RP5 STAKEHOLDER EVENT Small Scale Generation Connections 6 June 2011
Presentation Approach General background with respect to small scale generation connections Anticipated level of connection applications Network issues Technical issues associated with connection to the network Approach to assessing a connection application Typical connection arrangements and costs Resources and processes Control, communications and Distribution code Issues relating to small scale generation contained in the Utility Regulator s Next Steps Paper on Electricity Connection Policy for the Northern Ireland Distribution System dated 10 May 2011 2
Small Scale Generation seeking planning permission / connection to the 11kV system Volume of DOE Planning Applications for Generation 160 148 140 Number of Applications 120 100 80 60 40 20 14 17 18 9 11 7 12 15 19 39 75 28 56 47 37 61 51 41 89 97 0 Au g- 09 Se p- 09 Oc t- 09 No v- 09 De c- 09 Ja n- 10 Fe b- 10 Ma r- 10 Ap r- 10 Ma y- 10 Ju n- 10 J ul- 10 Au g- 10 Se p- 10 Oc t- 10 No v- 10 De c- 10 Ja n- 11 Fe b- 11 Ma r- 11 Ap r- 11 Ma y- 11 Date (Month) 3
Generation analysed by size Monthly Breakdown of kw Level of Generation in Planning 80 70 60 27 Number of Applications 50 40 30 20 10 0 1 12 5 12 1 2 15 1 2 6 2 2 1 6 3 3 1 5 1 6 5 6 2 2 Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10 Apr-10 May-10 Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Time (Month) 9 2 3 5 12 13 8 6 27 10 11 10 12 4 2 24 16 7 9 26 16 4 1 20 6 9 2 A.Less than 20kW B.20kW to 150 kw c.150 kw to 250 kw D.250kW + 4
Planning Applications (DOE) for small scale generation LOGUESTOWN Key Wind Turbines in planning COLERAINE Hydroelectric generators in planning LIMAVADY Diesel generators in planning LISAGHMORE Anaerobic Digesters in planning BALLYMENA LARNE KELLS STRABANE CREAGH MAGHERAFELT ANTRIM NEWTONABBEY RATHGAEL NEWTOWNARDS CASTLEREAGH OMAGH DUNGANNON WARRINGSTOWN DRUMNAKELLY LISBURN BALLYNAHINCH ENNISKILLEN BANBRIDGE NEWCASTLE NEWRY August 2009 5
Planning Applications (DOE) for small scale generation LOGUESTOWN Key Wind Turbines in planning Hydroelectric generators in planning LIMAVADY COLERAINE BALLYMONEY Diesel generators in planning LISAGHMORE Anaerobic Digesters in planning DUNGIVEN BALLYMENA LARNE KELLS STRABANE CREAGH MAGHERAFELT ANTRIM NEWTOWNSTEWART NEWTONABBEY RATHGAEL NEWTOWNARDS CASTLEREAGH OMAGH DUNGANNON WARRINGSTOWN DRUMNAKELLY LISBURN BALLYNAHINCH ENNISKILLEN ARMAGH BANBRIDGE KEADY NEWCASTLE NEWRY December 2009 6
Planning Applications (DOE) for small scale generation LOGUESTOWN Key Wind Turbines in planning Hydroelectric generators in planning LIMAVADY COLERAINE BALLYMONEY Diesel generators in planning LISAGHMORE Anaerobic Digesters in planning DUNGIVEN BALLYMENA LARNE KELLS STRABANE CREAGH MAGHERAFELT ANTRIM NEWTOWNSTEWART NEWTONABBEY RATHGAEL NEWTOWNARDS CASTLEREAGH OMAGH DUNGANNON WARRINGSTOWN DRUMNAKELLY LISBURN BALLYNAHINCH ENNISKILLEN ARMAGH BANBRIDGE KEADY NEWCASTLE NEWRY April 2010 7
Planning Applications (DOE) for small scale generation LOGUESTOWN Key Wind Turbines in planning Hydroelectric generators in planning LIMAVADY COLERAINE BALLYMONEY Diesel generators in planning LISAGHMORE Anaerobic Digesters in planning DUNGIVEN BALLYMENA LARNE KELLS STRABANE CREAGH MAGHERAFELT ANTRIM NEWTOWNSTEWART NEWTONABBEY RATHGAEL NEWTOWNARDS CASTLEREAGH OMAGH DUNGANNON WARRINGSTOWN DRUMNAKELLY LISBURN BALLYNAHINCH ENNISKILLEN ARMAGH BANBRIDGE KEADY NEWCASTLE NEWRY November 2010 8
Planning Applications (DOE) for small scale generation LOGUESTOWN Key Wind Turbines in planning Hydroelectric generators in planning LIMAVADY COLERAINE BALLYMONEY Diesel generators in planning LISAGHMORE Anaerobic Digesters in planning Existing Wind Turbine Sites DUNGIVEN BALLYMENA KELLS LARNE STRABANE CREAGH MAGHERAFELT ANTRIM NEWTOWNSTEWART NEWTONABBEY RATHGAEL NEWTOWNARDS CASTLEREAGH OMAGH DUNGANNON WARRINGSTOWN DRUMNAKELLY LISBURN BALLYNAHINCH ENNISKILLEN ARMAGH BANBRIDGE KEADY NEWCASTLE NEWRY January 2011 9
Typical 11 kv rural network 33/11kV source Light construction 25mm 2 3-phase open 85% of 11kV network is rural (overhead) Single phase network For Overhead line 60% is single-phase 70% is 25mm 2 (light construction) 10
Grid Connection Small scale renewables individual wind turbines or anaerobic digesters The 11kV network was mostly built in the 1950 s and 1960 s to bring electricity to rural homes, farms and communities. It was not designed to connect the size of wind turbines that are appearing today (typical farm maximum demand is around a tenth of a 250kW generator). Significantly power from generation flows in an opposite direction to traditional demand-related powerflows The cost of the connection will depend on the location of the applicant. This makes it difficult to provide indicative costs that can be used as a guide by prospective applicants. However if the location is at the extremity of the 11kV network the cost will be greater than a location closer to the central main line. 11
