दव ण त र य व द य त सवमवत

Similar documents
दव ण त र य व द य त सवमवत

य प र षण ल ख REGIONAL TRANSMISSION ACCOUNT. April 2018

Central Electricity Authority System Planning & Project Appraisal Division Sewa Bhawan, R.K. Puram, New Delhi

1. CONFIRMATION OF THE MINUTES OF THE 14 th PROTECTION SUB- COMMITTEE MEETING HELD ON 21 st March Grid Disturbances in the Southern Region

Agenda for Connectivity and Long Term (Open) Access of IPP Generation Projects in Odisha of Eastern Region

Central Electricity Authority System Planning & Project Appraisal Division Sewa Bhawan, R.K. Puram, New Delhi

Central Electricity Authority System Planning & Project Appraisal Division Sewa Bhawan, R K Puram, New Delhi

Annex_Tumkur In-principle(Phase-I) 1)Minutes of the meeting held on )In-principle Approval_Tumkur Phase-I

Central Electricity Authority System Planning & Project Appraisal Division Sewa Bhawan, R.K. Puram, New Delhi

HVDC Systems in India

Central Electricity Authority System Planning & Project Appraisal Division Sewa Bhawan, R.K. Puram, New Delhi

Agenda Note for Long Term Open Access Applications of New Generation in Southern Region

TRANSMISSION CAPACITY ADDITION PROGRAMME DURING No. 1 Introduction 1

Central Electricity Authority System Planning & Project Appraisal Division Sewa Bhawan, R.K. Puram, New Delhi

SOUTHERN REGIONAL POWER COMMITTEE BANGALORE

Central Electricity Authority System Planning & Project Appraisal Division Sewa Bhawan, R.K. Puram, New Delhi

Central Electricity Authority System Planning & Project Appraisal Division Sewa Bhawan, R.K. Puram, New Delhi

SOUTHERN REGIONAL POWER COMMITTEE BANGALORE

(i) Establishment of 400kV Pooling Station at Fatehgarh (with a provision to upgrade at 765kV level)

Additional Agenda for 31 st Standing Committee Meeting of Power System Planning for Northern Region

CONFERENCE ON TRANSMISSION & DISTRIBUTON MR N C VENUGOPAL TRANSMISSION SECTOR GROWTH & CHALLENGES. DATE 2 ND NOVEMBER 2012

Central Electricity Authority System Planning & Project Appraisal Division Sewa Bhawan, R.K. Puram, New Delhi

KERALA STATE ELECTRICITY REGULATORY COMMISSION. NOTIFICATION Dated, Thiruvananthapuram 6 th August,2007

Report. the feasibility of

MINUTES OF THE 1 st MEETING OF THE PROTECTION SUB-COMMITTEE HELD ON 25 th JULY 2006.

Guidelines for Solar Grid Power Projects

4,1 '~ ~ ~ 1I1f lc/)~ul I Central Electricity Authority

FAX : Member Secretary Southern Regional Power Committee 29, Race Course Cross Road Bangalore FAX :

PRAGATI ENGINEERING COLLEGE

ANNEXURES. ANNEXURE-I SRLDC vide letter dated 18 th September The updated status of upcoming Inter Regional Scheme ANNEXURE-II

Distribution List Chief Engineer (SP & PA) Central Electricity Authority Sewa Bhawan, R.K.Puram, New Delhi FAX :

Indian Power System Framework

SYSTEM OCCURRENCE: Various system occurrences during the period were analysed. Details are as under:

Central Electricity Authority ftf~o "5TUTTID m~';jt ~ct l:f~en';f '5f<qTlf-I I -..:;.. "" Power System Planning & Appraisal Division=II

Central Electricity Authority System Planning & Project Appraisal Division Sewa Bhawan, R.K. Puram, New Delhi

Need Assessment Document (NAD) DDUGJY

RFP Corrigendum No. 01

R.S.USHA CHIEF ENGINEER/ PLANNING & RC. Encl: Report and detailed estimate. To The Chief Engineer/D/Madurai Region

MINUTES OF THE 47 th SLCF MEETING HELD ON

Transmission System Bottlenecks & Planning for Mumbai Metropolitan Region

The Electric Power System

ANNEXURE-XV. SRPC Secretariat letter dated ICTs at Kozhikode S/S. Updated status of upcoming inter regional scheme

Minutes of the 19 th meeting of the Standing committee on transmission system of Northern Region held at Amritsar on 01/10/05.

पत स च/ Address List

Wheeling charges, Banking charges & Cross Subsidy Surcharge for Solar Power Generators

-As per List enclosed- 27 th meeting of the Standing Committee on Power System Planning of

Bangladesh s Power Sector : At a Glance

भ र उत प द स त लन रप टर LOAD GENERATION BALANCE REPORT

CONTINGENCY ANALYSIS AND RANKING ON 400 KV KARNATAKA NETWORK BY USING MIPOWER

भ र त स र क र क न र य व द य त प ध क र ण C E N T R A L E L E C T R I C I T Y A U T H O R I T Y

Case No. 163 of In the matter of

SAUDAMINI, Plot No.2, Sector-29, Gurgaon, Haryana Powergrid Corporation of India Ltd., SAUDAMINI, Plot No.2, Sector-29, Gurgaon

Intra-State Availability Based Tariff (ABT)

Agenda of 11 th System Studies Meeting in NER

FINAL FACILITY STUDY. 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1. September 10, 2010

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

GOVERNMENT OF ANDHRA PRADESH ABSTRACT

PCDO. Jan Launched portion of Viaduct Deck Structure from S-180 (KATRA- BANIHAL SECTION) Udhampur-Srinagar-Baramulla Rail Link Project

¼ããÀ ¹ã㪠ã Ôãâ ãìêã ã ãäà¹ããñ Ã

No. 15/3/2018-Trans-Pt(1) Government of India Ministry of Power Shram Shakti Bhawan, Rafi Marg, New Delhi **** OFFICE MEMORANDUM

PRESENTATION ON STRATEGIC APPROACH TOWARDS WIND SOLAR HYBRID SYSTEMS (SWES) FOR REMOTE TELECOM SITES IN INDIA & CASE STUDY OF RAJASTHAN

दक ष ण त र क ष द य त सक ष क षत, ब गल र. Southern Regional Power Committee, Bangalore

Employees' Provident Fund Organisation, India Ministry of Labour & Employment, Government of India

Enhancing Grid Stability in India

UP Electricity Regulatory Commission Vidyut Niyamak Bhawan, Vibhuti Khand, Gomti Nagar, Lucknow. Public Notice

Before the. Case No. 106 of 2009

City of Palo Alto (ID # 6416) City Council Staff Report

P.O BOX 429, NUKU ALOFA, Tel: (676) Fax: (676)

स त ष क म र उप मह प रब धक (पररवहन व य प र एव प रण ल सम ह) Santosh Kumar Dy GM (TBSG) Ref: ID/TSG/RB/KF/03 Dtd. : 4 th August 2016

SOUTHERN REGIONAL POWER COMMITTEE BENGALURU

Central Electricity Authority व य त प रण ल य जन एव म य कन प रभ ग-II Power System Planning & Appraisal Division-II

Policy for Net-Metering based Renewable Energy Applications, Madhya Pradesh, DRAFT

¼ããÀ ¹ã㪠ã Ôãâ ãìêã ã ãäà¹ããñ Ã

Transmission Corporation of Telangana, Jawaharlal Nehru Technological University Hyderabad

Seabrook Substation Reliability Improvement Project

ESIA Study for 1,050MW Coal Fired Power Plant, Lamu County, Kenya Need for the Project. 3 Need for the project... 2

Renewable Regulatory Fund (RRF) Mechanism : -

Infrastructure Revitalization in India Power System Operation Corporation (POSOCO) New Delhi, India

FORTISBC INC. PRUDENCY REVIEW KETTLE VALLEY SUBSTATION EXHIBIT A2 5

LATEST DEVELOPMENTS IN NEPAL POWER SECTOR INCLUDING THE STATUS OF D-M 400 KV CBTL

Analysis of Indian electricity distribution systems for integration of high shares of rooftop PV By Joerg Gaebler, IGEN Solar, GIZ India

Procurement Plan. Eskom Holdings SOC Limited. Eskom Investment Support Project

Electricity Industry Code Minimum Service Standards & Guaranteed Service Levels Quarterly Report July September 2008

STATE LOAD DISPATCH CENTRES (SLDC)

Power Sector Trends: Focus on States

SOLAR PLANT PERFORMANCE IN INDIA

1.0 Revised procedure for allocation of Inter State Transmission Project(s) under Tariff Based Competitive Bidding (TBCB)

Western Power s list of exemptions from compliance from Technical Rules granted after 1 July 2007.

