FINAL REPORT FOR THE C-130 RAMP TEST #3 OF A HYDREMA MINE CLEARING VEHICLE

Similar documents
REMOTE MINE AREA CLEARANCE EQUIPMENT (MACE) C-130 LOAD CELL TEST DATA

AFRL-RX-TY-TM

Robot Drive Motor Characterization Test Plan

TARDEC Technology Integration

UNCLASSIFIED: Dist A. Approved for public release. GVPM Track & Suspension Overview Mr. Jason Alef & Mr. Geoff Bossio 11 Aug 2011

Evaluation of SpectroVisc Q3000 for Viscosity Determination

TARDEC --- TECHNICAL REPORT ---

Vehicle Systems Engineering and Integration Activities - Phase 3

UNCLASSIFIED: Dist A. Approved for public release. GVPM Energy Storage Overview Mr. David Skalny & Dr. Laurence Toomey 10 August 2011

UNCLASSIFIED: Dist A. Approved for public release. GVPM Non-primary Power Systems Overview Kevin Centeck and Darin Kowalski 10 Aug 2011

TARDEC Robotics. Dr. Greg Hudas UNCLASSIFIED: Dist A. Approved for public release

Vehicle Systems Engineering and Integration Activities - Phase 4

F100 ENGINE NACELLE FIRE FIGHTING TEST MOCKUP DRAWINGS

UNCLASSIFIED: Distribution A. Approved for Public Release TACOM Case # 21906, 26 May Vehicle Electronics and Architecture

Tank Automotive Research, Development and Engineering Command (TARDEC) Overview

EXPLORATORY DISCUSSIONS - PRE DECISIONAL

Feeding the Fleet. GreenGov Washington D.C. October 31, 2011

2011 NDIA GROUND VEHICLE SYSTEMS ENGINEERING AND TECHNOLOGY SYMPOSIUM POWER AND MOBILITY (P&M) MINI-SYMPOSIUM AUGUST 9-11 DEARBORN, MICHIGAN

Alternative Fuels: FT SPK and HRJ for Military Use

REPORT DOCUMENTATION PAGE

TARDEC OVERVIEW. Tank Automotive Research, Development and Engineering Center. APTAC Spring Conference Detroit 27 March, 2007

GM-TARDEC Autonomous Safety Collaboration Meeting

DSCC Annual Tire Conference CATL UPDATE. March 24, 2011 UNCLASSIFIED: Dist A. Approved for public release

Servicing Hawker Vehicle Batteries with Standard Battery Charging and Test Equipment

LESSONS LEARNED WHILE MEASURING FUEL SYSTEM DIFFERENTIAL PRESSURE MARK HEATON AIR FORCE FLIGHT TEST CENTER EDWARDS AFB, CA 10 MAY 2011

INTELLIGENT ENERGY MANAGEMENT IN A TWO POWER-BUS VEHICLE SYSTEM. DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited.

Navy Coalescence Test on Petroleum F-76 Fuel with Infineum R655 Lubricity Improver at 300 ppm

EVALUATING VOLTAGE REGULATION COMPLIANCE OF MIL-PRF-GCS600A(ARMY) FOR VEHICLE ON-BOARD GENERATORS AND ASSESSING OVERALL VEHICLE BUS COMPLIANCE

High efficiency variable speed versatile power air conditioning system for military vehicles

Navy Coalescence Test on Camelina HRJ5 Fuel

An Advanced Fuel Filter

Energy Storage Requirements & Challenges For Ground Vehicles

FTTS Utility Vehicle UV2 Concept Review FTTS UV2 Support Variant

EVALUATION OF TWO SKID-MOUNTED CORE DRILLS FOR AIRFIELD PAVEMENT EVALUATION

UNCLASSIFIED: DIST A. APPROVED FOR PUBLIC RELEASE. ARMY GREATEST INVENTIONS CY 2009 PROGRAM MRAP Overhead Wire Mitigation (OWM) Kit

TRANSIENT MAGNETIC FLUX DENSITY MEASUREMENT RESULTS ON A FUSELAGE-LIKE TEST SETUP AND INVESTIGATION OF THE EFFECTS OF APERTURES

U.S. Army/CERDEC's Portable Fuel Cell Evaluation and Field Testing 2011 Fuel Cell Seminar & Expo Orlando, FL 31 Oct 2011

