K2 Wind Community Liaison Committee Meeting #2 Wednesday, May 28, 2014

Similar documents
File No February Prepared for: Prepared by:

Prepared for: Prepared by:

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation

Goldwind Americas. Construction Kickoff: Landowner Presentation. Construction Kickoff Presentation April 26th 2017

APPENDIX B. POTENTIAL CONSTRUCTION EQUIPMENT

Prepared for: Prepared by:

WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017

ACTIVE STATOR - A MORE EFFICIENT DRIVE TRAIN CONCEPT FOR A WIND TURBINE. Dr. Makhlouf Benatmane - Director Business Development

K L E I N W I N D K R A F T kleinwind.at

TRANSPOWER PLANS, BUILDS, MAINTAINS AND OPERATES NEW ZEALAND S HIGH VOLTAGE ELECTRICITY TRANSMISSION NETWORK THE NATIONAL GRID.

BENEFITS. Maximum unit power with excellent performance for high winds. - Class IA/WZII/WZIII.

Bohn to Kettle River Transmission Project

CENTURY MONTHLY DEVELOPMENT UPDATE JUNE 2018

Michigan Thumb Loop Transmission Line Project

ELECTRICITY GENERATION LICENCE APPLICATION - PUBLIC CONSULTATION BADGINGARRA WIND FARM

Siemens Gamesa Renewable Energy Unlocking Vietnam s Nearshore Wind Potential

Wind Turbine. Commissioning Utilizing Mini-Grid Power. Scottish Renewables Onshore Wind Conference & Exhibition Aggreko

The Capital Grid Project:

BENEFITS. Maximum output at minimum cost per kwh for medium wind sites. - Class IIA.

Power Transmission Solutions Grid Access

Kettle River Transmission Project

MAJOR SYSTEM FUNCTIONS

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director

PROJECTS $500K AND OVER FOR 2012

GRAND RENEWABLE ENERGY PARK PROJECT DESCRIPTION REPORT. Attachment C. Turbine Specifications

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016

SunZia Southwest Transmission Project

Overview of hydro electric dams and how they work Provide background on basic principles of hydropower and its history. Explain features that all

Alberta Electric System Operator Saleski Transmission Project Needs Identification Document

Engineers Ireland Site Visit 23 rd March 2010

NERSA PUBLIC HEARING: RENEWABLE ENERGY POWER PLANT LICENCE APPLICATION Riverbank Wind Power (Pty) Ltd: Wesley-Ciskei Wind Project

Ingenuity for Life Wind Power Morten Pilgaard Rasmussen. Restricted Siemens AG 2016

NAPIER WIND PROJECT WIND TURBINE SPECIFICATIONS REPORT. File No October Prepared for:

Grid Integration of Large Scale Wind and Solar

APPENDIX C - AESO PIP SUMMARY

Ottawa LRT Stage 2. McKellar Park Information Session

BENEFITS. Maximum output at minimum cost per kwh for low wind sites. - Class IIIA/WZII.

G87-ingles 14/12/06 17:44 Página 2 GAMESA G MW

SECTION 3 CUSTOMER CLASS SPECIFIC

UPGRADING THE AMTRAK KEYSTONE CORRIDOR

TABLE OF CONTENTS 1. GENERAL LABOUR COSTS EQUIPMENT COSTS...2

OEB's Appendix 2-B: Fixed Asset Continuity Schedule

Renewable and Distributed Energy Resource Technologies

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW)

Distributed Generation

National Wind Technology Center Dynamometer Upgrade

New dimensions. Siemens Wind Turbine SWT Answers for energy.

Currant Lake Transmission Project

SunZia Southwest Transmission Project

SOUTHWEST CALGARY RING ROAD (SWCRR)

Georgia Transmission Corporation Georgia Systems Operations Corporation

Now even more silent! The first certified* small wind turbine in Germany. Produce your own electricity around the clock all year long.

Powering Sydney s Future

Solar Energy Proposal City of Galesburg WORK SESSION FEBRUARY 26, 2018

SERVICE REPORT ELECTRICAL ENGINEERING FOUNDERS HILL REMAINDER ERF 13

ABB Wind Power Solution

Reliability Driven By Technology. M a k e t h e r i g h t m o v e...

Grizzly Bear Creek Wind Power Plant Connection Needs Identification Document

Vattenfall Capital Markets Day 2009

APPENDIX C PARTICIPANT INVOLVEMENT PROGRAM (PIP)

Renewable Energy: Where Are We and Where Are We Headed?

Bright outlook for improved profitability. Direct drive wind turbine SWT Answers for energy.

ENERGY STORAGE DEPLOYMENTS IN ONTARIO APPRO NOVEMBER 18, 2014 TORONTO

AGL Energy Solar Project Nyngan and Broken Hill

New Innovations and Game Changers

PRESS RELEASE. C-Power completes first wind farm in the Belgian North Sea

Western NY Public Policy Transmission Planning Report

Diversifying into Marine Energy. ABB March 2015

EMERGING REQUIREMENTS

Siemens G2 platform 2.3-MW geared wind turbines. Exceptional performance, proven reliability. Answers for energy.

See NT POWERCOS , Classification Based On Service Size.

Proposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in Stakeholder Webconference February 28, 2013

SL2000 Series Wind Turbine

GOLDWIND S48/750 (50Hz) Technical Specifications

Grand Bend Wind Farm. Wind Turbine Specifications Report. Grand Bend Wind Limited Partnership Northland Power Inc., as agent

Power Purchase and Grid Connection Procedures

Siemens Cold Climate Strategy

TABLE OF CONTENTS FIGURES:

MassDOT Highway ROW Solar PV Energy Program. Hongyan (Lily) Oliver Massachusetts Department of Transportation Office of Transportation Planning

V MW Creating more from less

Decision (Errata) Access Pipeline Inc. Errata to Decision Temporary Generation at Smoky Lake Pump Station.