Mohammad Alauddin Deputy Secretary Power Division Ministry of Power, Energy & Mineral Resources Govt. of the People s Republic of Bangladesh

Engineers Ireland Site Visit 23 rd March 2010

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Maharashtra Electricity Regulatory Commission (Renewable Purchase Obligation, Its. Regulations, 2016 STATEMENT OF REASONS

A. Operational Issues relating to recent Disturbances in Gajuwaka Simhadri - Kalpaka corridor

SOUTHERN REGIONAL POWER COMMITTEE BENGALURU

Implementation Status & Results Bosnia and Herzegovina ROAD INFRASTRUCTURE AND SAFETY PROJECT (P100792)

Generation Connections Industry Workshop 2017

GC108: EU Code: Emergency & Restoration: Black start testing requirement

Solar Energy Corporation of India Limited New Delhi Expression of Interest for Setting up of Solar PV Manufacturing Capacities in India

System Status Briefing

In-House Paper on the implementation of Single Part Tariff in Power Distribution

Transcription:

भ रत सरक र GOVERNMENT OF INDIA व द य त म त र लय MINISTRY OF POWER क द र य व द य त प र व करण CENTRAL ELECTRICITY AUTHORITY दव ण त र य व द य त सवमवत SOUTHERN REGIONAL POWER COMMITTEE तकन क सम तत क छब ब सव एव द क ष वव स क सत त ईसव ब ठक क क र यस च AGENDA NOTES FOR 26 TH MEETING OF TCC & 27 TH MEETING OF SRPC ब गल र BENGALURU

CONTENTS 1. CONFIRMATION OF THE MINUTES OF 25 th MEETING OF TCC... 2 2. CONFIRMATION OF THE MINUTES OF 26 th MEETING OF SRPC... 2 3. UPCOMING TRANSMISSION SYSTEM... 2 4. TRANSMISSION LINES APPROVED IN 38 th MEETING OF SCPSPSR... 21 5. NEW PROJECTS OF NTPC, NLC, NPCIL, JOINT VENTURE& UMPP... 21 6. NEW PROJECTS OF STATE SECTOR & IPP... 26 7. PAYMENT OF WHEELING CHARGES... 27 8. RESERVE SHUT DOWN (RSD)... 27 9. EMERGENCY RESTORATION SYSTEM (ERS)... 28 10. PROGRESS OF BUS/LINE REACTORS TO BE COMMISSIONED IN SR... 29 11. IEGC RELATED ISSUES REQUIRING ATTENTION/ACTION... 31 12. REVIEW OF PERFORMANCE OF ULDC SCHEME... 39 13. TRIPPING DETAILS/ DETAILS OF PENDING REMEDIAL MEASURES DISCUSSED AND FINALIZED IN PCC... 40 14 S3 REGION TO BE FORMED BY BIFURCATING S2 AND ATC TO BE CALCULATED FOR S2-S3 REGION BY FOLLOWING THE N-1 CONDITION IN 400 kv UDUMALPET PALAKKAD D/C LINES... 40 15. ITEMS DISCUSSED IN THE MEETING OF COMMERCIAL SUB COMMITTEE... 41 16. REIMBURSEMENT OF SRPC EXPENDITURE... 41 A FOR INFORMATION OF TCC/ SRPC... 42 1. GRID OPERATION... 42 2. ACCOUNTING OF COASTAL ENERGEN INJECTION / DRAWAL... 45 3. INSTALLATION OF SEMs ON BOTH ENDS ( CHARGING CLEARENCE FOR NEW TRANSMISSION ELEMENTS).... 46 4. AMR IMPLEMENTATION IN SOUTHERN REGION... 47 B ANY OTHER ITEM WITH THE PERMISSION OF THE CHAIR... 47 C DATE & VENUE OF THE NEXT TCC / SRPC MEETING... 47 Agenda Notes for the 26 h Meeting of TCC & 27 th Meeting of SRPC 1 of 47

SOUTHERN REGIONAL POWER COMMITTEE BENGALURU AGENDA NOTES FOR THE 26 th MEETING OF TCC & 27 th MEETING OF SRPC TO BE HELD AT HYDERABAD ON 11 th & 12 th MAY 2015 1. CONFIRMATION OF THE MINUTES OF 25 th MEETING OF TCC The Minutes of the 25 th Meeting of Technical Coordination Committee of SRPC held on 19 th December 2014 at Vishakhapatnam may kindly be confirmed. 2. CONFIRMATION OF THE MINUTES OF 26 th MEETING OF SRPC The Minutes of the 26 th Meeting of Southern Regional Power Committee held on 20 th December 2014 at Vishakhapatnam may kindly be confirmed. 3. UPCOMING TRANSMISSION SYSTEM 3.1 First Meeting of the Task Force on issues pertaining to LGB and Transmission Constraints was conducted on 19 th March 2015 in SRPC, Bengaluru. Record Notes of the Meeting is available at http://www.srpc.kar.nic.in/website/2014/meetings/special/m1tfm19-3-15.pdf. In that Meeting, the following had been agreed: Data in respect of annual peak demand, ISTS drawl requirement etc. would be validated and feedback furnished to planners. Firmed up generation was only needed to be considered. Progress with regard to important project milestones was needed to be provided. Spatial load projections was to be forecasted for proper assessment of Intra-state and ISTS requirements. Intra-State network needed to be firmed up in coordination with CEA/CTU (STU needed to coordinate with Intra-State utilities also) 3.2 Pending transmission elements in WR and SR for proper utilization of 765 kv Raichur- Sholapur line (Out of planned 18 elements) Sl. No Name of Transmission Element 1 Sholapur-Pune 765 kv S/C Exe. Agency PGCIL Sch. CoD Oct.20 14 Expected date Remarks Commissioned on 02.03.2015 2 Pune 765/400 kv S/S PGCIL Oct. 2014 Mar-15 Civil work under progress Land acquisitioned delayed, Expected commissioning by March 2015, Civil works and erection activity in progress Agenda Notes for the 26 h Meeting of TCC & 27 th Meeting of SRPC 2 of 47

3 Gooty- Madhugiri 400 kv D/C 4 Madhugiri 400/220 kv S/S 5 Madhugiri- Yelahanka 400 kv D/C line 6. Vijayawada- Nellore 400 kv D/C PGCIL PGCIL PGCIL PGCIL June 2014 June 2014 June 2014 Nov. 2014 May-15 March 2015 June 2015 Substation is ready. Downstream network not available Severe RoW problem at Tumkur (30 Loc), Bangalore Rural (35 Loc) and Bangalore Urban (10 Loc). 400 kv Yelahanka s/s is ready. LILO point at Yelahanka would be completed by July 2015 RoW problem being faced at Krishna Dist. (49 Loc) & Guttur Dist (23 Loc). Alternative arrangement is being planned. 3.3 Status of various Associated Transmission Systems (ATS) of upcoming generators (i) Common System Associated with Costal Energen Private Ltd and Ind-Barath Power Ltd. (LTOA) Gen. Proj. in Tuticorin area Part A Transmission Elements LILO of both ckts of Tuticorin JV - Madurai 400 kv D/C line at Tuticorin Pooling Stn. (Q) 765 kv Pooling Station at Tuticorin (initially charged in 400 kv) Line Length (ckm) Imp. Agency Sch COD Ant COD Constraints/ Remarks 9 PGCIL Jul'14 Jan 15 Line commissioned on 03.01.2015 PGCIL Jul'14 Jan 15 Substation commissioned in Jan 15 (ii) Common System Associated with Costal Energen Private Ltd and Ind-Barath Power Ltd. (LTOA) Gen. Proj. in Tuticorin area Part - B. Transmission Elements Line Length (ckm) Implem enting Agency Sch COD Ant COD/ Act COD Constraints/ Remarks 765 kv D/C Tuticorin Pooling Station - Salem Pooling Station line (Dharmapuri) (initially charged at 400 kv) 735 PGCIL Dec'14 Dec. 15 Agenda Notes for the 26 h Meeting of TCC & 27 th Meeting of SRPC 3 of 47