Transparent Armor Cost Benefit Study

Dual Use Ground Vehicle Condition-Based Maintenance Project B

U.S. Army s Ground Vehicle Energy Storage R&D Programs & Goals

Evaluation of Single Common Powertrain Lubricant (SCPL) Candidates for Fuel Consumption Benefits in Military Equipment

Transparent Armor Cost Benefit Study

US ARMY POWER OVERVIEW

Automatic Air Collision Avoidance System. Auto-ACAS. Mark A. Skoog Dryden Flight Research Center - NASA. AutoACAS. Dryden Flight Research Center

Energy Storage Commonality Military vs. Commercial Trucks

HIGH REPETITION RATE CHARGING A MARX TYPE GENERATOR *

Does V50 Depend on Armor Mass?

TARDEC Hybrid Electric Program Last Decade

US Army Non - Human Factor Helicopter Mishap Findings and Recommendations. Major Robert Kent, USAF, MC, SFS

Joint Light Tactical Vehicle Power Requirements

Evaluation of Digital Refractometers for Field Determination of FSII Concentration in JP-5 Fuel

Helicopter Dynamic Components Project. Presented at: HCAT Meeting January 2006

Open & Evolutive UAV Architecture

Monolithically Integrated Micro Flapping Vehicles

BALANCE OF PERFORMANCE PARAMETERS FOR SURVIVABILITY AND MOBILITY IN THE DEMONSTRATOR FOR NOVEL DESIGN (DFND) VEHICLE CONCEPTS

Robust Fault Diagnosis in Electric Drives Using Machine Learning

Hydro-Piezoelectricity: A Renewable Energy Source For Autonomous Underwater Vehicles

NoFoam Unit Installation, Evaluation and Operations Manual

Cadmium Repair Alternatives on High-Strength Steel January 25, 2006 Hilton San Diego Resort 1775 East Mission Bay Drive San Diego, CA 92109

Power Distribution System for a Small Unmanned Rotorcraft

INLINE MONITORING OF FREE WATER AND PARTICULATE CONTAMINATION OF JET A FUEL

Presented by Mr. Greg Kilchenstein OSD, Maintenance. 29August 2012

Up-Coming Diesel Fuel and Exhaust Emissions Regulations For Mobile Sources. Parminder Khabra RDECOM-TARDEC TACOM LCMC March 22, 2006 JSEM

Multilevel Vehicle Design: Fuel Economy, Mobility and Safety Considerations, Part B

Joint Oil Analysis Program Spectrometer Standards VHG Labs Inc. Qualification Report For D19-0, D3-100 and D12-XXX Series Standards

SIO Shipyard Representative Bi-Weekly Progress Report

Predator B: The Multi-Role UAV

REAR-WHEEL STEERING FOR AIRCRAFT RESCUE AND FIREFIGHTING VEHICLES; TEST AND EVALUATION

Application of Airbag Technology for Vehicle Protection

REMOTELY OPERATED HYDREMA FLAIL SYSTEM MILITARY UTILITY ASSESSMENT FINAL TEST REPORT

Fuel Efficient ground vehicle Demonstrator (FED) Vision

Development of Man Portable Auxiliary Power Unit using Advanced Large Format Lithium-Ion Cells

AFRL-RX-TY-TP

Additives to Increase Fuel Heat Sink Capacity

Blast Pendulum Testing of Milliken Tegris Panels

DESULFURIZATION OF LOGISTIC FUELS FOR FUEL CELL APUs

Joint Oil Analysis Program Spectrometer Standards SCP Science (Conostan) Qualification Report For D19-0, D3-100, and D12-XXX Series Standards

U.S. Army s Ground Vehicle Energy Storage R&D Programs & Goals

Endurance Testing of Redesigned Tab Spring for MI-RAMS System

Impact of 200 ppm HiTEC 4898C Lubricity Improver Additive (LIA) on F-76 Fuel Coalescence

Center for Ground Vehicle Development and Integration

Portable Fluid Analyzer

Power Technology Branch Army Power Division US Army RDECOM CERDEC C2D Fort Belvoir, Virginia

Program Overview. Chris Mocnik Robotic Vehicle Control Architecture for FCS ATO Manager U.S. Army RDECOM TARDEC

REPORT DOCUMENTATION PAGE

Membrane Wing Aerodynamics for µav Applications

Research Development and Engineering Command TARDEC/NAC

Additional Transit Bus Life Cycle Cost Scenarios Based on Current and Future Fuel Prices

DEVELOPMENT OF COMPACT VARIABLE- VOLTAGE, BI-DIRECTIONAL 100KW DC-DC CONVERTER

Quarterly Progress Report

Hybrid Components: Motors and Power Electronics

IMPACT OF FRICTION REDUCTION TECHNOLOGIES ON FUEL ECONOMY FOR GROUND VEHICLES G. R. Fenske, R. A. Erck, O. O. Ajayi, A. Masoner, and A. S.

