Small Scale Generation Connections

Similar documents
Generation Connections Industry Workshop 2017

RENEWABLES INTEGRATION STATUS REPORT

Commercial-in-Confidence Ashton Old Baths Financial Model - Detailed Cashflow

Renewable Generation Electrical Infrastructure and Grid Connection Services Provided by Power Systems Project and Consultancy Services (PCS) Ltd

Contents. 1 Introduction. 2. Advisory and Information Systems. 3. Supply. 3.1 Quality of Electric Supply. 3.2 Interference with other Customers

Operational Opportunities to Minimize Renewables Curtailments

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

SONI LTD TRANSMISSION CONNECTION CHARGING METHODOLOGY STATEMENT

FOR IMMEDIATE RELEASE

Ameren Missouri. AMENDED Renewable Energy Standard Compliance Report Prepared in Compliance with 4 CSR

BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada. IEEE PES Meeting July 2014

A Distribution Network Operator s View of Connecting Microgeneration For RegenSW - South Devon College 07 September 2011

Local Climatological Data Summary Aurora, Illinois

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director

FOR IMMEDIATE RELEASE

Smarter Network Storage UK first multi-purpose application of grid scale storage. Dr. Panos Papadopoulos, PhD, CEng

2018 1stXV Ven 2nd XV Ven 3rdXV Ven 4thXV Ven

FOR IMMEDIATE RELEASE

Economics of Integrating Renewables DAN HARMS MANAGER OF RATE, TECHNOLOGY & ENERGY POLICY SEPTEMBER 2017

P.O BOX 429, NUKU ALOFA, Tel: (676) Fax: (676)

FOR IMMEDIATE RELEASE

Unalakleet Update: Lessons learned & continual improvement. Alaska WWG

Electricity Industry Code Minimum Service Standards & Guaranteed Service Levels Quarterly Report July September 2008

Scheme of Control Agreement

FINAL FACILITY STUDY. 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1. September 10, 2010

FOR IMMEDIATE RELEASE

List of exemptions from compliance with the Technical Rules granted by Western Power after 1 July 2007

University of Michigan Eco-Driving Index (EDI) Latest data: October 2017

December 2018 RenewableGenerations Monthly Report

FOR IMMEDIATE RELEASE

Proposed Dounreay - Mybster 275 kv / 132 kv

Smart EV Managed Charging

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

What is the Future of Competitive Markets? Some Fundamental Preliminaries and View from Events in the PJM Market

System Status Briefing

Travel Action Plan De Montfort University

Local Climatological (Data Summary Molim, Illinois

Up and Down Months of the Stock Market

FOR IMMEDIATE RELEASE

Networks. Charges for Connection to the Distribution System Revision 10 Status: Approved. Commercial and Customer Asset Management ESB Networks

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Irrigation energy efficiency How to analyse your energy costs. Nick Bullock The Energy Guys

ELECTRICAL UTILITY COST REDUCTION THROUGH PREDICTIVE CONTROL BACKGROUND

Guidelines for connection of generators:

Analysis of IEC Recommendations in Selected APEC Economies

Power Purchase and Grid Connection Procedures

NJ Solar Market Update As of 6/30/15

Standard Battery Energy Storage System (BESS) Connection Arrangements

Scaling Successful Mini-grid Programs: Experience of Bangladesh

May 2017 Pei Sue Ong, Capital Accounting Advice Manager Pacific Gas and Electric Company

Glendale Water & Power Smart Grid Project

PROCUREMENT PLAN RENEWABLE ENERGY INTEGRATION PROJECT (REIP)

State Regulatory Affairs and Local Relations Update. ATC Customer Meeting November 19, 2009

ELECTRICAL UTILITY COST REDUCTION THROUGH PREDICTIVE CONTROL December 2008 BACKGROUND

Micro Embedded generation

Decision on Merced Irrigation District Transition Agreement

COMMISSION REGULATION (EU) / of XXX

PRESENTATION ON STRATEGIC APPROACH TOWARDS WIND SOLAR HYBRID SYSTEMS (SWES) FOR REMOTE TELECOM SITES IN INDIA & CASE STUDY OF RAJASTHAN

Western Power s list of exemptions from compliance from Technical Rules granted after 1 July 2007.