765 kv S/C Salem Pooling Station (Dharmapuri) - Madhugiri Pooling Station line (initially charged at 400 kv) 765/400 kv Salem Pooling station (initially charged at 400 kv) Extn. at 765/400 kv Tuticorin Pooling Stn 244 PGCIL Dec'14 Jul 15 Severe ROW problems in Karnataka portion of the line. PGCIL Dec'14 June 15 Supply, civil works & erection under progress. PGCIL Dec'14 Mar 15 Supply & civil works under progress. Extn. at 400/220 KV Madhugiri Pooling Stn Extn. at 400/220 kv Salem Sub station PGCIL Dec'14 Mar 15 Award placed in Oct'11. Engg., supply & civil works under progress. Commissioning matching with completion of line PGCIL Dec'14 Mar 15 Award placed in Oct'11. Engg., Supply & civil works under progress. It was noted that entire ATS of Coastal Energen may be completed by December 2015. TN had enquired about any transmission constraints in respect of Coastal Energen generation. One unit of Coastal Energen is already under COD. SRLDC had informed that since NTPL units were ready to declare COD by March/April 2015, backing down at Coastal Energen would be required depending on availability of units at NTPL and network loading. (iii)common Transmission Scheme Associated with ISGS Projects in Nagapattinam/ Cuddalore area of Tamil Nadu - Part-A (a) Transmission Elements LILO of Neyveli - Trichy 400 kv S/C line at Nagapattinam Pooling Station Line Length (ckm) Imp.A gency Sch COD Ant COD 46 PGCIL Oct'14 Complet ed Constraints/ Remarks Commissioned 400 kv Nagapattinam Pooling Station (GIS) (provision 765/400 kv in future in the same Sw.Yd.) PGCIL Oct'14 Mar 15 Commissioned Agenda Notes for the 26 h Meeting of TCC & 27 th Meeting of SRPC 4 of 47

(iv) Transmission system associated with IPPs of Nagapattinam/Cuddalore Area Package A Transmission elements Nagapattinam Pooling Station- Salem New 765 kv D/c line Salem New - Maiduguri 765 kv S/c line. Line Length (ckm) Imp.Agency Ant. COD Constraints/ Remarks 211.73 Powergrid Nagapattina m- Madhugiri Mar 15 Expected by April 2016 234.46 Transmission Company Limited (PNMTCL) (A subsidiary of PGCIL) Expected June 2016. Severe RoW issues being faced in Karnataka section. (v) Transmission System Associated with Contingency plan for Evacuation of Power from IL&FS (2x600MW) Transmission Elements Line Length (ckm) Imp. Agency Sch COD Ant COD Constraints/ Remarks LILO of 2nd Ckt of Neyveli - Trichy 400 kv D/C line at Nagapattinam Pooling Stn. Strengthening of Neyveli TS -II to Neyveli TS-I expansion link with higher capacity conductor Extn. of 765/400 kv Pooling Stn. at Nagapattinam by 02 nos. bays for termination of 2nd Ckt LILO line 44 PGCIL Jul'15 Jul'15 Award placed in Aug 14 28 PGCIL Jul'15 Jul'15 Award placed in Aug 14 PGCIL Jul'15 Jul'15 Award placed. Engg., supply, civil works under progress. PGCIL had informed HTLS conductor had been received and thus requested for shutdown (30-45 days) of Neyveli TS-I Exp. Neyveli TS-II line for restringing it with HTLS conductor. NLC stated that line outage could be considered during the planned unit outages of NLC TS-I Expansion i.e. during October to December 2015. It was agreed that NLC and POWERGRID would discuss the matter further bilaterally. Agenda Notes for the 26 h Meeting of TCC & 27 th Meeting of SRPC 5 of 47

SRLDC had stated that 400 kv Madurai-Udumalpet was getting overloaded and would further be aggravated with generation at Coastal Energen, NTPL & also wind. Generation from these stations get pooled at Madurai and thus evacuation of this power beyond was essential. (vi) Evacuation of Power from HNPCL (1040 MW) Power Plant Transmission Elements Line Length (ckm)/ MVA cap. Implemen ting Agency Target Date Target date completi on Constraints/ Remarks 400 kv Twin moose D/C Line from M/s. HNPCL Switchyard - Proposed Kamavarapukota S/S (Lot-I, II & III) Lot - III 200 ckm (100 x 2) APTRANS CO Jul 15 Oct 15 Works awarded. Works under execution for Lot-I. AP informed that out of 730 tower foundation 130 foundation had been completed. 400 kv Twin moose D/C Line from proposed Kamavarapukota S/S - Vemagiri 400 kv S/S APTRANS CO Mar 16 Tendering process under progress. 400 kv Twin moose D/C Line from Proposed Kamavarapukota S/S - Proposed 400 kv Chinna Korukondi S/S 400 kv Twin moose D/C Line from Proposed Chinna Korukondi - Proposed 400 kv Suryapet S/S Suryapet S/S - Nandiwanaparthi S/S 400 kv Quad D/C Line 212 APTRANS CO 212 APTRANS CO/ TSTRANS CO 240 TSTRANS CO Sept. 15 Mar 16 40% of works completed. Works awarded in March 2014. Tower erection under progress. Mar 15 Jun 15 Works awarded in Sep- 13 and 115 Towers erection completed. Agenda Notes for the 26 h Meeting of TCC & 27 th Meeting of SRPC 6 of 47

400 kv Quad D/C Line from Nandiwanaparthi S/S - Shankarapally S/S 222 TSTRANS CO Mar 15 Jun 15 Works awarded in Sep- 13 and 58 Towers erection completed. Startup Power Line from M/s. HNPCL TPP to 400/220 kv Kalpakka SS (Supervised by APTRANSCO) 7 APTRANS CO Line Charged on 07.02.2014 Kamavarapukota Substation 2x315 APTRANS CO Mar 16 Mar 16 Works awarded. Suryapet Substation 400/230/132 2x315 TSTRANS CO Mar 15 Jun 15 Work awarded on 29.07.2013 and under progress 2 Nos. of 400 KV Bay Extensions at 400 KV Shankarapalli S/S TSTRANS CO Mar 15 Mar 15 Work under progress 2 Nos. of 400 KV Bay Extensions at existing 400/220 KV Kalpaka S/S of HNPCL APTRANS CO All works completed for 1 No. of 400 KV Bay on 07.02.2014 APTRANSCO had informed that 400 kv KV Kota 220 kv KV Kota and 400 kv KV Kota Vemagiri lines had been planned as downstream system and they were under tendering stage. It was noted that both the units of HNPCL were expected to commission by June 2015 but entire ATS would be commissioned by March 2016.400/220 kv K V Kota SS would be critical and was needed to be expedited. SRLDC had pointed out that maximum evacuation from Vemagiri complex including HNPCL would be restricted to 600 MW without complete ATS of HNPCL as decided in the SCC of SR. Agenda Notes for the 26 h Meeting of TCC & 27 th Meeting of SRPC 7 of 47

(vii) Krishnapatnam Power Transmission Scheme (Unit I : 05.02.2015 (COD); Unit II : June 2015) Transmission Elements Line Length (ckm) Imp. Agency Origin al Target Date Target date completio n Constraints/ Remarks Krishnapatnam TPS- Nellore 400 kv D/C Quad Line Krishnapatnam TPS - Bonapally 400 kv D/C Line Bonapally - Chittoor Quad 400 kv D/C Line 400kV Krishnapattanam- Chittoor APTRANS CO 179.842 APTRANS CO 195.616 APTRANS CO Commissioned. Line charged on 23.11.12. Works completed and line charged with LILO arrangement. Temporary arrangement. May 15 Out of 187 towers 166 towers had been completed. Works of around 21 Kms. were pending. SRLDC had stated that evacuation from Krishnapattanam JV station would be restricted to 800 MW until complete ATS was in place. (viii) Transmission system of KPTCL for evacuation of power from Yeramarus TPS (2x800 MW) Transmission elements Imp.Age ncy Line Length (ckm)/ MVA cap. Sch. COD Constraints/ Remarks Bellary 400 kv Pooling Station near BTPS KPTCL Work Awarded Gulbarga 400/220 kv substation 2x500 MVA. Yeramarus TPS - Gulbarga 400 kv D/C line with quad moose conductor 400 kv switching station at Chikkanayakanahalli (C.N Halli) near Loop in Loop Out (LILO) point on the Nelamangala Talaguppa 400 kv lines to Hassan. KPTCL 2x500 Land identified. KPTCL Survey completed. Tendering yet to be taken up KPTCL Land yet to be identified Agenda Notes for the 26 h Meeting of TCC & 27 th Meeting of SRPC 8 of 47