GVSET Power & Energy Preview Mr. Chuck Coutteau Associate Director (Acting) Ground Vehicle Power & Mobility 19 August 2009

Predator Program Office

ITC-Germany Visit. Chuck Coutteau, Associate Director Ground Vehicle Power and Mobility Overview 10 November 2011

NDCEE National Defense Center for Energy and Environment

REPORT DOCUMENTATION PAGE

Linear Algebraic Modeling of Power Flow in the HMPT500-3 Transmission

REPORT DOCUMENTATION PAGE

Report No. D November 24, Live Fire Testing of Light Tactical Wheeled Vehicles was Effective for the Portions Completed

Transcription:

AFRL-RX-TY-TP-2008-4543 FINAL REPORT FOR THE C-130 RAMP TEST #3 OF A HYDREMA MINE CLEARING VEHICLE Prepared by: William R. Meldrum Mechanical Engineer Physical Simulation Team AMSRD-TAR-D U.S. Army Tank-Automotive Research, Development and Engineering Center Warren, MI 48397-5000 FEBRUARY 2008 Final Report for 5 February 2008 13 February 2008 DISTRIBUTION STATEMENT A: Approved for public release; distribution unlimited. AIRBASE TECHNOLOGIES DIVISION MATERIALS AND MANUFACTURING DIRECTORATE AIR FORCE RESEARCH LABORATORY AIR FORCE MATERIEL COMMAND 139 BARNES DRIVE, SUITE 2 TYNDALL AIR FORCE BASE, FL 32403-5323

NOTICE AND SIGNATURE PAGE Using Government drawings, specifications, or other data included in this document for any purpose other than Government procurement does not in any way obligate the U.S. Government. The fact that the Government formulated or supplied the drawings, specifications, or other data does not license the holder or any other person or corporation; or convey any rights or permission to manufacture, use, or sell any patented invention that may relate to them. This report was cleared for public release by the Air Force Research Laboratory, Materials and Manufacturing Directorate, Airbase Technologies Division, Public Affairs and is available to the general public, including foreign nationals. Copies may be obtained from the Defense Technical Information Center (DTIC) (http://www.dtic.mil). REPORT NUMBER AFRL-RX-TY-TP-2008-4543 HAS BEEN REVIEWED AND IS APPROVED FOR PUBLICATION IN ACCORDANCE WITH ASSIGNED DISTRIBUTION STATEMENT. //signature// WALTER M. WALTZ Work Unit Manager //signature// JEREMY R. GILBERTSON, Major, USAF Chief, Force Protection Branch //signature// ALBERT N. RHODES, Ph.D. Acting Chief, Airbase Technologies Division This report is published in the interest of scientific and technical information exchange, and its publication does not constitute the Government s approval or disapproval of its ideas or findings.

REPORT DOCUMENTATION PAGE Form Approved OMB No. 0704-0188 The public reporting burden for this collection of information is estimated to average 1 hour per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0704-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. PLEASE DO NOT RETURN YOUR FORM TO THE ABOVE ADDRESS. 1. REPORT DATE (DD-MM-YYYY) 2. REPORT TYPE 3. DATES COVERED (From - To) 4. TITLE AND SUBTITLE 5a. CONTRACT NUMBER 5b. GRANT NUMBER 5c. PROGRAM ELEMENT NUMBER 6. AUTHOR(S) 5d. PROJECT NUMBER 5e. TASK NUMBER 5f. WORK UNIT NUMBER 7. PERFORMING ORGANIZATION NAME(S) AND ADDRESS(ES) 8. PERFORMING ORGANIZATION REPORT NUMBER 9. SPONSORING/MONITORING AGENCY NAME(S) AND ADDRESS(ES) 10. SPONSOR/MONITOR'S ACRONYM(S) 11. SPONSOR/MONITOR'S REPORT NUMBER(S) 12. DISTRIBUTION/AVAILABILITY STATEMENT 13. SUPPLEMENTARY NOTES 14. ABSTRACT 15. SUBJECT TERMS 16. SECURITY CLASSIFICATION OF: a. REPORT b. ABSTRACT c. THIS PAGE 17. LIMITATION OF ABSTRACT 18. NUMBER OF PAGES 19a. NAME OF RESPONSIBLE PERSON 19b. TELEPHONE NUMBER (Include area code) Standard Form 298 (Rev. 8/98) Prescribed by ANSI Std. Z39.18

