much fuel can be stored below grade, except that no single tank can exceed 2, gallons. Diesel fuel can be stored for up to 18 months. Assuming that the pumping does not dramatically change the economics, most backup generators could be classified as an energy-limited resource (ELR) 2 and would qualify to participate in the capacity markets. 4.6 Value of backup generation in a regulated market Using real market data, we have shown that there are significant social savings if properly controlled backup generators are allowed to operate for profit in real power and capacity markets. The majority of this savings arises from the ability to ascribe a portion of the costs of these generators to the reliability application. Although there are no additional profits (with the potential exception of some real power profits in Lomg Island), the existing backup capacity will reduce prices by operating. By contrast in a regulated electricity market, the utility faces a different set of trade-offs and incentives. A firm that has installed a diesel generator has already accounted for the capital costs as the value of reliability. These firms could operate at an average cost of less than.3 $/kwh even after the retrofit with a diesel particulate filter (DPF). This is significantly cheaper than a new natural gas peaker. For every kwh provided by the generator rather than a peaking plant, the system saves approximately.2 $/kwh. If the firm valued reliability at $/MWh, however, it would need to recoup all the capital costs at an average levelized cost of.71 $/kwh. This is significantly more expensive than a peaking gas turbine at approximately.5 $/kwh, but is cheaper than a lower end value of lost load (VOLL) of 1 $/kwh. Allowing these private owners to recover their average costs would clearly increase the amount of backup capacity in the system as it has the effect of reducing the reliability value to zero. In general, however, it is unclear that a regulated utility would choose the diesel ICE over the peaking plant as it depends largely on whether it can incite firms with backup capacity to generate without lowering the implicit value for reliability. 5. Conclusions, implementation issues and recommendations The US electricity grid provides electricity with a reliability approaching 99.99%. In past, some have argued based on the value of lost load (VOLL) that the electricity grid is too reliable (9). Using the actual cost of purchasing and operating backup generators for providing electricity during the approximately 3 hours of outage per year, we calculate an implicit cost of reliability of 26 $/kwh or 85.9 $/kw-year for customers who have backup generators. This value is significantly higher than literature VOLLs. With an estimated 1.3 GW of backup generation in New York City, approximately 1% of the load has a VOLL much greater than the values in the literature. In New York City and Long Island, it is difficult to site new generation and transmission which has led to high zonal prices and reserve shortages. Since these generators operate only when the grid fails, they represent a large source of underutilized generation capacity which could be used to alleviate these shortages. These generators would be especially valuable during periods of peak electricity demand of approximately 2 hours a year. Bringing these generators into the market, however, cannot be achieved by market forces. Using price data from 25 and 26 from the NYISO, we 2 An ELR is a resource that is unable to operate continuously on a daily basis, but is able to operate for at least four consecutive hours each day. Examples include a pumped hydroelectric plant or battery that must charge, and a generator with environmental restrictions. 14

Deregulating Electricity Markets: Naïve Hopes vs. Market Reality

Deregulating Electricity Markets: Naïve Hopes vs. Market Reality Deregulating Electricity Markets: Naïve Hopes vs. Market Reality Lester Lave, Seth Blumsack, Jay Apt, & Sarosh Talukdar Electricity Center Carnegie Mellon University February 3, 2004 1 The U.S. Electricity

More information

CAPACITY LIMITED RESOURCES (CLR) / ENERGY LIMITED RESOURCES (ELR)

CAPACITY LIMITED RESOURCES (CLR) / ENERGY LIMITED RESOURCES (ELR) CAPACITY LIMITED RESOURCES (CLR) / ENERGY LIMITED RESOURCES (ELR) 1 INTRODUCTION A new bidding mechanism is available for qualified generators which allows them to offer generation in the New York market

More information

Capacity Market Rules for Energy Storage Resources

Capacity Market Rules for Energy Storage Resources Capacity Market Rules for Energy Storage Resources Zachary T Smith Manager, Capacity Market Design ICAPWG August 23 rd, 2018 Agenda Background Energy Storage Resource (ESR) overview Capacity Market Rules

More information

Grid Services From Plug-In Hybrid Electric Vehicles: A Key To Economic Viability?