LILO of both the circuits of Nelamangala Talaguppa 400 kv lines to the proposed pooling station near CN Halli. Termination of 400 kv D/C line feeding 400/220 KV station at Hassan from Nelamangala Talaguppa line at CN Halli 400 kv pooling station. Yermarus TPS - Bellary Pooling Station 400 kv D/C line with quad moose conductor Bellary Pooling Station - C.N.Hally 400 kv D/C line with quad moose conductor Bellary Pooling Station - New Madhugiri (near Tumkur) 765/400 kv station, 400 kv D/C line with quad moose conductor Bellary TPS Bellary Pooling Station 400 kv D/C line with quad moose conductor De-link 400 kv S/C line running between RTPS- BTPS-JSW-Guttur with BTPS and JSW Bus so as to retain direct connectivity between RTPS and Guttur JSW TPS Bellary Pooling Station 400 kv D/C line with quad moose conductor KPTCL After CN Halli land identification, survey would be taken up. KPTCL After CN Halli land identification, survey would be taken up. KPTCL 300 Works have been awarded for 11 km section only. NIT for the remaining portion to be floated by Feb-15 KPTCL 360 After CN Halli land identification, survey would be taken up. KPTCL 380 Works Awarded and under progress. KPTCL 10 Survey work in progress. KPTCL Only after all other Transmission Elements under Stage I are commissioned KPTCL Only after all other Transmission Elements under Stage I are commissioned. KPTCL/JSW to discuss to take up this work as dedicated transmission line by the generator. Constraints in evacuation BTPS Unit-III and Yeramarus TPP had been discussed in 38 th SCPSPSR and it had been decided that joint studies including SRPC,SRLDC,PGCIL Agenda Notes for the 26 h Meeting of TCC & 27 th Meeting of SRPC 9 of 47

and CEA would be performed and the issue would be further discussed in the next SCPSPSR. 400 kv Hiriyur-Nelamangala lines would further get overloaded in absence of adequate downstream network in Madhugiri. Commissioning of 400 kv Bellary PS-CN Halli- Mysore line would relieve the loading on Hiriyur-Nelamangala line and hence the commissioning of this section should be taken up on priority Generation from BTPS, YTPS and JSWEL would get evacuated upto Madhugiri s/s. However, there is no adequate downstream network to evacuate this generation beyond Madhugiri. KPTCL stated that injections at Madhugiri s/s could be evacuated to Yelahanka s/s after commissioning of 400 kv Madhugiri-Yelahanka lines. It was pointed out that 400 kv Madhugiri-Yelahanka line was ISTS line and hence Karnataka should not lean on ISTS network. KPTCL was requested to expedite ATS of Yeramarus TPP, downstream system at Madhugiri as well as at Yelahanka s/s. KPTCL had stated that major generators in Karnataka were located on northern side (above Hiriyur) while loads are concentrated in South Karnataka. Yelahanka downstream network was planned with UG cable and works were awarded recently. It would take 18 months to complete the same. KPTCL had informed the downstream system from Madhugiri s/s as below: 220 kv Madhugiri Antharasana Halli D/C 400 kv Madhugiri s/s 220 kv Madhugiri s/s D/C Tenders for the above line had been placed on 18.03.2015 and it may take 18 months for completion. KPTCL informed the downstream network from Yelahanka s/s as below: 400/220 kv Yelahanka s/s - 220 kv Yelahanka s/s D/C 400/220 kv Yelahanka s/s 220 kv BIAL s/s D/C (ix) Transmission System required for evacuation of power from Kudgi TPS (3x800 MW in Phase-I) of NTPC Limited Transmission elements Imp. Agency Schedule d COD Revised Target Date Constraints/ Remarks Kudgi TPS Narendra (new) 2xD/C Line M/s Kudgi Transmission Limited (L&T Feb-15 June-15 Survey activity is stopped by villagers of Honnudike and Hobli Gulur village falling Agenda Notes for the 26 h Meeting of TCC & 27 th Meeting of SRPC 10 of 47

Infrastructur e Development Projects Ltd.) under Tumkur (Taluk & District) (Effected span: Approx. 2 KMs.). Matter is brought to the notice of District Administration. Narendra(new)- Madhugiri 765 kv D/C Line Madhugiri -Bidadi 400 kv D/C (quad) Line Dec - 15 June- 16 The villagers are not allowing for any construction work at the respective locations and asking for huge compensation. Matter is brought to the notice of District Administration. These locations are nearer to 400/220 kv POWERGRID Bidadi substation. Being terminating point, no alternatives available for rerouting the line. Dec - 15 June- 16 It was noted that Unit-I of Kudgi TPS was expected to be commissioned by March 2016. PGCIL informed that SR-II portion of the line 765 kv Narendra (New Kudgi) Kolhapur line would be completed by May/June 2015. KPTCL had informed that their 220 kv lines for startup power would be ready by September 2015. It was noted that 400 kv Kudigi TPS- Narendra (New) D/C lines could be expedited, which would ensure start up power. 3.4 Status of upcoming links having impact on S1-S2 Sl. No. Transmission Element 1 400 kv Somanahalli- New Salem Schedule Expected Commissioning Date Remarks Jun-15 Jul-15 The works under Tamil Nadu portion had been completed and severe RoW problems for 35 Kms. stretch of Karnataka portion. 45 days shutdown for Hosur- Salem line would be required for stringing of this line. PGCIL would coordinate with Tamil Nadu. Agenda Notes for the 26 h Meeting of TCC & 27 th Meeting of SRPC 11 of 47

400 kv Mettur- 2 Thiruvalam 3 400 kv Mysore- Kozhikode 4 400 kv Mangalore (UPCL) -Kasargode- Kozhikode D/C Line Permission from Hubli Railway Jan. 2015 April 2015 division had been received May. 2015 June 2015 Held up due to ROW issue. Work started in October 2014 with Admn. Support as directed by court. PGCIL informed works under progress. Stringing works also started. In 26 th SRPC meeting, following were noted: Approved by Standing Committee & SRPC. KPTCL stated that they had furnished load flow studies and their comments keeping in view of 2000 MW HVDC link at Madakathara and hence the necessity of the line to be reexamined. KSEB, CTU & SRLDC stated that the line was absolutely essential. In the 38 th Meeting of SCPSPSR (07.03.2015) it was decided that implementation of this line could be initiated after considering use of Karnataka ESCOMS, if communicated within a month. In the 106 th meeting of OCC held on 10 th April 2015 it was noted that ICTs at Kozhikode S/S of PGCIL have not been commissioned. SRPC vide letter dated 15.04.2015 (Annexure-I) had requested PGCIL ensure that the Mysore - Kozhikode lines and the ICTs at Kozhikode come up simultaneously to avoid any evacuation constrains. 3.5 Critical Intra-regional transmission elements Sl. No. Transmission Element Expected CoD Remarks 1 765 kv Salem- Madhugiri June 2015 Severe RoW problem near Madhugiri. 2 400 kv Edamon-Kochi Govt. of Kerala issued G.O dated 19.08.2014, recommending additional compensation KSEB informed that Kerala Govt. had agreed for the compensation of 5 times market value. Still talks were going on. Agenda Notes for the 26 h Meeting of TCC & 27 th Meeting of SRPC 12 of 47