1.0 INTRODUCTION 1.1 General The Air Force Research Laboratory (AFRL) located at Tyndall Air Force Base (AFB) in Panama City FL, has coordinated with the Physical Simulation Team (PST) at the Tank Automotive Research, Development, and Engineering Center (TARDEC) located in Warren MI, to perform a third C-130 ramp test on the Hydrema Mine Clearing Vehicle (MCV). This test is being conducted to determine if the new rear bogie system on the Hydrema will allow the vehicle to meet the requirements to be considered C-130 transportable. The Air Force has strict specifications for loading any vehicle onto a C-130. Those specs state that the axle weights of the vehicle can not exceed 13,000 lbs. This weight limit applies to the ramp of the plane as well as the floor of the aircraft. 1.2 Testing of the System The test was conducted on February 5-7, 2008. The test consisted of several preliminary runs that were used to adjust the newly developed rear bogie system for optimal performance. Three final test runs were then conducted with the ramp at a 12 degree angle, and those results will be presented in this report. In additional 2 other test cases were investigated and recorded in order to allow the vehicle stay below the maximum height of 110 inside the aircraft. The Hydrema vehicle was driven slowly up the ramp shown in Figure 1. The ramp has 16 instrumented plates that are shown as letters A-P. Each plate has four load cells, one in each corner, and is capable of measuring up to a 20,000 lb load. The vehicle made several stops as it climbed the ramp in order to take clear readings of the tire forces at various locations. In order for the Hydrema to be considered C-130 transportable by the US Air Force, it must not exceed an axle load of 13,000 lbs anywhere on the ramp. To achieve this goal, the Hydrema vehicle has a set of bogie wheels in the front and a double set of bogie wheels in the rear that are installed just to load the vehicle onto the aircraft.

2.0 TEST SETUP 2.1 Test Equipment In order to monitor the weight of a vehicle as it is loaded into a C-130, two axial load measurement ramps have been designed, fabricated, and instrumented with load cells (See Figure 1). The load cells are wired to a data acquisition system and data is sampled continuously while the vehicle is loaded on and off the ramp. The ramp has 16 instrumented plates (A-P in Figure 1), that are 32 square. Each plate has four 5,000 lb load cells, one in each corner. This allows each plate to record loads up to 20,000 lbs. The load cells are wired to a summing box, also located on the bottom of the plate, where the readings from all 4 load cells are added together and sent to the data acquisition system. The plates can be reconfigured to take measurements as the vehicle climbs the ramp, on the floor of the plane, or a combination of both. The ramp angle can be changed from 12 to 15 degrees. For this test, the ramp will be left in the 12 degree configuration. It should be noted that plates P and H are in reverse order for this test. O C E P D H N G F I B J A K L M Figure 1. C-130 Measurement Ramps

2.2 Vehicle Configuration The Hydrema MCV is a four wheeled vehicle that weighs over 36,000 lbs. The vehicle has been equipped with a special hydraulic bogie wheel system that is specifically for loading into the C-130. This bogie system is shown in figures 2 and 3. Hydraulic cylinders force the bogie wheels down to the ground and essentially lift the vehicle up, taking some of the weight off the main axles and transferring it to the bogie axles. The hydraulic cylinders are run off of the vehicles main hydraulic system so no additional pumps or fluid need to be mounted to the vehicle. It is believed that these bogie axles will allow the Hydrema to meet the 13,000 lb axle limit. It should be noted that the rear bogie wheels will be treated as one axle, at the request of the Air Force, due to the small spacing between the two wheels. The center of the bogie axle will be the midpoint between the two tires. Figure 2. Hydrema Front Bogie Axle Figure 3. Hydrema Rear Bogie Axles