Grid Services From Plug-In Hybrid Electric Vehicles: A Key To Economic Viability? Grid Services From Plug-In Hybrid Electric Vehicles: A Key To Economic Viability? Paul Denholm (National Renewable Energy Laboratory; Golden, Colorado, USA); paul_denholm@nrel.gov; Steven E. Letendre (Green

More information

IMPACT OF MARKET RULES ON ENERGY STORAGE ECONOMICS

IMPACT OF MARKET RULES ON ENERGY STORAGE ECONOMICS IMPACT OF MARKET RULES ON ENERGY STORAGE ECONOMICS [Eric Cutter, Energy and Environmental Economics, 415-391-5100, eric@ethree.com] [Lakshmi Alagappan, Energy and Environmental Economics, 415-391-5100,

More information

Proposal Concerning Modifications to LIPA s Tariff for Electric Service

Proposal Concerning Modifications to LIPA s Tariff for Electric Service Proposal Concerning Modifications to LIPA s Tariff for Electric Service Requested Action: LIPA Staff proposes revisions to the Tariff for Electric Service under Service Classification No. 11 ( SC-11 ),

More information

Ancillary Services. Horace Horton Senior Market Trainer, Market Training, NYISO. New York Market Orientation Course (NYMOC)

Ancillary Services. Horace Horton Senior Market Trainer, Market Training, NYISO. New York Market Orientation Course (NYMOC) Ancillary Services Horace Horton Senior Market Trainer, Market Training, NYISO New York Market Orientation Course (NYMOC) June 5-8, 2018 Rensselaer, NY 12144 1 Ancillary Services SESSION OBJECTIVES: attendees

More information

MMP Investigation of Arthur Kill 2 and 3

MMP Investigation of Arthur Kill 2 and 3 MMP Investigation of Arthur Kill 2 and 3 Requestor Consolidated Edison Company of New York, Inc. Facility Name Arthur Kill 2 and 3 Date of Request January 27, 2003 Type of Facility NG Generator Topic of

More information

Overview of ISO New England and the New England Wholesale Power Markets

Overview of ISO New England and the New England Wholesale Power Markets Overview of ISO New England and the New England Wholesale Power Markets Boston Chapter of IEEE PES Technical Meeting June 15, 2010 Stephen J. Rourke Vice President, System Planning About ISO New England

More information

Unitil Energy Demand Response Demonstration Project Proposal October 12, 2016

Unitil Energy Demand Response Demonstration Project Proposal October 12, 2016 Unitil Energy Demand Response Demonstration Project Proposal October 12, 2016 Fitchburg Gas and Electric Light Company d/b/a Unitil ( Unitil or the Company ) indicated in the 2016-2018 Energy Efficiency

More information

Fuel Charges in Reference Levels

Fuel Charges in Reference Levels Fuel Charges in Reference Levels Shaun Johnson Director, MMA New York Independent System Operator Market Issues Working Group December 2, 2014 Rensselaer, NY 2014 New York Independent System Operator,

More information

Information Packet Kissimmee Utility Authority Customer-Owned Renewable Generation Interconnection And Net Metering Program

Information Packet Kissimmee Utility Authority Customer-Owned Renewable Generation Interconnection And Net Metering Program Information Packet Kissimmee Utility Authority Customer-Owned Renewable Generation Interconnection And Net Metering Program As part of our commitment to support renewable energy, Kissimmee Utility Authority

More information

JEA Distributed Generation Policy Effective April 1, 2018

JEA Distributed Generation Policy Effective April 1, 2018 Summary This JEA Distributed Generation Policy is intended to facilitate generation from customer-owned renewable and non-renewable energy generation systems interconnecting to the JEA electric grid. The

More information

Effects of Smart Grid Technology on the Bulk Power System

Effects of Smart Grid Technology on the Bulk Power System Effects of Smart Grid Technology on the Bulk Power System Rana Mukerji Senior Vice President Market Structures New York Independent System Operator Union College 2013 Environmental Science, Policy & Engineering

More information

The retail price a household pays for the last unit of grid-supplied electricity consumed is an

The retail price a household pays for the last unit of grid-supplied electricity consumed is an N O V E M B E R 2 0 1 7 Retail Pricing to Support Cost-Effective Distributed Generation Investment by Frank A. Wolak, Director, Program on Energy and Sustainable Development; Professor, Department of Economics,

More information

Docket No EI Date: May 22, 2014

Docket No EI Date: May 22, 2014 Docket No. 140032-EI Big Bend Units 1 through 4 are pulverized coal steam units that currently use distillate oil 2 for start-ups and for flame stabilization. The Company seeks to use natural gas in place

More information

Participation of Beacon Power s Flywheel Energy Storage Technology in NYISO s Regulation Service Market

Participation of Beacon Power s Flywheel Energy Storage Technology in NYISO s Regulation Service Market Beacon Power Corporation Participation of Beacon Power s Flywheel Energy Storage Technology in NYISO s Regulation Service Market Prepared for: New York Business Issues Committee May 21, 2008 Safe Harbor

More information

Why Japan remains skeptical of restructuring Study of Electricity Market Bidding Characteristics for Modeling Generation Capacity Growth

Why Japan remains skeptical of restructuring Study of Electricity Market Bidding Characteristics for Modeling Generation Capacity Growth Why Japan remains skeptical of restructuring Study of Electricity Market Bidding Characteristics for Modeling Generation Capacity Growth Satoru Ihara Retired (urotas@ieee.org) Tetsuo Sasaki, Toshihisa