3.6 Status of following upcoming inter-regional transmission schemes under various stages are furnished at Annexure - II. a) 765 kv Narendra Kolhapur D/C line, b) 765 kv Wardha Nizamabad D/C line, c) WR-SR 6000 MW HVDC Bipole Link [Raigarh (Chhatisgarh) -Pugalur/Trichur (TN/KER)], d) Angul - Srikakulam PS 765 kv D/C line, e) Additional inter-regional AC link for import into Southern Region, i.e., Warora- Warangal - Hyderabad- Kurnool 765 kv link f) System strengthening within SR for transmitting power beyond Vemagiri 3.7 Transmission line/elements constraints being observed in real time by SRLDC are given below. The over loadings of various transmission lines and ICTs in pictorial form are at Annexure-III Constraint Overloading of 400 kv Kolar-Hosur D/C line Overloading of 400kV Hiriyur-Nelamangala DC line: Overloading of 400kV Udumalpet-Palakkad DC line: Overloading of 400kV Jindal-BTPS SC Line: Remarks S2 Bid area drawal limited by N-1 of these lines. Even after commissioning of Mettur-Tiruvalam & Mysore- Kozhikode lines the limiting constraints could be there on these lines. With Full generation at Jindal and BTPS, and wind generation high, the flow on 400kV Hiriyur-Nelamangala DC line continuously near to 550MW and may worsen if generation at UPCL is low. 400kV Gooty-Madhugiri-Yelahanka DC line would relieve constraint to some extent Yeramarus Evacuation system, especially CN Halli corridor may relieve the constraint 220 kv DC Hiriyur-Gbnur commissioned recently- Relief of about 30-40 MW on each line obtained Kerala drawl is mainly through 400kV Udumalpet-Palakkad DC line. Kerala drawl capability would be limited by this line. Drawal capability would increase with 400 kv D/C Mysore- Kozhikode line Overloading of these lines would be relieved only with the commissioning of Mysore-Kozhikode line. With the full generation at Jindal, this line is getting loaded beyond 650 MW. Other evacuation paths are 400kV Jindal-Guttur and Two ICTs. But at 220 kv side also generation is available. Yeramarus system may relieve the constraint Agenda Notes for the 26 h Meeting of TCC & 27 th Meeting of SRPC 13 of 47

Overloading of Gazuwaka ICTs (2 x 315 MVA) Overloading of Nellore ICTs (2 x 315 MVA) Overloading of Vemagiri ICTs (2 x 315 MVA) Overloading of Somanahalli ICTs (2 x 500 MVA) It was noted that there was some space constraint for augmentation at Gazuwaka s/s. It was observed that loads at Nellore had increased drastically in recent times. AP informed that 220 kv Nellore-Sullurpet D/C line had been charged at one end and other end bay works were pending. In the 38 th Meeting of SCPSPSR (07.03.2015) reorientation of Nellore Vijayawada 400kV D/c line was agreed. It was observed that N-1 violation had been observed up to 60% of the time in the month of October 2014. AP was requested to coordinate with CTU in order to curtail overloading. Frequent N-1 violation were being observed. Redistribution/ reconfiguration of 220 kv transmission lines around these substations is required. In the 26 th meeting of SRPC the following had been noted: KPTCL had informed that comprehensive plan for Bengaluru (7,500 MW) has been envisaged and had been approved by the Board. Presently the load met was about 2,700 MW out of 5,600 MVA capacity. About Rs.1,100 Crore had been earmarked for the strengthening works. Tender had been finalized for strengthening Somanahalli - Peenya section and they were planning to complete it within one year. Overloading of Mysore ICTs (2 x 315 MVA) Overloading of Kalvinthapattu ICTs (2 x 315 MVA) & Pugalur ICTs (2 x 315 MVA) It was observed that N-1 violation had been observed up to 35% of the time in the month of December 2014. PGCIL informed that augmentation works had been awarded. It was emphasized the need for strengthening of downstream network. States were requested to plan for strengthening of downstream network. In the 26 th meeting of SRPC, PGCIL had informed that ICTs at Kalvinthapattu, Mysore, Pugalur, Trichy & Somanahalli were expected by 2017 (award placed during September 2014). Agenda Notes for the 26 h Meeting of TCC & 27 th Meeting of SRPC 14 of 47

3.8 SRLDC had also presented the following transmission system constraints in the state network wherein states were requested to update the system planned by the state Constraint 220 kv Bangalore Metro Network Overloading of 220 kv Shoolagiri-Hosur (TN) Yerandahalli-Somanahalli SC line 220 kv Sharavathy-Shimoga lines (4 Nos.) and 220 kv Sharavathy Talaguppa D/C Remarks 220 kv Metro Networks (Bangalore Urban area) are now radialized to prevent overloading of lines. The radialization decreases the reliability of supply. KPTCL to update Planned 220kV Network - to meet the future demands of Bangalore city and effective utilization of additional Transformer capacity approved Somanahalli, Yerrandahalli and Hosur are Industrial areas. 220 kv Yerrandahalli is connected with Hosur (TN) and Somanahalli. Normally, 220 kv Yerrandahalli split and part of load is fed from Hosur (TN) as the entire load cannot be met from either side (Somanahalli or Hosur). The line loading on this line also causes high flows on Shoolagiri-Hosur 230 kv S/C line. KPTCL had informed that they were planning alternate arrangements for Yerrandahally which was likely to be in place by July 2015. 400 kv Mylasandra SS had been planned as part of alternate arrangement. Contract had also been awarded however there were some disputes in land acquisition. Another 66 kv line had also been planned. With commissioning of Mylasandra S/S, loading on Somanahalli - Hosur would get reduced. 66 kv cable laying works between Velankeni- Naganathapuram were under progress and about to complete. Works on 66 kv Nagnathpuram - Electronic city (OH line) D/C, Sarjapura-Atibele, Sarjapur - Chandapura & Sarjapur - Bommasandra were also under progress. SRLDC stated that even if alternate arrangement was made by KPTCL, only limited relief would be obtained at Shoolagiri. The intra state system at Hosur/ Shoolagiri was needed to be strengthened by TANTRANSCO. TANTRANSCO informed that approval had been accorded for 2nd circuit of Hosur-Shoolagiri and Uddanapalli (near Hosur) SS.Contract and civil works had been awarded for Gurubarapalli S/S near Shoolagiri. With full generation of Sharavathy (>900 MW) there is no N- 1 reliability on 220 kv Sharavathy-Shimoga lines (4 Nos. >150 MW each) and 220 kv Sharavathy-Talaguppa D/C (>180 MW each). With the commissioning of rearrangement at Sharavathy-Talaguppa, the constraint on 220 kv Sharavathy-Talaguppa D/C would be solved to a certain extent. Agenda Notes for the 26 h Meeting of TCC & 27 th Meeting of SRPC 15 of 47

SRLDC enquired the status of rearrangement of 220 kv Sharavathy-Shimoga line which was proposed earlier. KPTCL informed that one circuit of Sharavathy-Shimoga would be converted to Sharavathy-Talaguppa. With this rearrangement there would be 3 lines to Shimoga and 3 lines to Talaguppa from Sharavathy. Constraints in Coastal and South AP Constraints in Chennai 230 kv System Constraints in 230 kv Evacuation lines of MTPS and Kundah complex Northern Kerala System Southern and coastal AP loads have increased and with increased generation at Rayalaseema TPP (5 units on bar at present, 220 MW each and 5 th Unit has been added without augmenting the evacuation which was designed for 2 units of 220 MW) the loadings on the following 220 kv lines are of concern, 220 kv Chinakampalli-Renigunta, 220 kv Chinakampalli-Rajampet, 220 kv Chinakampalli-Kalkiri SC line, 220 kv RYTPP Chinakampalli D/C line, 220 kv Tadikonda-Ongole, 220 kv VTS-Podili SC line, 220 kv VTS- Narsaraopet SC SRLDC pointed out that 220 kv Rayalseema TPS- Chinakampalli line were severely getting overloaded. AP informed that 400 kv Rayalseema TPS - Muddanur was expected by May/June 2015. 400 kv Kalkiri S/S was still under estimation stage. It was noted that as Rayalseema TPS Stage-IV was expected during 2015-16 the constraint would further be aggravated without the proper evacuation scheme of Rayalseema TPS. Presently Chennai area 230 kv network is heavily loaded. 230 kv Almatty-Manali DC line, 230 kv Manali-Koratur, 230 kv Kalavinthapattu S.P.Koil, 230 kv Kalavindapattu-Sruseri, 230 kv NCTPS-ETPS line are severely loaded. TN was requested to update the planned 230 kv network for evacuation of Chennai generators. 230 kv Kundah PH4-Thudialur line, 230 kv MTPS-III Gobi line, 230 kv MTPS-Ingur line and 230 kv Pugalur 4 Mywadi line. N-1 violation is frequently observed for MTPS-Gobi line. TN was requested to update the strengthening schemes planned for MTPS and Kundah complex. TN informed MTPS-Arasur and MTPS-Tingalur had commissioned. At present the North Kerala loads are largely fed from 400/220 kv Madakathara, 400/220 kv Palakkad and through 220 kv Kadakola-Kaniyampeta link which is feeding loads of Kaniyampeta, Vadakara and Thali paramba through split bus at Areakode and Kanhirode. The transmission line feeding to these stations are already highly stressed. Agenda Notes for the 26 h Meeting of TCC & 27 th Meeting of SRPC 16 of 47