The Hydrema also has its flail system rotated and stowed on the rear of the vehicle (Figure 4). All the chains and hammers for the system have been removed for transport. Figure 4. Stowage of flail system The axle spacing and overall length of the vehicle in its C-130 transport configuration are shown in Figure 5. 2.3 Test Procedure The test plan is to drive the Hydrema up the ramp and determine where the highest axle load readings will be found. After determining the worst case position, adjustments will be made to the bogie system to optimize the system. Upon achieving acceptable results, 3 final runs will be completed to show that the data is correct and repeatable. Due to small changes in position and alignment of the vehicle, the weight changes slightly from run to run. The final axle weight will be obtained by taking the average of the three runs. 3.0 Results It was determined that the peak axle loads were measured as the front main vehicle axle, and the rear bogie axle crossed over the hinge pin. This is where the top of the ramp is connected to the fuselage of the aircraft. For the three final test runs, the vehicle was paused just before first contact with the hinge pin, when the tire is centered on the hinge pin, and just after it clears the hinge. The rear bogie axle was measured in 6 positions, just before, on, and just over the hinge pin for both tires.

27 52 153 138 Overall length 412 Figure 5. Vehicle dimensions Several optimization test runs were completed. During these test runs the hydraulic pressure used in both the front and rear bogie axles were adjusted along with changing the tire pressures for the main axles. The tire and hydraulic pressures used for the final test runs are shown in Table 1 below. Table 1. Tire and Hydraulic Pressures Test Case #1 Test Case #2 Test Case #3 Tire Pressures Front Axle 20 psi 19 psi 40 psi Rear Axle 40 psi 40 psi 40 psi Bogie Axles 100 psi 100 psi 100 psi Hydraulic Pressures Front Bogie System 159 bar (2306 psi) 140 bar (2031 psi) 140 bar (2031 psi) Rear Bogie System 154 bar (2234 psi) 154 bar (2234 psi) 154 bar (2234 psi) Fuel level in vehicle Tank was ~¼ full. Tank was ~¼ full. Tank was ~¼ full.

The results for the final 3 test runs for each test scenarios can be found in the Appendix section of this report. Appendix A shows the results for scenario 1, Appendix B shows the results from scenario 2, and Appendix C shows the results for scenario 3. The average weight for the 3 runs can be found in Appendix D. This data shows that at no time during the loading of the Hydrema does any single axle exceed the 13,000 lb load limit. 4.0 Conclusion The data from this testing supports that the Hydrema MCV passes the axle restrictions placed on vehicles that are considered for C-130 transport. As long as the tire pressures and hydraulic pressures in the bogie axles are maintained, the loading is repeatable as demonstrated in these tests.

Appendix A Test Scenario 1 Ramp data recorded at 12 degree angle. All weights are in pounds. Test Run 8 Front Bogie Axle Front Axle Rear Axle Rear Bogie Tire 1 Rear Bogie Tire 2 Before Hinge 6705 11018 9997 12090 12111 On Hinge 6573 11231 9598 11955 12084 After Hinge 6552 11136 8980 12101 12169 Test Run 9 Before Hinge 6642 10879 10146 12070 12030 On Hinge 6569 11125 9911 12008 11945 After Hinge 6506 10918 9179 11930 11927 Test Run 11 Before Hinge 6659 10844 10063 12092 12159 On Hinge 6592 10963 9624 12064 12121 After Hinge 6573 11038 9026 12150 12146 Appendix B Test Scenario 2 Ramp data recorded at 12 degree angle. All weights are in pounds. Test Run 14 Front Bogie Axle Front Axle Rear Axle Rear Bogie Tire 1 Rear Bogie Tire 2 Before Hinge 5949 11995 9485 12079 12161 On Hinge 5821 12137 9140 11994 12183 After Hinge 5865 12075 8470 12116 12136 Test Run 15 Before Hinge 6006 11907 9487 12082 12129 On Hinge 5818 12105 9101 12026 12156 After Hinge 5957 11922 8560 12116 12060 Test Run 16 Before Hinge 5936 11922 9670 12001 12016 On Hinge 5840 12122 9093 11872 12044 After Hinge 5870 12056 8584 12017 12004

