Goldwind Americas Construction Kickoff: Landowner Presentation Construction Kickoff Presentation April 26th 2017
1 Introduction to Goldwind 2 Site Safety Awareness 3 Construction Schedule 4 Road Construction 5 Foundation Construction 6 Collection Line Installation 7 Turbine Delivery & Erection 8 Turbine Information 9 Substation Construction 10 Transmission Line Construction 11 Additional Q&A
Goldwind at a Glance World Leader in PMDD Technology No.1 Globally Goldwind is the world s largest WTG manufacturer according to 2015 installations No.1 PMDD Industry leader in Permanent Magnet Direct-Drive turbine technology 98+% Goldwind s fleet-wide turbine availability is 98+% 32GW More than 32 gigawatts installed worldwide with a fleet of more than 19,000 turbines 20+years Over 20 years of experience in wind
WORLD LEADER IN PMDD TECHNOLOGY Established in 1998, Goldwind pioneered the Chinese wind market by becoming one of the first companies to explore the potential of wind power. Today, Goldwind is a leader in the global wind industry with mature manufacturing capabilities, innovative permanent magnet direct-drive (PMDD) technology, and a proven track record. More than 6,000 employees around the world, of which approximately 1,000 employees dedicated to R&D and technical development Public ally traded on 2 stock exchanges Shenzhen A share: 002202 Hong Kong H share:2208 More than 32 GW of installed wind power capacity More than 19,000 of Goldwind's wind turbines have been installed around the world, with more than 15,000 units utilizing PMDD
Goldwind Americas North American Headquarters Chicago, IL Established in 2005 and currently employing approximately 100 people in a full-time capacity, Goldwind Americas is responsible for sales and service of Goldwind turbines in North and South America. 2005 2017 Our U.S.-based leadership team has over 150 cumulative years experience in wind and renewable energy related industries.
1 Introduction to Goldwind 2 Site Safety Awareness 3 Construction Schedule 4 Road Construction 5 Foundation Construction 6 Collection Line Installation 7 Turbine Delivery & Erection 8 Turbine Information 9 Substation Construction 10 Transmission Line Construction 11 Additional Q&A
This is a construction site Things to keep in mind Long, wide and heavy trucks will be delivering parts and cranes to the site. Cement trucks will be lined up to pour concrete foundations. Equipment will be on the road forklifts, rubber-tire cranes, aerial man lifts, etc. Stay away if ice is present Do not approach the turbine if trucks are present Do not park near work areas Do not contact Underground Collector System Limit deep ripping to no more than 36- inches Do not contact overhead wires Do not contact junction boxes Call before you dig Call if anything seems wrong Goldwind Americas
1 Introduction to Goldwind 2 Site Safety Awareness 3 Construction Schedule 4 Road Construction 5 Foundation Construction 6 Collection Line Installation 7 Turbine Delivery & Erection 8 Turbine Information 9 Substation Construction 10 Transmission Line Construction 11 Additional Q&A
Rattlesnake Construction Schedule April-Roads April- Foundations August- O&M Building August- Underground Electrical August- Substation September- Transmission Line October Turbine Delivery and Installation April 2018 Commercial Operation Goldwind Americas
Rattlesnake Layout Goldwind Americas
Rattlesnake Layout Goldwind Americas
Daily Progress Updates Goldwind Americas
1 Introduction to Goldwind 2 Site Safety Awareness 3 Construction Schedule 4 Road Construction 5 Foundation Construction 6 Collection Line Installation 7 Turbine Delivery & Erection 8 Turbine Information 9 Substation Construction 10 Transmission Line Construction 11 Additional Q&A
Road Construction April 2017-October 2017 Turbine String Road Construction New access roads (approx. 21 miles) Wide travel path to accommodate crane walks 16 wide permanent graveled surface Culvert and low water crossing installation Fence and gate and cattle guard installation Goldwind Americas
Road Construction Goldwind Americas
Road Construction Goldwind Americas
1 Introduction to Goldwind 2 Site Safety Awareness 3 Construction Schedule 4 Road Construction 5 Foundation Construction 6 Collection Line Installation 7 Turbine Delivery & Erection 8 Turbine Information 9 Substation Construction 10 Transmission Line Construction 11 Additional Q&A