The International Cost Estimating and Analysis Association (ICEAA) Southern California Chapter September 9, 2015

SPN High Value Project PO Route. RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN

Recharge the Future Interim Findings

ANCR CRU Statistics February 2007 to December 2007

Large Embedded Generation User Guide A

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Eastern Area Command. Year Due Sale. Year Purchased

2017 Risk and Profit Conference Breakout Session Presenters. 13. Ethanol and Biodiesel Market and Profitability Prospects

Review of Reliability Must-Run and Capacity Procurement Mechanism BBB Issue Paper and Straw Proposal for Phase 1 Items

Regulatory Annual Report 2014/15 In Compliance with the Reporting Requirements of Schedule 13 of the Electricity Concession Contract (I)

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Net +Plus Connection Code

Energy use in potato stores

Distribution Capacity Impacts of Plug In Electric Vehicles. Chris Punt, P.E. MIPSYCON 2014

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82

Docket No. DE Dated: 05/04/2015 Attachment CJG-1 Page 1

Past Due. Account Charges. Contract Charges Security Deposit Due - Jun 09, , Customer Service. Jun 19, PAST DUE $1,693.

New Jersey Solar Roundtable

Umatilla Electric Cooperative Net Metering Rules

Eyre Peninsula electricity supply options investigation

Review of U.S. market reforms for renewable integration, flexibility, and storage

DRAFT. Guidelines on Power quality & safety issues in usage of roof-top solar pv system CENTRAL ELECTRICITY AUTHORITY

Thomas Alston Director of Business and Policy Development. Presented By N. Scottsdale Rd, Suite 410 Scottsdale Arizona 85257

November 2018 Customer Switching Report for the Electricity and Gas Retail Markets

Merger of the generator interconnection processes of Valley Electric and the ISO;

RECOMMENDATION: It is recommended that the City Council, following a public hearing, adopt the attached resolution which:

NJ Solar Market Update

Grid Energy Storage: Policies

Massachusetts Electric Company and Nantucket Electric Company, Docket No. D.T.E

November 2017 Customer Switching Report for the Electricity and Gas Retail Markets

Residential Load Profiles

Operational Overview. Operational Forum, 24 th March 2010

Standards, Procedures and Policies for Grid Connection

STEEL IMPORTS UP 15% IN 2017 Finished Import Market Share Increased to 27%

Compliance of Solar PV Installation with the New Renewables SA Grid Code Jimmy Goulding, Electrical Technologist, Aurecon, South Africa

APPLICATION FOR INSTALLATION OF SMALL SCALE EMBEDDED ELECTRICITY GENERATION

Attention : Ms. G. Cheryl Blundon, Director of Corporate Services & Board Secretary

Michigan Thumb Loop Transmission Line Project

DLH revised action plan

FY2/18 2Q(March 2017~August 2018)

Transcription:

RP5 STAKEHOLDER EVENT Small Scale Generation Connections 6 June 2011

Presentation Approach General background with respect to small scale generation connections Anticipated level of connection applications Network issues Technical issues associated with connection to the network Approach to assessing a connection application Typical connection arrangements and costs Resources and processes Control, communications and Distribution code Issues relating to small scale generation contained in the Utility Regulator s Next Steps Paper on Electricity Connection Policy for the Northern Ireland Distribution System dated 10 May 2011 2

Small Scale Generation seeking planning permission / connection to the 11kV system Volume of DOE Planning Applications for Generation 160 148 140 Number of Applications 120 100 80 60 40 20 14 17 18 9 11 7 12 15 19 39 75 28 56 47 37 61 51 41 89 97 0 Au g- 09 Se p- 09 Oc t- 09 No v- 09 De c- 09 Ja n- 10 Fe b- 10 Ma r- 10 Ap r- 10 Ma y- 10 Ju n- 10 J ul- 10 Au g- 10 Se p- 10 Oc t- 10 No v- 10 De c- 10 Ja n- 11 Fe b- 11 Ma r- 11 Ap r- 11 Ma y- 11 Date (Month) 3

Generation analysed by size Monthly Breakdown of kw Level of Generation in Planning 80 70 60 27 Number of Applications 50 40 30 20 10 0 1 12 5 12 1 2 15 1 2 6 2 2 1 6 3 3 1 5 1 6 5 6 2 2 Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10 Apr-10 May-10 Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Time (Month) 9 2 3 5 12 13 8 6 27 10 11 10 12 4 2 24 16 7 9 26 16 4 1 20 6 9 2 A.Less than 20kW B.20kW to 150 kw c.150 kw to 250 kw D.250kW + 4