Stage-1 Wind evacuation system of TNEB : 400 kv Kanarapatti s/s, 400 kv Kayathar s/s, 400 kv Tirunelveli-Kanarpatti- Kayathar DC line, 400 kv Kayathar-Karaikudi-Pugalur DC line Strengthening of Hyderabad downstream system Voltages had been very low during peak load conditions. KSEB informed they had installed 1000 MVAR capacitor to contain low voltages. SRLDC pointed out more reactive power management is required in the North Kerala area to contain low voltages. Palakkad and Trichur areas were facing severe low voltages during peak load conditions. Kerala was requested to expedite the plan to relieve the constraints. In the 26 th Meeting of SRPC the following had been noted: TANTRANSCO had informed that Kanarpatty S/S would be commissioned by next year, while Kayathar S/S had been commissioned. The situation had eased to some extent with the commissioning of Kayathar S/S. Besides substantial wind presence, 2,000 MW of solar project were also coming up in the state. Hence, as a comprehensive measure, network strengthening at 400 kv and 230 kv was planned. Under kfw scheme, various 400 kv and 230 kv network strengthening schemes were under execution. 15 number of capacitor bank had also been planned to be installed shortly to address under voltage issue. SRLDC had pointed out that since wind generation had come down the situation had presently eased. With wind generation picking up from May 2015 onwards, there could be evacuation constraints coupled with low voltages. It was also suggested that TN may kindly furnish full details of the schemes along with schedule of commissioning dates. TANTRANSCO agreed to furnish the same. Congestion on 400/230 kv Tirunelveli ICTs. 230 kv Kayathar-Tirunelveli, 230 kv Udayathur-Tirunelveli, 230 kv Veerannam-Tirunelveli etc. Stage-1 Wind evacuation was planned when Wind installed capacity was 4,000 MW Present wind installed capacity is about 7,300 MW 230 kv Line flows are very high and voltages are very low during high wind condition. TN was requested to update the status of the Transmission system planned. In the 26 th meeting of SRPC, TSTRANSCO had agreed to furnish the details. Agenda Notes for the 26 h Meeting of TCC & 27 th Meeting of SRPC 17 of 47

3.9 The low voltage nodes in the Southern Region are given below. States were requested to restrict MVAR drawal & also install UV relays in those areas: S.No. Nodes Season/antecedent conditions 1 400 KV Somanahalli s/s During peak load conditions 2 400 kv Nelamangala s/s During peak load conditions 3. 400 kv Udumalpet s/s During peak load conditions and high wind period 4 400 kv Salem s/s During peak load conditions and high wind period 5 400 kv Palakkad s/s During peak load conditions 6 400 kv Trichur s/s During peak load conditions SRLDC pointed out that more reactive management is required in the North Kerala areas. In Kerala and Tamil Nadu overloading of 230 kv lines is one of the causes for under voltage problems. Without adequate reactive power management the ATC may have to be restricted. SRLDC had enquired whether RGCCP Kayamkulam could run as synchronous condensers which would help improve voltages. KSEB had been requested to interact with NTPC on this matter. In the OCC meetings it was noted that the OLTC for Madakatara ICTs was not functional. SRLDC had expressed concern and had requested KSEB to expedite the works. 3.10 SRLDC had presented the following high voltage nodes in the Southern Region and requested to expedite the commissioning of reactors : S.No. Nodes Season/antecedent conditions 1 400 KV Vijayawada s/s Whole year 2 400 kv Vemagiri s/s Whole year 3. 400 kv Gooty s/s 4 400 kv Kurnool s/s Monsoon period and off-peak period 5 400 kv Srisailam s/s 6 400 kv Kaiga s/s Whole year 7 400 kv Guttur s/s Whole year 8 400 kv Narendra s/s Whole year 9 400 kv Tirunelveli s/s 10 400 kv Kudankulam s/s 11 400 kv Sriperumbudur s/s 12 400 kv Raichur s/s During off-peak 13 400 kv Kurnool s/s 14 400 kv Nellore s/s Agenda Notes for the 26 h Meeting of TCC & 27 th Meeting of SRPC 18 of 47

KPTCL had informed that line reactor at Guttur and bus reactors at Hoody, Nelamangala & Talaguppa would be commissioned by June 2015. KPCL had informed that Raichur bus reactors would be commissioned by June 2015. NPCIL had informed they were moving ahead with the 2 x 125 MVAR reactors at Kaiga as agreed in the Standing Committee. APTRANSCO had informed that 80 MVAR reactor at Vemagiri was commissioned on 5 th March 2015. Bus reactor Guttur was commissioned on 23 rd March 2015 by KPTCL All utilities were requested to kindly expedite commissioning of reactors before onset of the monsoon. 3.11 SRLDC presentation on the planned transmission system ISTS and important corridors in 2016-17 which is at Annexure-IV. 3.12 SRLDC presentation on the envisaged transformation capacity by 2016-17 in various states is available at Annexure-V. All states are requested to plan the downstream network matching to planned transformation capacity and furnish the details to SRPC/SRLDC. 3.13 All the states had been requested to furnish the feedback/details on the above all issues within a period of one month. The details include transmission system planned, LGBR, ISTS requirement, detailed status of upcoming generation projects (state & IPPs), details regarding spatial load growth etc. Summary All the utilities were requested to kindly appraise their Management of the constraints being faced and also likely to be faced. Concrete action plan needed to be finalized and implemented. Some of the constraints were of emergent nature and thus fast track action was needed to be taken. All the concerned utilities would furnish the updated information for enabling status update to SRPC/TCC. Wherever downstream network is overloaded, measures to relieve the congestion needs to be taken. Wherever augmentation of capacity was planned, downstream network also needed to be planned. Planning aspects needed to be taken up with CEA/CTU. Load Generation Balance Assessment Internal Generation Intra-State IPPs Agenda Notes for the 26 h Meeting of TCC & 27 th Meeting of SRPC 19 of 47

ISTS Requirement Import Requirements LGB to assessed for Each Year next five year Subsequently for each fifth year Peak & Off peak conditions For different seasons For coordinated development process aiming at perspective optimization in meeting the growth targets, it would be appropriate that the State Transmission Utilities prepare their State Electricity Plans taking advantage of development plans for regional grid system and focusing on the specific requirements of the concerned State. To ensure that the planned transmission network gets implemented as per the schedule, the issues related to ROW, forest clearance and various other clearances would need to be addressed with the appropriate authority. States should come up with evacuation for its internal generators and not lean on ISTS. 3.14 400 kv Trichur-Kozhikode line (Madakkathara- Areakode) The following had been noted till 26 th Meeting of SRPC: KSEB had stated that this line had already been approved as Regional System Strengthening Scheme. North Kerala would benefit since 400 kv supply could be availed either from Udumalpet or from Mysore for all the 400 kv substations in Kerala. Multi circuit & multi-level circuit was their requirement for surrender of corridor. PGCIL had sought utilization of existing 220 kv Madakkathara- Malaparamba-Areakode S/C feeder. There was no possibility of surrender of RoW of KSEB line presently since energy security of Malabar region was involved. Line works could be taken up only after commissioning of the 400 kv Mysore-Kozhikode line. PGCIL had been requested to initiate the process so that construction could commence immediately after 400 kv Mysore-Kozhikode line was commissioned. 3.15 Closing of Upper Sileru-Balimela Line 3.15.1 In the 26 th meeting of SRPC the following had been noted: It had earlier been agreed that the Upper Sileru- Balimela Line be closed again on an experimental basis. Apprehensions of AP would be addressed including those relating to quick exchange of codes. Line was needed to be closed at the earliest and that the matter was also being reviewed by higher bodies. 3.15.2 Subsequently it was noted in the 105 th OCC Meeting (10.03.2015) that from 8 th January 2015 the line had been restored and idle charged from Upper Sileru end.. A Meeting had also been conducted in MoP on this issue. Agenda Notes for the 26 h Meeting of TCC & 27 th Meeting of SRPC 20 of 47