More information

Understanding Impacts of Distributed Solar Generation on Cost Recovery and Rates IAMU Annual Energy Conference Preconference Seminar

Understanding Impacts of Distributed Solar Generation on Cost Recovery and Rates IAMU Annual Energy Conference Preconference Seminar Understanding Impacts of Distributed Solar Generation IAMU Annual Energy Conference Preconference Seminar David A. Berg, PE Principal November 3, 2015 Your Presenter David Berg, PE Principal Dave Berg

More information

EITF Issue 15-A, Application of the Normal Purchases and Normal Sales Scope Exception to Certain Electricity Contracts within Nodal Energy Markets

EITF Issue 15-A, Application of the Normal Purchases and Normal Sales Scope Exception to Certain Electricity Contracts within Nodal Energy Markets EITF Issue 15-A, Application of the Normal Purchases and Normal Sales Scope Exception to Certain Electricity Contracts within Nodal Energy Markets Education Session January 22, 2014 1 Overview and agenda

More information

February 10, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

February 10, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 California Independent System Operator Corporation February 10, 2016 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California

More information

Demystifying Your Utility Bill

Demystifying Your Utility Bill New York City Chapter Hospitality Financial and Technology Professionals DEIRDRE LORD PH: (917) 750-3771 EMAIL: DLORD@THEMWH.COM Demystifying Your Utility Bill HFTP NYC CHAPTER MONTHLY MEETING JUNE 20,

More information

Net Metering Policy Framework. July 2015

Net Metering Policy Framework. July 2015 Net Metering Policy Framework July 2015 Table of Contents 1.0 BACKGROUND... 2 2.0 POLICY OBJECTIVE... 2 3.1 Eligibility... 3 3.1.1 Renewable Generation... 3 3.1.2 Customer Class... 3 3.1.3 Size of Generation...

More information

2008 Capacity/Energy Planning

2008 Capacity/Energy Planning DOCKET DE 09-091 EXHIBIT - MDC-2 2008 Capacity/Energy Planning Background PSNH retains load serving responsibility for customers who have not selected a competitive supplier. PSNH's monthly peak load for

More information

Grid Impacts of Variable Generation at High Penetration Levels

Grid Impacts of Variable Generation at High Penetration Levels Grid Impacts of Variable Generation at High Penetration Levels Dr. Lawrence Jones Vice President Regulatory Affairs, Policy & Industry Relations Alstom Grid, North America ESMAP Training Program The World

More information

Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any

Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any Draft Version 1 Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any kind, including without limitation,

More information

Consumer Guidelines for Electric Power Generator Installation and Interconnection

Consumer Guidelines for Electric Power Generator Installation and Interconnection Consumer Guidelines for Electric Power Generator Installation and Interconnection Habersham EMC seeks to provide its members and patrons with the best electric service possible, and at the lowest cost

More information

Net Metering in Missouri

Net Metering in Missouri Net Metering in Missouri Make A Good Policy Great (AGAIN) Executive Summary More and more Americans every year are able to produce their own electricity. As the cost of solar continues to plummet, homeowners

More information

2018 Load & Capacity Data Report

2018 Load & Capacity Data Report Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any kind, including without limitation, accuracy, completeness

More information

Solar-Wind Specific Request for Proposals

Solar-Wind Specific Request for Proposals Program Description Solar-Wind Specific Request for Proposals Power Production from Green Resources in North Carolina 04/19/2006 NC GreenPower (NCGP) is a statewide program designed to improve the quality

More information

OSIsoft Users Conference

OSIsoft Users Conference OSIsoft Users Conference Industrial Energy Strategies Workshop 2011 Turning Information Insight into Action A Case Study of Implementing a Non-residential Smart Metering System 1 Smart Grid Popular Topics

More information

Energy Storage Integration

Energy Storage Integration Energy Storage Integration Market Concepts James Pigeon Senior Market Design Specialist, Distributed Resources Integration MIWG September 29, 2016 Krey Corporate Center, Rensselaer, NY 2000-2016 New York

More information

ENERGY MANAGEMENT 4/22/2014. What are your approximate yearly energy costs? (Electricity, natural gas, etc.)