Appendix C Test Scenario 3 Ramp data recorded at 12 degree angle. All weights are in pounds. Test Run 17 Front Bogie Axle Front Axle Rear Axle Rear Bogie Tire 1 Rear Bogie Tire 2 Before Hinge 5938 11970 9527 12166 12298 On Hinge 5912 12055 8851 12092 12225 After Hinge 5943 12043 8354 12208 12289 Test Run 18 Before Hinge 5963 11959 9509 12140 12206 On Hinge 5884 12085 8950 12080 12174 After Hinge 5920 12054 8394 12214 11975 Test Run 19 Before Hinge 5912 12043 9505 12161 12179 On Hinge 5827 12102 9177 12041 12081 After Hinge 5864 12072 8306 12147 11971 Appendix D Average axle weights for the 3 final test runs for each scenario. All weights are in pounds. Average Weights Front Bogie Axle Front Axle Rear Axle Rear Bogie Tire 1 Rear Bogie Tire 2 Scenario #1 Before Hinge 6669 10914 10069 12084 12100 On Hinge 6578 11106 9711 12009 12050 After Hinge 6544 11031 9062 12060 12081 Scenario #2 Before Hinge 5964 11941 9547 12057 12102 On Hinge 5826 12121 9111 11964 12128 After Hinge 5897 12018 8538 12101 12067 Scenario #3 Before Hinge 5938 11991 9514 12156 12228 On Hinge 5874 12081 8993 12071 12160 After Hinge 5909 12056 8351 12190 12078

Addendum to Hydrema Ramp Test Final Report Dated Feb 13, 2008 Additional Vehicle Weight Information This addendum shows additional Hydrema weight information that was recorded February 27, 2008 with the vehicle on the ground instead of on the C-130 ramp. Three cases were recorded; just the vehicle on its main axles, the vehicle on its main axles with bogie wheels engaged, and the vehicle on its main axles with shoring in place. The tables below show the results of these tests and the figures show how the load plates were configured and how the shoring was set up. Table A1. Weight of the vehicle sitting on just its main axles. Test 3 Test 4 Test 5 Average Wheel Wt. Front Left 9025 9054 9067 9049 Front Right 9930 9947 9909 9929 Rear Left 9196 9251 9252 9233 Rear Right 9609 9580 9581 9590 Ave Vehicle Wt Vehicle Wt. 37760 37832 37809 37800 Table A2. Weight of the vehicle with the bogie axles engaged. Test 3 Test 4 Test 5 Average Axle Wt. Front Bogie Axle 6173 6126 6108 6136 Front Axle 12899 12838 12871 12869 Rear Axle 6183 6497 6522 6401 Rear Bogie Axle 12570 12272 12238 12360 Ave Vehicle Wt Vehicle Wt 37825 37733 37739 37766

M J O B G N L P C D Figure A1. Load plate configuration used to measure the weight of the vehicle on just the main axles only, and with the bogie axles engaged. Table A3. Weight on all ground contact points with the shoring installed. Test 1 Test 2 Test 3 Ave wt Shoring under cab front left 2614 2654 2626 2631 Shoring under cab front right 1972 2029 2035 2012 Front Left Tire 5475 5462 5483 5473 Front Right Tire 6242 6257 6275 6258 Shoring under cab rear left 767 647 680 698 Shoring under cab rear right 376 307 302 328 Shoring under flail front left 2729 2775 2751 2752 Shoring under flail front right 940 946 919 935 Rear Left Tire 5977 5975 5962 5971 Rear Right Tire 6331 6322 6307 6320 Shoring under flail rear left 757 843 831 810 Shoring under flail rear right 4000 3968 4029 3999 Hydrema total wt with shoring 38180 38185 38200 38188

Front Flail Shoring Rear Cab Shoring Front Cab Shoring Figure A2. Shoring under cab and front of flail. Figure A3. Shoring under rear of flail.

Rear Flail Shoring Rear Axle Front Flail Shoring Rear Cab Shoring Front Axle Front Cab Shoring M O D K B J N P E L C G Figure A4. Load Plate configuration for weight measurements with shoring. Table A4. Tire and Hydraulic Pressures Main Axle Tests Main Axles w/ Bogies Test Main Axles w/ Shoring Tests Tire Pressures Front Axle 40 psi 40 psi 30 psi Rear Axle 40 psi 40 psi 40 psi Bogie Axles 100 psi 100 psi 100 psi Hydraulic Pressures Front Bogie System 145 bar (2103psi) 145 bar (2103psi) 145 bar (2103psi) Rear Bogie System 154 bar (2234 psi) 154 bar (2234 psi) 154 bar (2234 psi) Fuel level in vehicle Tank was <¼ full. Tank was <¼ full. Tank was <¼ full.