3.16 Utilization of Jeypore - Gazuwaka link to its full capacity i.e 1000 MW 3.16.1 The issue regarding Utilization of Jeypore Gazuwaka link to its full capacity of 1,000 MW was earlier raised. Subsequently in the OCC meeting it had been noted that on account of issues of low voltage at Jeypore end and also upstream line loadings, at present ATC allowed on Jeypore (ER)-Gazuwaka (SR) HVDC link (rated capacity 1000 MW) was of the order of around 700 MW. 3.16.2 SRPC vide letter dated 12.02.2015 (Annexure-VI) had requested CTU, PGCIL that this issue be examined and SRPC be informed accordingly. Reply dated 11 th March 2015 of CTU in this regard is furnished at (Annexure - VII) 4. TRANSMISSION LINES APPROVED IN 38 th MEETING OF SCPSPSR 4.1 The 38 th Meeting of Standing Committee on Power System Planning of Southern Region (SCPSPSR) was held on 7 th March 2015. The Minutes of the Meeting is enclosed as (Annexure-VIII) 4.2 Modifications in the scope of Raigarh Pugalur Kerala 6000 MW HVDC Transmission System: In the meeting PGCIL had proposed modifications in the scope of HVDC terminals at Pugalur and NorthTrichur in addition to the set of 6000 MW terminals at Raigarh and Pugalur. Also the Pugalur N Trichur terminals had been proposed to be built with VSC based technology instead of the earlier conventional HVDC technology. In this regard, a Joint Meeting of Standing Committee of SR and SR was conducted on 20 th April 2015 at New Delhi. 5. NEW PROJECTS OF NTPC, NLC, NPCIL, JOINT VENTURE& UMPP 5.1 NTPC- Kudigi TPS Stage-I (3x800 MW) In the 26 th Meeting of SRPC, the following had been noted: NTPC had informed that Unit-I synchronization was planned for February 2016 while CoD was expected by April 2016. CoD of Unit II was expected subsequently after 6 months. CTU had informed that AP DISCOMs (undivided) were having share of 418 MW. After reorganization, revised application for LTA was needed to be furnished by NTPC/AP /Telangana. TSTRANSCO had informed that sharing percentage as per the AP Reorganization Act 2014 holds good for any project under construction also. They would ensure the needful in coordination with NTPC. Director (Grid & Tr), APTRANSCO had stated that any sharing would need to be carried out as per the Reorganization Act 2014. Agenda Notes for the 26 h Meeting of TCC & 27 th Meeting of SRPC 21 of 47

5.2 NLC-Neyveli TS-II Expansion (2x 250 MW) 5.2.1 In the 26 th Meeting of SRPC held on 20 th December 2014, NLC had informed that bulk of the issues relating to Heat Exchanger and Refractory works had been resolved. CoD of Unit I was expected by first week of January 2015. Unit II was also in advanced stage of commissioning and CoD of the unit was also expected by end January 2015. 5.2.2 In the 27 th Meeting of Commercial Sub Committee of SRPC held on 17 th March 2015 NLC had informed that CoD of both the Units would be by March 2015. 5.2.3 Subsequently, CERC wide order dated 01.04.2015 had allowed extension of time for injection of infirm power into the grid for the commissioning tests including full load test of Unit-I for a further period up to 30.6.2015 or actual date of commercial operation, whichever is earlier. 5.2.4 CoD of Unit- II of TPS II Expansion was declared with effect from 22 nd April 2015. 5.3 NLC - New Thermal Power Project (2x 500 MW) at Neyveli The following had been noted in the 26 th Meeting of SRPC: CoD of Unit-I & Unit II was expected by October 2017 & April 2018 respectively. 5.4 NPCIL-Kudankulam Nuclear Power Project (KKNPP) Stage-I (2x1000 MW) 5.4.1 The following had been noted in the 26 th Meeting of SRPC: Unit- I was running at 1,000 MW and CoD was expected before 22 nd January 2015. Unit II was planned to be critical by end April 2015 while synchronisation was planned by July 2015. 5.4.2 Subsequently Unit-I had been put on Commercial Operation w.e.f 0000 Hrs of 31.12.2014. 5.4.3 A Special Meeting with KKNPP/NPCIL, SRLDC & SRPC Secretariat was held in the Conference Hall of SRPC on 07 th April 2015 to discuss the operational and accounting issues in respect of KKNPP Units. The Record Notes of the Meeting is available at www.srpc.kar.nic.in/website/2015/meetings/special/kknpp-mtg-07-04-15.pdf.in that Meeting, the following was decided in respect of scheduling and accounting of energy exchanges by both the Units of KKNPP: Till commercial operation of Unit-II, the energy drawn for common station auxiliary CSAT would be accounted to Unit-I. With both Units under commercial operation,csat drawal would be shared in 50:50 ratio by Unit I & II. Agenda Notes for the 26 h Meeting of TCC & 27 th Meeting of SRPC 22 of 47

Unit-I and Unit-II energy exchanges would be computed based on SEMs at outgoing feeders, GT-1, GT-2, RAT-1, RAT-2 and CSAT. Infirm power injection by Unit-II would be accounted in line with the methodology followed during infirm power injection by Unit-I. As in the case of Unit-I, exemption for scheduling infirm power for Unit-II also needs to be obtained appropriately. Scheduling of infirm power injection by Unit-II would commence after stabilized operation of the unit (after achieving 200-300 MW stabilized generation). The infirm power injected prior to scheduling would be accounted post-facto based on the share allocation ratio of beneficiaries of Unit-II. After commercial operation of both units, the scheduling and accounting would be carried out separately (unit wise). When both the units under commercial operation, the energy accounting would be based on the outgoing feeders. The energy exchanges based on the SEMs on the outgoing feeders would be apportioned based on the SEM readings of GT-1, RAT-1 & 50% of CSAT for Unit-I and GT-2, RAT-2 & 50% of CSAT for Unit-II. 5.5 BHAVINI- Kalpakkam PFBR (500 MW) In the 26 th Meeting of Commercial Sub-Committee of SRPC held on 21 st November 2014, BHAVINI had informed that the unit would be commissioned during March 2015. 5.6 NLC Tamil Nadu Power Limited (NTPL - JV Company of NLC & TANGEDCO) at Tuticorin (2x500 MW) 5.6.1 The following had been noted in the 26 th Meeting of SRPC: NLC had informed that they had received Consent to Operate pending forest clearance. Synchronization of Unit-I was planned during January 2015 while CoD was scheduled by February 2015. CoD of Unit II was scheduled by March 2015. 5.6.2 A Meeting with NTPL, TANTRANSCO, SRTS-II, SRLDC & SRPC Secretariat was held on 20 th April 2015 to discuss the metering arrangements and accounting issues in respect of NTPL Units. The following had been noted in this Meeting: NTPL informed that Unit-I would be declared on commercial operation within ten days and Unit-II by end of May 2015. Till commercial operation of Unit-I, infirm power injection of both the units would be carried out as a whole of the station. Computation would be based on SEMs on outgoing feeders on 400kV &230kV side. Agenda Notes for the 26 h Meeting of TCC & 27 th Meeting of SRPC 23 of 47