Tank Farm Additional Storage Site Layout

Home Electrical Wiring. Getting the electricity from the main power lines to a location in the house

Pioneer P750/49. The Premium 750 KW Wind Turbine. green. pioneer. go go with

Bald Hill on track to start lithium concentrate production this quarter

The company. Operational philosophy. Worldwide presence. Product and design philosophy. our customers permanent performance

ESIA Study for 1,050MW Coal Fired Power Plant, Lamu County, Kenya Need for the Project. 3 Need for the project... 2

Project Title: Lowertown Ballpark (CHS Field) Solar Arrays Contract Number: EP4-34 Milestone Number: 1 Report Date: June 21, 2016

Main Aspects of Lebanon s Wind Power Purchase Agreements Overview of the 1 st Round and Perspectives on the Second

wire 2018: Cables for offshore wind turbines

Current State of the Renewable Energy in Kyushu Electric Power and Our Future Plan. Kyushu Electric Power Co. Inc. June 8, 2017

Adelaide Wind Power Project Turbine T05 (AD117) IEC Edition 3.0 Measurement Report

Guidelines for Solar Grid Power Projects

CASE STUDY: BERGEY EXCEL WIND TURBINE INSTALLATION NOVEMBER 2002

WINDEMULLER RENEWABLE ENERGY WINDEMULLER

Product Presentation. September 09

Interconnection System Impact Study Report Request # GI

Project Description - 1 -

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Transcription:

K2 Wind Community Liaison Committee Meeting #2 Wednesday, May 28, 2014

K2 Wind Background The K2 Wind Power Project is a 270 megawatt (MW) wind project being developed in the Township of Ashfield-Colborne-Wawanosh In August 2011, Capital Power, Samsung Renewable Energy and Pattern Energy (the project partners) entered into a limited partnership for the development, construction and operation of the Project. The Ontario Power Authority (OPA) signed a Power Purchase Agreement (PPA) for the Project in 2011. K2 Wind received its Renewable Energy Approval (REA) from the Ministry of the Environment on July 23, 2013. In late 2013, K2 Wind engaged AMEC Black & McDonald as the prime contractor for the Project. Commercial operation is anticipated for mid-2015.

K2 Wind - Project Components 140 Siemens SWT 2.3 wind turbines located on privately owned leased lands; Electrical collection and communications systems including a transmission line, collector lines, data cables, two substations and a Hydro One switching station for connection to the existing 500 kv transmission line; An operations and maintenance building; Protection and control buildings; Meteorological towers; Turbine access roads; and Temporary construction and laydown areas.

Anticipated Project Timeline Late 2013 Preliminary civil work Early 2014 - Access roads, turbine excavations Spring 2014 - Turbine foundations poured, electrical system and substations commence July 2014 - Turbines arrive, installation begins Mid-2015 - Project operations to begin

Project Update & Construction Overview 6

Access Road Construction New access roads will be constructed to support construction and transportation vehicles to each turbine site, and for use during operation of the Project. Work has commenced on access roads. 80 will be completed for the Project. Roads are composed of gravel and are 5 metres wide. Some access roads require turnaround areas for delivery trucks. These areas will be restored to pre-existing conditions, as possible, when construction is complete; All access roads have been planned in consultation with the landowners.

Access Road Construction

Access Road Construction

Turbine Foundation Construction Turbine foundations are made of poured-in-place reinforced concrete. The foundations are octagonal in shape with a diameter of approximately 19 metres, and are 3 metres thick.

Foundation construction Excavate foundation Pour mudmat Rebar bottom/anchor cage Rebar top/grounding Formwork/conduit Pour concrete Backfill external grounding

Foundation Construction

Foundation Construction

Foundation construction

Foundation construction

Foundation construction

Collector Lines 34.5 kv electrical collector lines and fibre optic cables will be installed. The lines will be primarily installed underground. The collector lines carry the electricity from the turbines to the Project s substation and transformer station. The cables will be installed immediately to one side of the access road and within the municipal road allowance. Directional drilling will begin shortly.

Collector Lines

Collector Lines

Substation, transformer station, switchyard The substation and switchyard property is located at the northwest corner of the Tower Line and Glens Hill Road. The transformer station will be located on the SW corner of Lanesville Line and Belgrave Road and will be contained within 10 acres. The transformer station was planned to allow for the collector system to be predominantly buried (as opposed to above ground on wooden poles) as requested by the Township of ACW and local residents.

Substation, transformer station, switchyard To allow most of the collector system to be buried, approx half of the collector lines will be routed to the transformer station. Here, the power will be stepped up to 230 kv, prior to being fed to the substation. Power is then stepped up to 500 kv prior to being fed to the Hydro One switching station and to the existing 500kV transmission line, which connects to the provincial energy grid. The substation houses the switching, control, protection, communication and metering system. Hydro One is underway with work on the switching station. Work on the substation will commence in June.

Example of a Switching Station

Turbine Components Turbine components are expected to be delivered starting in July. 140 Siemens SWT 2.3 wind turbines located on privately owned leased lands; Each wind turbine consists of eight key components: concrete tower foundation; four steel tower sections; nacelle (comprised of gearbox, electrical generator, step-up transformer and housing); three rotor blades; hub (the structure to where the blades attach); power convertor; electrical wiring and grounding; and, Lightning protection/fire detection and suppression system, including steel nacelle design to limit fire risk.

Turbine Components

Turbine Components

Turbine Components

Turbine Components

Questions? www.k2wind.ca K2Wind@capitalpower.com 519-441-1067