ENERGY MANAGEMENT 4/22/2014. What are your approximate yearly energy costs? (Electricity, natural gas, etc.) MICHIGAN CHAMBER OF COMMERCE ENERGY MANAGEMENT Webinar Electricity - Natural Gas April 23, 2014 10:00 A.M. - 11:00 A.M. EDT Presented by John M. Studebaker, Ph.D. www.studebakerenergy.net JStudebaker 4/23/14

More information

Vermont Public Power Supply Authority 2018 Tier 3 Annual Plan

Vermont Public Power Supply Authority 2018 Tier 3 Annual Plan Vermont Public Power Supply Authority 2018 Tier 3 Annual Plan Vermont s Renewable Energy Standard ( RES ) enacted through Act 56 in 2015 requires electric distribution utilities to generate fossil fuel

More information

Aging of the light vehicle fleet May 2011

Aging of the light vehicle fleet May 2011 Aging of the light vehicle fleet May 211 1 The Scope At an average age of 12.7 years in 21, New Zealand has one of the oldest light vehicle fleets in the developed world. This report looks at some of the

More information

Decision on Merced Irrigation District Transition Agreement

Decision on Merced Irrigation District Transition Agreement California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson, Vice President Policy & Client Services Date: March 13, 2013 Re: Decision on Merced Irrigation

More information

Contents. Solar Select TM Frequently Asked Questions

Contents. Solar Select TM Frequently Asked Questions Solar Select TM Frequently Asked Questions Contents Program Overview and How Solar Select Works... 1 Participation Requirements... 3 Cost and Payment... 4 Solar Production... 5 Development, Equipment,

More information

Demand Response - An End-to-End Approach from Markets to Consumers

Demand Response - An End-to-End Approach from Markets to Consumers Demand Response - An End-to-End Approach from Markets to Consumers Rana Mukerji Senior Vice President Market Structures New York Independent System Operator EPRI PDU Sector Council Meeting Boston, MA September

More information

Power Purchase Agreement for Commercial PV Systems

Power Purchase Agreement for Commercial PV Systems Power Purchase Agreement for Commercial PV Systems Dr. Özlem Döğerlioğlu IŞIKSUNGUR Managing Partner ozlem@dogerlihukuk.com WHO WE ARE? Döğerlioğlu Law Firm. CONTENT OF THE PRESENTATION Solar Energy Generation

More information

KANSAS CITY POWER AND LIGHT COMPANY P.S.C. MO. No. 7 Fourth Revised Sheet No. 39 Canceling P.S.C. MO. No. 7 Third Revised Sheet No.

KANSAS CITY POWER AND LIGHT COMPANY P.S.C. MO. No. 7 Fourth Revised Sheet No. 39 Canceling P.S.C. MO. No. 7 Third Revised Sheet No. P.S.C. MO. No. 7 Fourth Revised Sheet No. 39 Canceling P.S.C. MO. No. 7 Third Revised Sheet No. 39 PURPOSE: The purpose of the Solar Subscription Pilot Rider (Program) is to provide a limited number of

More information

24. SOLAR INCENTIVE PROGRAM II

24. SOLAR INCENTIVE PROGRAM II 24. SOLAR INCENTIVE PROGRAM II A. General California Senate Bill 1 requires publicly owned utilities that sell electricity at the retail level, to adopt, implement, and fund a solar incentive program for

More information

Solar Project Development in Regulated Markets. Smart and Sustainable Campuses Conference 2017

Solar Project Development in Regulated Markets. Smart and Sustainable Campuses Conference 2017 Solar Project Development in Regulated Markets Smart and Sustainable Campuses Conference 2017 Session Outline Overview of renewable energy procurement options Market structure and policy impacts on solar

More information

A Guide to the medium General Service. BC Hydro Last Updated: February 24, 2012

A Guide to the medium General Service. BC Hydro Last Updated: February 24, 2012 A Guide to the medium General Service Conservation Rate BC Hydro Last Updated: February 24, 2012 Executive summary The way Medium General Service (MGS) accounts pay for electricity is changing. MGS is

More information

All of Texas Has Excellent Solar Resources. United States Solar Installed (as of mid 2013): 10 GW Germany Solar Installed (end of 2013): 35.

All of Texas Has Excellent Solar Resources. United States Solar Installed (as of mid 2013): 10 GW Germany Solar Installed (end of 2013): 35. All of Texas Has Excellent Solar Resources United States Solar Installed (as of mid 2013): 10 GW Germany Solar Installed (end of 2013): 35.962 GW Benefits of Solar Investing in Solar Creates Good Local

More information

Energy Management Through Peak Shaving and Demand Response: New Opportunities for Energy Savings at Manufacturing and Distribution Facilities

Energy Management Through Peak Shaving and Demand Response: New Opportunities for Energy Savings at Manufacturing and Distribution Facilities Energy Management Through Peak Shaving and Demand Response: New Opportunities for Energy Savings at Manufacturing and Distribution Facilities By: Nasser Kutkut, PhD, DBA Advanced Charging Technologies

More information

Wholesale Electric Market Economics

Wholesale Electric Market Economics Wholesale Electric Market Economics Sponsored by the Institute for Policy Integrity 15 June 2011 Presented by Doug Hurley and Paul Peterson New England Markets and Relative Size All other ancillary services