After Commercial operation of Unit-I, Unit-I &Unit-II energy exchanges would be computed by apportioning the sum of the SEMs at outgoing 400kV feeders, 230 kv feeders (after charging of LILO) in proportion to the SEMs at HV side of GT-1& GT-2. Stand by SEMs at LV side of GTs would be provided within 15 days. Providing of Standby SEMs at LV side of GTs should not be insisted by SRLDC for commercial operation of Unit-I. SRLDC expressed that in the event of fuse failure on HV side of GT, energy apportioning could not be carried out. The SEMs at NTPL on the 230kV feeders would be treated as drawal points of Tamil Nadu. The methodology for accounting of drawal of energy during shutdown condition of the station through 400 kv feeders as well as 230 kv feeders would be in line with the approved methodology being adopted in respect of other ISGS (CGS) operating in SR. TANTRANSCO stated the decision in this regard needed to be taken by their management. They would appraise the methodology being followed in SR to their management. 5.7 Krishnapattanam UMPP (6x660 MW) In the 26 th Meeting of SRPC, APTRANSCO had informed that a Meeting with Developer and Procurers was conducted on 21 st August 2014. A Consultant had been appointed to look into commercial, financial and legal issues. Report of the Consultant was expected within one month time which would be shared with other Procurers. 5.8 Cheyyur UMPP (4000 MW) 5.8.1 The following had been noted in the 26 th Meeting of SRPC: TANTRANSCO had informed that Request for Qualification (RfQ) document was opened on 20.11.2013. Request for Proposal (RfP) documents were scheduled to be opened on 22.12.2014. The 1 st Unit would expected to be commissioned in 42 months from zero date (2018-19) and the subsequent units would be commissioned at the interval of six months. 5.8.2 As per the Minutes of 38 th Meeting of SCPSPSR, M/s Costal Tamil Nadu Power Ltd. (CTNPL) a SPV of PFC had applied for connectivity and LTA to CTU. The beneficiaries of the project are Southern Region-3,100 MW ( Tamil Nadu -1,600 MW, Karnataka 800 MW, Andhra Pradesh 400 MW & Kerala 400 MW), Western Region 400 MW (Maharashtra) and Northern Region 500 MW ( Uttar Pradesh 300 MW & Punjab 200 MW). Agenda Notes for the 26 h Meeting of TCC & 27 th Meeting of SRPC 24 of 47

5.9 Schedule of synchronizing/commissioning of the new projects of NTPC, NLC, NPCIL, BHAVINI, and Joint Venture & UMPP is furnished below: Station Unit Installed Capacity MW Scheduled date of synchronizing / commissioning Remarks NTPC Kayamkulam I, II, III 1050/ 1950 12 th Plan Gas supply by 2014. Kerala requested for 500 MW. TN & Puducherry would consider after knowing the tentative tariff. AP & KAR DISCOMs were not willing to procure the power. Kudgi Stage-I TPS I,I, III 3x800= 2400 Unit-I : Synchronization by March 2016 Unit-II : :Synchronization by October 2016 NTPC informed that they had requested KPTCL for startup power in August 2014. KPTCL informed that the works were under progress and there had been RoW issues. Expected date of completion was August 2015. NLC Neyveli-II Expn. I 250 CoD by June 2015 Injection of infirm power allowed up to 30.06.2015 II 250 CoD by May 2015 Startup power estimate furnished to SRLDC. New Thermal I 500 October 2017 Power Project II 500 April 2018 Sirkali TPP NPCIL Kudankulam Stage-I BHAVINI I, II, III 3x660 From GoI approval Unit I 52 months Unit II 58 months Unit-III 64 months PPA has been signed. Fuel imported coal. Approval of Feasibility Report was awaited from NLC Board. I 1000 CoD 31.12.2014 II 1000 Synchronization by NPCIL informed that fuel Aug./ Sep. 2015 loading would be done in June 2015 Kalpakkam (PFBR) I 500 September 2015 Agenda Notes for the 26 h Meeting of TCC & 27 th Meeting of SRPC 25 of 47

NTPL (JV Company of NLC & TANGEDCO) Tuticorin I 500 Original schedule: 40 months after LOA. LOA signed on 28.01.2009 Anticipated schedule: by April 2015 II 500 Original schedule: 45 months after LOA. LOA signed on 28.01.2009 Anticipated schedule: by May 2015 UMPP Krishnapattanam 3960 (6x660) Cheyyur 4000 The project is expected to be commissioned progressively from March 2019-2021 Achieved full load on 10 th March 2015 at 1748 hrs. Synchronized for the first time at 09:27 hrs on 09.04.2015. The developer had stopped the works at site and the project may get delayed. Meeting of Developer & Procurers was held on 21.08.2014. Consultant report was awaited. Site finalized during meeting of CMs held on 04.08.08. RfQ had been issued and project developer (M/s Coastal Tamil Nadu Power Ltd. which is SPV of PFC) had applied for LTA to CTU. RfP would be opened on 22.12.2014. 6. NEW PROJECTS OF STATE SECTOR & IPP 6.1 Updated status of new projects of State sector & IPPs is furnished below : Sl Name of project Located Owner Capacity Commissioning Schedule /Remarks No. in in MW 1 Krishnapattnam JV AP State 1600 U-I: COD declared on 05.02.2015 U-II: COD by June 2015 2 Rayalaseema TPS AP State 600 2015-16 ST-IV 3 Meenakshi PH-II AP IPP 700 2016-17 4 Simhapuri PH-II AP IPP 150 Synchronized on 30.12.2014 5 East Coast Energy AP IPP 1320 2015-16 Thermal AP : 300 MW 6 Thermal Powertech. AP IPP 1320 Unit-I: CoD on 2 nd March 2015 Unit-II : 2015-16 Unit-III : 2016-17 Undivided AP: 500 MW. PPA signed. TS : 100 MW Agenda Notes for the 26 h Meeting of TCC & 27 th Meeting of SRPC 26 of 47

7 NCC Krishnapattnam AP IPP 1320 Unit I & II : COD by 2015-16 AP : 250 MW 8 Hinduja NPCL, AP IPP 1050 CoD by June 2015 Vizag 9 Bellary TPS U-3 KAR State 700 CoD by Sept / Oct 2015 10 Yeramarus TPS KAR State 1600 Unit-I : by October 2015 and CoD by December 2015 Unit II: Synchronization by December 2015 and CoD by February 2016. 11 Coastal Energen TN IPP 1200 Unit-I : CoD declared on 23.12.2014 Unit-II: CoD by April 2015. 12 IL&FS TN IPP 1200 90% of the works completed. Environmental clearance is awaited. 13 Kakatiya TPP ST-II TN State 600 August 2015. 14 Singareni TN IPP 1200 Unit I : COD by October 2015 Unit II : COD by December 2015 7. PAYMENT OF WHEELING CHARGES 7.1 As per the procedure for calculation of Node wise PoC charges a Load Flow base case up to 110 kv network is modeled which gets truncated to 400 kv equivalence network. Due to this network truncation, power flow from upstream state to downstream state through voltage class below 400 kv gets replaced with a load equivalent to power flow through such lines at upstream state. This results into by upstream state bearing the cost of ISTS equivalent to power flow to downstream state. 7.2 To address this issue, in the 21 st Meeting of SRPC, it had been decided to raise the rate of Wheeling Charges of Inter-State Lines from 2.5 to 7.5 paisa/unit of energy wheeled ( 2.5 paise + 5 paise compensation). 7.3 Since then the Central Electricity Regulatory Commission (Sharing of Inter State Transmission Charges and Losses) (Third Amendment) Regulations, 2015 has been notified to be implemented from 01 st May 2015. In the same, it has been decided not to truncate the base case load flow model. In view of this the wheeling charges need to be again revised to 2.5 ps/unit. 8. RESERVE SHUT DOWN (RSD) 8.1 In the 104 th Meeting of Operation Coordination Sub-Committee of SRPC held on 10 th February 2015, the following had been noted: There was a scheme for RSD being followed in Western Region. SRPC Secretariat had presented the RSD procedure being followed in WR. In WR, Reserve Shut down of costlier unit was being considered for a minimum period of 3 days (72 hrs). Constituents had expressed that in the present scenario, RSD may not be suitable in SR. This region was in surplus only for few hours in a day and not even more than a day on sustained basis. Constituents also had expressed ISGS capacity Agenda Notes for the 26 h Meeting of TCC & 27 th Meeting of SRPC 27 of 47