Foundation Installation April 2017- July 2017 Typical GW 2.5 MW Foundation: 58 6 circular footprint 10 deep at Pedestal 412 cubic yards of Concrete 35 tons of Steel Backfilled to ensure positive drainage away from foundation Concrete produced on site batch plant Goldwind Americas
Foundation Installation Goldwind Americas
1 Introduction to Goldwind 2 Site Safety Awareness 3 Construction Schedule 4 Road Construction 5 Foundation Construction 6 Collection Line Installation 7 Turbine Delivery & Erection 8 Turbine Information 9 Substation Construction 10 Transmission Line Construction 11 Additional Q&A
Collection Line Installation August 2017- February 2018 Underground cable Approx. 39 miles of 3-phase 34.5kV cable installed between turbines and back to substation 4ft trench depth at 4ft below ground surface. Trench excavation with heavy rock trenchers Fiber optic and ground cable run in the same trench Fine screening of excavated material for cable bedding Backfilled to the surface and reclaimed to blend in with surroundings Short spans of overhead collection Goldwind Americas
Collection Line Installation Goldwind Americas
1 Introduction to Goldwind 2 Site Safety Awareness 3 Construction Schedule 4 Road Construction 5 Foundation Construction 6 Collection Line Installation 7 Turbine Delivery & Erection 8 Turbine Information 9 Substation Construction 10 Transmission Line Construction 11 Additional Q&A
Turbine Delivery and Erection Goldwind Americas
Turbine Erection and Delivery October 2017- February 2018 64 x Goldwind 2.5MW turbines 90m (300ft) hub height, 109m (360ft) rotor diameter Four piece steel tubular tower Delivery rate of 8 complete turbines per week, staged at each turbine location Multiple crane activities Two 300T-class crawler cranes for setting lower tower sections and building rotors Two 600T-class crawler cranes for erecting turbines Up to ten rough-terrain hydraulic cranes to unload and provide assists Crane walks and breakdowns Goldwind Americas
1 Introduction to Goldwind 2 Site Safety Awareness 3 Construction Schedule 4 Road Construction 5 Foundation Construction 6 Collection Line Installation 7 Turbine Delivery & Erection 8 Turbine Information 9 Substation Construction 10 Transmission Line Construction 11 Additional Q&A
The GW109/2.5 MW Turbine Product Cut-in Wind Speed Rated Wind Speed Max Tip Speed 2.5MW 3 m/s (7 mph) 10.3 m/s (23 mph) 174 mph Turbine Height 300 Foot Tubular Steel Tower Total Height 474 Feet Foundation Volume 709 cy (536.7cm) of Concrete 79 tons (71,667.6kg) of Steel 102 Tons Goldwind Americas
Goldwind 2.5 MW Turbine Product Summary Copyright Goldwind Americas
1 Introduction to Goldwind 2 Site Safety Awareness 3 Construction Schedule 4 Road Construction 5 Foundation Construction 6 Collection Line Installation 7 Turbine Delivery & Erection 8 Turbine Information 9 Substation Construction 10 Transmission Line Construction 11 Additional Q&A
Substation Construction August 2017- January 2018 LCRA s Bow Wood Substation goes online 04/28/2017 Energization of the Rattlesnake Substation January 2018 Goldwind Americas
1 Introduction to Goldwind 2 Site Safety Awareness 3 Construction Schedule 4 Road Construction 5 Foundation Construction 6 Collection Line Installation 7 Turbine Delivery & Erection 8 Turbine Information 9 Substation Construction 10 Transmission Line Construction 11 Additional Q&A
Transmission Line Construction September 2017- January 2018 Approximately 16 miles in length Runs from the Rattlesnake Substation to Bow Wood Substation Poles approx. every 800-1000ft Steel monopole construction Limited use of guy wires Goldwind Americas
1 Introduction to Goldwind 2 Site Safety Awareness 3 Construction Schedule 4 Road Construction 5 Foundation Construction 6 Collection Line Installation 7 Turbine Delivery & Erection 8 Turbine Information 9 Substation Construction 10 Transmission Line Construction 11 Additional Q&A
Project Contact Information Site Office Trailers 775 CR146 Melvin TX (1.4 mile north of CR128) Keith Kurtz Project Development & Asset Manager kkurtz@goldwindamericas.com (312) 858-0383 James Blount Site Construction Manager jblount@goldwindamericas.com (903) 517-6417 Goldwind Americas