More information

ANNUAL ELECTRIC POWER INDUSTRY REPORT

ANNUAL ELECTRIC POWER INDUSTRY REPORT SCHEDULE 1. IDENTIFICATION SURVEY CONTACTS: Persons to contact with question about this form RESPONSE DUE DATE: Please submit by April 30th following the close of calendar year Contact Title: Jocelyn Gwynn

More information

Non-BM Balancing Services Volumes and Expenditure

Non-BM Balancing Services Volumes and Expenditure Non-BM Balancing Services Volumes and Expenditure Contents 1 Introduction... 2 1.1 What are Balancing Services or Ancillary Services?... 2 1.2 What are Balancing Mechanism (BM) and Non-Balancing Mechanism

More information

Genbright LLC. AEE Technical Round Table 11/15/2017

Genbright LLC. AEE Technical Round Table 11/15/2017 Genbright LLC AEE Technical Round Table 11/15/2017 About Genbright Founded in 2013, Genbright was created to develop and monetize distributed energy technologies across the power industry including distributed

More information

a) The 2011 Net Metering and Buyback Tariff for Emission Free, Renewable Distributed Generation Serving Customer Load

a) The 2011 Net Metering and Buyback Tariff for Emission Free, Renewable Distributed Generation Serving Customer Load Memorandum To: Municipal Light Advisory Board; Municipal Light Board; file From: Belmont Light Staff Date: June 19, 2014 Re: Solar PV Distributed Generation 1. Background & Summary Belmont Light supports

More information

Frequently Asked Questions New Tagging Requirements

Frequently Asked Questions New Tagging Requirements Frequently Asked Questions New Tagging Requirements Q: Are there new E-tagging requirements related to the new fifteen minute market FERC Order No. 764 fifteen minute scheduling implemented on May 1, 2014?

More information

2016 Load & Capacity Data Report

2016 Load & Capacity Data Report Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any kind, including without limitation, accuracy, completeness

More information

SCHEDULE 62 COGENERATION AND SMALL POWER PRODUCTION SCHEDULE - IDAHO

SCHEDULE 62 COGENERATION AND SMALL POWER PRODUCTION SCHEDULE - IDAHO First Revision Sheet 62 62 I.P.U.C. No. 28 Original Sheet 62 SCHEDULE 62 COGENERATION AND SMALL POWER PRODUCTION SCHEDULE - IDAHO AVAILABLE: In all the electric territory served by the Company in the State

More information

White River Electric Association, Inc. Net Metering Information & Service Requirements

White River Electric Association, Inc. Net Metering Information & Service Requirements White River Electric Association, Inc. Net Metering Information & Service Requirements What is Net Metering? Net Metering is an electric policy and service for consumers who own and utilize renewable energy

More information

Net Metering in Illinois. Eric P. Schlaf Senior Economic Analyst Illinois Commerce Commission January 31, 2014

Net Metering in Illinois. Eric P. Schlaf Senior Economic Analyst Illinois Commerce Commission January 31, 2014 Net Metering in Illinois Eric P. Schlaf Senior Economic Analyst Illinois Commerce Commission January 31, 2014 Topics What is Net Metering Benefits of Net Metering Net Metering in US Net Metering in Illinois

More information

Reforming the TAC and Retail Transmission Rates. Robert Levin California Public Utilities Commission Energy Division August 29, 2017

Reforming the TAC and Retail Transmission Rates. Robert Levin California Public Utilities Commission Energy Division August 29, 2017 Reforming the TAC and Retail Transmission Rates. Robert Levin California Public Utilities Commission Energy Division August 29, 2017 1 CPUC Staff Rate Design Proposals Restructure the High-Voltage TAC

More information

Implications of Alberta s Evolving Electricity Market for Solar

Implications of Alberta s Evolving Electricity Market for Solar Implications of Alberta s Evolving Electricity Market for Solar Matt Ayres CEO, Market Surveillance Administrator matt.ayres@albertamsa.ca What does the Market Surveillance Administrator do? Investigation

More information

Robert L. Mitchell CEO and Co-Founder Atlantic Wind Connection

Robert L. Mitchell CEO and Co-Founder Atlantic Wind Connection Robert L. Mitchell CEO and Co-Founder Atlantic Wind Connection New Jersey Energy Link Electric superhighway connecting northern, central and southern New Jersey Delivers 3,000 megawatts of electricity

More information

GRID CONSTRAINT: OPTIONS FOR PROJECT DEVELOPMENT

GRID CONSTRAINT: OPTIONS FOR PROJECT DEVELOPMENT GRID CONSTRAINT: OPTIONS FOR PROJECT DEVELOPMENT 2 What s the Problem? Constrained grid is an issue that impacts many new renewables developments. A quick look at the distribution heat maps published by

More information

October 17, Please contact the undersigned directly with any questions or concerns regarding the foregoing.