Planning Applications (DOE) for small scale generation LOGUESTOWN Key Wind Turbines in planning COLERAINE Hydroelectric generators in planning LIMAVADY Diesel generators in planning LISAGHMORE Anaerobic Digesters in planning BALLYMENA LARNE KELLS STRABANE CREAGH MAGHERAFELT ANTRIM NEWTONABBEY RATHGAEL NEWTOWNARDS CASTLEREAGH OMAGH DUNGANNON WARRINGSTOWN DRUMNAKELLY LISBURN BALLYNAHINCH ENNISKILLEN BANBRIDGE NEWCASTLE NEWRY August 2009 5

Planning Applications (DOE) for small scale generation LOGUESTOWN Key Wind Turbines in planning Hydroelectric generators in planning LIMAVADY COLERAINE BALLYMONEY Diesel generators in planning LISAGHMORE Anaerobic Digesters in planning DUNGIVEN BALLYMENA LARNE KELLS STRABANE CREAGH MAGHERAFELT ANTRIM NEWTOWNSTEWART NEWTONABBEY RATHGAEL NEWTOWNARDS CASTLEREAGH OMAGH DUNGANNON WARRINGSTOWN DRUMNAKELLY LISBURN BALLYNAHINCH ENNISKILLEN ARMAGH BANBRIDGE KEADY NEWCASTLE NEWRY December 2009 6

Planning Applications (DOE) for small scale generation LOGUESTOWN Key Wind Turbines in planning Hydroelectric generators in planning LIMAVADY COLERAINE BALLYMONEY Diesel generators in planning LISAGHMORE Anaerobic Digesters in planning DUNGIVEN BALLYMENA LARNE KELLS STRABANE CREAGH MAGHERAFELT ANTRIM NEWTOWNSTEWART NEWTONABBEY RATHGAEL NEWTOWNARDS CASTLEREAGH OMAGH DUNGANNON WARRINGSTOWN DRUMNAKELLY LISBURN BALLYNAHINCH ENNISKILLEN ARMAGH BANBRIDGE KEADY NEWCASTLE NEWRY April 2010 7

Planning Applications (DOE) for small scale generation LOGUESTOWN Key Wind Turbines in planning Hydroelectric generators in planning LIMAVADY COLERAINE BALLYMONEY Diesel generators in planning LISAGHMORE Anaerobic Digesters in planning DUNGIVEN BALLYMENA LARNE KELLS STRABANE CREAGH MAGHERAFELT ANTRIM NEWTOWNSTEWART NEWTONABBEY RATHGAEL NEWTOWNARDS CASTLEREAGH OMAGH DUNGANNON WARRINGSTOWN DRUMNAKELLY LISBURN BALLYNAHINCH ENNISKILLEN ARMAGH BANBRIDGE KEADY NEWCASTLE NEWRY November 2010 8

Planning Applications (DOE) for small scale generation LOGUESTOWN Key Wind Turbines in planning Hydroelectric generators in planning LIMAVADY COLERAINE BALLYMONEY Diesel generators in planning LISAGHMORE Anaerobic Digesters in planning Existing Wind Turbine Sites DUNGIVEN BALLYMENA KELLS LARNE STRABANE CREAGH MAGHERAFELT ANTRIM NEWTOWNSTEWART NEWTONABBEY RATHGAEL NEWTOWNARDS CASTLEREAGH OMAGH DUNGANNON WARRINGSTOWN DRUMNAKELLY LISBURN BALLYNAHINCH ENNISKILLEN ARMAGH BANBRIDGE KEADY NEWCASTLE NEWRY January 2011 9

Typical 11 kv rural network 33/11kV source Light construction 25mm 2 3-phase open 85% of 11kV network is rural (overhead) Single phase network For Overhead line 60% is single-phase 70% is 25mm 2 (light construction) 10