Network Issues Significant proportion is single phase Network Voltage Thermal Issues Fault Levels Quality of Supply Voltage Dip Flicker Voltage Imbalance Harmonics 12
Single-phase and three-phase line construction Short Cross-arm Light pole 3-phase single-phase Single-phase to three-phase 11kV line conversion Complete rebuild often required 32,000 (indicative) 13
Network Voltage Controlled at source substation Needs to be set above nominal and controlled at this level to ensure adequate voltage at the end of the line Transformers along the line are not controlled to vary the voltage Generators will cause voltage rise at their point of connection particularly at times of minimum network demand This has the potential to cause voltage to exceed limits for customers on the circuit Effect worsens if generator is located remote from our source substation 14
Network Voltage without generation Voltage level Low demand Distance along circuit Heavy demand 15
Network Voltage rise as result of generator Voltage level Low demand Distance along circuit Heavy demand Location of generator 16
Voltage Dip Caused by a Surge of Current when connecting Generator Network Voltage I 17
Flicker Caused by the variations in the Generator output Network Voltage Power Output = Wind Speed 3 18
Voltage Imbalance Caused by Large No. Single Phase Load connections Balanced Network All Voltages Equal Imbalance Network Different Phase Voltage Circulating Current In induction Generator can cause overheating and disconnection 19
Harmonics Caused by Inverters & Variable Speed Drives Can cause overheating of electrical equipment Mains Frequency 50Hz Mains Frequency 50Hz Plus Harmonic Resulting Waveform (Frequency 50Hz Plus Harmonic) 20
Assessment of network connection of a generator Require detailed information from applicant Technology Generator size and detailed technical information Location Starting arrangements NIE carry out network studies to assess Least cost technically acceptable (LCTA) connection Voltage, Thermal and power quality Worst case assessment (generally minimum demand) Need to consider other generators Protection requirements We then consider the physical aspects of the connection Substation location Network extension Landowner and planning We then carry out a costing exercise Provide connection offer 21
Typical Connection Projects Example 1 Example Project 1 The developer has a project which requires no extension to the three-phase 11kV system - 150kW generator Work NIE installs a double pole 11kV structure below the overhead line to support the transformer NIE connects the transformer as a fused connection to the existing overhead line NIE arranges a short LV circuit from the transformer to the customer Cost Estimated Average Cost for construction 20k Communication and control equipment 20k Total Cost 40k 22
Physical work Existing line Generator Metering protection LV Cable or line Double pole And transformer Up to 200kVA Protection Pole changed & TX located below the existing overhead line About 20k incl. 3.5k O&M 23
Typical Connection Projects Example 2 Project 2 The developer has a project which requires no extension to the three- phase 11kV system - 250kW generator Work NIE installs an 11kV structure or cable arrangement NIE carries out civil engineering works establishes a safe enclosed compound and installs a ground mounted transformer (transformer is too heavy for pole mounting) NIE connects the transformer as a fused Tee d connection to the existing overhead line NIE arranges a short LV circuit from the transformer to the customer Cost Estimated Average Cost for construction 50k Communication and control equipment 20k Total Cost 70K 24
Physical work Existing line T off Generator Enclosure And transformer Up to 500kVA Protection Metering protection LV Cable or line Construction work about 50k incl. 10k O&M 25
Typical Connection Projects Example 3 Project 3A The developer has a project which requires extension of the threephase 11kV system - 150kW generator Basic cost 40k System uprating to 3-phase (4km @ 32k/km) 128k TOTAL 168k Project 3B The developer has a project which requires extension of the three-phase 11kV system - 250kW generator Basic cost 70k System uprating to 3-phase (4km @ 32k/km) 128k TOTAL 198k 26
Typical Connection Projects Example 4 Project 4A 4km from a three-phase line requiring upgrade of 5km of the existing 3-phase line 150kW generator Basic cost 40k System uprating to 3-phase 128k Backbone reinforcement 5km 125k TOTAL 293k Project 4B 4km from a three-phase line requiring upgrade of 5km of the existing 3-phase line 250kW generator Basic cost 70k System uprating to 3-phase 128k Backbone reinforcement 125k TOTAL 323k 27
Resources We have increased the resources applied to this area Present complement of staff dealing with small scale connection applications Team of 4 engineers (two recently recruited) Process and performance improvement engineer (recently recruited) One admin staff member (recently recruited) Whether this is the correct complement will need to be kept under review Depends very much on throughput from planning service 28