October 17, Please contact the undersigned directly with any questions or concerns regarding the foregoing. California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 October 17, 2017 Re: California

More information

NYISO Tariffs. New York Independent System Operator, Inc. Document Generated On: 2/27/2013

NYISO Tariffs. New York Independent System Operator, Inc. Document Generated On: 2/27/2013 NYISO Tariffs New York Independent System Operator, Inc. NYISO Tariffs Document Generated On: 2/27/2013 Contents 15 ISO Market Administration and Control Area Service Tariff Rate Schedules... 8 15.1 Rate

More information

SERVICE CLASSIFICATION "CEF" COMMUNITY ENERGY FACILITY

SERVICE CLASSIFICATION CEF COMMUNITY ENERGY FACILITY P.S.C. Del. No. 8 - Electric Original Leaf No. 95a SERVICE CLASSIFICATION "CEF" COMMUNITY ENERGY FACILITY A Community Energy Facility (CEF) consists of one or more generators located in Company s service

More information

Rate Schedules. Effective 1/1/2019

Rate Schedules. Effective 1/1/2019 Rate Schedules 2019 Effective 1/1/2019 SUMMARY OF RATE SCHEDULES REVISIONS FOR RATES EFFECTIVE JANUARY 1, 2019 (1) Rate component changes for Residential and Heating Service rate schedules. (2) General

More information

Household Renewable Energy

Household Renewable Energy Household Renewable Energy Commissioner Richard Campbell May 23, 2012 Renewable Energy Promotion Methods for Households Net Metering Interconnection Rules Subsidies Tax Credits 2 Net Metering Net metering

More information

Module 7 : Power System Structures. Lecture 33 : Structure of a Deregulated Industry. Objectives. Overview of A Deregulated Industry

Module 7 : Power System Structures. Lecture 33 : Structure of a Deregulated Industry. Objectives. Overview of A Deregulated Industry Module 7 : Power System Structures Lecture 33 : Structure of a Deregulated Industry Objectives In this lecture you will learn the following Structure of a deregulated industry. Different entities in a

More information

ENERGY STRATEGY FOR YUKON. Independent Power Production Policy

ENERGY STRATEGY FOR YUKON. Independent Power Production Policy ENERGY STRATEGY FOR YUKON Independent Power Production Policy May 20, 2014 Page 2 of 11 BACKGROUND The Government of Yukon released the Energy Strategy for Yukon in January 2009. The strategy sets out

More information

ANNUAL ELECTRIC POWER INDUSTRY REPORT

ANNUAL ELECTRIC POWER INDUSTRY REPORT SCHEDULE 1. IDENTIFICATION SURVEY CONTACTS: Persons to contact with question about this form RESPONSE DUE DATE: Please submit by May 16th following the close of calendar year Contact Title: Laina Starnes

More information

Montgomery Township Community Energy Aggregation

Montgomery Township Community Energy Aggregation Montgomery Township Community Energy Aggregation MCEA Round 2 Program Announcement! The Township of Montgomery is excited to announce another Montgomery Community Energy Aggregation program (MCEA Round

More information

Expanding Capacity Eligibility

Expanding Capacity Eligibility Expanding Capacity Eligibility Zachary T. Smith Manager, Capacity Market Design ICAPWG/MIWG January 22 nd, 2019, 10 Krey Blvd Agenda Background Capacity Supplier Payment Structure SCR Program Capacity

More information

Renewable Energy System Tariffs and Pricing

Renewable Energy System Tariffs and Pricing Renewable Energy System Tariffs and Pricing National Association of Regulatory Utility Commissioners Energy Regulatory Partnership Program with The National Commission for Energy State Regulation of Ukraine

More information

Electricity Trends in Pennsylvania

Electricity Trends in Pennsylvania Electricity Trends in Pennsylvania Energy and How We Pay for it in Pennsylvania: The Next Five Years and Beyond Central Susquehanna Citizen s Coalition April 1, 2010 William Steinhurst www.synapse-energy.com

More information

Level 7 Post Graduate Diploma in Engineering Power System Economics and Planning

Level 7 Post Graduate Diploma in Engineering Power System Economics and Planning 910-09 Level 7 Post Graduate Diploma in Engineering Power System Economics and Planning You should have the following for this examination one answer book non-programmable calculator pen, pencil, ruler

More information

Yukon s Independent Power Production Policy

Yukon s Independent Power Production Policy Yukon s Independent Power Production Policy Updated October 2018 BACKGROUND The Government of Yukon (YG) released the Energy Strategy for Yukon in January 2009. The strategy sets out YG s energy priorities,