Grid Connection Small scale renewables individual wind turbines or anaerobic digesters The 11kV network was mostly built in the 1950 s and 1960 s to bring electricity to rural homes, farms and communities. It was not designed to connect the size of wind turbines that are appearing today (typical farm maximum demand is around a tenth of a 250kW generator). Significantly power from generation flows in an opposite direction to traditional demand-related powerflows The cost of the connection will depend on the location of the applicant. This makes it difficult to provide indicative costs that can be used as a guide by prospective applicants. However if the location is at the extremity of the 11kV network the cost will be greater than a location closer to the central main line. 11

Network Issues Significant proportion is single phase Network Voltage Thermal Issues Fault Levels Quality of Supply Voltage Dip Flicker Voltage Imbalance Harmonics 12

Single-phase and three-phase line construction Short Cross-arm Light pole 3-phase single-phase Single-phase to three-phase 11kV line conversion Complete rebuild often required 32,000 (indicative) 13

Network Voltage Controlled at source substation Needs to be set above nominal and controlled at this level to ensure adequate voltage at the end of the line Transformers along the line are not controlled to vary the voltage Generators will cause voltage rise at their point of connection particularly at times of minimum network demand This has the potential to cause voltage to exceed limits for customers on the circuit Effect worsens if generator is located remote from our source substation 14

Network Voltage without generation Voltage level Low demand Distance along circuit Heavy demand 15

Network Voltage rise as result of generator Voltage level Low demand Distance along circuit Heavy demand Location of generator 16

Voltage Dip Caused by a Surge of Current when connecting Generator Network Voltage I 17

Flicker Caused by the variations in the Generator output Network Voltage Power Output = Wind Speed 3 18

Voltage Imbalance Caused by Large No. Single Phase Load connections Balanced Network All Voltages Equal Imbalance Network Different Phase Voltage Circulating Current In induction Generator can cause overheating and disconnection 19

Harmonics Caused by Inverters & Variable Speed Drives Can cause overheating of electrical equipment Mains Frequency 50Hz Mains Frequency 50Hz Plus Harmonic Resulting Waveform (Frequency 50Hz Plus Harmonic) 20

Assessment of network connection of a generator Require detailed information from applicant Technology Generator size and detailed technical information Location Starting arrangements NIE carry out network studies to assess Least cost technically acceptable (LCTA) connection Voltage, Thermal and power quality Worst case assessment (generally minimum demand) Need to consider other generators Protection requirements We then consider the physical aspects of the connection Substation location Network extension Landowner and planning We then carry out a costing exercise Provide connection offer 21

Typical Connection Projects Example 1 Example Project 1 The developer has a project which requires no extension to the three-phase 11kV system - 150kW generator Work NIE installs a double pole 11kV structure below the overhead line to support the transformer NIE connects the transformer as a fused connection to the existing overhead line NIE arranges a short LV circuit from the transformer to the customer Cost Estimated Average Cost for construction 20k Communication and control equipment 20k Total Cost 40k 22

Physical work Existing line Generator Metering protection LV Cable or line Double pole And transformer Up to 200kVA Protection Pole changed & TX located below the existing overhead line About 20k incl. 3.5k O&M 23

Typical Connection Projects Example 2 Project 2 The developer has a project which requires no extension to the three- phase 11kV system - 250kW generator Work NIE installs an 11kV structure or cable arrangement NIE carries out civil engineering works establishes a safe enclosed compound and installs a ground mounted transformer (transformer is too heavy for pole mounting) NIE connects the transformer as a fused Tee d connection to the existing overhead line NIE arranges a short LV circuit from the transformer to the customer Cost Estimated Average Cost for construction 50k Communication and control equipment 20k Total Cost 70K 24

Physical work Existing line T off Generator Enclosure And transformer Up to 500kVA Protection Metering protection LV Cable or line Construction work about 50k incl. 10k O&M 25

Typical Connection Projects Example 3 Project 3A The developer has a project which requires extension of the threephase 11kV system - 150kW generator Basic cost 40k System uprating to 3-phase (4km @ 32k/km) 128k TOTAL 168k Project 3B The developer has a project which requires extension of the three-phase 11kV system - 250kW generator Basic cost 70k System uprating to 3-phase (4km @ 32k/km) 128k TOTAL 198k 26

Typical Connection Projects Example 4 Project 4A 4km from a three-phase line requiring upgrade of 5km of the existing 3-phase line 150kW generator Basic cost 40k System uprating to 3-phase 128k Backbone reinforcement 5km 125k TOTAL 293k Project 4B 4km from a three-phase line requiring upgrade of 5km of the existing 3-phase line 250kW generator Basic cost 70k System uprating to 3-phase 128k Backbone reinforcement 125k TOTAL 323k 27