Feasibility Studies Study is optional No planning permission required The feasibility study will indicate -Connection Voltage Level -Connection Point to NIE Network -Details of the connection arrangement -Indicative costs of the proposed connection To carry out a feasibility study NIE require: 1. Completed Feasibility Study Enquiry Form 2. Copy of the generator's electrical data sheet 3. Payment 150kW or less 600 More than 150kW 1,200 A feasibility study does not reserve network capacity for a particular project 29
Network Connection & Capacity Study Offered to customers who have obtained all permissions, including planning permission There is no requirement to have a feasibility study carried out before you request a Network Connection & Capacity Study. This study is a full technical appraisal and requires you to submit a formal application (NIE Generator Questionnaire) and the full electrical technical specification of the generator being connected together with the payment:- Generation Maximum Installed Capacity Application Cost 20kW or less 600 21 kw - 150kW 1,800 151 kw - 2000kW 6,000. Connection offers to be processed within 3 months Offers remain valid for three months Work commences on acceptance of terms/20% deposit 30
Timescales - Planning Permission Not Required Application to Quotation Acceptance to Construction Procurement of Plant & Equipment Survey Construction 3 months 2 months 2 4 months Average time for connection is between 6-9 months, if plant and equipment is to be ordered. (Lead in time for major items of plant and equipment is up to 20 weeks.) Where NIE needs to install equipment on third party property, legal consent in the form of a wayleave agreement and/or easement is required from the relevant landowner. Timescales to obtain landowner approval depends on the landowner s willingness to sign the legal documents. Where a substation is required a substation lease must be obtained. 31
Timescales - Planning Permission Required Application to Quotation Survey & Wayleaves Acceptance to Construction Procurement of Plant & Equipment Planning Permission Construction 3 months 2 3 months 4 6 months 2 3 months Planning Permission required for construction of any overhead line greater than 100m in length. Turnaround time for planning permission approx 4-6 months. Average time for connection is approx 9 to 12 months following acceptance of terms. This timescale is subject to NIE being able to secure legalities i.e.. wayleaves, easements, substation leases and planning permission 32
Distribution Code, Communications and Control The D code is approved by the Utility Regulator NIE and connectees must comply D Code sets out technical requirements for generation connecting to the network Compliance with D Code is essential for efficient network operation Non-compliant generators will not get connected D Code Panel made up of industry and utility representatives Communications and Control requirement now in D Code for generation NIE is developing appropriate communication system for large volume of generators Cost presently detailed in connection offers - 20k per site Crucial to optimising the volume of generation connected to network Future use with Smart grid technology 33
Utility Regulators Next Steps Paper on Connection Policy Following generation issues dealt with in 1 st Stakeholders workshop Security Standards & constraints information Rebates Definition of connection assets and associated costs Timing of offers and connection agreements Clusters of generators Cost of connection and published information Operations and maintenance costs SPS and communications 34
Utility Regulators Next Steps Paper on Connection Policy - Subsidies for Micro generation Utility Regulators next steps Not making any decision at this time May consider any future proposals on a cross directorate level NIE consider that 100% charging is appropriate However there is a question over whether a strategic programme of 11kV reinforcement and conversion to three phase is necessary and if so how should be funded? How should such reinforcement be balanced by control of generation to maximise the total capacity of generation connections? NIE propose to conduct a study of the costs of reinforcement and the extent to which limited control of generation output and improved network control can avoid reinforcement. 35
Utility Regulators Next Steps Paper on Connection Policy - Scada and Control Utility Regulators next steps As part of NIE s next regulatory price control the Regulator will scrutinise SCADA and communications costs NIE consider that scada and control is fundamental to maximising the penetration of small scale generation on the 11kV network Seeking to develop the most cost effective approach Costs currently being charged will be reviewed in light of outturn Refunds provided if costs are lower than charged 36