More information

SSE Guide to the Energy Industry. Guide

SSE Guide to the Energy Industry. Guide SSE Guide to the Energy Industry Guide Understanding energy costs Non-commodity costs (NCCs) are increasing. It is therefore important to understand how they are calculated and how they can affect your

More information

Value Proposition of Resilience Investments Tampa Convention Center Tampa, Florida

Value Proposition of Resilience Investments Tampa Convention Center Tampa, Florida Value Proposition of Resilience Investments Economic Justification of Resiliency Investments Nisha Thirumurthy Senior Project Leader, Project Development and Finance National Renewable Energy Laboratory

More information

TERMS AND CONDITIONS

TERMS AND CONDITIONS XXV. NET METERING A. Applicability and Availability 1. The terms Net Metering Service, Demand Charge-based Time-of- Use Tariff, Net Metering Customer, Customer, Time-of-Use Customer, Time-of-Use Tier,

More information

Biennial Assessment of the Fifth Power Plan

Biennial Assessment of the Fifth Power Plan Biennial Assessment of the Fifth Power Plan Gas Turbine Power Plant Planning Assumptions October 17, 2006 Simple- and combined-cycle gas turbine power plants fuelled by natural gas are among the bulk power

More information

Proposal Concerning Modifications to LIPA s Tariff for Electric Service

Proposal Concerning Modifications to LIPA s Tariff for Electric Service Proposal Concerning Modifications to LIPA s Tariff for Electric Service Requested Action: The Trustees are being requested to approve a resolution adopting modifications to the Long Island Power Authority

More information

Review of the SMAQMD s Construction Mitigation Program Enhanced Exhaust Control Practices February 28, 2018, DRAFT for Outreach

Review of the SMAQMD s Construction Mitigation Program Enhanced Exhaust Control Practices February 28, 2018, DRAFT for Outreach ABSTRACT The California Environmental Quality Act (CEQA) review process requires projects to mitigate their significant impacts. The Sacramento Metropolitan Air Quality Management District (SMAQMD or District)

More information

NEWFOUNDLAND AND LABRADOR BOARD OF COMMISSIONERS OF PUBLIC UTILITIES AN ORDER OF THE BOARD NO. P.U. 17(2017)

NEWFOUNDLAND AND LABRADOR BOARD OF COMMISSIONERS OF PUBLIC UTILITIES AN ORDER OF THE BOARD NO. P.U. 17(2017) NEWFOUNDLAND AND LABRADOR BOARD OF COMMISSIONERS OF PUBLIC UTILITIES AN ORDER OF THE BOARD NO. P.U. (0) 0 0 IN THE MATTER OF the Electrical Power Control Act,, SNL, Chapter E-. (the EPCA ) and the Public

More information

Flexible Ramping Product Technical Workshop

Flexible Ramping Product Technical Workshop Flexible Ramping Product Technical Workshop September 18, 2012 Lin Xu, Ph.D. Senior Market Development Engineer Don Tretheway Senior Market Design and Policy Specialist Agenda Time Topic Presenter 10:00

More information

Creating A Greener Energy Future For the Commonwealth. Massachusetts Solar Carve-Out (SRECs): Overview & Program Basics.

Creating A Greener Energy Future For the Commonwealth. Massachusetts Solar Carve-Out (SRECs): Overview & Program Basics. Massachusetts Solar Carve-Out (SRECs): Overview & Program Basics December 18, 2012 Outline Learn how the solar PV market has grown in MA since 2007 Understand the policy design of the MA Solar Carve-Out

More information

Application of claw-back

Application of claw-back Application of claw-back A report for Vector Dr. Tom Hird Daniel Young June 2012 Table of Contents 1. Introduction 1 2. How to determine the claw-back amount 2 2.1. Allowance for lower amount of claw-back

More information

August 15, Please contact the undersigned directly with any questions or concerns regarding the foregoing.

August 15, Please contact the undersigned directly with any questions or concerns regarding the foregoing. California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 August 15, 2017 Re: California

More information

Power Systems Fundamentals

Power Systems Fundamentals Power Systems Fundamentals Yachi Lin Senior Manager, Transmission Planning New York Independent System Operator Market Overview Course September 20, 2017 Rensselaer, NY 2017 New York Independent System

More information

FITCHBURG GAS AND ELECTRIC LIGHT COMPANY NET METERING SCHEDULE NM

FITCHBURG GAS AND ELECTRIC LIGHT COMPANY NET METERING SCHEDULE NM Sheet 1 FITCHBURG GAS AND ELECTRIC LIGHT COMPANY SCHEDULE NM Applicability The following tariff provisions shall be applicable to a Host Customer, as defined herein, that requests net metering services

More information

The Gambia National Forum on

The Gambia National Forum on The Gambia National Forum on Renewable Energy Regulation Kairaba Hotel, The Gambia January 31 February 1, 2012 Tariff and Price Regulation of Renewables Deborah Erwin Public Service Commission of Wisconsin