Resources We have increased the resources applied to this area Present complement of staff dealing with small scale connection applications Team of 4 engineers (two recently recruited) Process and performance improvement engineer (recently recruited) One admin staff member (recently recruited) Whether this is the correct complement will need to be kept under review Depends very much on throughput from planning service 28

Feasibility Studies Study is optional No planning permission required The feasibility study will indicate -Connection Voltage Level -Connection Point to NIE Network -Details of the connection arrangement -Indicative costs of the proposed connection To carry out a feasibility study NIE require: 1. Completed Feasibility Study Enquiry Form 2. Copy of the generator's electrical data sheet 3. Payment 150kW or less 600 More than 150kW 1,200 A feasibility study does not reserve network capacity for a particular project 29

Network Connection & Capacity Study Offered to customers who have obtained all permissions, including planning permission There is no requirement to have a feasibility study carried out before you request a Network Connection & Capacity Study. This study is a full technical appraisal and requires you to submit a formal application (NIE Generator Questionnaire) and the full electrical technical specification of the generator being connected together with the payment:- Generation Maximum Installed Capacity Application Cost 20kW or less 600 21 kw - 150kW 1,800 151 kw - 2000kW 6,000. Connection offers to be processed within 3 months Offers remain valid for three months Work commences on acceptance of terms/20% deposit 30

Timescales - Planning Permission Not Required Application to Quotation Acceptance to Construction Procurement of Plant & Equipment Survey Construction 3 months 2 months 2 4 months Average time for connection is between 6-9 months, if plant and equipment is to be ordered. (Lead in time for major items of plant and equipment is up to 20 weeks.) Where NIE needs to install equipment on third party property, legal consent in the form of a wayleave agreement and/or easement is required from the relevant landowner. Timescales to obtain landowner approval depends on the landowner s willingness to sign the legal documents. Where a substation is required a substation lease must be obtained. 31

Timescales - Planning Permission Required Application to Quotation Survey & Wayleaves Acceptance to Construction Procurement of Plant & Equipment Planning Permission Construction 3 months 2 3 months 4 6 months 2 3 months Planning Permission required for construction of any overhead line greater than 100m in length. Turnaround time for planning permission approx 4-6 months. Average time for connection is approx 9 to 12 months following acceptance of terms. This timescale is subject to NIE being able to secure legalities i.e.. wayleaves, easements, substation leases and planning permission 32

Distribution Code, Communications and Control The D code is approved by the Utility Regulator NIE and connectees must comply D Code sets out technical requirements for generation connecting to the network Compliance with D Code is essential for efficient network operation Non-compliant generators will not get connected D Code Panel made up of industry and utility representatives Communications and Control requirement now in D Code for generation NIE is developing appropriate communication system for large volume of generators Cost presently detailed in connection offers - 20k per site Crucial to optimising the volume of generation connected to network Future use with Smart grid technology 33

Utility Regulators Next Steps Paper on Connection Policy Following generation issues dealt with in 1 st Stakeholders workshop Security Standards & constraints information Rebates Definition of connection assets and associated costs Timing of offers and connection agreements Clusters of generators Cost of connection and published information Operations and maintenance costs SPS and communications 34

Utility Regulators Next Steps Paper on Connection Policy - Subsidies for Micro generation Utility Regulators next steps Not making any decision at this time May consider any future proposals on a cross directorate level NIE consider that 100% charging is appropriate However there is a question over whether a strategic programme of 11kV reinforcement and conversion to three phase is necessary and if so how should be funded? How should such reinforcement be balanced by control of generation to maximise the total capacity of generation connections? NIE propose to conduct a study of the costs of reinforcement and the extent to which limited control of generation output and improved network control can avoid reinforcement. 35

Utility Regulators Next Steps Paper on Connection Policy - Scada and Control Utility Regulators next steps As part of NIE s next regulatory price control the Regulator will scrutinise SCADA and communications costs NIE consider that scada and control is fundamental to maximising the penetration of small scale generation on the 11kV network Seeking to develop the most cost effective approach Costs currently being charged will be reviewed in light of outturn Refunds provided if costs are lower than charged 36