More information

PEAK DEMAND MANAGEMENT IN NEW ENGLAND A DYNAMIC SOLUTION TO MANAGING PEAK DEMAND CHARGES

PEAK DEMAND MANAGEMENT IN NEW ENGLAND A DYNAMIC SOLUTION TO MANAGING PEAK DEMAND CHARGES PEAK DEMAND MANAGEMENT IN NEW ENGLAND A DYNAMIC SOLUTION TO MANAGING PEAK DEMAND CHARGES What are peak demand (capacity) charges? Every month your business is charged a fee called a capacity charge or

More information

New Jersey Solar Roundtable

New Jersey Solar Roundtable New Jersey Solar Roundtable Transition to a Market-based REC Financing System Michael Winka, Director NJBPU, Office of Clean Energy Presented at Thomas Edison Institute March 5, 2007 NJ Solar Financing

More information

IMM Quarterly Report: Summer 2017

IMM Quarterly Report: Summer 2017 IMM Quarterly Report: Summer 2017 MISO Independent Market Monitor David Patton, Ph.D. Potomac Economics September 19, 2017 Highlights and Findings: Summer 2017 The MISO markets performed competitively

More information

The Hybrid and Electric Vehicles Manufacturing

The Hybrid and Electric Vehicles Manufacturing Photo courtesy Toyota Motor Sales USA Inc. According to Toyota, as of March 2013, the company had sold more than 5 million hybrid vehicles worldwide. Two million of these units were sold in the US. What

More information

Regulatory Treatment Of Recoating Costs

Regulatory Treatment Of Recoating Costs Regulatory Treatment Of Recoating Costs Prepared for the INGAA Foundation, Inc., by: Brown, Williams, Scarbrough & Quinn, Inc. 815 Connecticut Ave., N.W. Suite 750 Washington, DC 20006 F-9302 Copyright

More information

March 14, Please contact the undersigned directly with any questions or concerns regarding the foregoing.

March 14, Please contact the undersigned directly with any questions or concerns regarding the foregoing. California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 March 14, 2017 Re: California

More information

Simple-Offer vs. Complex-Offer Auctions in Deregulated Electricity Markets

Simple-Offer vs. Complex-Offer Auctions in Deregulated Electricity Markets Simple-Offer vs. Complex-Offer Auctions in Deregulated Electricity Markets Rimvydas Baltaduonis ICES, George Mason University May, 2008 Motivation In April 2003 the U.S. Federal Energy Regulatory Commission

More information

Agricultural Internal Combustion (IC) Engine Conversion Incentive Program Questions and Answers

Agricultural Internal Combustion (IC) Engine Conversion Incentive Program Questions and Answers CALIFORNIA FARM BUREAU FEDERATION Agricultural Internal Combustion (IC) Engine Conversion Incentive Program Questions and Answers Q1. Who is eligible to sign up for an AG-ICE program? A. In order to be

More information

Demand Response as a Power System Resource

Demand Response as a Power System Resource Demand Response as a Power System Resource Richard Cowart Director, Regulatory Assistance Project www. erranet.org Major points today 1. What? What is Demand Response (DR)? 2. Why? Proven values of DR

More information

Final Report. LED Streetlights Market Assessment Study

Final Report. LED Streetlights Market Assessment Study Final Report LED Streetlights Market Assessment Study October 16, 2015 Final Report LED Streetlights Market Assessment Study October 16, 2015 Funded By: Prepared By: Research Into Action, Inc. www.researchintoaction.com

More information

Electric Vehicles: Opportunities and Challenges

Electric Vehicles: Opportunities and Challenges Electric Vehicles: Opportunities and Challenges Henry Lee and Alex Clark HKS Energy Policy Seminar Nov. 13, 2017 11/13/2017 HKS Energy Policy Seminar 1 Introduction In 2011, Grant Lovellette and I wrote

More information

2lr1344 CF 2lr1396. Drafted by: Heide Typed by: Rita Stored 02/02/12 Proofread by Checked by By: Senator Pinsky A BILL ENTITLED

2lr1344 CF 2lr1396. Drafted by: Heide Typed by: Rita Stored 02/02/12 Proofread by Checked by By: Senator Pinsky A BILL ENTITLED C Bill No.: Requested: Committee: CF lr Drafted by: Heide Typed by: Rita Stored 0/0/ Proofread by Checked by By: Senator Pinsky A BILL ENTITLED AN ACT concerning Electricity Community Energy Generating

More information

ABB Ability Performance Optimization for power generation

ABB Ability Performance Optimization for power generation ABB Ability Performance Optimization for power generation Maintain peak performance in any market As the world's leading provider of integrated power and automation solutions to the energy and water industries,

More information